International Cost Standard

Embed Size (px)

Citation preview

  • 8/10/2019 International Cost Standard

    1/42

    making the difference

    International

    construction

    cost survey

    2012

  • 8/10/2019 International Cost Standard

    2/42

    making the difference 1

    Introduction 2

    Country profiles

    Australia 8

    Canada 10

    China 12

    Germany 14

    India 16

    Ireland 18

    Japan 20

    Malaysia 22

    Russia 24

    Singapore 26

    South Africa 28

    South Korea 30

    UAE 32

    UK 34

    US 36

    Vietnam 38

    Contributors 40

    In this survey, trade, labour and material prices and prices per square metre are indicative, and should

    not be relied on. Costs are dependent on building design, inclusions, exclusions and site conditions. Cost

    comparisons between countries are subject to different interpretations, building methods, and standards

    for costing, measurement and construction. Costs may vary substantially between countries within regions.

    Professional advice should always be sought.

    Comparative values are based on average exchange rates for the calendar year 2011.

    Turner & Townsend plc 2012

    Contents

  • 8/10/2019 International Cost Standard

    3/42

    International construction cost survey 2012

    2 Turner & Townsend

    All the cost data presented here has come

    from our own professionals working in the

    commercial construction sector across the

    globe at the end of 2011. Our thanks go

    to them for their invaluable input.

    We welcome your feedback on ways we

    can improve it in future. If you have any

    comments on this survey or would like

    any further information, please contact:

    [email protected]

    For further information on our services,

    please visit www.turnerandtownsend.com

    or contact your nearest office.

    Whats happened since the last survey?

    2011 was a tough year for construction

    businesses in many countries. 2012 lookslike being a similar story but there are some

    reasons to be optimistic.

    At the beginning of 2012 most economies are still

    feeling the fallout from the global financial crisis

    (GFC) and recovery is still some years away.

    But the US economy is showing signs of working

    through its problems of spiralling budget deficits

    and housing oversupply, even though there

    is still much to be done. US unemployment is

    showing signs of easing and was at 8.5 percent

    in December 2011.

    Introduction

    Welcome to the 2012 edition of our International construction

    cost survey. In this survey you can find and compare

    construction, materials and labour costs and market

    conditions across many of the countries in which we operate.

    London Bridge Quarter, the Shard

    The focal point for a major commercial development in the heart

    of London, the Shard will be the tallest building in western Europe.

    Construction costs in most

    regions are expected to stay

    moderate during 2012.

    Barring natural disasters and

    other surprises, 2012 offers

    a window of opportunity to

    build your project on time

    and perhaps under budget.

  • 8/10/2019 International Cost Standard

    4/42

    making the difference 3

    In Europe the problems that started in Ireland

    and Greece have spread to Portugal, Italy and

    Spain. Falling asset values, high unemployment

    and crippling government debt in several of

    the Euro member countries are likely to result

    in economic weakness in 2012.

    In the US and Europe, governments are

    running out of policy levers, be they monetary

    stimulus or austerity measures such as higher

    taxes and pay cuts. Politically difficult as

    austerity measures are, they also prolong and

    exacerbate the downturn, as demand and

    consumption falls. This sets the retail, property

    and construction sectors on a downwards spiral.

    Those countries which introduced stimulus

    measures to boost their economies and

    construction sectors have mostly spent their

    stimulus budgets and there are few remaining

    policy levers or alternative stimuli to help their

    economies achieve self-sustaining growth.

    But with time businesses restructure, reduce

    their cost base, recapitalise and prepare for

    the future. The US seems to be at this stage

    of recovery in many sectors including the

    construction sector. The US went into the

    GFC first and so logically it will emerge first.

    In 2012 the US construction data should start

    to improve.

    The effects of the continuing difficulties

    in the developed economies are being felt

    everywhere, even in the growth economies

    of Asia, South America and Africa, through

    reduced international trade, tightening credit

    markets, falling share markets, lower retirement

    fund balances and lower house prices. Public

    infrastructure budgets have been cut, public

    works projects delayed and consumers are

    saving more, paying off debt, consuming less,

    and exercising caution. These are all good

    virtues after years of credit-fuelled growth,

    but demand is lower, and the construction

    sector struggles to find projects.

    However, worldwide there are many reasons to

    be optimistic. The Chinese, Indian, Vietnamese

    and African economies are on long-term

    growth paths that will improve living standards,

    creating jobs and opportunities for their

    people and the economies which supply them.

    There is still a long way to go so the demand

    for resources and skills will grow.

    The demand for energy and resources is driving

    the growth of many new projects in natural

    resources, gas, coal shale and renewable

    energies in countries as diverse as Australia,

    Kazakhstan, Mauritania, Brazil and the US,

    creating jobs, driving construction and wealth.

    South Africa is transforming its power sector

    with major investments in power stations.

    Australia has introduced a carbon tax that

    will eventually force the replacement of coal

    power stations with cleaner alternatives.

    Communications networks are being built, or

    upgraded as high-speed internet becomes global.

    Siemens City, Vienna

    World-class, energy-efficient construction, delivered to meticulously

    engineered costs, certified to US Green Building Gold standard.

  • 8/10/2019 International Cost Standard

    5/42

    International construction cost survey 2012

    4 Turner & Townsend

    Worldwide, these projects add up to a

    substantial portfolio of long-term construction

    work. It is a good time to build. Construction

    costs are generally benign as shown by our

    surveys. In most regions the markets are not

    overheated like they were in the last decade.

    That means projects are more likely to be

    built on time and budget. Contractors have

    retained their most skilled labour and many of

    the casuals employed when work is plentiful

    have left to pursue other opportunities.

    In many countries the construction sector

    is now very competitive and tendered prices

    often come in below budget. The surveys

    show that construction costs in half of the

    countries surveyed are still below 2008

    levels. Most of our respondents indicated

    that labour rates were well under control.

    Materials prices are also competitive. Commodity

    prices increased alarmingly in early 2011 but

    have now fallen. Steel prices fell in late 2011.

    Lower coking coal and iron ore prices indicate

    that steel could be cheaper in 2012. Copperprices have also fallen by 20 percent since March

    2011 which should mean cheaper costs for some

    electrical and plumbing materials in 2012.

    All of this bodes well for construction costs in

    2012 with forecast cost increases in line with

    2011. In other words, construction costs in

    most regions are expected to stay moderate

    during 2012. Barring natural disasters and

    other surprises, 2012 offers a window of

    opportunity to build your project on time

    and perhaps under budget.

    Part of the reason why construction markets

    are so competitive is that housing and

    non-residential building construction is hardly

    increasing in most developed economies,

    because there is little, if any, price growth.

    Eventually, this cyclical downturn will end as the

    fundamentals of supply and demand reassert.

    Housing markets will recover, consumers will

    start to borrow and spend again. The cycle

    will turn, and when it does costs will increase

    again as building, resources and infrastructure

    projects compete for resources and skills.

    Alstom Hydro, China

    Multiform energy-saving technologies are helping to make this

    146,000 m2hydropower manufacturing facility fully carbon neutral.

    King Edward VII Memorial Hospital, Bermuda

    The first P3 (PPP) project in Bermuda is being delivered using

    local contractors for stakeholders in the US, Europe and Bermuda.

  • 8/10/2019 International Cost Standard

    6/42

    making the difference 5

    Cost index high-rise apartments

    Cost Index2008=100 2008 2009 2010 2011

    Australia 100 96 94 96

    Canada 100 95 94 100

    China 100 78 80 81

    Germany 100 101 101 104

    India 100 100 117 150

    Ireland 100 92 85 83

    Malaysia 100 98 111 130

    Russia 100 105 98 100

    Singapore 100 74 79 79

    South Africa 100 107 107 107

    South Korea 100 99 99 99

    UAE 100 94 89 72

    UK 100 98 98 101

    US 100 99 97 101

    Vietnam 100 117 125 141

    Cost index CBD offices

    Cost Index2008=100 2008 2009 2010 2011

    Australia 100 96 96 97

    Canada 100 96 95 98

    China 100 82 84 89

    Germany 100 101 101 104

    India 100 105 112 140

    Ireland 100 78 72 71

    Malaysia 100 97 101 117

    Russia 100 105 99 100

    Singapore 100 83 83 83

    South Africa 100 121 121 121

    South Korea 100 99 99 99

    UAE 100 96 92 83

    UK 100 91 91 94

    US 100 97 94 97

    Vietnam 100 117 125 141

    The above two charts show construction costs indexed to 2008=100 for each region in the survey

    (except Japan). The indices are based on nominal costs in $/m2in the currency of the country.

    The indices show the increase or fall from year to year. The data indicates that in most regions

    construction costs have recovered to 2008 levels although China, Ireland, Singapore and the UAE

    are still substantially below. Between 2010 and 2011 India, Vietnam and Malaysia saw costs increase

    strongly. Conversely, the UAE has experienced quite strong price falls between 2010 and 2011.

    Moderate cost escalation is expected once again in 2012 following only moderate cost increases

    in most regions during 2011. The exceptions are India and South Africa where higher escalation

    is forecast by our teams on the ground. In Japan prices are forecast to fall slightly.

    0.0% 2.0% 4.0% 6.0% 8.0% 10.0%

    Estimated cost escalation 2012

    Canada

    Australia

    ChinaGermany

    India

    Ireland

    Japan

    Malaysia

    Russia

    Singapore

    South Africa

    South Korea

    UAE

    UK

    US

    Vietnam

  • 8/10/2019 International Cost Standard

    7/42

    International construction cost survey 2012

    6 Turner & Townsend

    Key economic indicators

    Ination

    2011

    GDP

    2011

    GDP forecast

    2012

    Unemployment

    rate

    Australia 2.6 2.1 3.3 5.2

    Canada 2.5 2.1 1.9 7.6

    China 4.0 9.5 9.0 4.0

    Germany 2.5 2.7 1.3 6.0

    India 10.6 7.8 7.5 9.5

    Ireland 2.2 0.4 1.5 14.3

    Japan 0.4 0.5 2.3 4.9

    Malaysia 3.3 5.2 5.1 3.2

    Russia 7.5 4.3 4.1 7.3

    Singapore 5.5 5.3 4.3 2.3

    South Africa 6.0 3.4 3.6 24.5

    South Korea 4.3 3.9 4.4 3.3

    UAE 2.5 3.3 3.8 4.3

    UK 4.5 1.1 1.6 7.8

    US 3.9 1.5 1.8 9.1

    Vietnam 22.0 5.8 6.3 5.0

    Cold Lukewarm Warm Hot Overheating

    Ireland Australia Germany

    South Korea Canada India

    UK China South Africa

    Japan

    Malaysia

    Russia

    Singapore

    UAE

    US

    Vietnam

    Cooler Staying the same Warmer

    Canada Australia Germany

    China Ireland India

    Vietnam Japan Russia

    Malaysia

    Singapore

    South Africa

    South Korea

    UAE

    UK

    US

    The information from which this

    survey is compiled has been provided

    by Turner & Townsend professionals

    based in 16 countries and regions.

    Our respondents have also provided

    their views on current and anticipated

    market conditions.

    How would you describe current market

    tendering conditions?

    Is the construction market getting warmer,cooler or staying the same?

  • 8/10/2019 International Cost Standard

    8/42

    making the difference 7

    Typical preliminaries as a percentage of total costs

    0.0% 2.0% 4.0% 6.0% 8.0% 10.0% 12.0% 14.0% 16.0% 18.0% 20.0%

    Canada

    Australia

    China

    Germany

    India

    Ireland

    Japan

    Malaysia

    Russia

    SingaporeSouth Africa

    South Korea

    UAE

    UK

    US

    Vietnam

    Contractors margin has been squeezed in those countries where work volumes have fallen and

    contractors have to compete more vigorously. With fewer jobs contractors will often submit

    very competitive prices just to keep work flowing. Often sub-contractor prices may be equally

    competitive allowing head contractors to claw back some lost margin during the job.

