JCM Model Project
Introduction of Amorphous high efficiency transformers in power distribution systems of
Southern Power Corporation (SPC)
KUROYANAGI HiromiSystem Service Department
Yuko‐Keiso Co.,Ltd.
JCM SEMINAR IN IINO HALL & CONFERENCE CENTER, JAPAN 3rd Mar, 2016
Contents1. Corporate Profile and Business in Vietnam
1‐1. Corporate Profile Overview1‐2. Our Business in Japan1‐3. Our Business in Vietnam
2. Introduction of Amorphous high efficiency transformers in power distribution systems2‐1. Project General Information2‐2. Overview of project2‐3. Consortium Structure2‐4. Responsibilities of parties in the Consortium2‐5. Project Schedule2‐6. Schedule for JCM Registration2‐7. Project Cycle of the JCM 2‐8. Applied JCM Methodology2‐9. Applied JCM Methodology
3. Project Advantages and Challenges3‐1. Project Advantages (1), (2)3‐2. Project Challenges
4. Project Expansion 4‐1. Project Expansion4‐2. Expansion of Project Area
1‐1. Corporate Profile OverviewCompany's Name YUKO‐KEISO Co.,Ltd
Founded December, 1963
Headquarters Tokyo
Office & Subsidiaries Domestic (Japan) : 4 offices (Yokohama, Saitama, Tochigi, Tokyo)
Overseas (Vietnam): 1 subsidiary (Hanoi)
Employees 161
Capital 100 million JPY
Annual sales 2.88 billion JPY (the term ended May, 2015)
Lines of Business ・Sales of instruments and automatic control equipment・Engineering service for instrumentations and automatic control systems・Design and installation of electric equipment, electrical communications equipment, air‐conditioning systems, security systems and disaster prevention equipment, and facilities ・Maintenance and management of equipment and facilities related to each item listed above
1. Corporate Profile and Business in Vietnam
1‐2. Our Business in Japan
1. Corporate Profile and Business in Vietnam
Figure: Building Automations System Configurations
YUKO-KEISO provides total control systems based on advanced system engineering for wide-ranging building facilities such as air conditioning, electrical equipment, disaster prevention, and security protection.
We have participated in the construction of many landmark structures in the central Tokyo area .
+ ENERGY‐SAVING SERVICE
http://www.azbil.com/products/bi/ba/index.html
1‐3. Our Business in Vietnam
1. Corporate Profile and Business in Vietnam
http://www.worldatlas.com/webimage/countrys/printpage/printpage.php?l=/webimage/countrys/asia/lgcolor/vncolor.gif
Office in Vietnam(No.32 Pham Huy Thong Str., Ba Dinh District, Hanoi, Vietnam)
Company's Name
Yuko Vietnam Co., Ltd.
Founded July, 2012
Lines of business
・Provide consulting services, installation and maintenance related to the installation of industrial machinery and equipment, mechanical ‐ electric – air equipment, fire protection systems.・Design and technical consulting, software development, assembly and installation of the control panel, integrating, commissioning, maintenance and technical support for the control systems of industrial plants, and control systems for factory automation, control systems and building management systems to save energy and protect environment.・Supervise the installation of electrical equipment and civil and industry works.・Support JCM Feasibility Study (FY 2012‐15)
2‐1. Project General Information
2. Introduction of Amorphous high efficiency transformers in power distribution systems
This project aims to introduce amorphous high efficiency transformers to power distribution systems of Electricity of Viet Nam, and expects to reduce transmission losses of the systems .
Name of Project “Introduction of Amorphous high efficiency transformers in power distribution systems of Southern Power Corporation (SPC)”
Host Country Vietnam
Project Participants JAPAN: YUKO KEISO Co., Ltd. Vietnam: Southern Power Corporation (EVN SPC)
Total equipment cost Approximately 400 million JPY
Period From beginning of Feb, 2015 to end of Mar, 2016
Site Transmission and distribution network in southern Vietnam
Technology Amorphous high efficiency transformer⇒With the use of amorphous high efficiency transformers, it is able to realize a reduction of transmission and distribution losses and contribute to Green House Gas emission reduction
Scale of investment EVN Southern Power Corporation is planning to purchase and install 1,618 Amorphous high efficiency transformers
Finance JCM support from Ministry of Environment of Japan
Expected GHG Reductions
623 tCO2/year
2‐2. Overview of project
2. Introduction of Amorphous high efficiency transformers in power distribution systems
Amorphous high efficiency transformer
Sites of Project Subject of Project
“④TRANSFORMERS” are the subjects of the project.
