Upload
others
View
9
Download
0
Embed Size (px)
Citation preview
1
INTERIM
VALUATIONS
Preparation for valuations of interim payment and advance payment
2
INTERIM VALUATIONS
Certificate
Of interim
certificate
Valuations
on Site
Preparations of Interim Valuations
3
INTERIM VALUATIONS
◼ The main items to be considered when valuing the works are:
◼ Measured work including preliminaries
◼ Value of variations and extras
◼ Value of nominated sub contractor or supplier work
◼ Fluctuations where applicable
◼ Unfixed material on site
◼ Retentions monies
◼ Previous payment
4
INTERIM VALUATIONS
◼ Valuations of
preliminaries
◼ Based on the amount
of the contract period
that has elapsed
◼ Based on the value of
work done
◼ Based on valuations
by individual
assessment
◼ The preliminaries cost
will be distribute based
on three (3) stages of
completions :
◼ Initial cost
◼ Recurring cost
◼ Final cost
5
CADANGAN MENAIKTARAF INFRASTRUKTUR JALAN DAN KERJA-KERJA
BERKAITAN DI KAWASAN PERINDUSTRIAN MURNI, SENAI, JOHOR
BILL NO. 1 - PRELIMINARIES Progress Payment No. 4
PAGE DESCRIPTION CONTRACT INITIAL RECURRENT COMPLETION REMARKS
REF. AMOUNT ( RM ) ( RM ) ( RM ) (RM )
B1/1/A WORKMEN 'S COMPENSATION 3,000.00 2,400.00 600.00 -
B1/1/A INSURANCE FOR PUBLIC LIABILITY 1,500.00 1,200.00 300.00 -
B1/1/A INSURANCE OF WORKS 1,500.00 1,200.00 300.00 -
B1/2/A STORAGE 8,000.00 8,000.00 - -
B1/2/B LICENCE SURVEYOR 10,000.00 8,000.00 2,000.00 -
B1/2/C PROGRESS PHOTOGRAPHS 2,000.00 - 2,000.00 -
B1/2/D WORK PROGRAMME 2,000.00 800.00 1,200.00 -
B1/2/E SIGNBOARD 2,500.00 2,000.00 - 500.00
B1/2/F HOARDING 10,000.00 8,000.00 - 2,000.00
B1/3/A SAFETY MEASURE 3,000.00 1,200.00 1,800.00 -
B1/3/B CIDB 3,500.00 3,500.00 - -
B1/3/C AS BUILT DRAWINGS FOR SERVICES 8,000.00 - - 8,000.00
B1/3/D SAFETY HELMET, BOOTS 2,000.00 - 2,000.00 -
B1/3/E COORDINATION WITH AUTHORITY - - - -
B1/3/F CLEANING AND CLEARING WORKS 3,000.00 - 600.00 2,400.00
B1/3/G DIGITAL CAMERA 2,000.00 1,600.00 400.00 -
B1/3/H TOSHIBA NOTE BOOK 10,000.00 8,000.00 2,000.00 -
TOTAL 72,000.00 45,900.00 13,200.00 12,900.00
PRELIMINARIES COST
Consultant to propose "calculation" of payment to be made for recurrent item
Collection
INITIAL COST : = 45,900.00
Less Item with underline -
45,900.00
RECCURRING COST : Value of W/done X Reccurent
Contract Sum - (PC + PS) -Preliminaries Cost
2,128,292.90 X 13,200.00 = 11,533.60
2,435,793.50
FINAL COST : = -
TOTAL CARRIED TO GENERAL SUMMARY : = 57,433.60
6
INTERIM VALUATIONS
◼ Based on the amount of
the contract period that
has elapsed
◼ Total value of prelim vs
period of completions
◼ Say, RM75,000.00 / 60
week
◼ So, RM 1,250 per
week
◼ Based on the value of
work done
◼ Value of work done for
that particular month
◼ Less ( prime cost +
provisional sum +
preliminaries)
◼ Multiply by total cost of
preliminaries work
7
INTERIM VALUATIONS
◼ Based on valuations by individual assessment
◼ Certain items may be required at the outset and can accordingly be valued in full, such as provision of temporary site fencing, constructions of temporary roads, and the erection of hoarding, storage compound etc.
◼ Items value in full or in part according to their usage, such scaffolding and plant
◼ Items valued in proportions to the works executed, such as wages of general foreman, cost of telephone call and inc.
◼ Items valued on completions such as cleaning and drying out
8
INTERIM VALUATIONS
◼ Valuation of measured works
◼ Items of works done individually extracted from BQ
◼ Approx qty may be measured for the work as executed
and priced at bill rates.
◼ It maybe practicable to value the work as an estimated
% of the total value of a work section.
◼ Pre-determined stages of completions may be
assessed as % of the value of the total work in the
contract.
◼
9
INTERIM VALUATIONS
◼ Valuations of variations and extra’s
◼ Any direct loss & expenses occur from
Architect /S.O instructions.
◼ QS should assess the value of these item to
be included in interim valuations
◼ The variations of omissions/addition from
original contract
◼ Net balance which is added to or deduct from
the valuation
10
INTERIM VALUATIONS
◼ Valuation of Nominated Sub Contractor or Supplier’s work◼ NSC submit account to QS for assessment through
Contractor
◼ The account shall include :◼ Work executed to date,
◼ Original quotations,
◼ Extra works,
◼ Material on site
◼ The amount to be paid shall be specified in interim valuations.
◼ Proof the Contractor has paid the NSC are required
◼ In the event C’tor default, Arch elect to pay direct
11
INTERIM VALUATIONS
◼ Fluctuations
◼ May inserted in a building /infra contract
◼ Adjustment for increase or decrease in the
cost of labour/material after date of tender
◼ Assessment of the value of fluctuations is
progressive and cumulative total added to
each valuations
12
INTERIM VALUATIONS
◼ Unfixed material◼ Based on a list prepared by general foreman of COW
which can be checked on site
◼ Material should be of the specified quality, be insured and properly protected and not be brought on to the site prematurely.
◼ Conditions to be fulfilled :◼ Intended for inclusion in the works
◼ Complete, satisfactory and adequately insured
◼ Have been set apart, clearly and visibly and reference to identify where they are stored, person whose order, their destinations is works
◼ If say from supplier , material shall pass unconditionally to the C’tor
13
INTERIM VALUATIONS
◼ Retention
◼ Retention by the employer of a proportion of
the monies due to the Contractor on an interim
certificate
◼ To create an incentive for the prompt and
satisfactory performance of the works
◼ To provide security for the employer against
default by the Contractor
14
INTERIM VALUATIONS
◼ Release for Retentions◼ Sectional completions
◼ Half of retentions on value of relevant part is release within 14 days taking possessions
◼ Another half, after DLP end
◼ Amount of retentions will be reduce accordingly
◼ Good practice to issue interim certificate
◼ Final payment of a nominated sub con bef practical completions◼ Where Arch/SO wish to secure payment of NSC bef main con
complete,
◼ He may release the retentions held against completed sub contract work.
◼ NSC must satisfactorily indemnify the contractor against latent defects.
◼ Gross retentions will be reduced by the amount of retentions released.
15
INTERIM VALUATIONS
◼ Release for Retentions (cont’d…)
◼ Practical completions
◼ Residue on issue of final certificate
16
PAKATAN UKUR BAHAN SDN. BHD. (440419-K)
JURUUKUR BAHAN & PERUNDING KOS BINAAN
Engineers/S.O Y Architects
No. 18-03, Jln Permas 10/7,
Bandar Baru Permas Jaya,
81750 Johor Bahru,
Johor Darul Takzim.
dated the 1st day of December 2003 for Valuation No.
the works known as Cadangan Pembangunan Kompleks Perdagangan
Pekan Rabu (4 Tingkat), Pencawang Elektrik TNB Dan Date
Tempat Pembuangan Sampah Di Atas Sebahagian Lot
P.T.D. 63718, Mukim Tebrau, Johor Bahru, Johor Darul Date in Site
Takzim.
For Certificate no.
indicates that(n) interim 'balance is due
from the employer Swissharta Sdn. Bhd.
No, 256, Jalan Sutera,
Taman Sutera,
Johor Darul Takzim.
+Gross valuation RM
is the contractor System Metal Aluminium & Glass
Construction Sdn Bhd Not retention stated below RM
18 & 20, Jalan Kempas 4, Taman Perindustrian Tampoi
Indah, 81200 Johor Bahru. Net valuation RM
Contract sum RM Previously certified RM
Balance indicated Ringgit One Million Five Hundred Seventy Three Thousand Six Hundred
(in words) Ninety Three And Sen Seven Only
Gross relentation (Limit 5% #) excluding payment under Clauses 24 and 31 RM
RM
The Contractor having confirmed to the Engineer/S.O. receipt of satisfactory
Sub-contractor RM
Sub-contractor RM
Sub-contractor RM RM
Balance of retention RM
Partial release of retention on sectional completion under Clause 16.1 (vi) RM
Partial release of retention on practical completion under Clause 30.5 (iii) RM RM
Net retention as shown in valuation RM
Signature Quantity Surveyor
' Insert the word "interim" or "final"
It is assumed that the Engineer/S.O. will (make any adjustment in respect + including the value of works by
of work wich he considers improperly executed; (b) unless otherwise agreed notify nominated sub-contractors as to this
nominated sub-contractors of payment due to them; (c) satisfy himself, if he wishes valuation
that previous payment to nominated sub-contractor have been discharge.
# Insert percentage or "limit"
Statement of Retention
Five (5)
7th July 2004
30-Jun-04
Five (5)
7,708,018.07
410,709.44
7,297,308.63
5,723,615.56
1,573,693.07
8,214,188.85
Q.S. VALUATION
Q.S.'s
COPY
below, the retention being adjusted accordingly
410,709.44
410,709.44
410,709.44
Previous releases to nominated sub-contractor's
indemnify. Final payment is to be made to the Nominated Sub-Contractors listed
17
PERUNTUKAN PEMBANGUNAN: MAKSUD : BUTIRAN :
TAJUK KERJA : CADANGAN MENAIKTARAF INFRASTRUKTUR JALAN DAN KERJA-KERJA
BERKAITAN DI KAWASAN PERINDUSTRIAN MURNI, SENAI, JOHOR
NAMA & ALAMAT KONTRAKTOR : TEAMCOAT METALCARE & DEVELOPMENT SDN BHD
No. 40 Jalan Penaga 10,
Kaw. Perindustrian Kota Putri,
81750 Masai,
Johor Darul Takzim.
NO. KONTRAK : MPKu.T/3/2007
JUMLAH HARGA ASAL KONTRAK : 2,507,793.50RM
JUMLAH BERSIH TAMBAHAN/POTONGAN : -RM
HARGA BARU KONTRAK : 2,507,793.50RM
A. BUTIR-BUTIR BAYARAN DAN POTONGAN
1. TARIKH PENILAIAN : 1hb. November 2007
2. NILAI KERJA DILAKSANAKAN DAN AMAUN-AMAUN LAIN YANG KENA BAYAR * 1,000,000.00RM
3. KURANGKAN Bayaran Interim Yang Terdahulu No. 1 - 2 459,438.58RM
4. NILAI BERSIH KERJA SEMASA 540,561.42RM
5. POTONGAN
a. Bayaran Balik Wang Pendahuluan
i) Amaun Terkumpul -RM
ii) Amaun Terdahulu -RM
iii) Amaun Semasa -RM
b. Akaun Deposit Wang Jaminan Perlaksanaan (Amaun Terdahulu) 51,048.73RM
c. Gantirugi Tertentu Dan Ditetapkan @ RM…….../hari selama ………. -RM
d. Potongan lain jika ada -RM
Jumlah Potongan 51,048.73RM 51,048.73RM
BAYARAN YANG DISYORKAN 489,512.69RM
……………………………………………… ……………………………………………… ………………………………………………
Perunding Jurutera/ Perunding Ukur Bahan Jurutera Bangunan/
Pengesyor yang bertanggungjawab Pengesyor yang bertanggungjawab Pegawai yang bertanggungjawab
Tarikh : ……………………………… Tarikh : ……………………………… Tarikh : ………………………………
B PERAKUAN BAYARAN
1. Bayaran Interim
a) Kepada Kontraktor Utama 440,561.42RM
b) Kepada Subkontraktor/Penerima Hak -RM
(Seperti di Lampiran A)
Jumlah Bayaran Interim 440,561.42RM 440,561.42RM
2. Kredit Akaun Deposit Wang Jaminan Perlaksanaan (10% dari Bayaran Disyorkan sehingga 5% harga kontrak) 48,951.27RM
BAYARAN DIPERAKUKAN 489,512.69RM
(Ringgit Malaysia: Empat Ratus Lapan Puluh Sembilan Ribu Lima Ratus Dua Belas dan Sen Enam Puluh Sembilan Sahaja)
Adalah disahkan bahawa semua peraturan kewangan dan kehendak di bawah Kontrak telah dipatuhi
Tarikh:………………..
1 Jumlah amaun yang dibayar dibawah Perakuan ini ialah
(Untuk diisi oleh Pegawai yang menyediakan baucer).
Sesalinan perakuan hendaklah dikembalikan kepada Jurukur Bahan/Wakil Pegawai Penguasa)
2 Bayaran wang pendahuluan yang telah dikeluarkan (Untuk diisi oleh Jurukur Bahan/Wakil Pegawai Penguasa)
3 Bayaran semula Wang Pendahuluan sehingga kini
4 Jumlah Wang Jaminan Yang Perlu Ditahan 125,389.68RM
* Termasuk Barang Tak Pasang, Pelarasan Turun Naik Harga, Tuntutan Bayaran Tambahan yang diluluskan
MAJLIS PERBANDARAN KULAI (MPKu)
PERAKUAN BAYARAN INTERIM NO : 3
Diberi Kuasa Untuk Memperakukan
Setiausaha /Pegawai Yang
…………………………………………………….
PERAKUAN BAYARAN INTERIM NO : 3
Amaun-amaun yang kena dibayar kepada Subkontraktor/ Pembekal Dinamakan, Penerima Hak dan Pegawai Penyelia Tapakbina
rJenis Kerja atau
BulanJumlah Harga
Jumlah Bayaran
Terdahulu
Amaun yang
diperakukan
(1) (3) (4) (5) (6)
A Perunding Kontraktor Utama
Nama :
Bank :
Alamat :
No. Akaun :
Jumlah Kecil
B Pembekal Dinamakan
Nama :
Bank :
Alamat :
No. Akaun :
Jumlah Kecil
C Penerima Hak
Nama : TEAMCOAT METALCARE Kontraktor 1,000,000.00RM 459,438.58RM 489,512.69RM
& DEVELOPMENT SDN BHD Utama
No. 40 Jalan Penaga 10,
Kaw. Perindustrian Kota Putri,
81750 Masai,
Johor Darul Takzim.
Bank : Affin Bank Berhad
Alamat : Taman Permas Jaya,
Johor Bahru, Johor
No. Akaun : 100730006258
Jumlah Kecil 489,512.69RM
D Pegawai Penyelia Tapak
Nama :
Bank :
Alamat :
No. Akaun :
Jumlah Kecil
Nota :
(2) Isikan nama subkontraktor/ penerima bayaran yang berkenaan
(3) Nyatakan jenis kerja atau bekalan atau bulan yang berkenaan bagi kategori Pegawai Penyelia. Tidak berkenaan bagi penerima hak.
(4) Isikan jumlah harga subkontraktor/ jumlah yang diserahhak. Tidak berkenaan bagi kategori pegawai penyelia.
