Integrated Township &
Convention Centre
� 3 SPVs are formed for execution of the projects
� APIIC Ltd and Emaar Holdings hold 26% and 74% equity in all 3 SPVs
� Hyderabad International Convention Centre was built on an extent of 15 acres.
� Besides equity, APIIC Ltd shall receive 2 and 3% Gross Annual Revenue as lease rentals
� The Golf Course with Boutique Hotel is developed on an extent of 235 acres.
� The assets will revert to Govt. of A P after 66 years of lease without any encumbrances.
� An integrated township, 18 – hole international golf course, a convention centre with 6000 seating capacity and a business hotel
� Convention centre was inaugurated in Jan, 2006
� Break-even in the 2nd year of operation as against normal period of 4 to 5 years
� Business Hotel commenced operations in Mar, 2006
� 18-hole Golf was started in April 2008
� Integrated Township Project is under execution and model homes and villas are constructed
� 703 flats in 8-blocks - construction works commenced and expected to allot by March 2010