1

Department of the Prime Minister and Cabinet

Introduction to SDD and SDD’s project methodology

Note: the policy examples in this document are for illustrative purposes only

Page 2: Introduction to SDD and SDD’s project methodologycdn.nsw.ipaa.org.au/docs/Course-Readings---Dip-Gov... · This will be a twelve week project for SDD involving five staff (three

2

Department of the Prime Minister and Cabinet

The best policy advice is strategic

Good policy is clear about the objectives and outcomes the policy is trying to achieve and the means by which those objectives and outcomes will be achieved.

Formulating the best policy advice requires the taking of a strategic approach

What do we mean by ‘Strategic approach’?

A strategic approach has numerous characteristics, most notably: •  Long term thinking; •  Holistic analysis; •  Using a strong evidence base; and •  Analysing underlying problems

Strategic policy projects intensive strategic focus on a particular policy problem, often with a dedicated team of policy officers from a range of multidisciplinary perspectives

To assist in taking a strategic approach, strategic policy projects may be instigated

Page 3: Introduction to SDD and SDD’s project methodologycdn.nsw.ipaa.org.au/docs/Course-Readings---Dip-Gov... · This will be a twelve week project for SDD involving five staff (three

3

Department of the Prime Minister and Cabinet

Complex problems have:

•  No definitive formulation (defining complex problems is a complex problem)

•  No stopping rule

•  Solutions that are better or worse (rather than true or false)

•  No immediate test of a solution

•  No enumerable (or an exhaustively describable) set of potential solutions

•  Within them, symptoms of other problems

•  High stakes - the planner has no right to be wrong (planners are liable for the consequences of their actions)

Strategic policy projects often address complex public policy problems

Complex problems have common characteristics1

Source: 1) The characteristics of complex problems are not unique and there are many variants. These characteristics are drawn from the work of Rittel and Webber on ‘wicked problems’ – an early conceptualisation of this approach, see Rittel, Horst, and Melvin Webber; "Dilemmas in a General Theory of Planning," pp. 155–169, Policy Sciences, Vol. 4, Elsevier Scientific Publishing Company, Inc., Amsterdam, 1973.

Examples of complex problems:

•  Water reform

•  COAG architecture

•  Schools reform

•  Micro-economic reform

•  Closing the gap

•  Congestion in cities

•  Behavioural change to drive energy efficiency

•  Health and hospitals

•  Federalism

•  Jobs and the economy of the future

•  Local government reform

•  Cyber-crime

We rarely get the chance to engage in policy design from scratch (e.g. design a new tax system from the ground up)

More often we are asked to look at an area with a range of policies, programs, incentives and disincentives at play and ask the questions : Where Australia could go from here? How could we improve upon our current situation? What are some steps we could take to move forward?

Doing this well requires people to combine both a sense of realism with innovative thinking

Policy formulation does not start with a clean slate

Page 4: Introduction to SDD and SDD’s project methodologycdn.nsw.ipaa.org.au/docs/Course-Readings---Dip-Gov... · This will be a twelve week project for SDD involving five staff (three

4

Department of the Prime Minister and Cabinet

Longer-term horizons

Holistic perspective

Underlying problems

Innovative and creative

solutions

Strong evidence

base Shape the

future debate

Inclusively engage

stakeholders

Consideration of implementation

Compellingly communicated

Multi-disciplinary perspective

•  Thinking beyond the next incremental decision

•  Consider how government may position the nation for the future through actions today

•  Thinking beyond any government silos

•  Consideration of issues from whole of government/society perspectives

•  Going beyond treating the symptoms to understand what is truly driving a problem and in turn how it can be addressed.

•  Taking the time to ensure that the right question is being answered

•  Consider and take on board ideas that may seem radical

•  Transformational change is considered

•  New approaches that can be used or solutions that can be borrowed from other domains

•  Applying the most robust analysis to the best available evidence, in order to develop informed answers to the questions posed

•  Create a space for new debates and new discussions to take place

•  Ensure a range of viewpoints are understood and accounted for.

•  This should lead not only to more informed policy advice, but also more innovative and creative solutions

•  Plan to manage and mitigate implementation risks.