Project Transformer
Single phase Three phase
The transmission and distribution network in
southern Vietnam(EVN SPC)
By Tonbi ko, https://commons.wikimedia.org/w/index.php?curid=42713363
2‐3. Consortium Structure
2. Introduction of Amorphous high efficiency transformers in power distribution systems
JCM Consortium
YUKO KEISO Co., (Representative of
consortium)EVN SPC
THIBIDI
MOEJ
Hitachi Metals
Indirect management of technology installment and operation
PurchaseAmorphous
Delivery and support maintenance
Report
Report activities
DeliveryOrder
Support on procedureOECC
Japan’s Ministry of environment (MOEJ) supports EVN SPC’s installment of the high‐efficient transformer (which uses Hitachi Metal’s Amorphous metals) by providing the JCM grant up to 50% of the purchase cost.
YUKO KEISO, as representative of the JCM consortium, plays a role of managing the project by collecting evidence of installation, operation of the Amorphous transformers from EVN SPC and applying for the JCM grant. YUKO KEISO is also in charge of reporting annual CO2 reduction volumes of the project to the MOEJ annually.
EVN SPC, as the representative of the consortium in Vietnam side buys and installs the Amorphous transformers utilized Hitachi Metal’s Amorphous metals and reports the operation status to YUKO KEISO by submitting evidence records. EVN SPC also required to report the annual operation records to YUKO KEISO for calculating annual CO2 reduction volumes.
Review
Support on developing methodology ・PDDMUMSS
GEC
2‐4. Responsibilities of parties in the Consortium
EVN SPC
・Purchasing, installing, operating amorphous transformers under the
supervision of YUKO KEISO
・Providing financial and technical documents so that YUKO KEISO could complete the required procedure to get
funding from MOEJ
・Providing operational data of purchased amorphous transformer for calculating
the GHG emission reductions
・Following maintenances scheme and routines as recommended by YUKO KEISO
YUKO KEISO
・Monitoring the purchasing, installation, operation of amorphous transformer.
・Applying, on behalf of the consortium, for JCM financing form MOEJ, then
transferring the whole amount of financial support to Vietnam partners.
・Monitoring the number of purchased transformers as required
・Monitoring and reporting, on behalf of the consortium, the GHG emission
reductions to MOEJ, so that MOEJ can inform MONRE as agreed in the MOU
2. Introduction of Amorphous high efficiency transformers in power distribution systems
2‐5. Project Schedule
2. Introduction of Amorphous high efficiency transformers in power distribution systems
Develop JCM Consortium Agreement
JCM Grant Application and
notification
Tender
Production
Installation and
operation
Reporting
Intermediate Inspection
Delivery the JCM grant
Actual project
FinalInspection
2‐6. Schedule for JCM Registration
2. Introduction of Amorphous high efficiency transformers in power distribution systems
2‐7. Project Cycle of the JCM
Submission of proposed JCM methodology
Approval of proposed
JCM methodology
Development of Project Design Document (PDD)
Validation
Registration
Monitoring
Verification
Issuance of credits
Project Participants (Project Owner)
Joint Committee (JC)
Project Participants
Project Participants
Joint Committee(JC)
Third Party Entity (TPE)
Joint Committee and Each Governments
‐ Provide necessary data/information for development of the methodology
‐ Explain the methodology to JC members if requested by JC
‐ Provide necessary data/information for development of the PDD‐ Submit necessary documents to JC and TPE to begin validation process‐ Cooperate with consultant and join the project site visit by TPE
‐ Explain the project to JC members if requested by JC‐ Submit registration request to JC
‐ Conduct monitoring, provide necessary data/ information to complete monitoring report
‐ Cooperate with consultant and join the project site visit
‐ Explain the project and the monitored result to JC members if requested by JC
Third Party Entity (TPE)
Responsible entityJCM process Role of project participant
Source: http://www.mmechanisms.org/document/20150929_JCM_goj_e_rev.pdf
2. Introduction of Amorphous high efficiency transformers in power distribution systems
2‐8. Applied JCM Methodology
Energizing time of the project amorphous transformersMonitoring option: Based on the actual measurement using measuring equipment (data used: measured values) Source of data: On‐site measurementMeasurement methods and procedures: counting the number of hours of this monitoring periodMonitoring frequency: once at the end of the monitoring period
Criterion 1 Single‐phase and/or three‐phase oil‐immersed transformer with amorphous metal core is installed in the distribution grid
Criterion 2 Load losses of the project transformer determined in line with IEC 60076‐1 or national/industrial standards complying with IEC 60076‐1 is equal or smaller than the standard values or specification values of load loss, required by the power company of the grid where the project transformer is installed, corresponding to its capacity and number of phases.
