Upload
others
View
21
Download
4
Embed Size (px)
Citation preview
INTRODUCTION
1.1 LOAD FREQUENCY CONTROL PROBLEM
Power system authorities have the responsibility to ensure that adequate
power is delivered to the load reliably and economically. In order to ensure
adequate delivery of power to the load reliably and economically, an electric
energy system must be maintained a t the desired operating level characterized
by nominal frequency, voltage profile and load flow configuration. It is kept in
this nominal state by close control of the real and reactive powers generated in
the controllable sources of the system. The generation changes must be made
to match the load perturbations at the nominal conditions, if the nominal state
is to be maintained.
Power system control is required to maintain a continuous balance
between electrical generatior and a varying load demand, while system
frequency, voltage levels and security are maintained. Further, it is desirable
that the cost of such generation should be minimum. The variable nature of the
consumer power demand necessitates changes in the total generation in order
that the power balance is maintained.
The system frequency fluctuations should be kept within strict limits
because of the following reasons:
1. Most types of a.c. motors run at speeds that are directly related to the
frequency.
2. The generator turbines, particularly steam-driven ones, are designed to
operate a t a very precise speed and hence constant turbine speed is an
important requirement in thermal stations.
The velocity of the expanding steam is beyond the control of the operator
and the turbine efficiency requires the perfect speed match. A turbo-rotor with
its many huge turbine blades constitutes a mechanical system of many natural
frequencies. These frequencies are quite undamped and they are each subject
to resonance at various rotor speeds. It is important under load that the rotor
never drifts into a speed range where building of dangerous amplitude would
result. Hydro-turbines are not subject to this type of danger.
3. A large number of electrically operated clocks are driven by synchronous
motors, and the accuracy of these clocks is a function not only of the
frequency error but, actually, of the integral of this error.
4. The overall operation of a power system can be better controlled if the
frequency error is kept within strict limits.
The last reason is equally important. Unusual deviations in frequency
indicates that something is basically wrong with the system. In modern electric
energy systems the frequency constancy is normally kept within % 0.05 Hz.
The frequency is closely related to the real power balance in the overall
network. Under normal operating conditions the system generators run
synchronously and generate together the power that at each moment is being
drawn by all loads, plus the real power losses. The ideal way to operate the
system would therefore be to instruct the machine operators to set all
watergates and steam valves of the various generators a t values that would
exactly correspond to the load demand. We would then have a perfect real
power balance with constant frequency.
Unfortunately, reality is not so accommodating. As it is well known that
the system load can be predicted only to within certain limits. Its fluctuations
are entirely random in character, and it is indeed impossible to accomplish a
perfect instant by instant match between generation and demand. There will
always be a small surplus or deficiency in the generation and this ever present
mismatch will cause frequency fluctuations.
In any power system, it is a desirable feature to achieve a better
frequency constancy than is obtained by the speed governing system alone. In
an interconnected power system, it is also desirable to maintain the tie-line
power flow at a given level irrespective of load changes in any area. To
accomplish this it becomes necessary to automatically manipulate the operation
of main steam valves or hydro-gates in accordance with a suitable control
strategy, which in turn controls the real power output of electric generators.
The controlling of real power output of electric generators in this way is termed
as automatic generation control (AGC) or Automatic Load Frequency Control
(ALFC).
Most large Generators are equipped with two major control loops. The
automatic voltage regulator (AVR) loop controls the magnitude of the terminal
voltage V. The voltage is continuously sensed, rectified and smoothed. This d.c
signal, being proportional to I V I , is compared with d.c reference V, the
resulting "error voltage" after amplification and signal shaping, serves as the
input to the exciter which finally delivers the voltage to the generator field
winding. This excitation control loop controls the reactive power.
The Automatic Load-Frequency Control loop regulates the megawatt
output and frequency (speed) of the generator. The loop is not a single one as
in the case of AVR. A relatively fast primary loop responds to a frequency
signal which is an indirect measure of megawatt balance. Via the speed
governor and the control valves the steam (or hydro) flow is regulated with the
intent of matching the megawatt output to relatively fast (one to several
seconds) load fluctuations. Thus tending to maintain megawatt balance, this
primary loop performs indirectly a course speed or frequency control.