•  Consider how best to implement change through the whole delivery system, connecting front-line service delivery to cabinet room policy decision making

•  Persuasive •  Communicated in a simple

and logical fashion which is compelling to the reader

•  Sound rationale and use of narrative to aide communication

•  involves ‘inter-systems’ thinking – thinking beyond any particular portfolio or disciplinary perspective

Solving these complex public policy problems requires a strategic approach

These represent some of the key elements associated with taking a strategic approach to policy

Not all elements will be relevant to any given policy issue

Given time and resourcing constraints, it is simply not possible to always consider all policy issues using an intensive strategic approach

Use of the strategic approach should be based on the complexity of the problem, resource and time constraints

Most of the projects SDD undertakes are complex and require a strategic approach to be taken

Page 5: Introduction to SDD and SDD’s project methodologycdn.nsw.ipaa.org.au/docs/Course-Readings---Dip-Gov... · This will be a twelve week project for SDD involving five staff (three

5

Department of the Prime Minister and Cabinet

To complete strategic policy projects rigorously to tight deadlines, our approach has five broad components

Projects are set up for success with concrete deliverables

Regular meeting rhythm and process

STAIR is an approach to problem

solving and policy development

‘Nailing the question’ is a key feature of SDD’s distinctiveness

Complex strategic policy projects require a significant amount of time spent just getting the question right

Narrative and storytelling used to communicate efficiently and effectively

Communication a focus right from day one, never just at the end of a project

Critical to our approach is bringing people along the journey and getting input from the start

Complex and wide-ranging policy projects require input from a broad range of people

STAIR employs private-sector techniques adjusted for a

complex policy environment to State, Test, Analyse,

Iterate and Resolve

The way each of these components is used varies across different projects and SDD’s approach is evolving and is not ‘set in stone’.

Page 6: Introduction to SDD and SDD’s project methodologycdn.nsw.ipaa.org.au/docs/Course-Readings---Dip-Gov... · This will be a twelve week project for SDD involving five staff (three

6

Department of the Prime Minister and Cabinet

Strategic project teams need to build a culture of trust, collaboration and innovation

Trust

People should feel comfortable to speak up and put their ideas on the table This happens when:

•  Team members are encouraged to put their views forward and they are discussed respectfully

•  The confidentiality of sensitive information and viewpoints is maintained

•  A sense of shared ‘team ownership’ for the project and its outcomes is cultivated

Collaboration

Innovation

Collaboration is vital both within the team and with external stakeholders This happens when:

•  Project management harnesses team member’s different skill sets and experiences effectively

•  A common sense of the policy narrative for the project is developed while capitalising on the different perspectives of team members

•  Ongoing SDD staff are paired up effectively with secondees and interns

•  Expectations for the project are clearly outlined to team members and external stakeholders

Left-field or ‘out-of-the-square thinking should be encouraged This happens when:

•  Project teams ask the question: ‘what is the piece of really interesting work or analysis we could do here?’

•  There is time to read widely and test whether policy solutions can be borrowed from other domains

•  People take a ‘citizen-centred’ approach and think about what the problems are for people on the ground and how any proposed solutions would impact on them

Page 7: Introduction to SDD and SDD’s project methodologycdn.nsw.ipaa.org.au/docs/Course-Readings---Dip-Gov... · This will be a twelve week project for SDD involving five staff (three

7

Department of the Prime Minister and Cabinet

The best way to understand SDD’s project methodology is to apply it using a case study scenario

The Prime Minister recently attended a dinner where an academic gave a speech on women’s participation in Australia, noting that Australia has slipped to number 50 on the 2009 World Economic Forum Gender Global Index of women’s labour market participation. The Secretary has asked for a strategic policy project to consider ways in which the workforce participation rate of women in Australia could be increased. The Secretary has stressed that he would like the project to consider all the issues and drivers associated with the problem, rather than focusing purely on economic issues. This will be a twelve week project for SDD involving five staff (three ongoing and two secondees).

Commissioning Brief: Hypothetical example – Women’s workforce participation project

Over the course of the day your group will complete five activities that echo the first key steps of a typical SDD project: 1.  An information gathering activity where you will identify

the precise nature of the problem and its context, and familiarise yourself with current thinking;

2.  A project scoping activity where you will develop an ‘issues tree’ to systematically break the problem down into its component issues and use this analysis to generate a project plan;

3.  A statement generation activity where you will have a ‘first crack at the answer’, tease-out your core assumptions and identify the most effective analytical methods to test these assumptions;

4.  A stakeholder mapping activity where you will identify the individuals/groups most affected by your project and consider how best to identify, balance and respond to, their competing needs and interests; and

5.  A ‘ghost deck’ activity where you will use narrative techniques to ‘storyboard’ your project’s aims, assumptions and analyses and present your argument to your project sponsor.

