Upload
cornelius-peters
View
215
Download
0
Tags:
Embed Size (px)
Citation preview
Intro : Project Management
1.Project : series of related jobs usually directed toward some major output and requiring a significant period of time to perform
2.PM : management activities of planning, directing, and controlling resources (people, equipment, material) to meet the technical, cost, and time constraints of a project
Project Management
Gantt Chart
Activity 1Activity 2Activity 3Activity 4Activity 5Activity 6
Time
Pure Project Advantages
Pure Project
A pure project is where a self-contained team works full-time on the project
1. The project manager has full authority over the project2. Team members report to one boss3. Shortened communication lines4. Team pride, motivation, and commitment are high
Pure Project Disadvantages
1. Duplication of resources
2. Organizational goals and policies are ignored
3. Lack of technology transfer
4. Team members have no functional area "home"
Functional Project
President
Research andDevelopment
Engineering Manufacturing
ProjectA
ProjectB
ProjectC
ProjectD
ProjectE
ProjectF
ProjectG
ProjectH
ProjectI
Example, Project “B” is in the functional area of Research and Development.
Example, Project “B” is in the functional area of Research and Development.
Functional Project: Advantages
1. A team member can work on several projects
2. Technical expertise is maintained within the functio-nal area
3. The functional area is a “home” after the project is completed
4. Critical mass of specialized knowledge
Functional Project: Disadvantages
1. Aspects of the project that are not directly related to the functional area get short-changed
2. Motivation of team often weak
3. Responded to slowly
Matrix Project Organization Structure
President
R & D Engineering Manufacturing Marketing
ManagerProject A
ManagerProject B
ManagerProject C
Projects Matrix: Advantages
1. Enhanced communications between functional areas
2. Pinpointed responsibility
3. Duplication of resources is minimized
4. Functional “home” for team members
5. Policies of the parent organization are followed
Projects Matrix: Disadvantages
1. Too many bosses
2. Depends on project manager’s negotiating skills
3. Potential for sub-optimization
Work Breakdown Structure
Program
Project 1 Project 2
Task 1.1
Subtask 1.1.1
Work Package 1.1.1.1
Level
1
2
3
4
Task 1.2
Subtask 1.1.2
Work Package 1.1.1.2
Network-Planning Models
1. A project is made up of a sequence of activities that form a network representing a project
2. The path taking longest time through this network of activities is called the “critical path”
3. The critical path provides a wide range of scheduling information useful in managing a project
4. Critical Path Method (CPM) helps to identify the critical path(s) in the project networks
Prerequisites for Critical Path Methodology
A project must have:
1. well-defined jobs or tasks whose completion marks the end of the project;
2. independent jobs or tasks;
3. and tasks that follow a given sequence.
Types of Critical Path Methods
1. CPM with a Single Time Estimatea. Used when activity times are known with certaintyb. Used to determine timing estimates for the project, each
activity in the project, and slack time for activities 2. CPM with Three Activity Time Estimates
a. Used when activity times are uncertain b. Used to obtain the same information as the Single Time
Estimate model and probability information3. Time-Cost Models
a. Used when cost trade-off information is a major consideration in planning
b. Used to determine the least cost in reducing total project time
Steps in the CPM with Single Time Estimate
1. Activity Identification2. Activity Sequencing and Network Construction3. Determine the critical path
From the critical path all of the project and activity timing information can be obtained
CPM with Single Time Estimate
Consider the following consulting project:
Activity Designation Immed. Pred. Time (Weeks)Assess customer's needs A None 2Write and submit proposal B A 1Obtain approval C B 1Develop service vision and goals D C 2Train employees E C 5Quality improvement pilot groups F D, E 5Write assessment report G F 1
Develop a critical path diagram and determine the duration of the critical path and slack times for all activities.
First draw the network
A(2) B(1) C(1)
D(2)
E(5)
F(5) G(1)
A None 2
B A 1
C B 1
D C 2
E C 5
F D,E 5
G F 1
Act. Imed. Pred. Time
Early starts and early finish times
ES=9EF=14
ES=14EF=15
ES=0EF=2
ES=2EF=3
ES=3EF=4
ES=4EF=9
ES=4EF=6
A(2) B(1) C(1)
D(2)
E(5)
F(5) G(1)
Determine late starts and late finish times
ES=9EF=14
ES=14EF=15
ES=0EF=2
ES=2EF=3
ES=3EF=4
ES=4EF=9
ES=4EF=6
A(2) B(1) C(1)
D(2)
E(5)
F(5) G(1)
LS=14LF=15
LS=9LF=14
LS=4LF=9
LS=7LF=9
LS=3LF=4
LS=2LF=3
LS=0LF=2
Hint: Start with LF=15 or the total time of the project and go backward in the network from G to A.
Hint: Start with LF=15 or the total time of the project and go backward in the network from G to A.
Critical Path & Slack
ES=9EF=14
ES=14EF=15
ES=0EF=2
ES=2EF=3
ES=3EF=4
ES=4EF=9
ES=4EF=6
A(2) B(1) C(1)
D(2)
E(5)
F(5) G(1)
LS=14LF=15
LS=9LF=14
LS=4LF=9
LS=7LF=9
LS=3LF=4
LS=2LF=3
LS=0LF=2
Duration=15 weeks
Slack=(7-4)=(9-6)= 3 Wks
Example
A(7)
B(5.333)
C(14)
D(5)
E(11)
F(7)
H(4)
G(11)
I(18)
Duration = 54 Days
Question
Answer: a. SOW (or Statement of Work)
A project starts with a written description of the objectives to be achieved, with a brief statement of the work to be done and a proposed schedule all contained in which of the following?
a. SOW
b. WBS
c. Early Start Schedule
d. Late Start Schedule
e. None of the above
Question
Some activities in a project there may be some leeway from when an activity can start and when it must finish. What is this period of time called when using the Critical Path Method?
a. Early start timeb. Late start timec. Slack timed. All of the abovee. None of the above
Answer: c. Slack time
Question
How much “slack time” is permitted in the “critical path” activity times?
a. Only one unit of time / activity b. No slack time is permittedc. As much as the maximum activity time in the
networkd. As much as is necessary to add up to the total
time of the projecte. None of the above
Answer: b. No slack time is permitted (All critical path activities must have zero slack time, otherwise they would not be critical to the project completion time.)
Question
When looking at the Time-Cost Trade Offs in the Minimum-Cost Scheduling time-cost model, we seek to reduce the total time of a project by doing what to the least-cost activity choices?
a. Crashing them b. Adding slack timec. Subtracting slack timed. Adding project time e. None of the above Answer: a. Crashing them
(We “crash” the least-cost activity times to seek a reduced total time for the entire project and we do it step-wise as inexpensively as possible.)