Integration of CLIC TBM in CLEX Electronics allocation and cables tracing Wilfrid Farabolini (CEA/IRFU)…

Embed Size (px)

DESCRIPTION

1 st idea: additional drills on the ceiling Pros: - Minimum changes to the building Cons:- Delicate drilling (present cable tray and TBL line to be removed, dust inside) - Cables length > 20 m if to follow present cable trays - Problem to install new racks in the gallery - Staff in the gallery during operations CLIC Module TBL CALIFES