Internal Lining of Pressure Vessels

Embed Size (px)

Citation preview

  • 7/22/2019 Internal Lining of Pressure Vessels

    1/21

    Abu Dhabi Company for Onshore Oil Operations

  • 7/22/2019 Internal Lining of Pressure Vessels

    2/21

    Introduction

    History

    1st & 2nd Catastrophic Failures

    New Selection Criteria

    New Lining Systems

    Inspection of the New Lining Systems

    Conclusion & Recommendations

    Internal Linings of High Pressure Vessels

    211/12/2003 12:03 PM

  • 7/22/2019 Internal Lining of Pressure Vessels

    3/21

    Operating Pressure : 100 Bar

    Operating Temperature : 105 C

    Date in Operation : April 2000

    Material of Const. : CS-HICN 516-60 N

    Design Code : ASME VIII

    Shell Thickness : 114 mm

    Inner Diameter : 2000 mm

    Tang./Tang. : 6500 mm

    Fluid : Wet Sour gas

    H2S : 3.5 mole %

    Chloride : 1500 ppm

    CO2 : 4.5 mole %

    INTRODUCTION OPERATING CONDITIONS

    3

  • 7/22/2019 Internal Lining of Pressure Vessels

    4/21

    INTRODUCTION OPERATING CONDITIONS

    4

    Typical 4 Nos. Test Separators

  • 7/22/2019 Internal Lining of Pressure Vessels

    5/21

    Factory Applied Internal Lining by Ceramic Filled epoxy in Nov. 1998.

    Test Separators Commissioning in Nov. 2000.

    Catastrophic Failure in April 2001

    Inspection

    Initial Failure Route Causes

    Field Re-lining Using the Same Lining

    Same Pattern Catastrophic Failure After 45 Days

    Inspection

    Failure Route Causes

    HISTORY

    5

  • 7/22/2019 Internal Lining of Pressure Vessels

    6/21

    1St Failure Inspection Findings:

    Peel off and flaking on 80% of the entire surface

    Total removal on 30% of the entire surface

    Superficial rust under flaked off areas

    2ndFailure Inspection Findings:

    Peel off and flaking on lesser extent of the entire surface

    Total removal on 30% of the entire surface

    Superficial rust under flaked off areas

    1st & 2nd CATASTROPHIC FAILURES

    6

  • 7/22/2019 Internal Lining of Pressure Vessels

    7/21

    7

    Shell

    Internal

    Surface.

    1st & 2nd CATASTROPHIC FAILURES

  • 7/22/2019 Internal Lining of Pressure Vessels

    8/21

    8

    Shell

    Internal

    Surface.

    Manway Nozzles Internal.

    1st & 2nd CATASTROPHIC FAILURES

  • 7/22/2019 Internal Lining of Pressure Vessels

    9/21

    Failure Mechanism:i. High polymer X-linking materials above critical

    value

    ii. Broad thermal cycling effect

    iii. Explosive Decompression due to dense polymerX-linking

    iv. Aggressive environment

    1st & 2nd CATASTROPHIC FAILURES

    9

  • 7/22/2019 Internal Lining of Pressure Vessels

    10/21

    No track records found for similar services.

    Documented compliance with the requested materialperformance technical data sheet.

    Unconditional full recovery of the contractvalue if the applied system exhibits any of thefollowing defects after 12 months of services.

    i. Lining De-lamination.

    ii. Blister free for single layer system.

    iii. 10% surface blisters for multi-layer system.

    NEW SELECTION CRITERIA

    1

  • 7/22/2019 Internal Lining of Pressure Vessels

    11/21

    iv. >5% coating cracks on top layer of multi layer liningsystem and cracks free single layer lining system.

    iv. A reduction in average lining thickness in excess of 30%.

    iv. 20% reduction in the adhesion forces between any two

    adjacent layers or to the substrate, compared to thatmeasured prior to boxing up.

    1

    NEW SELECTION CRITERIA

  • 7/22/2019 Internal Lining of Pressure Vessels

    12/21

    11 proposed lining systems.

