19
IN0057 Revision 02 – 1 of 16 POWER PERFORMANCE PASSION SP PRO Powerchain Installation Note Installation of an SP PRO Powerchain System Introduction This installation note will demonstrate how to install and configure SP PRO units in a Powerchain system, either as a single phase, three phase or split phase system with up to three worker units per phase (four SP PRO inverters per phase – one manager, with three worker units). Preparation This document needs to be read in conjunction with the SP PRO Instruction Manual and SP LINK instruction manual (both found in the SP LINK Help menu) Powerchain Definitions System Manager – Must be connected to L1 – all configuration, control and interaction is via this SP PRO Phase Manager – Main SP PRO on L2, L3 and/or Split(180°) Worker – any other SP PRO within system on any phase. Summary of steps The following is a summary of the steps required to complete the installation. Once the installation is completed, use the outline below as a check list: Installation step Pages 1 Install the SP PROs, including the DC and AC wiring. 2 - 6 2 Install and Configure the Batteries (DC Power to the SP PROs is required to complete the process) 3 Connect the SP PRO SYNC connections and terminators 7 4 Verify Firmware 8 5 Create the configuration for the SP PRO Powerchain system, using the Site Configuration Wizard in SP LINK 9 6 Connect to the SP PRO System Manager via SP LINK, assign the SP PROs in the Powerchain system and save the configuration 11 7 Test the system function 12

Installation of an SP PRO Powerchain System

  • Upload
    others

  • View
    4

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Installation of an SP PRO Powerchain System

IN0057 Revision 02 – 1 of 16 POWER PERFORMANCE PASSION

SP PRO Powerchain

Installation Note

Installation of an SP PRO Powerchain System

Introduction

This installation note will demonstrate how to install and configure SP PRO units in a Powerchain system,

either as a single phase, three phase or split phase system with up to three worker units per phase (four

SP PRO inverters per phase – one manager, with three worker units).

Preparation

• This document needs to be read in conjunction with the SP PRO Instruction Manual and SP LINK

instruction manual (both found in the SP LINK Help menu)

Powerchain Definitions

• System Manager – Must be connected to L1 – all configuration, control and interaction is via this

SP PRO

• Phase Manager – Main SP PRO on L2, L3 and/or Split(180°)

• Worker – any other SP PRO within system on any phase.

Summary of steps

The following is a summary of the steps required to complete the installation. Once the installation is

completed, use the outline below as a check list:

Installation step Pages

1 Install the SP PROs, including the DC and AC wiring. 2 - 6

2 Install and Configure the Batteries

(DC Power to the SP PROs is required to complete the process)

3 Connect the SP PRO SYNC connections and terminators 7

4 Verify Firmware 8

5 Create the configuration for the SP PRO Powerchain system, using the Site Configuration Wizard in SP LINK

9

6 Connect to the SP PRO System Manager via SP LINK, assign the SP PROs in the Powerchain system and save the configuration

11

7 Test the system function 12

Page 2: Installation of an SP PRO Powerchain System

IN0057 Revision 02 – 2 of 16 POWER PERFORMANCE PASSION

SP PRO Powerchain

Installation Note

Installation

The SP PROs must be installed as per the installation instructions in the user manual. It is a good idea to place a label on the top right-hand corner of each SP PRO. This will help to identify each inverter in the Powerchain system during system commissioning and testing.

AC Wiring

All Neutral connections from inverters must be connected together at the same common point as required. The neutral conductor connecting to the loads must be maintained such that operation of any external SP PRO isolators cannot sever the link between Neutral and Earth. All of the AC wiring linking the Load L and N circuits between any particular phase manager and its workers complies with the following:

1. The L and N cables either run in the same conduit or a twin cable is used. It is important that the cable pairs run in parallel and do not separate.

2. Minimise the cable length between an SP PRO and the sub board where it is connected to the other SP PROs on the same phase. The maximum allowable cable run is 10 metres from SP PRO to sub board.

SINGLE PHASE TWO WORKERS EXTERNAL CONTACTOR (OPTION 1) Figure 1 shows the SP PRO Single Phase Powerchain AC wiring schematic with two workers and an external CT & AC source contactor.

