Interfaces Between CCS trackside and other subsystems

Joint sector research and validation for the specification of the electromagnetic

compatibility

Page 2: Interfaces Between CCS trackside and other subsystems Joint sector research and validation for the specification of the electromagnetic compatibility

Sector involvement• Cross acceptance Working party– Collection and classification of national rules

• CCS TSI editing including update of the “Interfaces Between CCS trackside and other subsystems”– Specification of target system

• EMC Working Party– Contributing to the EMC target specification– Projects aiming in closing the EMC open points

14/12/2010 2

Page 3: Interfaces Between CCS trackside and other subsystems Joint sector research and validation for the specification of the electromagnetic compatibility

Motivation of the sector involvement• Requirements for the compatibility between vehicles

and axle counters + track circuits for the authorisation of vehicles are currently an open point in the TSI CCS. – As a consequence national rules have to be followed today,

in some cases national rules do not exist

• The joint sector projects aim to – a reach broad European acceptance of the new limits – test specifications – provide the scientific input for the closure of open points

related to the vehicle/train detection interface

14/12/2010 3

Page 4: Interfaces Between CCS trackside and other subsystems Joint sector research and validation for the specification of the electromagnetic compatibility

Overview of EMC Project planning

• 2010: partial validation of TS 50238-2 (vehicles and track circuits in the 15kV network)

• 2011-?: validation of TS 50238-3 (vehicles and axle counters)

• 2012-2014: closure of TSI CCS open points in FP7 4th call project proposal EUREMCO

• 2013-2015: closure of TSI CCS open point “eddy current brake” – CTG project idea for FP7 5th call

14/12/2010 4

Page 5: Interfaces Between CCS trackside and other subsystems Joint sector research and validation for the specification of the electromagnetic compatibility

EMC phase 1

• TS 50238-2 establishes new vehicles emission limits and vehicle test methods for the compatibility with track circuits

• funding provided by CER/EIM/UIC for the partial validation in the 15kV network

• Tests have been carried out by DB, SBB and ÖBB with the support of Siemens

• Test report expected by end of December 2010• To be included in the CCS TSI at the next revision

14/12/2010 5

Page 6: Interfaces Between CCS trackside and other subsystems Joint sector research and validation for the specification of the electromagnetic compatibility

EMC phase 2

• TS 50238-3 establishes new vehicles emission limits and vehicle test methods for the compatibility with axle counters

• UIC applied for TEN-T co-funding for a joint validation campaign of 8 CER/EIM (UIC) members in all networks in 2011

• Expected outcome:– Validated list of practically relevant parameters– Susceptibility limits for axle counters missing so far– Validation of vehicle emission limits and vehicle test method of TS

50238-3 and proposal for improvements– Proposal for the quantification of other relevant parameters

• Funding rejected – further strategy to be developed !!!

14/12/2010 6

Page 7: Interfaces Between CCS trackside and other subsystems Joint sector research and validation for the specification of the electromagnetic compatibility

EMC phase 3 - EUREMCO • If positively approved, EUREMCO will finalise the validation of

the TS 50238-2 (track circuits) for DC 1,5kV, 3kV and AC 15kV/16,7Hz, 25kV/50Hz

• Expected outcomes:– Set of test signals to test track circuits again transients– Clear definitions and specifications for the assessment of transients– Limits for the characteristic parameters of transients for both vehicles

and power supply (sources) and track circuits (destination)– Clear understanding of the influence of the infrastructure on the

conducted emissions of vehicles– Transfer function from test results within the same power supply

system (for track circuits).– Requirements that rolling stocks will not disrupt track circuits on non-

electrified lines

14/12/2010 7

Page 8: Interfaces Between CCS trackside and other subsystems Joint sector research and validation for the specification of the electromagnetic compatibility

EUREMCO: EUropean Rail ElectroMagnetic COmpatibility

• UNIFE applied jointly with 10 UNIFE/CER/EIM/UIC members for FP7 4th call co-funding for a project in 2012-14

• Funding: €2,1m, Budget: €3,6m

14/12/2010 8

Page 9: Interfaces Between CCS trackside and other subsystems Joint sector research and validation for the specification of the electromagnetic compatibility

Remaining open point:Eddy current brake

• A CTG project idea which has been picked up by ERRAC in the « sector wishlist » for the FP7 5th for a joint project of UNIFE/CER/EIM/UIC members in 2013-15

• Funding: open• Expected outcome:

– Improve understanding of the interaction of the eddy current brake with the track and trackside signalling equipment

– Identify critical thermal, mechanic and electromagnetic parameters and its related vehicle and trackside compatibility limits

– Develop design, engineering and operational guidelines for new eddy current brakes and new trackside signalling equipment

14/12/2010 9

Page 10: Interfaces Between CCS trackside and other subsystems Joint sector research and validation for the specification of the electromagnetic compatibility

Conclusion• Sector target – simplified vehicle autorisation

through:– Harmonised EMC limits, both for signalling susceptibility as well as for

vehicle emissions– Harmonised test method proving the vehicle conformity with the

specified limits

• Final goal – one assessement applicable for all networks compliant with the INTERFACE document

• Precondition:– Strong cooperation of all stakeholders: railway

undertakings, infrastructure managers as well as manufacturers (both of vehicles as well as of signalling)

14/12/2010 10