Page 8: Introduction to SDD and SDD’s project methodologycdn.nsw.ipaa.org.au/docs/Course-Readings---Dip-Gov... · This will be a twelve week project for SDD involving five staff (three

8

Department of the Prime Minister and Cabinet

Focus on scoping STAIR approach to problem solving and policy development Inclusively engaging stakeholders Compellingly communicated Dedicated project management

Page 9: Introduction to SDD and SDD’s project methodologycdn.nsw.ipaa.org.au/docs/Course-Readings---Dip-Gov... · This will be a twelve week project for SDD involving five staff (three

9

Department of the Prime Minister and Cabinet

Project scoping is our opportunity to really nail the question – and identify the different approaches we can bring

We are in the privileged position to be able to challenge the question we are being asked to solve – we should use this privilege effectively in the scoping stage. Then we can deliver a solution to the real problem

What is the problem?

What is the real goal or outcome that we want to achieve? And therefore, what is the real question we are being asked?

What has been tried in the past? Is there a better question to be asked?

What are the constraints? And which of these constraints are truly binding?

What is in and out of scope?

Complex problems cross multiple dimensions – to make the project tractable we need to agree on what is out of scope.

Some things may be out of scope for political or practical reasons

Clarifying scope is important in managing stakeholder expectations.

Can the problem be solved?

Sometimes the combination of constraints and scope mean that we cannot make a meaningful contribution – we should be honest and say that

We can still maximise our contribution by providing clarity on the issue and identifying the barriers to solving the problem

What is the interesting piece of work we can do?

In most projects we need to do more than review existing literature or data.

What is the different approach that we can take?

What is the distinctive piece of analysis or modeling that will illustrate an aspect of the problem in a different way – leading to a distinct solution?

Page 10: Introduction to SDD and SDD’s project methodologycdn.nsw.ipaa.org.au/docs/Course-Readings---Dip-Gov... · This will be a twelve week project for SDD involving five staff (three

10

Department of the Prime Minister and Cabinet

The first step is to get a preliminary understanding of the problem

Read background information

Search for relevant information

Discuss with colleagues & team

‘Get smart’ on the topic

Ask questions!

PM&C Library

Page 11: Introduction to SDD and SDD’s project methodologycdn.nsw.ipaa.org.au/docs/Course-Readings---Dip-Gov... · This will be a twelve week project for SDD involving five staff (three

11

Department of the Prime Minister and Cabinet

Case study exercise: Information Gathering

Exercise 1—Information gathering

Task: Read the available background

information and discuss to develop a

preliminary understanding of the issue

and context Tips: •  Read all the materials provided

•  Think through the questions provided

•  Always keep in mind, ‘how big is this

issue’ and ‘what am I really trying to

address here?’ •  Discuss within your team, this brings

out opinions and different ways of

looking at information very quickly

Time: This should take about 45

minutes, read through the material

yourself and then discuss for 30 minutes

Page 12: Introduction to SDD and SDD’s project methodologycdn.nsw.ipaa.org.au/docs/Course-Readings---Dip-Gov... · This will be a twelve week project for SDD involving five staff (three

12

Department of the Prime Minister and Cabinet

Once familiar with the problem and its context, we break it down into its component parts to structure our thinking

How can the government use non-traditional behavioural change tools to influence citizens to reduce GHGs when using energy?

Which behaviours are currently creating household GHGs?

What equipment/appliances are the main sources of GHGs?

Which citizens are creating GHGs? (audience)

What changes can citizens make to produce less GHGs?

Can citizens move to cleaner sources of energy?

Can citizens stop using energy?

Can citizens remove GHGs from the atmosphere?

Can they buy carbon offsets?

Can they contribute to others buying carbon offsets? Can they buy charcoal to remove carbon?

Can they remove carbon from other ways?

Can citizens use energy more efficiently?

Can we change some citizen behaviour to stop energy use?

Can we eliminate an appliance? Can we change some citizen behaviour to use less?

Can we switch to appliances/equipment that is more efficient?

Can we move citizens to all clean energy?

Can we move some citizens in part to cleaner energy?

What new behavioural change levers could be used to influence citizens to reduce GHG?

