1
© 2011 Westinghouse Electric Company LLC. All Rights Reserved.
International Atomic Energy Agency 16th Meeting of the Technical Working Group
on Advanced Technologies for LWRs (UK LWR Activities)
Alan Palin Manager, Business Development Westinghouse Europe, Middle East & Africa (EMEA)
2
© 2011 Westinghouse Electric Company LLC. All Rights Reserved.
Contents
National Status of the UK Programme
Applying New Technologies to existing plant
Impact of Fukushima
Questions
3
© 2011 Westinghouse Electric Company LLC. All Rights Reserved.
National Status of the UK Programme
An update from July 2010
Sourced Material
4
© 2011 Westinghouse Electric Company LLC. All Rights Reserved.
UK Perspective
• Between now and 2020 – 12GW of oil & coal closes as result
of Large Combustion Plant Directive – 7GW of nuclear closes from end of
Magnox and closure of 5 of the 7 AGRs
• Gap between predicted demand & supply
• Government Policy now supportive of new nuclear build
– New approach to licensing – Reliant on Utilities to fund
investment – Utilities pushing for higher carbon
prices to support investment in nuclear vs coal
Loss of capacity & carbon concerns => UK Government Policy of new nuclear build
5
© 2011 Westinghouse Electric Company LLC. All Rights Reserved.
Nominated & approved sites 1.Bradwell, Essex,
• NDA 2. Hartlepool, Durham,
• EDF Energy 3. Heysham, Lancashire,
• EDF Energy 4. Hinkley Point, Somerset,
• EDF Energy 5. Oldbury, Gloucestershire,
• Horizon 6. Sellafield, Cumbria,
• NuGen 7. Sizewell, Suffolk,
• EDF Energy 8. Wylfa, Anglesey,
• Horizon
Sourced Material
6
© 2011 Westinghouse Electric Company LLC. All Rights Reserved.
EDF Energy UK (EDF Energy/Centrica Joint Venture) 2 x 1600 MW EPRs for Hinkley 2 x 1600 MW EPRs for Sizewell 1st operating 2018, 4 by 2025 second tranche to follow
NuGeneration Ltd (Iberdrola/GDF Suez/SSE Joint Venture) Up to 3600MW operating by 2025 Technology to be decided
Horizon Nuclear Power Ltd (RWE/EoN Joint Venture) 6000 MW operating by 2025 Technology to be decided in 2011
New Build Plans for UK
Sourced Material
7
© 2011 Westinghouse Electric Company LLC. All Rights Reserved.
Where are we now…
Justification: Completed October 2010
Electricity Market Reform: Consultation closed 11th March 2011
National Policy Statements:
Granted 18th July 2011
Fukushima: 11th March 2011
Weightmen Report:
Commissioned in end March 2011
Interim GDA: Conclusions, Expected Dec 2011
Investment approval for first plant: Expected 2012
Update on New Build since July 2010 ……
Sourced Material
8
© 2011 Westinghouse Electric Company LLC. All Rights Reserved.
Applying New Technologies to Existing Plant
Power Up-rating in the UK – comparisons with Europe
9
© 2011 Westinghouse Electric Company LLC. All Rights Reserved.
Typical Uprate Work Scope
NSSS Scope Fuel Safety Analyses Systems & Components
BOP Scope Systems & Components Design Change Packages Installation
T/G Scope HP Turbine upgrade/mods Generator Rewind/Replacement
Licensing Scope License Amendment Request FSAR, Tech Spec, etc
Environmental Impact State, Federal, Local
Grid Impact Studies Outage Planning Training, simulator, procedures,
etc
10
© 2011 Westinghouse Electric Company LLC. All Rights Reserved.
Types of Power Uprates
Measurement Uncertainty Recapture (MUR) Power Uprate: 1%<X<2%
Taking credit for a way to reduce inaccuracy in feed water flow measurement hence more accurate calculation of power calorimetric
Stretch Power Uprate (SPU): 2%<X<7% Within the design capacity of the plant; Usually involves changes to
instrumentation setpoints but NOT major plant modifications
Extended Power Uprate (EPU): X > 7% EPUs require significant modifications to major BOP equipment (e.g., high-
pressure turbines, condensate pumps & motors, main generators and/or transformers)
MUR COMPLETED 34 Americas PWRs 5 European PWRs
2 Asian PWRs 1 in UK - Sizewell B
SPU COMPLETED 42 Americas PWRs 2 European PWRs
4 Asian PWRs
EPU COMPLETED 13 Americas PWRs 10 European PWRs
11
© 2011 Westinghouse Electric Company LLC. All Rights Reserved.
