Pre-analytics
Suzanne Celmer-HarterLDR 678 PracticumInstrumentation: PrepLink/Remisol/Inlet UpgradeAugust 11, 2015
Beaumont Health
Jeffrey Plassins, MT(ASCP), Administrative Director, Laboratory Services for Beaumont Health-Dearborn and Oakwood (legacy) labs30+ years of laboratory experienceWorked for Beaumont Health-Dearborn for the past 5 years
Site Supervisor
Practicum Overview:Manage a project that will: Replace the inlet of the automation line with a dynamic inletReplace the 13 year old automation line computer and software system with PrepLink automation line controllerReplace the outdated and unsupported chemistry instrumentation middleware with Remisol and add Command Central workstations
Practicum Objectives:Review/signoff on CAD drawings for new inlet configuration of automation lineHold meetings regularly to disseminate project information to team membersMeet weekly with Beckman Coulter (vendor) representativesCoordinate site visit to another laboratory to visualize new line configuration and obtain information for the projectMeet regularly with BCI project manager
Practicum Objectives:Arrange for Urinalysis instrument to be removed from line and obtain new specimen loading inlet deck for offline capabilitiesAssess space and data needs for projectArrange for staging and assembly areas for inlet modules and materials neededAssist with computer configuration, testing, and validation of PrepLink line controllerSupervise installation of inlet and line upgrade from custom to code
Practicum Objectives:Prepare staff for automation downtime and arrange for training on new line componentsWork with Remisol project planners to determine server configuration, preplanning needs, rules writing, and operational issuesSupervise development of Remisol rules writing and configuration of Command Central workstationsArrange for training of staff on Remisol and Command Central
Update on Practicum Objectives:Inlet Upgrade-Old Configuration
Update on Practicum Objectives:Inlet Upgrade-new configuration
Update on Practicum Objectives: PrepLink Line Controller
Update on Practicum Objectives: New configuration of Outlets/Stockyards
Update on Practicum Objectives:Inlet/PrepLink/RemisolWhat has been completed?Next steps?Timeframe Remisol implementation?
To date: I have 328 hours documented for my practicum.Never assume anything will go as planned.The best examples of things that were problematic even though I was prepared:Unplanned demise of the automation line computer 3 weeks before the plan go-live.Having to start over again with the new Beaumont IT to work on security issues for Remisol project.Waiting for others to respond.
Lessons Learned:
Make sure you and your staff understands the workflow and process in both the current and proposed states. Education and training of the staff on new procedures is paramount to success of the project.
Lessons Learned:
Plan, research, do your homework, and go on site visits to obtain as much information as possible prior to start of project. It makes the planning phase and addressing problems easier. Talk to professional colleagues to learn best practices, inside information and create a network that you can use for collaboration. This was especially useful when working out issues. Lessons Learned:
Work with IT at every stage and make them your ally.Design data drops and locations of peripherals that work best with the workflow configuration. Make sure you involve your staff in the decision-making process to gain buy-in and knowledgeable information.Validate and document every procedural change and testing stage. This is especially important if you have to provide proof to an accreditation agency.
Lessons Learned:
Remember this is a process. Some weeks you make take two steps forward, one step back. Others may be just two steps backwards and still others, all forward movement. With patience and perseverance, you get to the end of the practicum.Lessons Learned: