Upload
pattabhi-ramaraju
View
259
Download
0
Embed Size (px)
Citation preview
7/22/2019 Internal Lining of Pressure Vessels
1/21
Abu Dhabi Company for Onshore Oil Operations
7/22/2019 Internal Lining of Pressure Vessels
2/21
Introduction
History
1st & 2nd Catastrophic Failures
New Selection Criteria
New Lining Systems
Inspection of the New Lining Systems
Conclusion & Recommendations
Internal Linings of High Pressure Vessels
211/12/2003 12:03 PM
7/22/2019 Internal Lining of Pressure Vessels
3/21
Operating Pressure : 100 Bar
Operating Temperature : 105 C
Date in Operation : April 2000
Material of Const. : CS-HICN 516-60 N
Design Code : ASME VIII
Shell Thickness : 114 mm
Inner Diameter : 2000 mm
Tang./Tang. : 6500 mm
Fluid : Wet Sour gas
H2S : 3.5 mole %
Chloride : 1500 ppm
CO2 : 4.5 mole %
INTRODUCTION OPERATING CONDITIONS
3
7/22/2019 Internal Lining of Pressure Vessels
4/21
INTRODUCTION OPERATING CONDITIONS
4
Typical 4 Nos. Test Separators
7/22/2019 Internal Lining of Pressure Vessels
5/21
Factory Applied Internal Lining by Ceramic Filled epoxy in Nov. 1998.
Test Separators Commissioning in Nov. 2000.
Catastrophic Failure in April 2001
Inspection
Initial Failure Route Causes
Field Re-lining Using the Same Lining
Same Pattern Catastrophic Failure After 45 Days
Inspection
Failure Route Causes
HISTORY
5
7/22/2019 Internal Lining of Pressure Vessels
6/21
1St Failure Inspection Findings:
Peel off and flaking on 80% of the entire surface
Total removal on 30% of the entire surface
Superficial rust under flaked off areas
2ndFailure Inspection Findings:
Peel off and flaking on lesser extent of the entire surface
Total removal on 30% of the entire surface
Superficial rust under flaked off areas
1st & 2nd CATASTROPHIC FAILURES
6
7/22/2019 Internal Lining of Pressure Vessels
7/21
7
Shell
Internal
Surface.
1st & 2nd CATASTROPHIC FAILURES
7/22/2019 Internal Lining of Pressure Vessels
8/21
8
Shell
Internal
Surface.
Manway Nozzles Internal.
1st & 2nd CATASTROPHIC FAILURES
7/22/2019 Internal Lining of Pressure Vessels
9/21
Failure Mechanism:i. High polymer X-linking materials above critical
value
ii. Broad thermal cycling effect
iii. Explosive Decompression due to dense polymerX-linking
iv. Aggressive environment
1st & 2nd CATASTROPHIC FAILURES
9
7/22/2019 Internal Lining of Pressure Vessels
10/21
No track records found for similar services.
Documented compliance with the requested materialperformance technical data sheet.
Unconditional full recovery of the contractvalue if the applied system exhibits any of thefollowing defects after 12 months of services.
i. Lining De-lamination.
ii. Blister free for single layer system.
iii. 10% surface blisters for multi-layer system.
NEW SELECTION CRITERIA
1
7/22/2019 Internal Lining of Pressure Vessels
11/21
iv. >5% coating cracks on top layer of multi layer liningsystem and cracks free single layer lining system.
iv. A reduction in average lining thickness in excess of 30%.
iv. 20% reduction in the adhesion forces between any two
adjacent layers or to the substrate, compared to thatmeasured prior to boxing up.
1
NEW SELECTION CRITERIA
7/22/2019 Internal Lining of Pressure Vessels
12/21
11 proposed lining systems.
8 Lining Manufacturers declined.
3 Manufacturers accepted the set criteria.
Epoxy Novolac resin (VOC 27%) applied onGRS-1 Test Separator.
Vinyl Ester Glass Flake applied on GRS-2 Test
Separator.
Solvent free two components hybridized epoxyapplied on GRS-3 & 4 Test Separators.
111/12/2003 12:03 PM
NEW LINING SYSTEMS
7/22/2019 Internal Lining of Pressure Vessels
13/21
INTERIM INSPECTION:
i. Conducted interim inspection within 3 monthsexposure.
ii.
GRS-1 Test Separator lining system was found insound conditions and fully meet the acceptancecriteria.
iii. Minor surface cracks within the acceptance
criteria were found on the GRS-2 TestSeparator.
iv. Catastrophic total failure was found on GRS-3 &4 Test Separators.
INSPECTION OF NEW LINING SYSTEMS
1
INSPECTION OF NEW LINING SYSTEMS
7/22/2019 Internal Lining of Pressure Vessels
14/21
INTERIM INSPECTION:
v. Decision made to continue the service on theGRS-1 & 2 Test in services for additional periodof six months and re-inspect.
vi. Postpone the decision on GRS-3&4 TestSeparators to get more concert data from GRS-1& 2 within 6 months. The two Separators wereout of services.
INSPECTION OF NEW LINING SYSTEMS
1
INSPECTION OF NEW LINING SYSTEMS
7/22/2019 Internal Lining of Pressure Vessels
15/21
Final Inspection:
i. GRS-1 Test Separator lining system was found insound conditions and fully meet the acceptancecriteria.
ii. Propagation of the surface cracks within theacceptance criteria were found on the GRS-2 TestSeparator.
INSPECTION OF NEW LINING SYSTEMS
1
GRS 2 Sepa ato Inte im Inspection Findings
7/22/2019 Internal Lining of Pressure Vessels
16/21
GRS-2 Separator Interim Inspection Findings
1
Coating in good condition at shell 9 OclockCoating in good condition at 2nd side man way
Small defects on the manway Small Surface crack
GRS 3 & 4 Separators Interim Inspection Findings
7/22/2019 Internal Lining of Pressure Vessels
17/21
111/12/2003 12:03 PM
GRS-3 & 4 Separators Interim Inspection Findings
Deposits and foreign broken metals parts
Peeled off coating at Demister Peeled of coating at buffle plate
Irregular coating at the top (looks like sagging)
GRS-3 & 4 Separators Interim Inspection Findings
7/22/2019 Internal Lining of Pressure Vessels
18/21
1
GRS-3 & 4 Separators Interim Inspection Findings
Peel off at the dish end manway Cracks and peel off at the demister
Peel of at the demisterBlisters at 3 Oclock and 9 Oclock
GRS 3&4 CATASTROPHIC FAILURES
7/22/2019 Internal Lining of Pressure Vessels
19/21
Failure Mechanism:
i. High polymer X-linking materials above criticalvalue
ii. Broad thermal cycle effect
iii. Explosive Decompression due to high polymerX-linking
iv. Aggressive environment
GRS-3&4 CATASTROPHIC FAILURES
1
CONCLUSION & RECOMMENDATIONS
7/22/2019 Internal Lining of Pressure Vessels
20/21
Both Epoxy Novolac resin and Glass Vinyl Ester lining
systems are acceptable for high pressure &temperature wet sour gas services.
Carry out the minor repairs on GRS-2 Test Separator
and return to services.
Box up GRS-1 Test separator and return to services.
Apply Epoxy Novolac resin lining system on GRS-3 &
4 test separators.
Conduct Off-stream inspection every two years.
CONCLUSION & RECOMMENDATIONS
2
7/22/2019 Internal Lining of Pressure Vessels
21/21
Abu Dhabi Company for Onshore Oil Operations