A slower secondary loop maintains the fine adjustment of the frequency,
and also by "reset" action maintains proper megawatt interchange with other
pool members. This loop is insensitive to rapid load and frequency changes but
focuses instead a driftlike changes which take place over periods of minutes.
The AVR and ALFC control loops are loosely coupled. The AVR loop
mainly controls the reactive power through excitation input and ALFC loop
controls the active power output. However the AVR loop is much faster than
ALFC loop and there is, therefore, a tendency for the AVR dynamics to settle
down before they can make themselves felt in the slower load-frequency control
channel. So AVR and ALFC loops are treated independently.
A control area is defined as a power system, a part of a system, or a
combination of systems to which a common generation control scheme is
applied. The electrical interconnections within each control area are very strong
as compared to the ties with the neighbouring areas. All the generators in a
control area swing in unison or coherently, and it is characterized by a single
frequency. It is necessary to consider as many control areas as the number of
such coherent groups. Automatic Generation Control problem of a large
interconnected power system has been studied by dividing the whole system
into a number of control areas.
A power system area generally has interconnections which are physically
remote from the controlling station or dispatching center. Feedback regulatory
control of the system required the measurement of tie-line flows a t
interconnections and the transmission of measured data over data links to the
controlling plant or dispatching center.
During normal operating conditions, Automatic Generation Control is
characterized by random variation of loads in each control area. AGC matches
area generation to area load plus scheduled net interchange by controlling
generation to maintain the net interchange schedule and scheduled power
system frequency. For normal operating conditions, it is important to minimize
from below 1 cycle per minute (CPM) to about 10 CPM. The lower frequencies
are associated with random load changes caused by AGC, while the higher
frequencies are associated with random load changes caused by the primary
speed governor control.
Proper selection of frequency bias setting is extremely important for
AGC of interconnected systems. The bias responses of an area to a sudden load
or generation change in a remote area is preceded by a natural governing
response of the area. The bias setting will determine whether the bias response
remains that of the natural governing response, or whether the bias response
is in a direction to add to it or subtract from it.
In order to study the effect of frequency bias setting on the system
performance, M.L.Kothari (133) analyzed AGC problem of Zequal area reheat
thermal system in the discretemode. A practical sampling period of 2 seconds
is chosen. Detailed investigations reveal that
(a) Frequency bias setting, B, which match the prevailing area frequency
response characteristic 13, impose no further change on frequency, tie-line
flow, and local generation.
(b) Frequency bias settings which are less than 13 impose further decrease
in frequency tie-line flow and local generation and thus amount to
withdrawing assistance to needy area.
(c) Frequency bias settings which are greater than 13, cause reduction in
frequency deviation, increase in tie-line flow and decrease local
generation. This is desirable since the assistance to needy area is
enhanced.
The main problem faced in practice is due to the fact that the area
frequency response characteristic is not constant over the operating period
since it depends on number of generating units talung part in the regulation
process, and the prevailing load characteristics. Number of regulating units in
a area change, their regulating characteristic vary over a wide limits, load
varies over a wide range and hence 13 varies over a wide range. Obvious remedy
to this problem is to set frequency bias setting equal to the highest possible
value of 13, thus ensuring 13213 for all operating conditions.
Control action is conventionally based on the Area Control error
computation. A time deviation term is added in the western North American
interconnected systems. Present industry practice is to set the frequency bias
coefficient approximately equal to the "natural" system frequency characteristic,
during heavy load conditions. The natural characteristic is measured for large
disturbances, with bias coefficients normally changed only a t the start of a new
calendar year. Power networks consist of number of utilities interconnected
together and power is exchanged between the utilities over the tie-lines by
which they are interconnected. The net power flow on tie-lines is scheduled on
apriori contract basis. It is, therefore, important to have some degree of control
over the net power flow on the tie-lines. Load-frequency control allows
individual utilities to interchange power to aid in overall security while
allowing the power to be generated most economically.
For a number of years, the problem of Load Frequency Control has been
one of the most accentuated topics in the operation of autonomous and
interconnected systems. The solution of this problem has been one of the first
practical applications of the decentralized control of large scale dynamic
systems. The development of modern computers facilitated the design of all
digital AGC systems. The computerized AGC can incorporate the traditional
load frequency control, which is designed to match the generation to the
varying system demand, and an Economic Dispatch program that distributes
the generation and the generating units so that the total system cost is
minimized.
Load-frequency control is very important item in power system operation
and control for supplying sufficient and reliable electric power with good
quality. Many control strategies have been proposed to achieve better
performance. Due to the non-linearities of various components of power
systems, a linear model obtained by linearization around an operating point is
usually adopted for the controller design. However, because of the inherent
characteristics of changmg loads, the operating point of a power system may
vary very much during a daily cycle. As a result, a fixed controller which is
optimal under one operating condition may no longer be suitable in another
status. In view of this, some authors have applied the variable structure control
to make the control insensitive to the plant parameter changes. However, this
method requires the information of the system states which are not easily
measurable. On the other hand, recently, various adaptive control techniques
have been proposed for dealing with large parmeter variations. Basically,
adaptive control systems can be classified into two categories, namely the self-
tuning regulators and the model reference control systems. The former which
is based on explicit identification of the system transfer function has the
difficulty in designing an efficient on-line identifier. As to the latter, due to the
requirement of satisfying the perfect model following conditions and the state
information of the system, it is rather difficult to be applied to LFC in the
sense of practical implementation.
Most of the work reported in the literature pertaining to LFC of
interconnected power systems is centered around tie-line frequency bias control
strategy. Supplementary controllers are designed to regulate the area control
errors to zero effectively. Several modern design techniques have been used to
optirnize the parameters of the supplementary controllers. Supplementary
controllers regulate the generation so as to match load variation, the frequency
and tie-power deviation from scheduled values. This would result in
accumulations of time error and inadvertent interchange accumulations would
also occur due to errors in measurements of frequencies and tie-powers,
scheduled frequency and tie-power scheduled frequency and tie-power settings
or internal offsets in scheduled settings. It is expected that individual areas will
make all reasonable efforts to minimize time error and inadvertent interchange
accumulations by minimizing or eliminating source causes. Accumulations will
nevertheless occur and there is a need for correcting them. Such corrections are
achieved by making appropriate offsets in system frequency schedules to
compensate for time error accumulations and offsets in area net interchange
schedules to cornpensate fcr ~nsdvertent interchange accumulations. Detailed
literature survey shows that the above mentioned two-step correction scheme
has been used for illustrations in spite of practical difficulties. In order to avoid
such practical difficulties, the utilities are looking forward for a control strategy
that not only maintains constancy of system frequency and desired tie-line
power flow but also zero steady state error. It is essentially in this direction,
the investigations have been carried out by many researchers.
Load frequency control in electric power systems represents the first
realization of a higher level control system. It has made the operation of
interconnected systems possible and today it is still the basis of any advanced
concept for the guidance of large system. A peculiarity of LFC lies in the fact
that each partner in the interconnection has equal rights and possibilities,
being limited only by the installed power in the area and the capability of the
tie-lines. Thus it is not a centralized control system when the total
interconnection is considered. Economic dispatch control and security control
schemes demand the system as a prerequisite for LFC. In the historical
development, LFC systems were installed because of stability problems and the
need for better control of the active power. In Europe the relative ease of
controlling hydraulic power stations has contributed very much to the success
of LFC. In the United States LFC has gained an importance with the growth
of interconnected systems mainly supplied by thermal power stations.
1.2 STATEMENT OF THE PROBLEM
The control of frequency during load variations in a power system is one
of the major problems encountered in the operation of the system as of most
of the electrical appliances need a constant frequency. The development of
design technique for load-frequency control of large interconnected systems is
an important control problem in power system. Many techniques and models
have been proposed in the last few decades using conventional and modern
control concepts for load frequency control problem for improving dynamic
response and stability of the system. However the classical techniques are
having their own drawbacks. In recent literature many people applied modern
control theory for solving LFC problem.