Figure 1: Single Phase AC wiring schematic with external contactor/CT and two workers

AC Source Power > 15 kW for SPMC or 30 kW for SPLC models

Page 3: Installation of an SP PRO Powerchain System

IN0057 Revision 02 – 3 of 16 POWER PERFORMANCE PASSION

SP PRO Powerchain

Installation Note

SINGLE PHASE TWO WORKERS INTERNAL CONTACTOR (OPTION 2) Figure 2 shows the Single Phase Powerchain AC wiring where no external contactor and CT is installed. This configuration can be used when the AC source capacity is no more than 15kW per phase for the SPMC models, or 30kW per phase for the SPLC models.

Figure 2: Single Phase AC Wiring Schematic with 2 Workers AC Source Power < 15 kW for SPMC or 30 kW for SPLC models

THREE PHASE TWO WORKERS PER PHASE Figure 3 (following page) shows a Three Phase Powerchain system with two workers per phase. An external three phase AC source contactor is required with external CTs for each phase. NOTE: A three phase Powerchain system with one or more workers per phase MUST have external CTs and an external AC Source contactor fitted. NOTE: Three phase circuits which have loads that cannot tolerate a phase failure must be protected by a Phase Failure Relay (not supplied).

Page 4: Installation of an SP PRO Powerchain System

IN0057 Revision 02 – 4 of 16 POWER PERFORMANCE PASSION

SP PRO Powerchain

Installation Note

Figure 3: Three Phase AC wiring schematic, external contactor, two workers per phase

Page 5: Installation of an SP PRO Powerchain System

IN0057 Revision 02 – 5 of 16 POWER PERFORMANCE PASSION

SP PRO Powerchain

Installation Note

Main DC Wiring

The SP PRO Powerchain main DC wiring diagram is illustrated in Figure 4. Battery protection must be a minimum of 630A per group. After the DC battery protection, the cables can be split into one circuit per SP PRO, each supplied by minimum 70mm2 V90HT cables. Each circuit is protected by a 250A HRC fuse or DC circuit breaker.

Figure 4: Main DC wiring schematic showing nine SP PROs.

Page 6: Installation of an SP PRO Powerchain System

IN0057 Revision 02 – 6 of 16 POWER PERFORMANCE PASSION

SP PRO Powerchain

Installation Note

Pre-charge and Midpoint Wiring

The SP PRO Powerchain DC pre-charge and midpoint wiring layout is shown in Figure 5. The pre-charge wiring is wired as a bus arrangement and connected to the battery via a common connection for all SP PROs. This will allow all SP PROs to be pre-charged together. The Midpoint wiring need only be connected to the System Manager (L1). The System Manager carries out the battery sense and midpoint readings for the system. The pre-charge and midpoint wiring must be protected by suitable fuses or a three pole circuit breaker rated at least 2A DC per SP PRO. For the system below (Fig. 5) the pre-charge circuit breaker rating is 18A or more.

Figure 5: DC pre-charge and midpoint schematic showing nine SP PROs

Page 7: Installation of an SP PRO Powerchain System

IN0057 Revision 02 – 7 of 16 POWER PERFORMANCE PASSION

SP PRO Powerchain

Installation Note

SP PRO SYNC Interconnection

Every SP PRO in a Powerchain system must be interconnected via its SYNC interface. Connect every

SP PRO together via the SYNC-1 or SYNC-2 connection, using the supplied cat5 cables.

The SYNC-1 and SYNC-2 connection points are identical, so either may be used for each connection.

Each SP PRO can be connected together in any sequence, with the most logical sequence being

connections between adjacent SP PROs. Ensure that all SP PROs in the Powerchain system are linked into

one single SYNC chain.

Note: Termination connectors MUST be fitted to the two unused SYNC connectors.