Where are the main sources of GHGs omitted (geography)?

How are citizen GHG emissions distributed throughout the year? Why are citizens indulging in GHG behaviour when alternatives exist?

Can we use financial tools? Can we use motivational tools? Can we use norm tools? Can we use effort tools?

What new proposals can we conceive (including drawn from non-energy efficiency initiatives)?

What has been done (or is planned ) in Australia to reduce household GHG emissions?

What has been done internationally to reduce citizen’s GHG?

Can we optimise the running of the appliance/ equipment?

Travel (34%) Home appliances (59%) Other uses (7%)

Segment 1 Segment 2 Segment 3 Other segments

Who was targeted?

What tools was used? How was it measured?

How effective was it?

Who was targeted?

What tools was used? How was it measured?

How effective was it? Who will be targeted?

Others?

Issue trees can be used for identifying and/or clarifying the problem

For illustrative purposes only

Page 13: Introduction to SDD and SDD’s project methodologycdn.nsw.ipaa.org.au/docs/Course-Readings---Dip-Gov... · This will be a twelve week project for SDD involving five staff (three

13

Department of the Prime Minister and Cabinet

Capturing all the relevant information on a single scoping slide supports a focused discussion with the sponsor or client

Overall question/problem Context

Probably the hardest part of the project

•  What precisely is the problem – which is often very different to the problem that we have been presented with

•  What precisely is the question that our project will seek to answer

Context is important as it illustrates that we have sufficient understanding of the issues to have a credible crack at the problem

It also allows us to check that we have correctly defined and understood the ‘universe’ in which the problem is situated

Scope Stakeholder Engagement

There are three key things in defining our scope:

•  What issues are we going to focus on

•  What issues are we not going to focus on (possibly more important)

•  What is the ‘cool’ piece of analysis we are going to do that will separate our work from other work in the area

The focus of this section is on identifying the key stakeholders that we need to engage

A more detailed stakeholder engagement plan needs to be developed once the scope has been agreed

Governance and team resources End products

This is the “bottom line” of the scope for the sponsor and senior management. It tells them the resource cost, and the cost in their time to make the project a success. Don’t ‘cost pad’, but don’t fall into the trap of underestimating the true cost of the work

A clear focus on the end products is critical in framing all the work - it needs to identify the product and the audience

•  Cabinet Submission;

•  Briefing for the PM

Having a clear scoping document and then getting it agreed with the project sponsor and steering group is critical in ensuring that expectations are met on all sides

Page 14: Introduction to SDD and SDD’s project methodologycdn.nsw.ipaa.org.au/docs/Course-Readings---Dip-Gov... · This will be a twelve week project for SDD involving five staff (three

14

Department of the Prime Minister and Cabinet

Case study exercise: Project Scoping

Exercise 2—Project scoping

Task: Break the problem down into

manageable components by building an

issue tree Tips: •  Use the MECE principle, trying to

ensure that the branches of the tree

are Mutually Exclusive and

Collectively Exhaustive, so that the

solution space is covered efficiently

•  There’s no single correct answer,

there are many ways to break up any

problem •  Can you break it down by cohort, by

barrier, by action, or some other

categorisation? Time: This should take about 60

minutes, though in a normal project it

might be revised many times over!

Page 15: Introduction to SDD and SDD’s project methodologycdn.nsw.ipaa.org.au/docs/Course-Readings---Dip-Gov... · This will be a twelve week project for SDD involving five staff (three

15

Department of the Prime Minister and Cabinet

Focus on scoping STAIR approach to problem solving and policy development Inclusively engaging stakeholders Compellingly communicated Dedicated project management

Page 16: Introduction to SDD and SDD’s project methodologycdn.nsw.ipaa.org.au/docs/Course-Readings---Dip-Gov... · This will be a twelve week project for SDD involving five staff (three

16

Department of the Prime Minister and Cabinet

Our STAIR methodology employs private-sector techniques adjusted for our complex policy environment

State... ...what you think is the root cause of/ solution to, the problem

Test... ...your statement with key stakeholders

Analyse... ...the assumptions that underlie your statement by gathering evidence

Iterate... ...to progressively refine your statement to reflect new knowledge

Resolve... ...the project by agreeing recommendations & identifying next steps

You may find that you revisit the statement generation step as you gather more evidence and your thinking evolves – this is not evidence that your project is failing, to the contrary, it is a fundamental quality of the STAIR model.