    Preliminaries include job set-up costs, such as scaffolding, approvals, insurances, power and

    water, cleaning and handover, and work supervision. Typically, higher cost countries have higher

    preliminaries. In many countries costs of power and water are increasing. Also regulatory

    compliance adds further preliminary costs.

    Typical contractors margin on medium commercial job (5000m2GFA)

    0.0% 2.0% 4.0% 6.0% 8.0% 10.0% 12.0% 14.0% 16.0%

    Canada

    Australia

    China

    Germany

    India

    Ireland

    Japan

    Malaysia

    Russia

    Singapore

    South Africa

    South Korea

    UAE

    UK

    US

    Vietnam

  • 8/10/2019 International Cost Standard

    9/42

    International construction cost survey 2012

    8 Turner & Townsend

    Australia

    The Australian construction market is lukewarm at best with weak consumer confidence and

    falling house prices deterring residential construction in most states. Commercial construction

    is also weak with some oversupply from the previous boom. Tendering is competitive for thelimited number of new private construction projects coming to the market. However, construction

    of an unprecedented pipeline of resources and energy projects is ramping up. Gradually, this is

    expected to increase construction costs as shortages of trade skills, engineering and management

    worsen. Further adding to costs, a carbon tax was recently legislated and a mining profits tax

    is currently in the final stages of debate prior to passing into legislation.

    Country profiles

    Australia international building costs per m2of internal area

    2008 2009 2010 2011 2011

    AUD AUD AUD AUD USD

    Residential

    Detached house medium standard 1,518 1,445 1,445 1,474 1,517

    Detached house prestige 2,250 2,150 2,100 2,142 2,205

    Townhouse medium standard 1,715 1,640 1,650 1,683 1,732

    Apartments private medium density 2,050 1,950 1,900 1,938 1,995

    Apartments high rise 2,500 2,400 2,350 2,397 2,467

    Aged care/affordable unit 2,400 2,300 2,260 2,305 2,373

    Commercial

    Offices business park 1,895 1,820 1,820 1,838 1,892

    CBD offices up to 20 floors medium 3,000 2,880 2,880 2,909 2,994

    CBD offices prestige 3,360 3,200 3,200 3,232 3,327

    Warehouses

    Warehouse/factory unit basic 830 750 760 768 790

    Large warehouse distribution centre 640 590 600 606 624

    High-tech factory/laboratory 1,540 1,500 1,500 1,515 1,559

    Retail

    Large shopping centre including mall 2,200 2,150 2,150 2,172 2,235

    Neighbourhood including supermarket 1,810 1,750 1,750 1,768 1,819

    Prestige car showroom 4,400 4,200 4,200 4,242 4,366

    Hotels

    Three-star travellers 2,840 2,800 3,247 3,279 3,376

    Five-star luxury 3,850 3,750 3,750 3,788 3,899

    Resort style 4,185 4,000 4,000 4,040 4,158

    Hospitals

    Day centre 2,900 2,900 2,900 2,929 3,015

    Regional hospital 3,300 3,270 3,270 3,303 3,400

    General hospital 5,500 5,300 5,134 5,185 5,337

    Schools

    Primary and secondary 1,985 1,900 1,900 1,919 1,975

    University 3,130 3,050 3,050 3,081 3,171

    Carparks

    Multistorey above ground 850 832 800 808 832

    Multistorey below ground 1,250 1,235 1,173 1,185 1,219

    Airports

    Airport terminal 8,000 7,000 6,500 6,565 6,757

  • 8/10/2019 International Cost Standard

    10/42

    making the difference 9

    Australia major projects

    AUD

    Chevron Gorgon 43bn

    Chevron Wheatstone 30bn

    APLNG Gladstone 16bn

    BHP Olympic Dam 30bnSantos GLNG 16bn

    Australia hourly cost of labour (including overheads)

    2010 2011 2011

    AUD AUD USD

    Group 1 tradesman eg plumber, electrician 65 68 70

    Group 2 tradesman eg carpenter, bricklayer 55 57 59Group 3 tradesman eg carpet layer, tiler, plasterer 53 55 57

    General labourer 37 38 40

    Site foreman 69 72 75

    Australia costs of materials

    Concrete 30 mpa (m3) (1,500m3job) 186 186 191

    Reinforcement bar 16mm (tonne) (120 tonne job) 1,300 1,250 1,286

    Concrete block (400 x 200) per 1,000 (>10,000 block job) 3,360 3,360 3,459

    Standard brick per 1,000 541 541 557

    Structural steel beams (tonne) (>100 tonne job) 2,955 2,955 3,042

    Glass pane 6mm (m2) 47 47 48Softwood timber for framing 100mm x 50mm (m) 29 29 30

    Plasterboard 13mm (m2) 39 39 40

    Emulsion paint (litre) 15 15 15

    Copper pipe 15mm (m) (>1,000m job) 12 12 12

    Copper cable (m) (3C + E, 2.5mm PVC) (>100,000m job) 5 5 5

    Australia key trades (excluding preliminaries and builders margins)

    Excavate basement (m3) (1,800m3job) 29 29 30

    Excavate footings (m) 71 71 73

    Concrete in slab (m3) (1,500m3job) 256 256 264

    Reinforcement in beams (tonne) 2,442 2,442 2,514Formwork to soffit of slab (m2) 120 120 124

    Blockwork in wall (m2) (10,000 block job) 131 131 135

    Structural steel beams (tonne) 6,298 6,298 6,483

    Pre-cast concrete wall (m2) 299 299 308

    Curtain wall glazing incl support system (m2) (1,000m2job) 1,051 1,051 1,082

    Plasterboard 13mm thick to stud wall (m2) (3,000m2job) 30 30 31

    Single solid core door incl frame and hardware (no) (50 door job) 765 765 787

    Painting to walls primer + 2 coats (m2) 15 15 15

    Ceramic tiling (m2) (1,000m2job) 109 109 112

    Vinyl flooring to wet areas (m2) (500m2job) 71 71 73

    Carpet medium tufted (m2) (4,500m2job) 80 80 82

    Lighting installation (m2

    ) (>5,000m2

    job) 81 81 83Copper pipe 15mm to wall (m) (>1,000m job) 60 60 62

    Fire sprinklers (per m2) (5,000m2job) 46 46 47

    Air conditioning incl main plant (m2) (>5,000m2job) 300 300 309

  • 8/10/2019 International Cost Standard

    11/42

    International construction cost survey 2012

    10 Turner & Townsend

    Canada

    At present the construction market in Canada is moderate to slow. Public investment in

    infrastructure and rail projects is the dominant construction type, whereas private sector

    development is quite weak. The housing construction market is slowing. Tendering is

    competitive and wage increases have remained moderate on a weaker outlook and concerns

    over Europe. Gradually, the economy will be boosted by strong mining investment helping to

    stimulate ancillary businesses and the resumption of stronger building construction levels.

    Canada international building costs per m2of internal area

    2008 2009 2010 2011 2011

    CAD CAD CAD CAD USD

    Residential

    Detached house medium standard 3,000 2,750 2,700 2,800 2,836

    Detached house prestige 4,000 3,750 3,700 3,800 3,849

    Townhouse medium standard 1,379 1,313 1,300 1,400 1,418

    Apartments private medium density 1,909 1,818 1,800 1,900 1,925

    Apartments high rise 1,697 1,616 1,600 1,700 1,722

    Aged care/affordable units 2,057 1,959 1,940 2,000 2,026

    Commercial

    Offices business park 1,696 1,616 1,600 1,700 1,722

    CBD offices up to 20 floors medium 2,047 1,970 1,950 2,000 2,026

    CBD offices prestige 2,968 2,828 2,800 2,900 2,938

    Warehouses

    Warehouse/factory unit basic 912 869 860 900 912

    Large warehouse distribution centre 1,007 960 950 1,000 1,013

    High-tech factory/laboratory 1,378 1,313 1,300 1,400 1,418

    Retail

    Large shopping centre including mall 1,378 1,313 1,300 1,400 1,418

    Neighbourhood including supermarket 1,166 1,111 1,100 1,200 1,216

    Prestige car showroom 1,484 1,414 1,400 1,500 1,520

    Hotels

    Three-star travellers 1,378 1,313 1,300 1,400 1,418

    Five-star luxury 2,862 2,727 2,700 2,800 2,836

    Resort style 2,862 2,727 2,700 2,800 2,836

    Hospitals

    Day centre 3,710 3,535 3,500 3,700 3,748

    Regional hospital 5,724 5,454 5,400 5,700 5,774General hospital 6,890 6,565 6,500 6,800 6,888

    Schools

    Primary and secondary 1,802 1,717 1,700 1,800 1,823

    University 3,498 3,333 3,300 3,500 3,546

    Carparks

    Multistorey above ground 795 758 750 800 810

    Multistorey below ground 1,060 1,010 1,000 1,100 1,114

    Airports

    Airport terminal 5,724 5,454 5,400 5,700 5,774

  • 8/10/2019 International Cost Standard

    12/42

    making the difference 11

    Canada major projects

    CAD

    Halton Region Hospital 1bn

    Humber River Regional Hospital 1bn

    Air Rail Link 310m

    Union Station Revitalisation 640mToronto-York Spadina Subway Extension 2.6bn

    Canada hourly cost of labour (including overheads)

    2010 2011 2011

    CAD CAD USD

    Group 1 tradesman eg plumber, electrician 60 60 61

    Group 2 tradesman eg carpenter, bricklayer 55 55 56Group 3 tradesman eg carpet layer, tiler, plasterer 50 50 51

    General labourer 45 45 46

    Site foreman 75 75 76

    Canada costs of materials

    Concrete 30 mpa (m3) (1,500m3job) 150 165 167

    Reinforcement bar 16mm (tonne) (120 tonne job) 1,200 1,350 1,368

    Concrete block (400 x 200) per 1,000 (>10,000 block job) 700 725 734

    Standard brick per 1,000 900 900 912

    Structural steel beams (tonne) (>100 tonne job) 2,000 2,100 2,127

    Glass pane 6mm (m2) 165 165 167Softwood timber for framing 100mm x 50mm (m) 25 25 25

    Plasterboard 13mm (m2) 10 10 10

    Emulsion paint (litre) 10 10 10

    Copper pipe 15mm (m) (>1,000m job) 6 10 10

    Copper cable (m) (3C + E, 2.5mm PVC) (>100,000m job) 4 7 7

    Canada key trades (excluding preliminaries and builders margins)

    Excavate basement (m3) (1,800m3job) 15 15 15

    Excavate footings (m) 20 20 20

    Concrete in slab (m3) (1,500m3job) 190 190 192

    Reinforcement in beams (tonne) 1,800 1,900 1,925Formwork to soffit of slab (m2) 140 140 142

    Blockwork in wall (m2) (10,000 block job) 120 120 122

    Structural steel beams (tonne) 3,000 3,250 3,292

    Pre-cast concrete wall (m2) 300 325 329

    Curtain wall glazing incl support system (m2) (1,000m2job) 900 925 937

    Plasterboard 13mm thick to stud wall (m2) (3,000m2job) 25 25 25

    Single solid core door incl frame and hardware (no) (50 door job) 1,500 1,600 1,621

    Painting to walls primer + 2 coats (m2) 8 10 10

    Ceramic tiling (m2) (1,000m2job) 85 85 86

    Vinyl flooring to wet areas (m2) (500m2job) 60 65 66

    Carpet medium tufted (m2) (4,500m2job) 55 55 56

    Lighting installation (m2

    ) (>5,000m2

    job) 50 50 51Copper pipe 15mm to wall (m) (>1,000m job) 65 65 66

    Fire sprinklers (per m2) (5,000m2job) 35 35 35

    Air conditioning incl main plant (m2) (>5,000m2job) 310 310 314

  • 8/10/2019 International Cost Standard

    13/42

    International construction cost survey 2012

    12 Turner & Townsend

    China

    Construction demand in China fell by as much as ten percent over the last six months because of

    government measures introduced late last year to moderate growth to more sustainable levels, curb

    the sharp spike in property prices and reduce inflationary pressures. These included restrictions on

    pre-sales, restrictions on loans for purchases of third homes, higher minimum mortgage rates and

    tighter financing for second-home purchases. Property transactions in the key cities of Beijing,

    Shanghai and Shenzen have fallen strongly in response. Weaker demand for Chinese exports

    threatens to slow manufacturing growth in 2012, however the Chinese Government has strong

    reserves and policies to stimulate the economy if the global economy does deteriorate further.