JCM_VN_AM005 Eligibility Criteria
JCM_VN_AM005
Installation of energy efficient transformers in a power distribution grid, Version 1.0
Monitoring requirement
Applied JCM Methodologies
2‐9. Applied JCM Methodology
2. Introduction of Amorphous high efficiency transformers in power distribution systems
3‐1. Project Advantages(1)
3. Project Advantages and Challenges
1. The financing programme for JCM Model Project supported EVN SPC to install the amorphous transformers with the lower cost.(Tender price compared to JCM)
Calculated by THIBDI and OECC (8 Jan 2015)
0 1 2 3 4
EVN SPC tender
Tender with JCM (before discount)
Tender with JCM (after discount)
$2 $2
$4
$2
million
Conventional (Phase2) Amorphous(Phase2)
Type of transformer Phase 2
Amorphous, 1 phase 1,466
Amorphous, 3 phase 152
Conventional (silicon‐based),1 phase
731
Conventional (silicon‐based),3 phase
75
Total (pcs) 1,618
EVN SPC’s total demand of transformers in 2015, Stage2(not including Rural Energy projects using WB and KfWloan)
3‐1. Project Advantages(2)
3. Project Advantages and Challenges
2. Simple scheme→ This JCM Model Project only supported for equipment cost (Not
included construction costs )→ Project plan is clear and hence it lead to more certainty to
complete
3. Contribute to capacity building→ Study tour to Japan (EVN SPC and THIBIDI visited an amorphous
core factory)→ Effectively transfer the technology→ To build local capacity for manufacturing amorphous transformer
in Vietnam
4. Currency is Japanese Yen5. Property of the project will be thoroughly owned and
managed by EVN SPC (lifetime management is 18 in the Japanese Law )
6. Cooperative relationship
3‐2. Project Challenges
3. Project Advantages and Challenges
1. Monitoring period → After completing the installation, EVN SPC shall regularly report the
operational status (number) to YUKO KEISO until 2020
2. Property management period→ Lifetime management of project transformers is 18 years in the
Japanese Law
3. How to execute and perform the consortium agreement successfully
4. Manual preparation → Implementing the project effectively is required documentation of
procedure and
4‐1. Project Expansion
Phase1 (JFY 2014) Phase2 (JFY 2015)
Host Country Vietnam
ProjectParticipants
JAPAN: YUKO KEISO Co., Ltd.
Vietnam: EVN SPC Vietnam: EVN SPCEVN HCMCEVN CPCDNPC
Total equipment cost
Approximately 500 million JPY Approximately 3 billion JPY
Period From beginning of Feb, 2015 to end ofMar, 2016
From beginning of Feb, 2016 to end of Mar, 2017
Site Transmission and distribution network in the southern part of Vietnam
Transmission and distribution network in the southern and middlepart of Vietnam
Scale of investment
1,618 Amorphous high efficiency transformers
4,834 Amorphous high efficiency transformers
Expected GHG Reductions
623 tCO2/year 4,360 tCO2/year
4. Project Expansion
4‐2. Expansion of Project Area
Phase1
JFY 2014
Phase2
JFY 2015
Phase 3
JFY 2016By Tonbi ko, https://commons.wikimedia.org/w/index.php?curid=42713363
Southern, Middle and North part of Vietnam
4. Project Expansion
Thank you for your kind attention!