SYNC interconnection of the SP PROs

All Others End Start

Page 8: Installation of an SP PRO Powerchain System

IN0057 Revision 02 – 8 of 16 POWER PERFORMANCE PASSION

SP PRO Powerchain

Installation Note

Update Firmware and reset to factory defaults

Download the latest SP LINK (version 14.0 or higher) from the Selectronic web site. This will contain the latest SP PRO firmware 14.00 or higher and the Communications Card firmware 4.00 or higher. Apply DC power to all the SP PROs in the Powerchain system and wait until they start. Connect the SP LINK PC to the USB port on the SP PRO that will be assigned as the System Manager (the Manager on L1 phase). Select Firmware Update from the Easy Start Guide and update all of the SP PROs in the Powerchain system to latest version of firmware (Version 14.00 or higher and Comm Card version 4.00 or higher, if not already updated). All SP PROs in the Powerchain system will be updated via the System Manager.

Each SP PRO is shipped with a factory default configuration. If any of the SP PROs in the Powerchain have been configured then they must be set back to factory defaults before proceeding. If in doubt, it is best to revert each unit to factory defaults. To set an SP PRO to factory defaults: Apply battery power to the SP PRO and leave in Idle. Press and Hold the Alarm and Generator buttons (B) then press the ON button (C) until all LEDs go green. Release all buttons.

For more detailed instructions on how to update firmware and reset an SP PRO to factory defaults, please refer to Appendix I on page 14.

Page 9: Installation of an SP PRO Powerchain System

IN0057 Revision 02 – 9 of 16 POWER PERFORMANCE PASSION

SP PRO Powerchain

Installation Note

SP PRO Configuration

The Site Configuration Wizard is used to create the configuration for the Powerchain system. All

communications and system configuration are carried out by connecting to the System Manager (L1).

Once the system is configured, communications to other SP PROs in the Powerchain system is via the

System Manager. The data communications ports on the other SP PROs are disabled.

1. Make sure the USB lead is connected between the System Manager and PC.

2. Make sure the DC power is present at all of the SP PROs.

Wait until the front panel LEDs are stable.

3. Start Selectronic SP LINK.

4. Select “Site Configuration Wizard” and step though the wizard to setup the system to suite the

Powerchain system application.

Hint: For information on how to use the “Site Configuration Wizard”, right click on the page in

SP LINK and a help guide will appear.

Page 10: Installation of an SP PRO Powerchain System

IN0057 Revision 02 – 10 of 16 POWER PERFORMANCE PASSION

SP PRO Powerchain

Installation Note

When all settings have been configured in “Site Configuration Wizard”, from the menu bar, select

File > Site Information > Save.

5. SP LINK will automatically detect when the System Manager SP PRO is ON and the USB cable is

connected. Click “Connect” to connect to the SP PRO.

Page 11: Installation of an SP PRO Powerchain System

IN0057 Revision 02 – 11 of 16 POWER PERFORMANCE PASSION

SP PRO Powerchain

Installation Note

6. Go to the Powerchain Inverter Assignments tab. Drag and drop the serial numbers of the

Unassigned Inverters box into L2 or L3 Managers or L1, L2 and L3 Workers as appropriate.

Hint: To identify an SP PRO, double click on a serial number and the battery LEDs on the associated

SP PRO will flash RED for 3 seconds.

7. Once all SP PROs are assigned, click “Save Assignments”. The default settings passcode is 74.

8. At the Configuration Settings tab, click the “Configure SP PRO” button.

SP PRO Powerchain Configuration is now complete

Page 12: Installation of an SP PRO Powerchain System

IN0057 Revision 02 – 12 of 16 POWER PERFORMANCE PASSION

SP PRO Powerchain

Installation Note

Operation of the SP PRO

Once the SP PROs are installed and configured correctly, the system is controlled by the System Manager (the first SP PRO on L1). All other SP PROs will follow the operational mode of the System Manager automatically. Start-up

• Turn on the Battery Sense / Pre-charge isolator (See Fig 3). Wait until the SP PROs turn on. • Turn on the Battery Isolator

Note: All buttons and battery LEDs are disabled on the Phase Managers and the Workers.

1. After the SP PRO has powered up and the front panel LEDs are stable.

2. Connect to the System Manager via SP LINK.

3. In SP LINK navigate to “Data view > Powerchain”. Verify that all the real time readings from

each of the phases is correct.

