  • Integrating VDC into Everyday Projects

    VIRTUAL DESIGN & CONSTRUCTION AT HOLDER CONSTRUCTION

    December 12, 2005 Virtual Builders Roundtable

    Michael Kenig, Holder Construction [email protected]

  • Overview

    • Holder and BIM: Some Basic Philosophies

    • Highlight Some Experiences– Benefits, Challenges, and Lessons Learned

    • Updates - Some Industry Ongoing Efforts

  • Holder and BIM

    • Basic Philosophies:– A question of “when”, not “if”!– Only for “Gehry-esque” type projects?

    • BIM Projects fall into 1 of 2 categories1. Designed (in 3D)2. Conversion (to 3D)

    • To date, no “Gehry-esque”; only “Conversions”

  • Virtual Design and Construction

    BIM UpdateBuilding Information Modeling

    Excerpted From Internal Holder Presentation

  • Why Change ?WHAT WE ‘RE DOING WORKS

    FINE!!

    GET REAL. WE’RE IN THE FIELD.

    WE’RE BUILDERS!!

  • Why Change ?

    HOW’S THAT WORKING FOR YOU NOW ???

    WOULD YOU RATHER FIND OUT

    IT’S WRONG BEFORE YOU GET

    OUT IN THE FIELD, OR AFTER ??!

  • Building Information Modeling

    Virtual Design & Construction

    Object Based. Parametric.

    What Is BIM?

  • Coke Foundations: Scope Clarification BIM Examples

  • Holder BIM GuideBook

    What Holder’s Doing?

  • Jump In

    Get Wet

    Splash Around!

  • BIM Benefits1. Visualization – Infinite cut sections/drawings

    2. Conflict, Interference and Collision Detection

    3. Scheduling and Phasing – What if’s

    4. Sequencing, Workflow, Safety and Site Logistics

    5. "Smart Drawings": Estimating and Quantity Extraction

    6. Scope Clarification, Trade Coordination and Options Analysis

    7. As-Builts, Facility Management, and BD uses

    …and many others we are still discovering!

  • Examples of Benefits

    • Options Analysis (Value Engineering)• Scope Reconciliation (comparisons)• Virtual Mock-Ups

    Brick Precast

  • Progressive Data Center

    Phases started / used: “Conversion” from 2D

    What was modeled: Entire Project

    Who did the modeling: Outsourced

  • Logistics And Sequencing

  • A1010 A1010.4009 Continuous Footing 2 339.98 cy 237.29 80 674.58 A1010.400 120_100cy 4000 Rw - PUR (Continuous Footing 2) 339.98 cy 83 28 218.502 120_2_100 4000 Rw - PUR (Continuous Footing 2) 339.98 cy 83 28 218.50

    A1010.400 120_101cy Concrete Admixtures - PUR (Continuous Footing 2) 339.98 cy 1 339.982 120_2_101 Concrete Admixtures - PUR (Continuous Footing 2) 339.98 cy 1 339.98

    A1010.400 120_102cy Concrete Pumping - MAT (Continuous Footing 2) 339.98 cy 10 3 399.822 120_2_102 Concrete Pumping - MAT (Continuous Footing 2) 339.98 cy 10 3 399.82

    A1010.400 130_103sf Foundation Plywood - MAT (Continuous Footing 2) 17 851.85 sf 0.26 4 641.482 130_2_103 Foundation Plywood - MAT (Continuous Footing 2) 7 140.74 sf 0.65 4 641.48

    A1010.400 130_104sf Foundation Form Lumb - MAT (Continuous Footing 2) 17 851.85 sf 0.25 4 462.962 130_2_104 Foundation Form Lumb - MAT (Continuous Footing 2) 5 950.62 bf 0.75 4 462.96

    A1010.400 140_105cy Pour Cont. Footings - LAB (Continuous Footing 2) 339.98 cy 13.2 4 487.761 140_1_105 Pour Cont. Footings - LAB (Continuous Footing 2) 339.98 cy 13.2 4 487.76

    A1010.400 140_106sf Form Cont. Footings - LAB (Continuous Footing 2) 17 851.85 sf 1.1 19 637.041 140_1_106 Form Cont. Footings - LAB (Continuous Footing 2) 7 140.74 sf 2.75 19 637.04

    A1010 A1010.4039 Pad Footing w Bolts 2 56.34 cy 470.39 26 503.51A1010.403 120_139cy 4000 Rw - PUR (Pad Footing w Bolts 2) 56.34 cy 83 4 676.542 120_2_139 4000 Rw - PUR (Pad Footing w Bolts 2) 56.34 cy 83 4 676.54