The present work deals with new control strategy of quenching
transients of a load frequency control problem. The load-frequency problem is
represented by a new state space model for a single area and for two area
electric power systems. The state variables selected in this model are frequency,
first and second derivatives of frequency. The steady state operating points
before and after the load disturbance are named as initial state and final states
of the system. Now the problem is to move the system from this initial to the
final state in a definite time without any oscillations. Hence the LFC problem
is restructured as a state transition problem (initial and final states) using a
suitable control parameters. With the help of pontryagin's Maximum PrincipIe
the optimal control is proved to be bang-bang control by minimizing the time
of state transfer. The control parameter taken in this work is the position of
speed changer which is not an external parameter.
A single area power system is considered and the optimal controllers are
synthesized for increase in load position of the system. The switching instants
for the control strategy are evaluated. It is observed that the frequency
transients are quenclred at much faster rates without any oscillations.
The above technique of designing an optimal controller has been
extended for decrease in load position. It is observed that the frequency
transients are quenched at much faster rates. In this analysis the transients a t
switching are not considered. The amount of deviation may be upto 50% of load
disturbance.
For single area power system, studies have been conducted to find the
control strategies to determine the control vector u, and up with different step
load disturbances starting from 0.01 per unit to 0.05 per unit in steps of
0.01 per unit. For each load disturbance, the control inputs for bang-bang
control have been determined. Curves have been drawn between Af on x-axis
and AD.f on y-axis showing the trajectory of operating point.
For optimum LFC, the time taken for the system from disturbed state
to the equilibrium state (Af = 0) should be minimum. To achieve this two
control inputs ul and u2 have been selected. The magnitude and the instant a t
which these controls are to be applied have been different for various load
disturbances. The control input u l is applied after some elapsed time from the
instant of occurrence of load disturbance. This delay has been assumed, as the
time required for sensing the disturbance and changng control position.
The philosophy of the proposed control strategy for increased load
changes is depicted in fig 1.1.
fig. 1.1
'0' is the initial and final equilibrium state after disturbance. 'OA' is the trajectory of the uncontrolled system for step load change. 'AB' is the trajectory of the system with control u,. 'BO' is the trajectory of the system with control u,.
For each load disturbance, the control input u, is changed to a value
equal to a t least the load disturbance. The trajectory of the operating point is
plotted. The time at which u, is to be applied is determined with the help of the
curves plotted with initial state (Af=O) and backward integration of system
equations. The intersection of this trajectory with the u, trajectory gives the
time a t which u, is to be applied for minimum time of transfer. If the curves
don't intersect, the LFC with Af=O is not possible.
From the graphs drawn for different load disturbances, the following
observations are made.
The minimum value of u, or u2 should be at least equal to the magnitude
of the load disturbance.
If the magnitude of u, or u, is increased, the total time taken for the
system to come back to equilibrium state with Af=O decreases.
From time response curves, it can be seen that for higher value of u, and
u,, the system response is fast in returning to the equilibrium state.
For the implementation of the optimal LFC, for different load
disturbances, the control strategies u, and u, magnitudes and the time a t which
they are to be applied can be stored in a look up table of the computer. When
there is a disturbance, the computer can select appropriate optimal values of
u, and u, and apply a t proper instants so that the system may be restored to
new equilibrium state.
13
The method suggested in this provides optimal load frequency controller,
which takes minimum time to come to new equilibrium state with Af=O
compared to methods suggested by others. In addition, LFC controller
suggested can easily by implemented as it does not require a feed back system
or state estimator.
The review of literature of load frequency control is presented in the I1
chapter.
A new state space model for load frequency control is presented in the
chapter 111. The model presented is tested for different load disturbances
ranging from 0.01 per unit upto 0.05 per unit in steps of 0.01 per unit and
compared with the model given by 0.E.Elgerd. rB.11
Chapter N deals with the design of optimum speed regulation constant
R for uncontrolled and controlied mode for various load disturbances from 0.01
per unit upto 0.05 per unit in steps of 0.01 per unit with the present model.
The results are discussed in the same chapter.
The synthesis of optimal controllers of a single area power system, for
an increase and decrease of load disturbances, the strategy, the control inputs
and the switching instants are presented in the chapter V. An attempt is made
to find control inputs for two area power system and results for the both cases
are evaluated and presented in this chapter.
The conclusions and further scope of the proposed strategy are presented
in the chapter VI.