    China international building costs per m2of internal area

    2008 2009 2010 2011 2011

    CNY CNY CNY CNY USD

    Residential

    Detached house medium standard 5,800 4,400 4,480 4,540 699

    Detached house prestige 6,500 5,100 5,170 5,240 806

    Townhouse medium standard 4,800 4,000 4,050 4,110 632

    Apartments private medium density 4,500 3,200 3,290 3,330 512

    Apartments high rise 5,000 3,900 3,980 4,030 620

    Aged care/affordable units 3,700 2,600 2,670 2,710 417

    Commercial

    Offices business park 5,500 4,400 4,500 4,690 722

    CBD offices up to 20 floors medium 8,400 6,900 7,090 7,450 1,146

    CBD offices prestige 10,500 8,900 9,140 9,300 1,431

    Warehouses

    Warehouse/factory unit basic 3,000 2,300 2,360 2,580 397

    Large warehouse distribution centre 3,300 2,700 2,780 3,050 469

    High-tech factory/laboratory 6,100 5,300 5,450 5,870 903

    Retail

    Large shopping centre including mall 7,500 5,900 6,080 6,180 951

    Neighbourhood including supermarket 5,100 4,000 4,120 4,220 649

    Prestige car showroom 3,900 3,400 3,500 3,650 562

    Hotels

    Three-star travellers 6,800 5,500 5,660 5,780 889

    Five-star luxury 11,300 10,000 10,300 10,540 1,622

    Resort style 9,100 8,300 8,550 8,750 1,346

    Hospitals

    Day centre 4,500 4,200 4,320 4,410 679

    Regional hospital 5,500 5,100 5,250 5,350 823

    General hospital 6,100 5,700 5,870 5,980 920

    Schools

    Primary and secondary 3,800 3,500 3,610 3,640 560

    University 5,700 5,200 5,350 5,390 829

    Carparks

    Multistorey above ground 2,200 2,000 2,080 2,140 329

    Multistorey below ground 5,300 4,500 4,640 4,780 736

    Airports

    Airport terminal 11,500 10,300 10,600 10,900 1,677

  • 8/10/2019 International Cost Standard

    14/42

    making the difference 13

    China major projects

    CNY

    National Trunk Road Network 900bn

    SouthNorth Water Transfer 500bn

    Silk Road Renaissance 330bn

    Tianjin Binhai New Area 1tnChinas Renewable Energy Development Plan 2tn

    China hourly cost of labour (including overheads)

    2010 2011 2011

    CNY CNY USD

    Group 1 tradesman eg plumber, electrician 19 22 3

    Group 2 tradesman eg carpenter, bricklayer 18 21 3Group 3 tradesman eg carpet layer, tiler, plasterer 17 19 3

    General labourer 11 13 2

    Site foreman 31 36 6

    China costs of materials

    Concrete 30 mpa (m3) (1,500m3job) 370 430 66

    Reinforcement bar 16mm (tonne) (120 tonne job) 3,400 4,500 692

    Concrete block (400 x 200) per 1,000 (>10,000 block job) 18 32 5

    Standard brick per 1,000 365 450 69

    Structural steel beams (tonne) (>100 tonne job) 7,400 8,600 1,323

    Glass pane 6mm (m2) 460 530 82Softwood timber for framing 100mm x 50mm (m) 53 62 10

    Plasterboard 13mm (m2) 32 38 6

    Emulsion paint (litre) 60 65 10

    Copper pipe 15mm (m) (>1,000m job) 64 53 8

    Copper cable (m) (3C + E, 2.5mm PVC) (>100,000m job) 15 18 3

    China key trades (excluding preliminaries and builders margins)

    Excavate basement (m3) (1,800m3job) 20 34 5

    Excavate footings (m) 34 54 8

    Concrete in slab (m3) (1,500m3job) 420 560 86

    Reinforcement in beams (tonne) 5,200 6,500 1,000Formwork to soffit of slab (m2) 90 90 14

    Blockwork in wall (m2) (10,000 block job) 150 155 24

    Structural steel beams (tonne) 9,000 9,800 1,508

    Pre-cast concrete wall (m2) 155 210 32

    Curtain wall glazing incl support system (m2) (1,000m2job) 1,600 1,600 246

    Plasterboard 13mm thick to stud wall (m2) (3,000m2job) 130 180 28

    Single solid core door incl frame and hardware (no) (50 door job) 2,200 2,670 411

    Painting to walls primer + 2 coats (m2) 42 48 7

    Ceramic tiling (m2) (1,000m2job) 180 210 32

    Vinyl flooring to wet areas (m2) (500m2job) 385 385 59

    Carpet medium tufted (m2) (4,500m2job) 390 390 60

    Lighting installation (m2

    ) (>5,000m2

    job) 660 320 49Copper pipe 15mm to wall (m) (>1,000m job) 82 85 13

    Fire sprinklers (per m2) (5,000m2job) 210 280 43

    Air conditioning incl main plant (m2) (>5,000m2job) 490 490 75

  • 8/10/2019 International Cost Standard

    15/42

    International construction cost survey 2012

    14 Turner & Townsend

    Germany

    Construction orders grew at a moderate two percent year-on-year according to The German

    Construction Industry Federation. However, housing grew at a more robust 6.6 percent higher

    than 2010, based on positive income expectations and low interest rates. Maintenance and

    expansion projects have also injected some further positivity into the construction market with

    an increase in turnover of seven percent year-on-year. However, this year has seen demand

    for public construction decline with a decrease in orders of two percent. Despite the continuing

    European sovereign debt woes and the weakness in neighbouring trading partners, the German

    economy has shown considerable resilience. Construction levels in 2012 should remain positive,

    tendering competitive and escalation moderate.

    Germany international building costs per m2of internal area

    2008 2009 2010 2011 2011

    EUR EUR EUR EUR USD

    Residential

    Detached house medium standard 820 830 833 857 1,192

    Detached house prestige 1,160 1,170 1,174 1,208 1,680

    Townhouse medium standard 1,740 1,760 1,766 1,817 2,528

    Apartments private medium density 1,071 1,068 1,085 1,105 1,536

    Apartments high rise 1,020 1,017 1,033 1,052 1,463

    Aged care/affordable units 780 778 790 804 1,119

    Commercial

    Offices business park 1,130 1,140 1,144 1,177 1,637

    CBD offices up to 20 floors medium 1,130 1,140 1,144 1,177 1,637

    CBD offices prestige 1,620 1,640 1,646 1,693 2,354

    Warehouses

    Warehouse/factory unit basic 860 861 872 900 1,252

    Large warehouse distribution centre 1,073 1,074 1,088 1,123 1,563

    High-tech factory/laboratory 1,560 1,575 1,575 1,626 2,262

    Retail

    Large shopping centre including mall 895 900 903 929 1,292

    Neighbourhood including supermarket 895 900 903 929 1,292

    Prestige car showroom 870 880 883 908 1,263

    Hotels

    Three-star travellers 1,210 1,220 1,224 1,259 1,751

    Five-star luxury 2,652 2,662 2,666 2,742 3,814

    Resort style 1,718 1,728 1,732 1,782 2,478

    Hospitals

    Day centre 1,350 1,365 1,370 1,409 1,960

    Regional hospital 2,160 2,180 2,188 2,250 3,130

    General hospital 2,350 2,375 2,383 2,452 3,410

    Schools

    Primary and secondary 1,170 1,180 1,184 1,218 1,694

    University 1,370 1,385 1,390 1,430 1,988

    Carparks

    Multistorey above ground 524 526 533 548 762

    Multistorey below ground 597 599 607 624 868

    Airports

    Airport terminal 1,080 1,090 1,094 1,125 1,565

  • 8/10/2019 International Cost Standard

    16/42

    making the difference 15

    Germany major projects

    USD

    Trans Europa Naturgas Pipeline (TENP) Upgrade 120m

    Frankfurt Chlor-Alkali Plant Expansion 140m

    Stuttgart 21 5.2bn

    Germany hourly cost of labour (including overheads)

    2010 2011 2011

    EUR EUR USD

    Group 1 tradesman eg plumber, electrician 39 35 49

    Group 2 tradesman eg carpenter, bricklayer 36 36 50Group 3 tradesman eg carpet layer, tiler, plasterer 35 36 50

    General labourer 24 33 46

    Site foreman 40 40 56

    Germany costs of materials

    Concrete 30 mpa (m3) (1,500m3job) 118 122 170

    Reinforcement bar 16mm (tonne) (120 tonne job) 760 786 1,094

    Concrete block (400 x 200) per 1,000 (>10,000 block job) 4,400 4,553 6,333

    Standard brick per 1,000 550 569 792

    Structural steel beams (tonne) (>100 tonne job) 2,850 2,949 4,102

    Glass pane 6mm (m2) 53 55 76Softwood timber for framing 100mm x 50mm (m) 3 3 4

    Plasterboard 13mm (m2) 4 4 5

    Emulsion paint (litre) 5 5 6

    Copper pipe 15mm (m) (>1,000m job) 9 9 13

    Copper cable (m) (3C + E, 2.5mm PVC) (>100,000m job) 4 4 6

    Germany key trades (excluding preliminaries and builders margins)

    Excavate basement (m3) (1,800m3job) 13 13 19

    Excavate footings (m) 25 26 36

    Concrete in slab (m3) (1,500m3job) 133 137 190

    Reinforcement in beams (tonne) 1,800 1,852 2,575Formwork to soffit of slab (m2) 35 36 50

    Blockwork in wall (m2) (10,000 block job) 63 65 90

    Structural steel beams (tonne) 3,020 3,106 4,320

    Pre-cast concrete wall (m2) 90 93 129

    Curtain wall glazing incl support system (m2) (1,000m2job) 435 447 622

    Plasterboard 13mm thick to stud wall (m2) (3,000m2job) 50 51 72

    Single solid core door incl frame and hardware (no) (50 door job) 820 843 1,173

    Painting to walls primer + 2 coats (m2) 5 5 7

    Ceramic tiling (m2) (1,000m2job) 50 51 72

    Vinyl flooring to wet areas (m2) (500m2job) 33 34 47

    Carpet medium tufted (m2) (4,500m2job) 25 26 36

    Lighting installation (m2

    ) (>5,000m2

    job) 53 55 76Copper pipe 15mm to wall (m) (>1,000m job) 28 29 40

    Fire sprinklers (per m2) (5,000m2job) 75 77 107

    Air conditioning incl main plant (m2) (>5,000m2job) 30 31 43

  • 8/10/2019 International Cost Standard

    17/42

    International construction cost survey 2012

    16 Turner & Townsend

    India

    Construction growth is expected to accelerate during 2012. The government is focusing on

    infrastructure creation and this is having an impact on the industrial and infrastructure construction

    segments. This sector is forecast to grow by 21.5 percent in 2012. The high-rise construction

    sector is also strong with numerous mixed-use, high-rise buildings under construction and strong

    escalation experienced. The expanded presence of overseas contractors in this segment has

    increased costs by as much as 30 percent for high-rise construction in the past 1218 months.