    A1010.403 120_140cy Concrete Admixtures - PUR (Pad Footing w Bolts 2) 56.34 cy 1 56.342 120_2_140 Concrete Admixtures - PUR (Pad Footing w Bolts 2) 56.34 cy 1 56.34

    A1010.403 120_141cy Concrete Pumping - MAT (Pad Footing w Bolts 2) 56.34 cy 10 563.442 120_2_141 Concrete Pumping - MAT (Pad Footing w Bolts 2) 56.34 cy 10 563.44

    A1010.403 130_142lf Foundation Edgeform - MAT (Pad Footing w Bolts 2) 860.42 lf 2 1 720.832 130_2_142 Foundation Edgeform - MAT (Pad Footing w Bolts 2) 860.42 lf 2 1 720.83

    A1010.403 130_143sf Foundation Plywood - MAT (Pad Footing w Bolts 2) 1 447.58 sf 0.65 940.932 130_2_143 Foundation Plywood - MAT (Pad Footing w Bolts 2) 1 447.58 sf 0.65 940.93

    A1010.403 130_144sf Foundation Form Lumb - MAT (Pad Footing w Bolts 2) 1 447.58 sf 0.25 361.92 130_2_144 Foundation Form Lumb - MAT (Pad Footing w Bolts 2) 482.53 bf 0.75 361.9

    A1020 Caissons and Piles 17 524.32

    A1020 A1020.0100 Caissons 65.2 cy 268.78 17 524.32A1020.010 0203 cy Caissons - Caissons cy 65.2 cy 41 2 673.182 A120101240 Place & Finish (Caissons) 65.2 cy 25 1 629.993 A120101005 Prep (Caissons) 65.2 cy 10 6523 A120101090 Haul Caisson Spoils (Caissons) 65.2 cy 6 391.2

    A1020.010 0203 ea Caissons - Caissons ea 56 ea 50 2 800.003 A120101160 Set Anchorbolts/Embeds (Caissons) 56 ea 50 2 800.00

    A1020.010 0203 lf Caissons - Caissons lf 561 lf 8 4 488.003 A120101020 Caisson Drilling (Caissons) 561 lf 4 2 244.003 A120101100 Caisson Casing (Caissons) 561 lf 4 2 244.00

    Quantity and Cost Extraction

    • Deep Foundations

    • Spread Footings

    • Continuous Footings

    Code Description Qty Unit UPriceCost

    5D – Quantities And Cost

  • Quantity and Cost Extraction

    • Windows / Glazing

    • Drywall Partitions

    • Access Flooring

    B2020 Windows Glass and Glazing 230 341.34

    B2020 B2020.0001 SD Opening 01 1 311.42 sf 23 30 162.58B2020.655 1841 sf SD Opening 01 1 311.42 sf 23 30 162.583 Z216001150 SD Opening 01 1 311.42 sf 23 30 162.58

    B2020 B2020.0201 Storefront Glzg G2Ctg 500.16 sf 20 10 003.29B2020.020 0806 sf Extr Storefront Glzng - Storefront sf 500.16 sf 20 10 003.293 B220201000 Exterior Storefront 1in Insulated Glazing & Mullions 500.16 sf 14 7 002.303 B220201020 Exterior Storefront Coating - Medium Grade 500.16 sf 6 3 000.99

    B2020 B2020.0301 Ribbon Glzg G2Ctg 2 261.94 sf 23 52 024.53B2020.030 0803 sf Extr Ribbon Glzng - Glass sf 2 261.94 sf 23 52 024.533 B220301000 Exterior Ribbon 1in Insulated Glazing & Mullions 2 261.94 sf 17 38 452.923 B220301020 Exterior Ribbon Coating - Medium Grade 2 261.94 sf 6 13 571.62

    C1010 Interior Walls 1 282 032.96

    C1010 C1010.4799 Drywall Furred Col 2 9 296.98 sf 3.5 32 539.42C1010.479 405_561sf Drywall - Furred Columns - SUB (Drywall Furred Col 2) 9 296.98 sf 3.5 32 539.423 405_3_561 Drywall - Furred Columns - SUB (Drywall Furred Col 2) 9 296.98 sf 3.5 32 539.42