Page 17: Introduction to SDD and SDD’s project methodologycdn.nsw.ipaa.org.au/docs/Course-Readings---Dip-Gov... · This will be a twelve week project for SDD involving five staff (three

17

Department of the Prime Minister and Cabinet

In the STAIR approach we quickly generate an initial answer as a way of identifying key elements and then iteratively improve on that answer

Strengths of the STAIR approach

•  Allows the team to come to a position quickly and to communicate an answer throughout the project

•  Coming to a position early on means it is constantly tested – e.g. against beliefs, existing positions, data, stakeholders – which helps strengthen the veracity of the position

•  Well targeted to the problem under consideration

•  More flexible to changing commissioning environment (which often occurs in high stakes projects)

•  Close and constant liaison with stakeholders means they are part of developing the solution, rather than merely being consumers of the end product

•  Close liaison with stakeholders allows a more immediate assessment of which constraints are actually binding

The STAIR approach involves making the best assessment of the answer very early, and then undertaking the necessary analysis to see if the answer is supported

The initial answer statement is heavily informed by early consultation with senior stakeholders and subject matter experts. This approach brings the key elements to the surface quickly.

The process is iterative – the answer statement guides the analysis, but then the analysis usually leads to an amendment of the answer statement. Supporters of this kind of approach argue that this iterative approach closes on the right answer much more rapidly than a more comprehensive approach

By focusing on the statement, analysis is prioritised, so time is not wasted researching areas well away from the actual solution, nor is time wasted on ‘interesting’ areas of analysis that are not central to the real problem

What is the STAIR approach?

.

The key to the STAIR approach is that it surfaces rapidly the key issues and elements of the problem, by focusing stakeholders attention on whether they agree or disagree with your answer statement

Page 18: Introduction to SDD and SDD’s project methodologycdn.nsw.ipaa.org.au/docs/Course-Readings---Dip-Gov... · This will be a twelve week project for SDD involving five staff (three

18

Department of the Prime Minister and Cabinet

While the STAIR approach has many benefits, we must account for the pitfalls and counter them wherever possible

•  Deep and broad consultations with a diverse range of stakeholders is critical in developing the issues tree and the initial answer statement. The statement needs to be tested with project sponsors and subject matter experts before detailed analysis begins.

•  Management practices need to support ‘left field thinking’ – particularly at the scoping stage. Alternative views can also be sought through broad consultations – not just talking to the usual experts

•  Senior stakeholders and team members need to be familiar with the STAIR approach and the importance of iteration when they are using it – although even the strongest warnings to senior stakeholders will not fully mitigate this risk

•  Avoiding demands for “policy-based evidence” is a challenge for all policymakers. The STAIR approach just makes this risk more explicit

•  Sponsors and steering/reference group members need to be familiarised with the strengths and weaknesses of the STAIR approach – including that the first ‘go’ at the answer is to surface the key issues as much as to get it right

How to manage these risks

•  Does not provide a comprehensive cost-benefit analysis of all the options – which makes the approach inherently more risky.

•  If there are multiple possible solutions we are not guaranteed of finding the best solution

•  Choosing the initial (and often obvious) solution may preclude us from exploring the genuinely innovative solutions

•  The team may become overly attached to the initial statement, which runs the risk of not fully interrogating all possible answers

•  Senior stakeholders may become overly attached to the initial solution – particularly if it is compellingly communicated and they announce it publicly

•  The approach runs the risk of generating “policy-based evidence” to support the initial disposition of project sponsors or key clients

•  The STAIR approach requires the team to take risks – to have a go at the answer with only limited knowledge. To be successful there needs to be a trusting relationship between the team, the project sponsor and the steering/reference group

Risks of a STAIR approach

The STAIR approach is not without risks, but if these are well mitigated it provides a highly effective way to tackle complex problems against tight deadlines

Page 19: Introduction to SDD and SDD’s project methodologycdn.nsw.ipaa.org.au/docs/Course-Readings---Dip-Gov... · This will be a twelve week project for SDD involving five staff (three

19

Department of the Prime Minister and Cabinet

We develop a statement tree to rapidly develop a testable answer that brings out the key elements of the problem

Government should automate service delivery

Statement of the answer:

Statement of the problem Satisfaction with service

delivery is declining

‘Facts’ to test answer statement:

Citizens prefer government

services to be automated

We can identify services that

should be automated

The benefits for government outweigh the

costs

This is feasible in the current

legislative framework

Sub elements:

Source: BCG experience

There’s nothing wrong with being wrong! The point of the answer statement is to test it and refine it, not get it right the first go

The statement and ‘facts’ (its underlying assumptions) need to be clear and testable

Be prepared to share you statement with as many people as possible, and get their input on what needs to change

Have your best go at getting it right, drawing on as much expertise as you can, but don’t anchor yourself to it; your first statement will change!