Penerima Bayaran
(2)
Pegawai Pengesyor
18
Advance Payment on Work Contract
◼ The Contractor shall be entitled to an Advance
Payment on the Contract amounting to 25% of the
Builder's works* (subject to a maximum of RM10
Million) on compliance with the following conditions:-
◼ (i) On return of the Letter of Acceptance duly signed by
the Contractor together with the Performance Bond (if
any), Insurance Policies, confirmation from SOCSO
Authorities (if applicable) and the receipts for all
premium paid,
◼ (ii) Production of a Banker's Guarantee on a standard
approved format equal in value to the advance
proposed to be paid.
19
Advance Payment on Work Contract
◼ The advance payment shall be recouped when the cumulative total value of the Builder's Work executed and certified (including the amount certified for materials on site) in the Interim Certificate reaches twenty five (25) percent of the Contract value of Builder's Works*;
◼ By way of a fixed percentage from the total certified value of the Builder's Work executed (including the amount certified for the materials on site) during the period covered by the Interim Certificate, in all the subsequent Certificate on the basis that the Advance Payment made shall be fully recovered in the Interim Certificate in which the cumulative total certified value of Builder's Work executed (including the amount certified for materials on site) reaches seventy five percent (75%) of the total Contract value of the Builder's Work*.
20
Advance Payment on Work Contract
The deduction shall be calculated as follows:
RM A
◼ RM D = 200 --------- percent of RM P
RM B
Where ;
◼ RM D = Cumulative deduction to be made in Interim Cert.
◼ RM A = Total amount of Advance Payment paid
◼ RM B = Total Contract value of Builder's work*
◼ RM P = Gross certified value of Builder’s Work executed (including the amount certified for materials site) in excess of 25% of RM B.
*Contract Sum less P.C. Sums, Provisional Sums and Contingencies (if any).
21
Advance Payment on Work Contract
◼ The liability under the Bank Guarantee shall be terminated upon realization by the Government of the full sum of Advance paid.
◼ However if the full sum of the Advance paid cannot be realized before the completion date of the Contract or any authorised extension thereof or in the case of the contract been determined before the date of the determination, then the balance of the Advance repayable to the Government shall be recovered from the Bank Guarantee.
22
Advance Payment on Work Contract
◼ This special provision apply to Nominated
Sub-contractor or Nominated Supplier and
shall be entitled to an Advance Payment on
the Contract amounting to 20% of the
Package Value ( subject to a maximum of
RM5 million) on compliance with the same
conditions as stated in Surat Pekeliling
Perbendaharaan Bil. 10 Tahun 2002
(Tambahan Keenam SPP Bil. 2 Tahun
1995)).
Purposes of Interim Payment
◼To ensure that the Contractor is
regularly paid throughout the progress
of the works.
◼To maintain the Contractor’s cash-flow
and thus minimizing any deficit; which
may affect the smooth running of the
project.
◼To assist Contractor to overcome cash-
flow problems.23
◼To provide a source of self-financing in
respect of their own commitments to
suppliers and sub-contractors.
◼To relieve the contractor of the burden
of financing the whole of the works until
completion.
24
Purposes of Interim Payment cont’d
Procedure of Payment as per PAM
◼ The contractor is to submit a payment application at
interim claim intervals (if none stated 1 month).
◼ The application must include details that enable the
architect or QS to ascertain the amount due in the
interim certificate.
◼ Generally, the payment claim should include amounts
claimed for work performed, value of materials on
site, variations performed, amounts due to NSCs,
loss and expense claims, and amounts claimed
under any other provision of the contract. Due
allowance for retention money and amounts
previously certified.25
Procedure of Payment as per PAM
◼ On receipt of the contractor’s application, the QS must prepare
an interim valuation. The QS calculates the gross valuation of
the work carried out by the contractor to date.
◼ Within 21 days of receipt of the contractor’s application (and
after receiving the QS’s payment valuation), the architect is to
issue an interim certificate to the employer with a copy to the
contractor.
◼ Within 21 days from the date of the certificate, the employer
must pay the contractor the amount certified, subject to his
rights to set-off.
◼ If the employer fails to make payment within the specified time,
then the contractor is entitled to recover interest for late payment
calculated at a rate specified in the appendix.
26