Page 13: Installation of an SP PRO Powerchain System

IN0057 Revision 02 – 13 of 16 POWER PERFORMANCE PASSION

SP PRO Powerchain

Installation Note

4. SP LINK can also provide individual information for each of the SP PROs in the Powerchain.

Select “L1 or L2 or L3” in SP LINK, then Manager or Worker to display the SP PRO’s distinct

information.

Select the DataView > Now screen and check that there are no faults displayed in the Attention

Required box.

Shutdown • Turn off the Battery Isolator • Turn off the Battery Sense / Pre-charge isolator

Additional information

Selectronic web site – http://www.selectronic.com.au or contact the Selectronic Sales Team.

Page 14: Installation of an SP PRO Powerchain System

IN0057 Revision 02 – 14 of 16 POWER PERFORMANCE PASSION

SP PRO Powerchain

Installation Note

Appendix I: Instructions on How to Update Firmware

Reset each SP PRO back to factory defaults

Each SP PRO must be set back to factory defaults before setting up Powerchain. This process clears out the current configuration in the SP PRO so it is ready to accept a new Powerchain configuration. To reset to factory default, on the front panel of the SP PRO:

1. Press and hold the Generator and Alarm buttons (B),

2. Whist still holding these buttons, when the SP PRO beeps do a short press on the On button (C),

3. All Green front panel LEDs will come on. Let go of the Generator and Alarm buttons,

4. The SP PRO will now reset and go through the start-up sequence.

Page 15: Installation of an SP PRO Powerchain System

IN0057 Revision 02 – 15 of 16 POWER PERFORMANCE PASSION

SP PRO Powerchain

Installation Note

Update Firmware

1. Install the latest version of SP LINK on your computer. Start Selectronic SP LINK.

2. Make sure all of the SP PROs in the Powerchain are connected via the Sync lead.

3. Apply battery power to all of the SP PROs in the Powerchain.

4. Connect the SP LINK PC to the System Manager via a USB lead.

5. In the Easy Start Guide, select “Firmware Update…”.

6. The Easy Start Guide will automatically detect when the SP PRO is ON and USB cable is plugged

into the SP PRO and computer. Click “Connect” to start the Firmware Update process.

Page 16: Installation of an SP PRO Powerchain System

IN0057 Revision 02 – 16 of 16 POWER PERFORMANCE PASSION

SP PRO Powerchain

Installation Note

7. In the SP PRO Firmware update screen click Update firmware and restart SP PRO on

completion button.

Note: If firmware is already up to date then the “Update firmware and restart SP PRO

on completion” button will be disabled.

Important:

a. Managed batteries may turn OFF during the firmware update. If this occurs, turn the

batteries ON, close the SP PRO Firmware Update window. Reconnect to the SP PRO and

continue Firmware update (step 7 and 8). Repeat the process until the firmware is

updated.

b. In the case where the SP PRO firmware upload is complete and the batteries turn OFF

while the SP PRO is performing a firmware upgrade, turn the batteries ON and wait until

the front panel LEDs are stable. This may take a few minutes.

8. After the firmware is uploaded to all the SP PROs in the Powerchain system, they will

automatically restart. You will need to wait about 5 minutes for the restart to complete. A wait

time will be displayed in the firmware update screen. Communications with the SP PRO will be

lost during this time.

9. Once the restart timer times out, SP LINK will display the Connection screen.

Page 17: Installation of an SP PRO Powerchain System

1

1

2

2

3

3

4

4

5

5

6

6

D D

C C

B B

A A

Title

Number RevisionSizeC

Date: 7/05/2020 Sheet ofFile: U:\R&D\..\1ph 2W.SchDoc Drawn By:

SP PRO Powerchain Wiring Diagram

Prepared for IN0057 2

Pat Graham31

CT

+12VRELAY 1 N/O

RELAY 1 C

LOAD SOURCE EXTERNALCTL N L N

SP PROSYSTEM MANAGER

CB

EXPANSION CARD GND

AC SOURCE

Generator or Grid

System Manager

RELAY

10A 240VACN/C Contacts12V Coil

CBRated to AC SourceCountactor Wiring

6A

Figure 1 - SP Pro Single Phase AC Wiring Layout with External AC Source Contactor and 2 Workers