    During 2012 construction costs are expected to grow by up to seven percent, one of the highest

    escalation rates globally.

    India international building costs per m2of internal area

    2008 2009 2010 2011 2011

    INR INR INR INR USD

    Residential

    Detached house medium standard 14,850 16,500 28,000 30,000 655

    Detached house prestige 19,350 21,500 35,000 37,500 818

    Townhouse medium standard 18,000 20,000 22,000 25,000 546

    Apartments private medium density 17,100 19,000 18,000 20,000 436

    Apartments high rise 30,000 32,500 35,000 45,000 982

    Aged care/affordable units 12,600 14,000 16,000 18,000 393

    Commercial

    Offices business park 21,600 27,000 25,000 30,000 655

    CBD offices up to 20 floors medium 25,000 26,250 28,000 35,000 764

    CBD offices prestige 30,000 32,500 35,000 38,000 829

    Warehouses

    Warehouse/factory unit basic 27,000 30,000 35,000 26,500 578

    Large warehouse distribution centre 31,500 35,000 37,000 33,500 731

    High-tech factory/laboratory 33,300 37,000 38,000 40,000 873

    Retail

    Large shopping centre including mall 24,300 27,000 35,000 38,000 829

    Neighbourhood including supermarket 20,700 23,000 26,000 26,000 567

    Prestige car showroom 13,500 15,000 16,000 17,500 382

    Hotels

    Three-star travellers 32,130 35,700 35,000 38,000 829

    Five-star luxury 75,735 84,150 70,000 75,000 1,637

    Resort style 29,835 33,150 38,000 48,000 1,048

    Hospitals

    Day centre 16,200 18,000 20,000 21,000 458

    Regional hospital 27,000 30,000 35,000 37,000 808

    General hospital 24,300 27,000 25,000 29,000 633

    Schools

    Primary and secondary 9,000 10,000 15,000 18,000 393

    University 22,500 25,000 35,000 38,000 829

    Carparks

    Multistorey above ground 40,500 45,000 40,000 38,000 829

    Multistorey below ground 16,200 18,000 25,000 24,000 524

    Airports

    Airport terminal 40,500 45,000 55,000 65,000 1,419

  • 8/10/2019 International Cost Standard

    18/42

    making the difference 17

    India major projects

    USD

    Delhi Mumbai Industrial Corridor (DMIC) 100bn

    Information Technology Investment Region (ITIR Bangalore) 50bn

    Jawaharlal Nehru National Solar Mission (JNNSM) 75bn

    National Highways Development Programme 75bnLavasa Hill City 31bn

    India hourly cost of labour (including overheads)

    2010 2011 2011

    INR INR USD

    Group 1 tradesman eg plumber, electrician 45 56 1.2

    Group 2 tradesman eg carpenter, bricklayer 45 50 1.1Group 3 tradesman eg carpet layer, tiler, plasterer 40 38 0.8

    General labourer 18 20 0.4

    Site foreman 80 80 1.7

    India costs of materials

    Concrete 30 mpa (m3) (1,500m3job) 3,500 5,000 109

    Reinforcement bar 16mm (tonne) (120 tonne job) 35,000 40,500 884

    Concrete block (400 x 200) per 1,000 (>10,000 block job) 20,000 35,000 764

    Standard brick per 1,000 7,000 6,250 136

    Structural steel beams (tonne) (>100 tonne job) 65,000 50,000 1,091

    Glass pane 6mm (m2) 500 500 11Softwood timber for framing 100mm x 50mm (m) 150 275 6

    Plasterboard 13mm (m2) 250 280 6

    Emulsion paint (litre) 300 340 7

    Copper pipe 15mm (m) (>1,000m job) 1,400 1,300 28

    Copper cable (m) (3C + E, 2.5mm PVC) (>100,000m job) 2,200 2,450 53

    India key trades (excluding preliminaries and builders margins)

    Excavate basement (m3) (1,800m3job) 900 750 16

    Excavate footings (m) 400 475 10

    Concrete in slab (m3) (1,500m3job) 5,500 6,500 142

    Reinforcement in beams (tonne) 55,000 56,000 1,222Formwork to soffit of slab (m2) 500 525 11

    Blockwork in wall (m2) (10,000 block job) 1,000 1,075 23

    Structural steel beams (tonne) 65,000 82,500 1,801

    Pre-cast concrete wall (m2) 6,000 8,250 180

    Curtain wall glazing incl support system (m2) (1,000m2job) 7,000 9,250 202

    Plasterboard 13mm thick to stud wall (m2) (3,000m2job) 3,500 2,250 49

    Single solid core door incl frame and hardware (no) (50 door job) 30,000 27,500 600

    Painting to walls primer + 2 coats (m2) 200 200 4

    Ceramic tiling (m2) (1,000m2job) 2,800 2,800 61

    Vinyl flooring to wet areas (m2) (500m2job) 1,800 2,100 46

    Carpet medium tufted (m2) (4,500m2job) 1,500 2,350 51

    Lighting installation (m2

    ) (>5,000m2

    job) 2,800 2,900 63Copper pipe 15mm to wall (m) (>1,000m job) 1,500 1,775 39

    Fire sprinklers (per m2) (5,000m2job) 1,200 825 18

    Air conditioning incl main plant (m2) (>5,000m2job) 5,000 3,625 79

  • 8/10/2019 International Cost Standard

    19/42

    International construction cost survey 2012

    18 Turner & Townsend

    Ireland

    Tender prices stabilised for the first time in four years by mid 2011. However, severe shortages of work

    in all sectors will cause tender prices to remain very competitive in 2012. A recent survey highlighted

    the dangerous situation where nearly half of all tenders are below realistic levels. Construction labour

    rates have not increased during 2011. Some material prices have risen slightly due to smaller levels

    of production volumes and less economies of scale. The pharmaceutical and hi-tech sectors continue

    to attract high levels of construction investment encouraged by the activities of the Irish Development

    Authority and the attractive corporate tax environment. Public sector investment is being concentrated

    in previously neglected education and health sectors. Further cuts in public-funded capital

    expenditure are likely to satisfy the requirements of the IMF/ECB/ESFS bail-out conditions.

    Ireland international building costs per m2of internal area

    2008 2009 2010 2011 2011

    EUR EUR EUR EUR USD

    Residential

    Detached house medium standard 1,500 1,100 1,000 1,000 1,391

    Detached house prestige 2,200 1,800 1,700 1,600 2,225

    Townhouse medium standard 1,400 1,080 1,000 1,000 1,391

    Apartments private medium density 1,750 1,500 1,375 1,350 1,878

    Apartments high rise 1,800 1,650 1,525 1,500 2,086

    Aged care/affordable units 2,500 2,000 1,850 1,825 2,538

    Commercial

    Offices business park 1,750 1,300 1,200 1,175 1,634

    CBD offices up to 20 floors medium 2,500 1,950 1,800 1,775 2,469

    CBD offices prestige 3,750 2,950 2,725 2,675 3,720

    WarehousesWarehouse/factory unit basic 650 550 500 500 695

    Large warehouse distribution centre 1,100 975 900 875 1,217

    High-tech factory/laboratory 1,800 1,650 1,550 1,525 2,121

    Retail

    Large shopping centre including mall 2,950 2,500 2,300 2,250 3,129

    Neighbourhood including supermarket 2,950 2,200 2,025 2,000 2,782

    Prestige car showroom 3,250 2,900 2,675 2,650 3,686

    Hotels

    Three-star travellers 2,000 1,700 1,575 1,550 2,156

    Five-star luxury 3,300 3,000 2,775 2,750 3,825

    Resort style 2,450 2,200 2,025 2,000 2,782

    Hospitals

    Day centre 3,000 2,400 2,200 2,150 2,990

    Regional hospital 4,500 3,500 3,225 3,175 4,416

    General hospital 4,500 3,500 3,225 3,175 4,416

    Schools

    Primary and secondary 1,230 1,230 1,125 1,050 1,460

    University 2,500 2,200 2,035 1,975 2,747

    Carparks

    Multistorey above ground 570 570 525 500 695

    Multistorey below ground 960 960 875 875 1,217

    Airports

    Airport terminal 4,300 3,900 3,600 3,500 4,868

  • 8/10/2019 International Cost Standard

    20/42

    making the difference 19

    Ireland major projects

    EUR

    INTEL 200m+

    Rapid Schools Bundle 2 (Lots 14 Primary/Post Primary Schools) 100m+

    National Paediatric Hospital at Mater Hospital 400m+

    Pfizer 100200mGoogle Data Centre 50100m

    Ireland hourly cost of labour (including overheads)

    2010 2011 2011

    EUR EUR USD

    Group 1 tradesman eg plumber, electrician 29 29 40

    Group 2 tradesman eg carpenter, bricklayer 29 29 40Group 3 tradesman eg carpet layer, tiler, plasterer 29 29 40

    General labourer 24 24 33

    Site foreman 29 29 40

    Ireland costs of materials

    Concrete 30 mpa (m3) (1,500m3job) 54 60 83

    Reinforcement bar 16mm (tonne) (120 tonne job) 650 700 974

    Concrete block (400 x 200) per 1,000 (>10,000 block job) 420 400 556

    Standard brick per 1,000 410 420 584

    Structural steel beams (tonne) (>100 tonne job) 990 1,020 1,419

    Glass pane 6mm (m2) 41 42 58Softwood timber for framing 100mm x 50mm (m) 1 1 1

    Plasterboard 13mm (m2) 3 3 4

    Emulsion paint (litre) 4 4 6

    Copper pipe 15mm (m) (>1,000m job) 2 3 4

    Copper cable (m) (3C + E, 2.5mm PVC) (>100,000m job) 1 1 1

    Ireland key trades (excluding preliminaries and builders margins)

    Excavate basement (m3) (1,800m3job) 11 9 13

    Excavate footings (m) 18 18 25

    Concrete in slab (m3) (1,500m3job) 67 72 100

    Reinforcement in beams (tonne) 825 900 1,252Formwork to soffit of slab (m2) 30 28 39

    Blockwork in wall (m2) (10,000 block job) 22 22 31

    Structural steel beams (tonne) 1,875 1,900 2,642

    Pre-cast concrete wall (m2) 50 48 67

    Curtain wall glazing incl support system (m2) (1,000m2job) 470 420 584

    Plasterboard 13mm thick to stud wall (m2) (3,000m2job) 55 50 70

    Single solid core door incl frame and hardware (no) (50 door job) 750 720 1,001

    Painting to walls primer + 2 coats (m2) 4 5 7

    Ceramic tiling (m2) (1,000m2job) 58 55 76

    Vinyl flooring to wet areas (m2) (500m2job) 35 32 45

    Carpet medium tufted (m2) (4,500m2job) 25 25 35

    Lighting installation (m2

    ) (>5,000m2

    job) 14 14 19Copper pipe 15mm to wall (m) (>1,000m job) 28 28 39

    Fire sprinklers (per m2) (5,000m2job) 70 70 97

    Air conditioning incl main plant (m2) (>5,000m2job) 300 300 417

  • 8/10/2019 International Cost Standard

    21/42

    International construction cost survey 2012

    20 Turner & Townsend

    Japan

    After nearly two decades of economic stagnation the construction industry displayed signs

    of recovery during late 2010 and 2011. However, the devastating earthquake and tsunami in

    March 2011 temporarily halted this improvement. More than 300,000 houses were destroyed

    in the disaster along with roads, ports and energy facilities. In April 2011 the government

    announced an aid package to assist with the reconstruction. Construction demand is forecast

    to grow by 2.6 percent in 2012 to 45.3tn Japanese yen, assisted substantially by the reconstruction

    package. The restoration projects are likely to cover infrastructure, residential construction and the

    restoration of various production facilities damaged in the disaster.