Uprate Comparison
• Uprates provide additional generating capacity with relatively low site implementation
& licensing risk
12
© 2011 Westinghouse Electric Company LLC. All Rights Reserved.
The impact of Fukushima
The Weightman Report and its impact on the AP1000
13
© 2011 Westinghouse Electric Company LLC. All Rights Reserved.
Secretary of State for Energy and Climate Change, Rt. Hon Chris Huhne MP: “Safety is and will continue to be our number one priority. I am pleased that today’s report confirms that the UK’s current safety arrangements are working.”
Chief Nuclear Inspector, Dr. Mike Weightman: “The extreme natural events that preceded the accident at Fukushima – the magnitude 9 earthquake and subsequent huge tsunami – are not credible in the UK…But we are not complacent. No matter what the differences are, and how high the standard of design and subsequent operation of the nuclear facilities here in the UK, the quest for improvement must never stop.”
Interim report on Fukushima by the Chief Nuclear Inspector
Sourced Material
14
© 2011 Westinghouse Electric Company LLC. All Rights Reserved.
UK GDA - Weightman Report
The Interim Weightman Report outlines 26 recommendations, it groups these recommendations into a number of sub categories including: - General Relevant to the Regulator Relevant to the Nuclear Industry Way Forward
Response on interim report requested by 15 June Westinghouse response has been provided
commenting on recommendations relevant to nuclear industry
Response will be made public, timing likely to align with issuance of final Weightman report
15
© 2011 Westinghouse Electric Company LLC. All Rights Reserved.
Major Safety Advancements of AP1000 Event/Threats Response Summary
Events /Threats Westinghouse AP1000
Earthquakes and Floods
Seismic Design: AP1000 designed to withstand an earthquake that would happen once in every 10,000 years. Plants are being sited in seismically stable regions Robust: Designed to withstand other natural disasters: flooding, tornados, tsunamis, hurricanes.
Earthquakes and Floods
AP1000 can be safely shut down and maintained during a station blackout for 7 days. The advanced passive safety features rely on natural forces such as gravity, natural circulation, condensation and convection. The ultimate heat sink is the atmosphere. Power Sources Redundant safety-related DC batteries support safe shutdown for 72 hours (3 days). Two redundant 80 kw ancillary diesel generators provide cooling water to the
containment shell and spent fuel pool. Ancillary diesels can run for 4 days with no offsite support.
Two redundant 4 MW standby diesel generators can power equipment for 7 days with no offsite support (not required to cope with station blackout)
Water Sources Passive Containment Cooling Tank provides cooling to the containment shell for 72
hours Ancillary Storage Tank provides cooling to the containment shell and to the spent fuel
pool after 72 hours for a period for 4 more days
16
© 2011 Westinghouse Electric Company LLC. All Rights Reserved.
Major Safety Advancements of AP1000 Event/Threats Response Summary
Events /Threats Westinghouse AP1000
Containment Integrity
Containment Design: The 44.5 mm (1¾”) steel containment is a high integrity steel pressure vessel surrounded by a shield building that protects it from missiles, including aircraft impact. Hydrogen Management: Battery powered hydrogen igniters & passive hydrogen recombiners prevent explosions
Spent Fuel Pool Integrity and Cooling
Structure: Spent fuel pool features 1+ m (3-5’) thick, heavily reinforced concrete structures lined with steel Makeup Water: Spent fuel will remain covered with water sources located in the spent fuel building for at least 3 days. Following 3 days, water is provided by the ancillary storage tank. Robust Building: Designed for protection against seismic events, natural disasters and aircraft impact.
Control Room Habitability
Heavily shielded room with a 72-hour air-pressurization system. Control room dose minimal
17
© 2011 Westinghouse Electric Company LLC. All Rights Reserved.
Questions