Figure 2 - SP PRO Single Phase AC Wiring Layout with 2 Workers

(From ACC)

AC SOURCECONTACTOR

EXTERNAL

LOAD SOURCE EXTERNALCTL N L N

SP PROWORKER 1

LOAD SOURCE EXTERNALCTL N L N

SP PROWORKER 2

LOAD

SPMC - 63ASPLC - 125A

CBsLess than 10m to sub boardCable Routing Requirements

Line and Neutral must run together

LOAD SOURCE EXTERNALCTL N L N

SP PROSYSTEM MANAGER

AC SOURCE

Generator or Grid

LOAD SOURCE EXTERNALCTL N L N

SP PROWORKER 1

LOAD SOURCE EXTERNALCTL N L N

SP PROWORKER 2

LOAD

SPMC - 63ASPLC - 125A

CBs

Less than 10m to sub boardCable Routing Requirements

Line and Neutral must run togetherSPMC - 63ASPLC - 125A

CBs

PICT104 PICT105

PICT106 PICT107

COCT1

PIExpansion Card109

PIExpansion Card1010

COExpansion Card1

PIRelay103 PIRelay104

PIRelay105 PIRelay106

CORelay1

PISingle Phase Contactor103 PISingle Phase Contactor104

PISingle Phase Contactor105 PISingle Phase Contactor106

COSingle Phase Contactor1

PISingle Phase Load?011

PISingle Phase Load?012

COSingle Phase Load?

PISingle Phase Load?011

PISingle Phase Load?012

PISingle Phase MCB103

PISingle Phase MCB104 COSingle Phase MCB1

PISingle Phase MCB303 PISingle Phase MCB304

COSingle Phase MCB3

PISingle Phase MCB?03

PISingle Phase MCB?04 COSingle Phase MCB?

PISingle Phase MCB?03

PISingle Phase MCB?04

PISingle Phase MCB?03

PISingle Phase MCB?04

PISingle Phase MCB?03

PISingle Phase MCB?04

PISingle Phase MCB?03

PISingle Phase MCB?04

PISingle Phase MCB?03

PISingle Phase MCB?04

PISingle Phase MCB?03

PISingle Phase MCB?04

PISingle Phase Source102

PISingle Phase Source103

COSingle Phase Source1

PISingle Phase Source?02

PISingle Phase Source?03

COSingle Phase Source?

PISP PRO108

COSP PRO1

PISP PRO?08

COSP PRO? PISP PRO?08 PISP PRO?08

PISP PRO?08 PISP PRO?08

PIRelay106

PIExpansion Card1010

PICT104

PIRelay103

PISingle Phase MCB304 PICT105 PISingle Phase Contactor103

PISingle Phase MCB103 PICT106

PISP PRO108

PICT107

PISingle Phase MCB104

PISP PRO108

PIExpansion Card109 PIRelay105

PIRelay104 PISingle Phase Contactor105

PISingle Phase Contactor104 PISingle Phase Load?011

PISingle Phase MCB?03

PISingle Phase Contactor106

PISingle Phase Load?012 PISingle Phase Source103

PISP PRO108 PISP PRO?08

PISingle Phase Load?011

PISingle Phase MCB?03

PISingle Phase Load?012 PISingle Phase Source?03

PISP PRO?08

PISingle Phase MCB303 PISingle Phase Source102

PISingle Phase MCB?03

PISingle Phase Source?02

PISingle Phase MCB?04

PISP PRO?08 PISP PRO108

PISingle Phase Source103

PISingle Phase Source?03

PISP PRO108 PISP PRO?08

Page 18: Installation of an SP PRO Powerchain System

1

1

2

2

3

3

4

4

5

5

6

6

D D

C C

B B

A A

Title

Number RevisionSizeC

Date: 7/05/2020 Sheet ofFile: U:\R&D\..\3ph 2W.SchDoc Drawn By:

SP PRO Powerchain Wiring Diagram

Prepared for IN0057 2

Pat Graham2 3

PHASE A

PHASE B

PHASE C

CT

CT

CT

GND

+12VRELAY 1 N/O

RELAY 1 C

LOAD SOURCE EXTERNALCTL N L N

SP PROL1 SYSTEM MANAGER

LOAD SOURCE EXTERNALCTL N L N

SP PROL2 PHASE MANAGER

LOAD SOURCE EXTERNALCTL N L N

SP PROL3 PHASE MANAGER

LOAD

AC SOURCECONTACTOR

3P CB

SPMC - 63ASPLC - 125A

1P CBs

RELAY

10A 240VACN/C Contacts12V Coil

EXPANSION CARD

System Manager

(From ACC)

AC SOURCE

Generator or Grid

Figure 3 - SP Pro Three Phase AC Wiring Layout with External AC Source Contactor and 2 Workers Per Phase

MANAGER GROUP

SPMC - 63ASPLC - 125A

1P CBs

SPMC - 63ASPLC - 125A

1P CBs

6A

EXTERNAL

LOAD SOURCE EXTERNALCTL N L N

SP PROL1 WORKER 1

LOAD SOURCE EXTERNALCTL N L N

SP PROL2 WORKER 1

LOAD SOURCE EXTERNALCTL N L N

SP PROL3 WORKER 1

WORKER GROUP 1

LOAD SOURCE EXTERNALCTL N L N

SP PRO

L1 WORKER 2

LOAD SOURCE EXTERNALCTL N L N

SP PRO

L2 WORKER 2

LOAD SOURCE EXTERNALCTL N L N

SP PRO

L3 WORKER 2

WORKER GROUP 2

PICT204 PICT205

PICT206 PICT207

COCT2 PICT304 PICT305

PICT306 PICT307

COCT3 PICT404 PICT405

PICT406 PICT407

COCT4

PIExpansion Card209

PIExpansion Card2010

COExpansion Card2

PIRelay203 PIRelay204

PIRelay205 PIRelay206

CORelay2

PISingle Phase MCB1003

PISingle Phase MCB1004 COSingle Phase MCB10

PISingle Phase MCB1103

PISingle Phase MCB1104 COSingle Phase MCB11

PISingle Phase MCB1203

PISingle Phase MCB1204 COSingle Phase MCB12

PISingle Phase MCB1303

PISingle Phase MCB1304 COSingle Phase MCB13

PISingle Phase MCB1403

PISingle Phase MCB1404 COSingle Phase MCB14

PISingle Phase MCB1503

PISingle Phase MCB1504 COSingle Phase MCB15

PISingle Phase MCB1603

PISingle Phase MCB1604 COSingle Phase MCB16

PISingle Phase MCB1703

PISingle Phase MCB1704 COSingle Phase MCB17

PISingle Phase MCB1803

PISingle Phase MCB1804 COSingle Phase MCB18

PISP PRO708

COSP PRO7 PISP PRO808

COSP PRO8 PISP PRO908

COSP PRO9

PISP PRO?08

COSP PRO? PISP PRO?08 PISP PRO?08

PISP PRO?08 PISP PRO?08 PISP PRO?08

PIThree Phase Contactor101

PIThree Phase Contactor102

PIThree Phase Contactor103 PIThree Phase Contactor104

PIThree Phase Contactor105 PIThree Phase Contactor106

COThree Phase Contactor1

PIThree Phase Load1011

PIThree Phase Load1012

PIThree Phase Load1013

PIThree Phase Load1014

COThree Phase Load1

PIThree Phase MCB103

PIThree Phase MCB104 COThree Phase MCB1

PIThree Phase Source101

PIThree Phase Source102

PIThree Phase Source103 COThree Phase Source1

PIRelay206

PIExpansion Card2010

PICT205 PIThree Phase Contactor101

PIThree Phase MCB103

PICT206

PISP PRO808

PICT207

PICT305 PIThree Phase Contactor101

PIThree Phase MCB103

PICT306

PISP PRO908

PICT307

PICT405 PIThree Phase Contactor103

PIThree Phase MCB103

PICT406

PISP PRO708

PICT407

PIExpansion Card209 PIRelay205

PIRelay204 PIThree Phase Contactor105

PISingle Phase MCB1003