    Japan international building costs per m2of internal area

    2011 2011

    Yen USD

    Residential

    Detached house medium standard 201,500 2,506

    Detached house prestige 235,800 2,933

    Townhouse medium standard 186,700 2,322

    Apartments private medium density 189,300 2,355

    Apartments high rise 284,000 3,533

    Aged care/affordable units 164,800 2,050

    Commercial

    Offices business park 230,500 2,867

    CBD offices up to 20 floors medium 266,500 3,315

    CBD offices prestige 303,800 3,779

    Warehouses

    Warehouse/factory unit basic 154,500 1,922

    Large warehouse distribution centre 207,900 2,586

    High-tech factory/laboratory 455,000 5,660

    Retail

    Large shopping centre including mall 304,000 3,781

    Neighbourhood including supermarket 368,400 4,582

    Prestige car showroom 485,000 6,033

    Hotels

    Three-star travellers 349,000 4,341

    Five-star luxury 523,400 6,510

    Resort style 289,500 3,601

    Hospitals

    Day centre 164,000 2,040

    Regional hospital 164,000 2,040

    General hospital 247,800 3,082

    Schools

    Primary and secondary 202,400 2,518

    University 186,300 2,317

    Carparks

    Multistorey above ground 205,300 2,554

    Multistorey below ground 444,800 5,533

    Airports

    Airport terminal 370,000 4,602

  • 8/10/2019 International Cost Standard

    22/42

    making the difference 21

    Japan hourly cost of labour (including overheads)

    2011 2011

    Yen USD

    Group 1 tradesman eg plumber, electrician 2,400 30

    Group 2 tradesman eg carpenter, bricklayer 2,210 27Group 3 tradesman eg carpet layer, tiler, plasterer 2,140 27

    General labourer 1,700 21

    Site foreman 2,440 30

    Japan costs of materials

    Concrete 30 mpa (m3) (1,500m3job) 11,900 148

    Reinforcement bar 16mm (tonne) (120 tonne job) 66,000 821

    Concrete block (400 x 200) per 1,000 (>10,000 block job) 110,000 1,368

    Standard brick per 1,000 97,500 1,213

    Structural steel beams (tonne) (>100 tonne job) 80,000 995

    Glass pane 6mm (m2) 1,730 22Softwood timber for framing 100mm x 50mm (m) 12,100 151

    Plasterboard 13mm (m2) 230 3

    Emulsion paint (litre) 270 3

    Copper pipe 15mm (m) (>1,000m job) 661 8

    Copper cable (m) (3C + E, 2.5mm PVC) (>100,000m job) 181 2

    Japan key trades (excluding preliminaries and builders margins)

    Excavate basement (m3) (1,800m3job) 450 6

    Excavate footings (m) 500 6

    Concrete in slab (m3) (1,500m3job) 13,710 171

    Reinforcement in beams (tonne) 97,000 1,207Formwork to soffit of slab (m2) 2,680 33

    Blockwork in wall (m2) (10,000 block job) 4,410 55

    Structural steel beams (tonne) 114,960 1,430

    Pre-cast concrete wall (m2) 15,140 188

    Curtain wall glazing incl support system (m2) (1,000m2job) 100,000 1,244

    Plasterboard 13mm thick to stud wall (m2) (3,000m2job) 3,050 38

    Single solid core door incl frame and hardware (no) (50 door job) 73,600 915

    Painting to walls primer + 2 coats (m2) 860 11

    Ceramic tiling (m2) (1,000m2job) 5,820 72

    Vinyl flooring to wet areas (m2) (500m2job) 3,380 42

    Carpet medium tufted (m2) (4,500m2job) 4,300 53

    Lighting installation (m2

    ) (>5,000m2

    job) 4,500 56Copper pipe 15mm to wall (m) (>1,000m job) 2,290 28

    Fire sprinklers (per m2) (5,000m2job) 4,000 50

    Air conditioning incl main plant (m2) (>5,000m2job) 28,900 359

    Japan major projects

    Yen

    Tokyo Sky Tree 65bn

    Japan Post Tower 88bn

    Loop Road (Kanjo) No. 2 NA

    Redevelopment in Shinjuku 8-Chome NATokyo Waterfront Redevelopment in Aomi R-District NA

  • 8/10/2019 International Cost Standard

    23/42

    International construction cost survey 2012

    22 Turner & Townsend

    Malaysia

    The public sector construction market in Malaysia is expected to moderate with reduced

    government spending. However, several mega projects are announced including the Mass Rapid

    Transport programme, the Marina Island Pangkor 2nd International Resort and Entertainment

    Island, and various energy sector developments. There is increasing demand for space from

    SMEs in the industrial sector mainly in the automotive, energy, electrical and logistics sectors.

    The new 1Malaysia housing programme, an affordable housing development aimed at the

    middle-income group, should boost the residential market. Commercial office and retail

    construction should also benefit as a result of this activity.

    Malaysia international building costs per m2of internal area

    2008 2009 2010 2011 2011

    MYR MYR MYR MYR USD

    Residential

    Detached house medium standard 1,436 1,400 1,500 1,800 589

    Detached house prestige 1,897 1,850 1,980 2,300 753

    Townhouse medium standard 974 950 1,000 1,200 393

    Apartments private medium density 1,169 1,140 1,200 1,400 458

    Apartments high rise 1,538 1,500 1,700 2,000 655

    Aged care/affordable units 1,250 1,220 1,310 1,500 491

    Commercial

    Offices business park 1,957 1,900 2,000 2,300 753

    CBD offices up to 20 floors medium 2,575 2,500 2,600 3,000 982

    CBD offices prestige 3,605 3,500 3,700 4,200 1,375

    Warehouses

    Warehouse/factory unit basic 1,228 1,200 1,250 1,400 458

    Large warehouse distribution centre 1,536 1,500 1,600 1,800 589

    High-tech factory/laboratory 2,560 2,500 2,600 3,000 982

    Retail

    Large shopping centre including mall 3,021 3,000 3,200 3,400 1,113

    Neighbourhood including supermarket 2,517 2,500 2,700 2,900 949

    Prestige car showroom 3,323 3,300 3,500 3,700 1,211

    Hotels

    Three-star travellers 3,525 3,500 3,600 3,800 1,244

    Five-star luxury 6,042 6,000 6,200 6,600 2,160

    Resort style 6,300 6,250 6,450 6,900 2,259

    Hospitals

    Day centre 1,611 1,600 1,700 1,800 589

    Regional hospital 2,115 2,100 2,200 2,400 786

    General hospital 2,366 2,350 2,500 2,700 884

    Schools

    Primary and secondary 805 800 850 900 295

    University 3,021 3,000 3,200 3,400 1,113

    Carparks

    Multistorey above ground 1,008 1,000 1,150 1,200 393

    Multistorey below ground 1,511 1,500 1,600 1,700 556

    Airports

    Airport terminal 4,600 4,500 4,700 5,000 1,637

  • 8/10/2019 International Cost Standard

    24/42

    making the difference 23

    Malaysia major projects

    MYR

    Greater KL Mass Rapid Transit 40bn

    Warisan Merdeka 100-Storey Tower 5bn

    Support for Corridors 853bn

    Development of 1,084 hectare

    Malaysian Rubber Board Land, Sungai Buloh 10bn

    Kuala Lumpur International Financial District (KLIFD) 26bn

    Malaysia hourly cost of labour (including overheads)

    2010 2011 2011

    MYR MYR USD

    Group 1 tradesman eg plumber, electrician 19 20 7

    Group 2 tradesman eg carpenter, bricklayer 15 15 5Group 3 tradesman eg carpet layer, tiler, plasterer 19 20 7

    General labourer 10 10 3

    Site foreman 50 55 18

    Malaysia costs of materials

    Concrete 30 mpa (m3) (1,500m3job) 230 230 75

    Reinforcement bar 16mm (tonne) (120 tonne job) 2,900 3,220 1,054

    Concrete block (400 x 200) per 1,000 (>10,000 block job) 3,600 3,980 1,303

    Standard brick per 1,000 360 400 131

    Structural steel beams (tonne) (>100 tonne job) 4,000 4,420 1,447

    Glass pane 6mm (m2) 188 189 62Softwood timber for framing 100mm x 50mm (m) 25 34 11

    Plasterboard 13mm (m2) 25 26 9

    Emulsion paint (litre) 38 39 13

    Copper pipe 15mm (m) (>1,000m job) 24 27 9

    Copper cable (m) (3C + E, 2.5mm PVC) (>100,000m job) 15 16 5

    Malaysia key trades (excluding preliminaries and builders margins)

    Excavate basement (m3) (1,800m3job) 27 28 9

    Excavate footings (m) 32 33 11

    Concrete in slab (m3) (1,500m3job) 332 339 111

    Reinforcement in beams (tonne) 3,507 3,578 1,171Formwork to soffit of slab (m2) 50 51 17

    Blockwork in wall (m2) (10,000 block job) 67 68 22

    Structural steel beams (tonne) 6,500 6,632 2,171

    Pre-cast concrete wall (m2)

    Curtain wall glazing incl support system (m2) (1,000m2job) 400 408 134

    Plasterboard 13mm thick to stud wall (m2) (3,000m2job) 90 92 30

    Single solid core door incl frame and hardware (no) (50 door job) 800 816 267

    Painting to walls primer + 2 coats (m2) 8 8 3

    Ceramic tiling (m2) (1,000m2job) 110 112 37

    Vinyl flooring to wet areas (m2) (500m2job) 98 100 33

    Carpet medium tufted (m2) (4,500m2job) 90 92 30

    Lighting installation (m2

    ) (>5,000m2

    job) 150 153 50Copper pipe 15mm to wall (m) (>1,000m job) 78 80 26

    Fire sprinklers (per m2) (5,000m2job) 100 102 33

    Air conditioning incl main plant (m2) (>5,000m2job) 300 306 100

  • 8/10/2019 International Cost Standard

    25/42

    International construction cost survey 2012

    24 Turner & Townsend

    Russia

    Russia has had a positive year in 2011 with overall GDP rising by 5.1 percent year-on-year by the

    third quarter 2011. The main reason for the increase is due to the continuing strong commodity prices

    in the oil and gas, and mining sectors. However, the construction market remains quite depressed

    relative to the years before the GFC. The main sectors showing renewed growth include industrial and

    infrastructure and the commercial retail and logistics sectors. These are predicted to grow significantly

    throughout 2012. Construction prices generally remain depressed and provide good value for

    money in the market. While some sectors in construction are growing, the overall spare capacity

    in the supply chain is projected to keep construction inflation below five percent in 2012.