    8 Lining Manufacturers declined.

    3 Manufacturers accepted the set criteria.

    Epoxy Novolac resin (VOC 27%) applied onGRS-1 Test Separator.

    Vinyl Ester Glass Flake applied on GRS-2 Test

    Separator.

    Solvent free two components hybridized epoxyapplied on GRS-3 & 4 Test Separators.

    111/12/2003 12:03 PM

    NEW LINING SYSTEMS

  • 7/22/2019 Internal Lining of Pressure Vessels

    13/21

    INTERIM INSPECTION:

    i. Conducted interim inspection within 3 monthsexposure.

    ii.

    GRS-1 Test Separator lining system was found insound conditions and fully meet the acceptancecriteria.

    iii. Minor surface cracks within the acceptance

    criteria were found on the GRS-2 TestSeparator.

    iv. Catastrophic total failure was found on GRS-3 &4 Test Separators.

    INSPECTION OF NEW LINING SYSTEMS

    1

    INSPECTION OF NEW LINING SYSTEMS

  • 7/22/2019 Internal Lining of Pressure Vessels

    14/21

    INTERIM INSPECTION:

    v. Decision made to continue the service on theGRS-1 & 2 Test in services for additional periodof six months and re-inspect.

    vi. Postpone the decision on GRS-3&4 TestSeparators to get more concert data from GRS-1& 2 within 6 months. The two Separators wereout of services.

    INSPECTION OF NEW LINING SYSTEMS

    1

    INSPECTION OF NEW LINING SYSTEMS

  • 7/22/2019 Internal Lining of Pressure Vessels

    15/21

    Final Inspection:

    i. GRS-1 Test Separator lining system was found insound conditions and fully meet the acceptancecriteria.

    ii. Propagation of the surface cracks within theacceptance criteria were found on the GRS-2 TestSeparator.

    INSPECTION OF NEW LINING SYSTEMS

    1

    GRS 2 Sepa ato Inte im Inspection Findings

  • 7/22/2019 Internal Lining of Pressure Vessels

    16/21

    GRS-2 Separator Interim Inspection Findings

    1

    Coating in good condition at shell 9 OclockCoating in good condition at 2nd side man way

    Small defects on the manway Small Surface crack

    GRS 3 & 4 Separators Interim Inspection Findings

  • 7/22/2019 Internal Lining of Pressure Vessels

    17/21

    111/12/2003 12:03 PM

    GRS-3 & 4 Separators Interim Inspection Findings

    Deposits and foreign broken metals parts

    Peeled off coating at Demister Peeled of coating at buffle plate

    Irregular coating at the top (looks like sagging)

    GRS-3 & 4 Separators Interim Inspection Findings

  • 7/22/2019 Internal Lining of Pressure Vessels

    18/21

    1

    GRS-3 & 4 Separators Interim Inspection Findings

    Peel off at the dish end manway Cracks and peel off at the demister

    Peel of at the demisterBlisters at 3 Oclock and 9 Oclock

    GRS 3&4 CATASTROPHIC FAILURES

  • 7/22/2019 Internal Lining of Pressure Vessels

    19/21

    Failure Mechanism:

    i. High polymer X-linking materials above criticalvalue

    ii. Broad thermal cycle effect

    iii. Explosive Decompression due to high polymerX-linking

    iv. Aggressive environment

    GRS-3&4 CATASTROPHIC FAILURES

    1

    CONCLUSION & RECOMMENDATIONS

  • 7/22/2019 Internal Lining of Pressure Vessels

    20/21

    Both Epoxy Novolac resin and Glass Vinyl Ester lining

    systems are acceptable for high pressure &temperature wet sour gas services.

    Carry out the minor repairs on GRS-2 Test Separator

    and return to services.

    Box up GRS-1 Test separator and return to services.

    Apply Epoxy Novolac resin lining system on GRS-3 &

    4 test separators.

    Conduct Off-stream inspection every two years.

    CONCLUSION & RECOMMENDATIONS

    2

  • 7/22/2019 Internal Lining of Pressure Vessels

    21/21

    Abu Dhabi Company for Onshore Oil Operations