    C1010 C1010.4809 Drywall Furred Col 3 2 370.28 sf 3.5 8 295.98C1010.480 405_562sf Drywall - Furred Columns - SUB (Drywall Furred Col 3) 2 370.28 sf 3.5 8 295.983 405_3_562 Drywall - Furred Columns - SUB (Drywall Furred Col 3) 2 370.28 sf 3.5 8 295.98

    C1010 C1010.4849 Drywall NR Part FH 2 1 048.82 sf 6 6 292.93C1010.484 405_566sf Drywall - Unrated Partitions - Full height - SUB (Drywall NR Part FH 2) 1 048.82 sf 6 6 292.933 405_3_566 Drywall - Unrated Partitions - Full height - SUB (Drywall NR Part FH 2) 1 048.82 sf 6 6 292.93

    C1010 C1010.4859 Drywall NR Part FH 3 37 900.68 sf 6 227 404.07C1010.485 405_567sf Drywall - Unrated Partitions - Full height - SUB (Drywall NR Part FH 3) 37 900.68 sf 6 227 404.073 405_3_567 Drywall - Unrated Partitions - Full height - SUB (Drywall NR Part FH 3) 37 900.68 sf 6 227 404.07

    C3020 C3020.5449 Access FloorA 2 78 123.61 sf 13.8 1 078 105.85C3020.544 409_667sf Access Flooring -- CCN1500 - Bare - SUB (Access FloorA 2) 78 123.61 sf 13.8 1 078 105.853 409_3_667 Access Flooring -- CCN1500 - Bare - SUB (Access FloorA 2) 78 123.61 sf 13.8 1 078 105.85

    C3020 C3020.5459 Access FloorB 2 1 963.08 sf 15 29 446.15C3020.545 409_668sf Access Flooring -- CCN1500 -- HPL - SUB (Access FloorB 2) 1 963.08 sf 15 29 446.153 409_3_668 Access Flooring -- CCN1500 -- HPL - SUB (Access FloorB 2) 1 963.08 sf 15 29 446.15

    C3020 C3020.5484 Access Floor Support 80 119.34 ft 0.33 26 439.38C3020.210 1001 ft Raised Access Floor Support 80 119.34 ft 0.33 26 439.383 C322101000 Raised Access Flooring (Raised Access Flooring) 80 119.34 ft 0.33 26 439.38

    Code Description Qty Unit UPriceCost

    5D – Quantities And Cost

  • Coordination

  • Making the Business Case

    Issue:Issue: Generator exhaust pipe and battery room exhaust duct conflict in areaway.

    Result: Duct penetrations through precast wall panels were relocated and generator exhaust pipe routing was modified in field.

    Potential Cost Savings = $60,000

    2D HVAC Plan

    2D Pipe Plan

    Photo of Installation

    3D Overhead Rendering of Areaway

  • Challenges / Lessons Learned

    • Conversions on “Fast-Tracked” Projects

    • Level of Granularity, decide early

    • Prefabrication: Higher quality, lower cost

    • File Sharing: FTP Site (two way)

  • Challenges / Lessons Learned

    • Trusting the Data (side-by-side estimates)

    • Visualization is the low hanging fruit

    • The 3 Fears (“for our convenience”)

    • Changing our Everyday Processes

  • Update on Other Ongoing Efforts

    • CURT OAEC Productivity (AGC Report)

    • AGC PIAC’s “BIM Taskforce”

    • AIA / AGC Joint Committee Survey

    One of the limitations of 2D drawings is that only people can read them.

    Chuck Eastman, GA Tech

  • CURT WP-1202:The Case for Change (Owners!)

    The Drivers:

    • Owner Leadership

    • Integrated Project Structure

    • Open Information Sharing

    • Bldg. Info Models (BIM)

  • Impact of Shifting Curve to the LeftImpact of Shifting Curve to the Left

    On Contractors?

    On Owners?

    X X X

  • “Strategy” – Organize Differently / Technology

    Many Teams already Collaborative / Integrated

    Optimized Process - FCFIHP Teams (Follow up Whitepaper from CURT)

  • Only a Few Early Adopters Leading the Way

    Looking for Anything that Will Help

    Need Designers to use the Technology

    New Position – Project Modelers

    “Conversions” (temporary during transition)

    “Where are builders on this?”(AGC Report to CURT Conference, Nov. 8)

  • AGC’s Private Industry Advisory Counsel (PIAC)BIM Task Force

    • Owner’s Perspective

    • Challenges Limiting Implementation

    • Barriers Implementation (removing them)

    Regarding BIM, we need to get past the “what it is” and focus on “what it does”!