    Russia international building costs per m2of internal area

    2008 2009 2010 2011 2011

    RUB RUB RUB RUB USD

    Residential

    Detached house medium standard 28,500 30,000 31,000 32,000 1,091

    Detached house prestige 57,000 60,000 62,000 57,000 1,943

    Townhouse medium standard 23,750 25,000 27,900 35,000 1,193

    Apartments private medium density 47,500 50,000 43,400 45,000 1,534

    Apartments high rise 57,000 60,000 55,800 57,000 1,943

    Aged care/affordable units 47,500 50,000 43,400 43,000 1,466

    Commercial

    Offices business park 37,620 39,600 43,400 44,000 1,500

    CBD offices up to 20 floors medium 50,160 52,800 49,600 50,000 1,705

    CBD offices prestige 62,700 66,000 55,800 57,000 1,943

    Warehouses

    Warehouse/factory unit basic 20,425 21,500 23,250 25,000 852

    Large warehouse distribution centre 24,510 25,800 26,350 26,000 886

    High-tech factory/laboratory 56,700 57,000 58,250 60,000 2,045

    Retail

    Large shopping centre including mall 40,641 42,780 46,500 47,000 1,602

    Neighbourhood including supermarket 29,803 31,372 34,100 30,000 1,023

    Prestige car showroom 28,500 30,000 37,200 38,000 1,295

    Hotels

    Three-star travellers 56,430 59,400 62,000 63,000 2,148

    Five-star luxury 70,538 74,250 77,500 75,000 2,557

    Resort style 64,645 69,100 73,000 70,000 2,386

    Hospitals

    Day centre 37,500 40,000 42,500 51,000 1,739

    Regional hospital 50,000 53,000 51,000 75,000 2,557

    General hospital 65,000 68,000 70,000 60,000 2,045

    Schools

    Primary and secondary 45,000 48,000 49,000 50,000 1,705

    University 50,000 54,000 57,000 63,000 2,148

    Carparks

    Multistorey above ground 21,300 22,355 23,250 23,000 784

    Multistorey below ground 17,000 18,000 26,350 31,000 1,057

    Airports

    Airport terminal 90,000 96,000 100,000 105,000 3,580

  • 8/10/2019 International Cost Standard

    26/42

    making the difference 25

    Russia major projects

    USD

    Russian Sustainable Tourism in North Caucasus Mountains 30bn

    South Stream Gas Pipeline 15.5bn

    2014 Winter Olympics Infrastructure 11bn

    2018 FIFA World Cup Infrastructure NA

    Kaliningrad Nuclear Power Plant 9bn

    Russia hourly cost of labour (including overheads)

    2010 2011 2011

    RUB RUB USD

    Group 1 tradesman eg plumber, electrician 310 500 17

    Group 2 tradesman eg carpenter, bricklayer 310 500 17Group 3 tradesman eg carpet layer, tiler, plasterer 310 500 17

    General labourer 248 400 14

    Site foreman 496 600 20

    Russia costs of materials

    Concrete 30 mpa (m3) (1,500m3job) 3,000 4,500 153

    Reinforcement bar 16mm (tonne) (120 tonne job) 24,500 27,000 920

    Concrete block (400 x 200) per 1,000 (>10,000 block job) 1,000 1,500 51

    Standard brick per 1,000 9,000 10,000 341

    Structural steel beams (tonne) (>100 tonne job) 35,000 35,000 1,193

    Glass pane 6mm (m2) 900 950 32Softwood timber for framing 100mm x 50mm (m) 170 175 6

    Plasterboard 13mm (m2) 125 140 5

    Emulsion paint (litre) 40 44 2

    Copper pipe 15mm (m) (>1,000m job) 300 320 11

    Copper cable (m) (3C + E, 2.5mm PVC) (>100,000m job) 31 33 1

    Russia key trades (excluding preliminaries and builders margins)

    Excavate basement (m3) (1,800m3job) 465 470 16

    Excavate footings (m) 400 410 14

    Concrete in slab (m3) (1,500m3job) 4,000 5,000 170

    Reinforcement in beams (tonne) 30,000 46,000 1,568Formwork to soffit of slab (m2) 900 900 31

    Blockwork in wall (m2) (10,000 block job) 1,200 1,300 44

    Structural steel beams (tonne) 75,000 85,000 2,898

    Pre-cast concrete wall (m2) 5,000 6,000 205

    Curtain wall glazing incl support system (m2) (1,000m2job) 23,250 25,000 852

    Plasterboard 13mm thick to stud wall (m2) (3,000m2job) 2,100 2,300 78

    Single solid core door incl frame and hardware (no) (50 door job) 24,000 25,000 852

    Painting to walls primer + 2 coats (m2) 250 290 10

    Ceramic tiling (m2) (1,000m2job) 1,650 1,800 61

    Vinyl flooring to wet areas (m2) (500m2job) 1,500 1,500 51

    Carpet medium tufted (m2) (4,500m2job) 1,850 1,800 61

    Lighting installation (m2

    ) (>5,000m2

    job) 3,100 3,500 119Copper pipe 15mm to wall (m) (>1,000m job) 800 500 17

    Fire sprinklers (per m2) (5,000m2job) 900 950 32

    Air conditioning incl main plant (m2) (>5,000m2job) 6,000 6,000 205

  • 8/10/2019 International Cost Standard

    27/42

    International construction cost survey 2012

    26 Turner & Townsend

    Singapore

    The Singapore market has been quite moderate in 2011 and escalation has been minimal for

    most building types. Singapores internationally connected economy is experiencing both the

    opportunities of trading with East Asia and the general slowdown in the rest of the world. The

    economy is growing at below the trend of recent years, recording 4.9 percent growth in 2011.

    Housing and apartment construction is quite resilient based on low unemployment rates, confidence

    and wage growth, but the office, retail and hotel sectors appear to be easing. Singapores expertise

    in shipping and fabrication will benefit from the strong growth in energy and resources projects

    in Malaysia and Australia. In 2012 cost escalation of five percent is expected for construction

    projects, which is broadly in line with general inflation. Wage increases are moderate, but some

    building material prices (steel and concrete) have fluctuated.

    Singapore international building costs per m2of internal area

    2008 2009 2010 2011 2011

    SGD SGD SGD SGD USD

    Residential

    Detached house medium standard 4,000 3,500 3,850 4,000 3,178

    Detached house prestige 4,900 4,400 4,400 4,600 3,655

    Townhouse medium standard 3,400 2,800 2,800 2,800 2,225

    Apartments private medium density 3,000 2,000 2,000 2,100 1,669

    Apartments high rise 3,400 2,500 2,700 2,700 2,145

    Aged care/affordable units 1,500 1,350 1,450 1,500 1,192

    Commercial

    Offices business park 2,300 2,000 2,000 2,000 1,589

    CBD offices up to 20 floors medium 3,000 2,500 2,500 2,500 1,986

    CBD offices prestige 3,200 2,800 2,800 2,900 2,304

    Warehouses

    Warehouse/factory unit basic 1,400 1,200 1,200 1,200 953

    Large warehouse distribution centre 1,600 1,500 1,700 1,800 1,430

    High-tech factory/laboratory 3,000 2,800 2,800 3,000 2,384

    Retail

    Large shopping centre including mall 3,000 2,500 3,000 3,200 2,542

    Neighbourhood including supermarket 2,400 2,000 2,000 2,100 1,669

    Prestige car showroom 3,500 3,300 3,300 3,300 2,622

    Hotels

    Three-star travellers 3,300 2,700 3,100 3,200 2,542

    Five-star luxury 4,800 4,000 4,150 4,200 3,337

    Resort style 3,200 2,600 3,000 3,000 2,384

    Hospitals

    Day centre 2,000 1,800 1,750 1,800 1,430

    Regional hospital 3,500 3,000 3,000 3,100 2,463

    General hospital 3,500 3,000 3,000 3,100 2,463

    Schools

    Primary and secondary 1,500 1,500 1,500 1,500 1,192

    University 2,500 2,500 2,500 2,700 2,145

    Carparks

    Multistorey above ground 1,200 900 1,200 1,200 953

    Multistorey below ground 2,000 1,600 1,600 1,700 1,351

    Airports

    Airport terminal

  • 8/10/2019 International Cost Standard

    28/42

    making the difference 27

    Singapore major projects

    USD

    Mass Rapid Transit Extensions 6.7bn

    Marina Bay 2bn

    Marina South 500m

    Singapore hourly cost of labour (including overheads)

    2010 2011 2011

    SGD SGD USD

    Group 1 tradesman eg plumber, electrician 25 25 20

    Group 2 tradesman eg carpenter, bricklayer 20 20 16Group 3 tradesman eg carpet layer, tiler, plasterer 20 21 17

    General labourer 12 15 12

    Site foreman 30 30 24

    Singapore costs of materials

    Concrete 30 mpa (m3) (1,500m3job) 126 152 121

    Reinforcement bar 16mm (tonne) (120 tonne job) 1,580 1,770 1,406

    Concrete block (400 x 200) per 1,000 (>10,000 block job) 800 808 642

    Standard brick per 1,000 250 253 201

    Structural steel beams (tonne) (>100 tonne job) 5,200 5,200 4,132

    Glass pane 6mm (m2) 55 56 44Softwood timber for framing 100mm x 50mm (m) 13 13 10

    Plasterboard 13mm (m2) 21 22 17

    Emulsion paint (litre) 20 20 16

    Copper pipe 15mm (m) (>1,000m job) 12 13 10

    Copper cable (m) (3C + E, 2.5mm PVC) (>100,000m job) 2 2 2

    Singapore key trades (excluding preliminaries and builders margins)

    Excavate basement (m3) (1,800m3job) 21 21 17

    Excavate footings (m) 50 50 40

    Concrete in slab (m3) (1,500m3job) 200 242 192

    Reinforcement in beams (tonne) 1,580 1,770 1,406Formwork to soffit of slab (m2) 30 31 25

    Blockwork in wall (m2) (10,000 block job) 35 35 28

    Structural steel beams (tonne) 5,200 5,200 4,132

    Pre-cast concrete wall (m2) 110 110 87

    Curtain wall glazing incl support system (m2) (1,000m2job) 500 500 397

    Plasterboard 13mm thick to stud wall (m2) (3,000m2job) 21 25 20

    Single solid core door incl frame and hardware (no) (50 door job) 800 824 655

    Painting to walls primer + 2 coats (m2) 8 8 6

    Ceramic tiling (m2) (1,000m2job) 70 70 56

    Vinyl flooring to wet areas (m2) (500m2job) 150 150 119

    Carpet medium tufted (m2) (4,500m2job) 70 70 56

    Lighting installation (m2

    ) (>5,000m2

    job) 200 200 159Copper pipe 15mm to wall (m) (>1,000m job) 27 27 21

    Fire sprinklers (per m2) (5,000m2job) 80 80 64

    Air conditioning incl main plant (m2) (>5,000m2job) 260 260 207

  • 8/10/2019 International Cost Standard

    29/42

    International construction cost survey 2012

    28 Turner & Townsend

    South Africa

    The deteriorating situation in Europe has had flow-on effects to South Africa, including weakening

    confidence, and depressing the Rand exchange rate, which has caused the cost of imported materials

    to increase. This together with strong wage increases (coming off a low base) is pushing construction

    costs ahead at up to eight percent per annum. Construction growth is moderate with the major

    local contractors forced to look abroad for much of their work. Civil construction, including mining

    project investments, is still the dominant sector in terms of value of work in progress (accounting

    for almost 62 percent of the total construction activity). The housing sectors are in a cyclical low,

    but the resources sectors show promising growth which will flow on to the rest of the economy.