PISingle Phase MCB1304 PISingle Phase MCB1604

PIThree Phase Contactor102 PIThree Phase Load1011

PISingle Phase MCB1004

PISP PRO808

PISingle Phase MCB1103

PISingle Phase MCB1404 PISingle Phase MCB1704

PIThree Phase Contactor102 PIThree Phase Load1012

PISingle Phase MCB1104

PISP PRO908

PISingle Phase MCB1203

PISingle Phase MCB1504 PISingle Phase MCB1804

PIThree Phase Contactor104 PIThree Phase Load1013

PISingle Phase MCB1204

PISP PRO708

PISingle Phase MCB1303 PISP PRO?08

PISingle Phase MCB1403 PISP PRO?08

PISingle Phase MCB1503 PISP PRO?08

PISingle Phase MCB1603

PISP PRO?08

PISingle Phase MCB1703

PISP PRO?08

PISingle Phase MCB1803

PISP PRO?08

PISP PRO708

PIThree Phase MCB104

PISP PRO808 PISP PRO908

PISP PRO?08

PIThree Phase Contactor106 PIThree Phase Load1014

PIThree Phase Source103

PISP PRO808

PIThree Phase MCB104

PISP PRO908

PIThree Phase MCB104

PISP PRO?08

PIThree Phase Source103 PICT204

PIRelay203

PIThree Phase Source101 NLPHASE A

PICT304 PIThree Phase Source102 NLPHASE B

PICT404 PIThree Phase Source103 NLPHASE C

Page 19: Installation of an SP PRO Powerchain System

1

1

2

2

3

3

4

4

5

5

6

6

D D

C C

B B

A A

Title

Number RevisionSizeC

Date: 7/05/2020 Sheet ofFile: U:\R&D\..\DC Wiring.SchDoc Drawn By:

SP PRO Powerchain Wiring Diagram

Prepared for IN0057 2

Pat Graham3 3

B+ B- S+ Mid S-

Shunt 1AShunt 2ATemp

ExpansionCard

L1 SYSTEMMANAGER

B+ B- S+ Mid S-

Shunt 1AShunt 2ATemp

ExpansionCard

L1 WORKER 1

B+ B- S+ Mid S-

Shunt 1AShunt 2ATemp

ExpansionCard

L2 PHASEMANAGER

B+ B- S+ Mid S-

Shunt 1AShunt 2ATemp

ExpansionCard

L3 PHASEMANAGER

B+ B- S+ Mid S-

Shunt 1AShunt 2ATemp

ExpansionCard

L1 WORKER 2

B+ B- S+ Mid S-

Shunt 1AShunt 2ATemp

ExpansionCard

L2 WORKER 2

B+ B- S+ Mid S-

Shunt 1AShunt 2ATemp

ExpansionCard

L2 WORKER 1

B+ B- S+ Mid S-

Shunt 1AShunt 2ATemp

ExpansionCard

L3 WORKER 1

B+ B- S+ Mid S-

Shunt 1AShunt 2ATemp

ExpansionCard

L3 WORKER 2

250A Secondary CBs orfuses to protect individualinverter wiring Battery isolator

and overcurrentprotection

Battery Temperature Sensor

Min

imum

bat

tery

cab

le s

ize

for

each

cab

le o

f 70

mm

2

V90H

T pe

r in

vert

er

B+ B- S+ Mid S-

Shunt 1AShunt 2ATemp

ExpansionCard

L1 SYSTEMMANAGER

B+ B- S+ Mid S-

Shunt 1AShunt 2ATemp

ExpansionCard

L1 WORKER 1

B+ B- S+ Mid S-

Shunt 1AShunt 2ATemp

ExpansionCard

L2 PHASEMANAGER

B+ B- S+ Mid S-

Shunt 1AShunt 2ATemp

ExpansionCard

L3 PHASEMANAGER

B+ B- S+ Mid S-

Shunt 1AShunt 2ATemp

ExpansionCard

L1 WORKER 2

B+ B- S+ Mid S-

Shunt 1AShunt 2ATemp

ExpansionCard

L2 WORKER 2

B+ B- S+ Mid S-

Shunt 1AShunt 2ATemp

ExpansionCard

L2 WORKER 1

B+ B- S+ Mid S-

Shunt 1AShunt 2ATemp

ExpansionCard

L3 WORKER 1

B+ B- S+ Mid S-

Shunt 1AShunt 2ATemp

ExpansionCard

L3 WORKER 2

Battery Sense / Prechargeisolator and over currentprotection.