    South Africa international building costs per m2of internal area

    2008 2009 2010 2011 2011

    ZAR ZAR ZAR ZAR USD

    Residential

    Detached house medium standard 4,500 5,000 5,000 5,300 746

    Detached house prestige 8,000 9,000 9 000 9,500 1,338

    Townhouse medium standard 5,000 6,000 6,000 5,800 817

    Apartments private medium density 4,800 6,000 6,300 6,200 873

    Apartments high rise 7,000 7,500 7,500 7,500 1,056

    Aged care/affordable units 5,000 5,500 5,500 5,500 775

    Commercial

    Offices business park 4,500 5,000 5,300 6,500 915

    CBD offices up to 20 floors medium 7,000 8,500 8,500 8,500 1,197

    CBD offices prestige 7,500 10,000 10,000 11,500 1,619

    Warehouses

    Warehouse/factory unit basic 3,700 3,700 3,700 3,800 535

    Large warehouse distribution centre 3,900 3,900 3,900 4,000 563

    High-tech factory/laboratory 4,500 6,000 6,300 6,000 845

    Retail

    Large shopping centre including mall 5,500 7,800 7,800 8,000 1,127

    Neighbourhood including supermarket 6,000 6,800 6,800 7,000 986

    Prestige car showroom 6,200 7,000 7,000 7,500 1,056

    Hotels

    Three-star travellers 5,500 8,000 8,400 8,600 1,211

    Five-star luxury 7,000 10,000 10,500 10,500 1,479

    Resort style 6,900 9,700 10,185 10,000 1,408

    Hospitals

    Day centre 4,500 5,500 5,500 6,000 845

    Regional hospital 6,000 7,000 7,000 7,500 1,056

    General hospital 7,500 8,500 8,500 9,000 1,267

    Schools

    Primary and secondary 4,500 5,000 5,000 7,000 986

    University 5,000 6,000 6,000 9,000 1,267

    Carparks

    Multistorey above ground 3,200 3,500 4,000 3,800 535

    Multistorey below ground 3,500 4,000 4,800 4,500 634

    Airports

    Airport terminal 20,000 20,900 20,900 20,900 2,943

  • 8/10/2019 International Cost Standard

    30/42

    making the difference 29

    South Africa major projects

    ZAR

    Medupi Power Station 125bn

    Kusile Power Station 141bn

    RMI Integrated Titanium and Zirconium Beneficiation Complex 15bn

    Xstrata Tweefontein Optimisation Project 8bnXstrata Atcom East 3.8bn

    Pascoulama 5bn

    South Africa hourly cost of labour (including overheads)

    2010 2011 2011

    ZAR ZAR USD

    Group 1 tradesman eg plumber, electrician 50 52 7

    Group 2 tradesman eg carpenter, bricklayer 45 48 7Group 3 tradesman eg carpet layer, tiler, plasterer 35 40 6

    General labourer 15 18 3

    Site foreman 200 200 28

    South Africa costs of materials

    Concrete 30 mpa (m3) (1,500m3job) 940 834 117

    Reinforcement bar 16mm (tonne) (120 tonne job) 7,727 8,100 1,141

    Concrete block (400 x 200) per 1,000 (>10,000 block job) 1,450 2,000 282

    Standard brick per 1,000 1,500 1,600 225

    Structural steel beams (tonne) (>100 tonne job) 15,000 20,000 2,816

    Glass pane 6mm (m2) 400 400 56Softwood timber for framing 100mm x 50mm (m) 70 70 10

    Plasterboard 13mm (m2) 46 46 6

    Emulsion paint (litre) 40 37 5

    Copper pipe 15mm (m) (>1,000m job) 30 35 5

    Copper cable (m) (3C + E, 2.5mm PVC) (>100,000m job)

    South Africa key trades (excluding preliminaries and builders margins)

    Excavate basement (m3) (1,800m3job) 50 60 8

    Excavate footings (m) 60 78 11

    Concrete in slab (m3) (1,500m3job) 1,085 917 129

    Reinforcement in beams (tonne) 7,727 8,910 1,255Formwork to soffit of slab (m2) 135 126 18

    Blockwork in wall (m2) (10,000 block job) 210 210 30

    Structural steel beams (tonne) 24,000 24,500 3,450

    Pre-cast concrete wall (m2) 450 460 65

    Curtain wall glazing incl support system (m2) (1,000m2job) 1,600 2,100 296

    Plasterboard 13mm thick to stud wall (m2) (3,000m2job) 200 540 76

    Single solid core door incl frame and hardware (no) (50 door job) 1,683 1,600 225

    Painting to walls primer + 2 coats (m2) 27 27 4

    Ceramic tiling (m2) (1,000m2job) 200 200 28

    Vinyl flooring to wet areas (m2) (500m2job) 154 160 23

    Carpet medium tufted (m2) (4,500m2job) 220 220 31

    Lighting installation (m2

    ) (>5,000m2

    job) 85 12Copper pipe 15mm to wall (m) (>1,000m job) 55 40 6

    Fire sprinklers (per m2) (5,000m2job) 165 260 37

    Air conditioning incl main plant (m2) (>5,000m2job) 1,300 1,300 183

  • 8/10/2019 International Cost Standard

    31/42

    International construction cost survey 2012

    30 Turner & Townsend

    South Korea

    South Korea is experiencing improvements in the private domestic construction sector as the economy

    experiences quite healthy growth and gradual cyclical recovery. However, the country has recently

    felt the impact of international economic conditions including tighter financing, higher input costs

    including oil, and interrupted trade with Japan since the earthquake. The private development sector

    has undergone a period of deregulation with less involvement by public institutions. This has increased

    demand for private development and should assist the private sector construction markets in

    2012. Public sector construction continues to remain subdued with public works and large-scale

    project construction in a slowdown. Public sector construction is unlikely to be higher in 2012

    than in 2011. The engineering, fabrication and shipbuilding sectors have healthy order books with

    Asian and Australian energy projects. Construction cost escalation should be modest in 2012.

    South Korea international building costs per m2of internal area

    2008 2009 2010 2011 2011

    KRW KRW KRW KRW USD

    Residential

    Detached house medium standard 1,167,307 1,155,750 1,150,000 1,150,000 1,038

    Detached house prestige 1,725,585 1,708,500 1,700,000 1,700,000 1,535

    Townhouse medium standard 1,380,468 1,366,800 1,360,000 1,360,000 1,228

    Apartments private medium density 1,116,555 1,105,500 1,100,000 1,100,000 993

    Apartments high rise 1,421,070 1,407,000 1,400,000 1,400,000 1,264

    Aged care/affordable units 1,220,000 1,200,000 1,180,000 1,200,000 1,083

    Commercial

    Offices business park 1,116,555 1,105,500 1,100,000 1,100,000 993

    CBD offices up to 20 floors medium 1,370,317 1,356,750 1,350,000 1,350,000 1,219

    CBD offices prestige 1,725,585 1,708,500 1,700,000 1,700,000 1,535

    Warehouses

    Warehouse/factory unit basic 954,450 945,000 900,000 900,000 813

    Large warehouse distribution centre 761,287 753,750 750,000 700,000 632

    High-tech factory/laboratory 2,639,130 2,613,000 2,600,000 2,600,000 2,348

    Retail

    Large shopping centre including mall 1,725,585 1,708,500 1,700,000 1,700,000 1,535

    Neighbourhood including supermarket 954,450 945,000 900,000 950,000 858

    Prestige car showroom 1,898,144 1,879,350 1,870,000 1,870,000 1,688

    Hotels

    Three-star travellers 1,522,575 1,507,500 1,500,000 1,500,000 1,354

    Five-star luxury 3,045,150 3,015,000 3,000,000 3,200,000 2,889

    Resort style 1,827,090 1,809,000 1,800,000 2,050,000 1,851

    Hospitals

    Day centre 1,116,555 1,105,500 1,100,000 1,100,000 993

    Regional hospital 1,624,080 1,608,000 1,600,000 1,600,000 1,445

    General hospital 1,725,585 1,708,500 1,700,000 1,700,000 1,535

    Schools

    Primary and secondary 1,015,050 1,005,000 1,000,000 1,000,000 903

    University 1,370,317 1,356,750 1,350,000 1,360,000 1,228

    Carparks

    Multistorey above ground 558,277 552,750 550,000 550,000 497

    Multistorey below ground 812,040 804,000 800,000 800,000 722

    Airports

    Airport terminal 2,500,000 2,600,000 2,550,000 2,550,000 2,302

  • 8/10/2019 International Cost Standard

    32/42

  • 8/10/2019 International Cost Standard

    33/42

    International construction cost survey 2012

    32 Turner & Townsend

    UAE

    The economies of Abu Dhabi and Dubai are strengthening, driven by high levels of investment in

    Abu Dhabi, strong tourism growth and the gradual emergence of the UAE as the financial hub for

    the region. However, oversupply in residential and commercial markets will continue to constrain

    construction growth in the UAE, with Dubai worse affected after growing strongest during 20068.

    It may take several years until healthy sales rates resume and price growth occurs. Construction

    costs have fallen substantially with prices in steady decline since 2008 and now up to 25 percent

    lower. Abu Dhabi has much less of an oversupply problem, a healthy backlog of projects and

    prospects for construction growth are better in 2012.

    UAE international building costs per m2of internal area

    2008 2009 2010 2011 2011

    AED AED AED AED USD

    Residential

    Detached house medium standard 7,500 7,000 6,500 6,000 1,634

    Detached house prestige 9,500 9,250 9,000 9,750 2,654

    Townhouse medium standard 7,500 6,525 5,550 5,250 1,429

    Apartments private medium density 7,000 6,500 6,000 5,500 1,497

    Apartments high rise 9,000 8,500 8,000 6,500 1,770

    Aged care/affordable units 5,720 5,340 4,960 4,750 1,293

    Commercial

    Offices business park 5,300 4,800 4,550 4,000 1,089

    CBD offices up to 20 floors medium 6,000 5,750 5,500 5,000 1,361

    CBD offices prestige 8,000 7,500 7,000 6,750 1,838

    Warehouses

    Warehouse/factory unit basic 6,000 5,250 4,500 4,250 1,157

    Large warehouse distribution centre 5,500 4,750 4,000 4,000 1,089

    High-tech factory/laboratory 7,625 6,875 6,125 6,000 1,634

    Retail

    Large shopping centre including mall 8,000 7,500 7,000 6,500 1,770

    Neighbourhood including supermarket 8,500 8,000 7,500 7,000 1,906

    Prestige car showroom

    Hotels

    Three-star travellers 10,000 9,750 9,500 9,000 2,450

    Five-star luxury 13,000 12,750 12,500 12,000 3,267

    Resort style 15,000 15,000 15,000 14,500 3,948

    Hospitals

    Day centre 7,000 6,500 6,000 5,750 1,565

    Regional hospital 8,500 8,000 7,500 7,250 1,974

    General hospital 9,000 8,500 8,000 8,750 2,382

    Schools

    Primary and secondary 7,000 6,500 6,000 5,750 1,565

    University 7,800 7,300 6,800 6,500 1,770

    Carparks

    Multistorey above ground 3,500 3,500 3,500 3,500 953

    Multistorey below ground 4,500 4,500 4,500 4,250 1,157

    Airports

    Airport terminal

  • 8/10/2019 International Cost Standard

    34/42

    making the difference 33

    UAE major projects

    AED

    Etihad Rail 40bn

    Louvre Abu Dhabi 2m

    Khalifa Port and Industrial Zone (KPIZ) 26.5bn

    Presidential Palace 6mYas Mall 2m

    UAE hourly cost of labour (including overheads)

    2010 2011 2011

    AED AED USD

    Group 1 tradesman eg plumber, electrician 30 30 8

    Group 2 tradesman eg carpenter, bricklayer 30 30 8Group 3 tradesman eg carpet layer, tiler, plasterer 28 28 8

    General labourer 15 15 4

    Site foreman 75 75 20

    UAE costs of materials

    Concrete 30 mpa (m3) (1,500m3job) 350 250 68

    Reinforcement bar 16mm (tonne) (120 tonne job) 3,000 2,900 790

    Concrete block (400 x 200) per 1,000 (>10,000 block job) 3,500 3,500 953

    Standard brick per 1,000

    Structural steel beams (tonne) (>100 tonne job) 5,500 5,500 1,497

    Glass pane 6mm (m2) Softwood timber for framing 100mm x 50mm (m) 90 90 25

    Plasterboard 13mm (m2) 10 10 3

    Emulsion paint (litre) 170 46

    Copper pipe 15mm (m) (>1,000m job)

    Copper cable (m) (3C + E, 2.5mm PVC) (>100,000m job)

    UAE key trades (excluding preliminaries and builders margins)

    Excavate basement (m3) (1,800m3job) 35 30 8

    Excavate footings (m) 35 30 8

    Concrete in slab (m3) (1,500m3job) 500 460 125

    Reinforcement in beams (tonne) 3,750 4,000 1,089Formwork to soffit of slab (m2) 100 100 27

    Blockwork in wall (m2) (10,000 block job) 125 100 27

    Structural steel beams (tonne) 13,000 10,000 2,723

    Pre-cast concrete wall (m2) 650 650 177

    Curtain wall glazing incl support system (m2) (1,000m2job) 1,800 1,400 381

    Plasterboard 13mm thick to stud wall (m2) (3,000m2job) 150 120 33

    Single solid core door incl frame and hardware (no) (50 door job) 4,000 3,650 994

    Painting to walls primer + 2 coats (m2) 15 11 3

    Ceramic tiling (m2) (1,000m2job) 225 100 27

    Vinyl flooring to wet areas (m2) (500m2job) 125 105 29

    Carpet medium tufted (m2) (4,500m2job) 300 300 82

    Lighting installation (m2

    ) (>5,000m2

    job) 150 150 41Copper pipe 15mm to wall (m) (>1,000m job) 55 55 15

    Fire sprinklers (per m2) (5,000m2job) 100 95 26

    Air conditioning incl main plant (m2) (>5,000m2job) 650 690 188

  • 8/10/2019 International Cost Standard

    35/42

    International construction cost survey 2012

    34 Turner & Townsend

    UK

    The UK market continues to be directly affected by economic uncertainties within Europe, as the

    eurozone represents the UKs largest trading partner. Consumer confidence within the UK is on

    the decline, and this economic ambiguity is having a negative effect on private sector activities

    in the face of dwindling public sector investment due to government austerity measures. This

    is making the industry increasingly dependent on long-term infrastructure projects and a rise

    in private sector investment to fill the void. Unemployment is rising as employers attempt to

    maintain current staffing levels leading to lower than inflation level wage increases. However,

    falling inflation rates should ease the pressure on wages throughout 2012.

    UK international building costs per m2of internal area

    2008 2009 2010 2011 2011

    GBP GBP GBP GBP USD

    Residential

    Detached house medium standard 1,050 1,050 1,020 1,058 1,696

    Detached house prestige 1,465 1,465 1,465 1,519 2,436

    Townhouse medium standard 1,008 1,200 1,200 1,244 1,995

    Apartments private medium density 1,624 1,800 1,800 1,867 2,994

    Apartments high rise 2,170 2,300 2,300 2,385 3,824

    Aged care/affordable units 1,800 1,820 1,820 1,887 3,026

    Commercial

    Offices business park 1,500 1,500 1,500 1,556 2,495

    CBD offices up to 20 floors medium 2,972 2,700 2,700 2,800 4,489

    CBD offices prestige 1,833 3,800 3,800 3,941 6,319

    Warehouses

    Warehouse/factory unit basic 691 800 800 830 1,331

    Large warehouse distribution centre 867 900 900 933 1,496

    High-tech factory/laboratory 1,365 1,500 1,500 1,556 2,495

    Retail

    Large shopping centre including mall 2,200 2,200 2,200 2,281 3,657

    Neighbourhood including supermarket 1,835 1,835 1,835 1,903 3,051

    Prestige car showroom 2,000 2,000 2,000 2,074 3,325

    Hotels

    Three-star travellers 1,300 1,200 1,200 1,244 1,995

    Five-star luxury 2,500 2,500 2,500 2,593 4,158

    Resort style 2,500 2,500 2,500 2,593 4,158

    Hospitals

    Day centre 1,295 1,531 1,531 1,588 2,546

    Regional hospital 2,639 2,514 2,514 2,607 4,180

    General hospital 1,740 1,733 1,733 1,797 2,881

    Schools

    Primary and secondary 1,553 1,590 1,350 1,400 2,245

    University 2,240 2,200 2,180 2,261 3,625

    Carparks

    Multistorey above ground 437 450 450 467 749

    Multistorey below ground 870 850 850 881 1,413

    Airports

    Airport terminal 3,150 3,050 3,050 3,163 5,072

  • 8/10/2019 International Cost Standard

    36/42

    making the difference 35

    UK major projects

    GBP

    Crossrail 14.5bn

    High Speed Railway 2 32.7bn

    London 2012 Olympics 2bn

    London Tideway Improvements 4bnForth Replacement Crossing 1bn

    UK hourly cost of labour (including overheads)

    2010 2011 2011

    GBP GBP USD

    Group 1 tradesman eg plumber, electrician 30 30 48

    Group 2 tradesman eg carpenter, bricklayer 30 30 48Group 3 tradesman eg carpet layer, tiler, plasterer 30 30 48

    General labourer 18 18 29

    Site foreman 45 46 74

    UK costs of materials

    Concrete 30 mpa (m3) (1,500m3job) 85 83 133

    Reinforcement bar 16mm (tonne) (120 tonne job) 700 744 1,193

    Concrete block (400 x 200) per 1,000 (>10,000 block job) 1,050 1,071 1,717

    Standard brick per 1,000 450 454 728

    Structural steel beams (tonne) (>100 tonne job) 1,600 1,786 2,864

    Glass pane 6mm (m2) 30 31 50Softwood timber for framing 100mm x 50mm (m) 2 2 3

    Plasterboard 13mm (m2) 5 5 8

    Emulsion paint (litre) 2 2 3

    Copper pipe 15mm (m) (>1,000m job) 1 1 2

    Copper cable (m) (3C + E, 2.5mm PVC) (>100,000m job) 0.15 0.15 0.24

    UK key trades (excluding preliminaries and builders margins)

    Excavate basement (m3) (1,800m3job) 45 43 69

    Excavate footings (m) 12 12 19

    Concrete in slab (m3) (1,500m3job) 110 107 172

    Reinforcement in beams (tonne) 950 1,010 1,619Formwork to soffit of slab (m2) 42 36 58

    Blockwork in wall (m2) (10,000 block job) 35 36 58

    Structural steel beams (tonne) 1,900 2,120 3,399

    Pre-cast concrete wall (m2) 50 63 101

    Curtain wall glazing incl support system (m2) (1,000m2job) 550 570 914

    Plasterboard 13mm thick to stud wall (m2) (3,000m2job) 18 19 30

    Single solid core door incl frame and hardware (no) (50 door job) 750 720 1,154

    Painting to walls primer + 2 coats (m2) 5 5 8

    Ceramic tiling (m2) (1,000m2job) 40 41 66

    Vinyl flooring to wet areas (m2) (500m2job) 25 24 38

    Carpet medium tufted (m2) (4,500m2job) 25 24 38

    Lighting installation (m2

    ) (>5,000m2

    job) 65 67 107Copper pipe 15mm to wall (m) (>1,000m job) 10 10 16

    Fire sprinklers (per m2) (5,000m2job) 30 31 50

    Air conditioning incl main plant (m2) (>5,000m2job) 160 166 266

  • 8/10/2019 International Cost Standard

    37/42

    International construction cost survey 2012

    36 Turner & Townsend

    US

    The outlook for 201213 is for continued slow to moderate growth and a likely return to

    pre-recession economic activity by 2014, subject to the European financial system not causing

    further setbacks. New York, Texas and Massachusetts are experiencing stronger construction

    growth, while Arizona, Nevada and Florida are much weaker. Construction costs should

    increase moderately in 2012 with labour up by two to four percent and materials up by four

    to eight percent. Gypsum-based products such as plasterboard are set to spike upwards in

    2012. Residential is unlikely to recover in 2012 with the market still somewhat oversupplied,

    but markets and companies are consolidating, rightsizing, and setting up for a resumption

    of growth. Multi-unit residential, education, health and energy projects should lead the way.

    US international building costs per m2of internal area

    2008 2009 2010 2011

    USD USD USD USD

    Residential

    Detached house medium standard 1,570 1,475 1,435 1,495

    Detached house prestige 1,925 1,750 1,710 1,800

    Townhouse medium standard 1,475 1,330 1,300 1,350

    Apartments private medium density 1,420 1,590 1,520 1,600

    Apartments high rise 2,075 2,045 2,020 2,100

    Aged care/affordable units 1,300 1,400 1,420 1,550

    Commercial

    Offices business park 1,600 1,905 1,850 1,885

    CBD offices up to 20 floors medium 2,215 2,150 2,085 2,140

    CBD offices prestige 2,610 2,505 2,440 2,520

    WarehousesWarehouse/factory unit basic 750 850 840 860

    Large warehouse distribution centre 915 990 1,100 1,140

    High-tech factory/laboratory 1,520 1,615 1,700 1,785

    Retail

    Large shopping centre including mall 1,580 1,600 1,500 1,560

    Neighbourhood including supermarket 860 900 840 910

    Prestige car showroom 1,425 1,390 1,325 1,380

    Hotels

    Three-star travellers 1,485 1,580 1,525 1,575

    Five-star luxury 2,680 2,720 2,550 2,600

    Resort style 2,420 2,630 2,250 2,300

    Hospitals

    Day centre 1,645 1,765 2,045 2,055

    Regional hospital 3,100 3,210 3,290 3,340

    General hospital 3,000 3,110 3,260 3,300

    Schools

    Primary and secondary 1,450 1,510 1,495 1,570

    University 2,160 2,240 2,150 2,200

    Carparks

    Multistorey above ground 700 730 690 700

    Multistorey below ground 1,325 1,395 1,295 1,315

    Airports

    Airport terminal 3,650 3,525 3,425 3,550

  • 8/10/2019 International Cost Standard

    38/42

    making the difference 37

    US major projects

    USD

    California High-Speed Rail 99bn

    Bay Bridge East Span Replacement 6.3bn

    Fab 42 5bn

    The Ohio River Bridges 4.1bnInterstate 69 Extension SIU #3 1.8bn

    US cost variations

    National average % 100

    Charlotte, NC 83

    Houston, TX 92

    Seattle, WA 111

    Chicago, IL 115

    Los Angeles, CA 115

    San Francisco, CA 125

    New York Metro 132

    Source: ENR

    NB: Construction costs vary widely across the US:

    US hourly cost of labour (including overheads)

    2010 2011

    USD USD

    Group 1 tradesman eg plumber, electrician 73 75

    Group 2 tradesman eg carpenter, bricklayer 64 65Group 3 tradesman eg carpet layer, tiler, plasterer 54 57

    General labourer 51 53

    Site foreman 75 77

    US costs of materials