Note: Battery Sense voltageis measured from theSystem Manager only.

Figure 4 - SP PRO Main DC Wiring Layout Showing 9 Units

Figure 5 - SP PRO Precharge & Midpoint Wiring Layout Showing 9 Units

WORKERGROUP 2

WORKERGROUP 1

MANAGERGROUP

WORKERGROUP 2

WORKERGROUP 1

MANAGERGROUP

PIBattery Bank101

COBattery Bank1

PIBattery Bank No Temp101

COBattery Bank No Temp1

PIDC Circuit Breaker101

PIDC Circuit Breaker102

PIDC Circuit Breaker103

PIDC Circuit Breaker104 CODC Circuit Breaker1

PIF101

PIF102

COF1

PIF201

PIF202

COF2

PIF301

PIF302

COF3

PIF401

PIF402

COF4

PIF501

PIF502

COF5

PIF601

PIF602

COF6

PIF701

PIF702

COF7

PIF801

PIF802

COF8

PIF901

PIF902

COF9

PIPrecharge Breaker101

PIPrecharge Breaker102

PIPrecharge Breaker103

PIPrecharge Breaker104 COPrecharge Breaker1

PISP PRO DC108

COSP PRO DC1

PISP PRO DC208

COSP PRO DC2

PISP PRO DC308

COSP PRO DC3

PISP PRO DC408

COSP PRO DC4

PISP PRO DC508

COSP PRO DC5

PISP PRO DC608

COSP PRO DC6

PISP PRO DC708

COSP PRO DC7

PISP PRO DC808

COSP PRO DC8

PISP PRO DC908

COSP PRO DC9

PISP PRO DC1008

COSP PRO DC10

PISP PRO DC1108

COSP PRO DC11

PISP PRO DC1208

COSP PRO DC12

PISP PRO DC1308

COSP PRO DC13

PISP PRO DC1408

COSP PRO DC14

PISP PRO DC1508

COSP PRO DC15

PISP PRO DC1608

COSP PRO DC16

PISP PRO DC1708

COSP PRO DC17

PISP PRO DC1808

COSP PRO DC18

PIBattery Bank101

PIBattery Bank No Temp101

PIPrecharge Breaker103 PIPrecharge Breaker101

PIDC Circuit Breaker101

PIDC Circuit Breaker102

PIDC Circuit Breaker103

PIDC Circuit Breaker104

PIF101

PIF102

PISP PRO DC108

PIF201

PIF202

PISP PRO DC208

PIF301

PIF302

PISP PRO DC308

PIF401

PIF402

PISP PRO DC408

PIF501

PIF502

PISP PRO DC508

PIF601

PIF602

PISP PRO DC608

PIF701

PIF702

PISP PRO DC708

PIF801

PIF802

PISP PRO DC808

PIF901

PIF902

PISP PRO DC908

PIPrecharge Breaker102

PISP PRO DC1008 PISP PRO DC1108 PISP PRO DC1208

PISP PRO DC1308 PISP PRO DC1408 PISP PRO DC1508

PISP PRO DC1608 PISP PRO DC1708 PISP PRO DC1808

PIPrecharge Breaker104

PISP PRO DC1008 PISP PRO DC1108 PISP PRO DC1208

PISP PRO DC1308 PISP PRO DC1408 PISP PRO DC1508

PISP PRO DC1608 PISP PRO DC1708 PISP PRO DC1808

PISP PRO DC108 PISP PRO DC208 PISP PRO DC308

PISP PRO DC408 PISP PRO DC508 PISP PRO DC608

PISP PRO DC708 PISP PRO DC808 PISP PRO DC908

PISP PRO DC1008 PISP PRO DC1108 PISP PRO DC1208

PISP PRO DC1308 PISP PRO DC1408 PISP PRO DC1508

PISP PRO DC1608 PISP PRO DC1708 PISP PRO DC1808