Tips for statement tree

Page 20: Introduction to SDD and SDD’s project methodologycdn.nsw.ipaa.org.au/docs/Course-Readings---Dip-Gov... · This will be a twelve week project for SDD involving five staff (three

20

Department of the Prime Minister and Cabinet

Answer statement Sub-Issue Analysis Output Resp/Due Date

It is feasible to reduce the number of factories

Some factories have excess capacity

Determine capabilities on an ‘equivalent unit’ basis

Capacity (Kg 13mm Equiv)

Demand is not rising at a significant rate to require new factories

Determine demand on an ‘equivalent unit’ basis

Demand (Proj)

Closing a factory saves more money that the cost of shutting down

From previous analysis Determine which factory provides greatest savings

Savings From Branch Closure

(Branch A)

There are no significant risks to shutting down factories

Determine risk of having fewer than three locations

Capacity can be increased in remaining factories

Ability to shift machinery

The STAIR approach supports good work planning and output management

Ulv MM SD Total

91 92 93 94

Kg

Reduction in FC

VC Savings In Other Plant

Other Trans- port etc

Total Sav- ings

How you are going

to find out?

What will you

produce?

Who will do it by when?

What you need to prove?

Page 21: Introduction to SDD and SDD’s project methodologycdn.nsw.ipaa.org.au/docs/Course-Readings---Dip-Gov... · This will be a twelve week project for SDD involving five staff (three

21

Department of the Prime Minister and Cabinet

1 2 3Potential sources include:

Domestic

•  Departments and agencies (e.g. Treasury, the Productivity Commission)

•  Research organisations (e.g. ABS, CSIRO)

•  Longitudinal data sets (e.g. HILDA)

International

•  OECD

•  World Bank

•  UN Organisations

We can build on existing data by:

•  Undertaking new modelling

•  Scrutinising and then amending the assumptions underpinning data

•  Building ‘driver trees’ and using the data to solve our specific questions

•  Testing other people’s research findings with stakeholders

Potential methods include:

•  Surveys

•  Focus groups

•  Workshops

•  Case studies

•  Interviews

•  Discourse/textual analysis

We can test our statements using three broad sources of data

We should consider innovative ways to approach analyses and draw on both quantitative and qualitative methodologies

We can draw upon existing analyses

We can perform our own analyses using existing data

We can generate / commission our own data

Page 22: Introduction to SDD and SDD’s project methodologycdn.nsw.ipaa.org.au/docs/Course-Readings---Dip-Gov... · This will be a twelve week project for SDD involving five staff (three

22

Department of the Prime Minister and Cabinet

When testing statements it also helps to consider them from different perspectives

These perspectives are not mutually exclusive and overlap

Top- down (e.g. institutional perspective) Bottom-up (e.g. individual citizen’s perspective)

Multi-disciplinary perspectives (e.g. economic, administrative anthropological and legal)

Multi-cohort perspectives (e.g. majority/minority groups)

1

2

3

Page 23: Introduction to SDD and SDD’s project methodologycdn.nsw.ipaa.org.au/docs/Course-Readings---Dip-Gov... · This will be a twelve week project for SDD involving five staff (three

23

Department of the Prime Minister and Cabinet

Statements can be tested using both top-down and bottom-up perspectives

1

From a bottom up perspective, the policy maker might consider: •  What impact might an increase in the GST have on

Joanne, a working mum from Wollongong?

•  Would an increase in the GST create further administrative burden for a particular small business operating in the retail sector?

•  How would the increase in GST be explained to this particular small business?

Bottom up – focus on individuals

•  Brings an individual’s perspective to policy problems and solutions

•  It assesses the costs and benefits of policy options for particular individuals

•  Focuses on local level circumstances and encourages thinking about what might be achieved on the ground for a particular individual or group of individuals

Top down – focus on systems •  Brings a system-wide

perspective to policy problems and solutions

•  It assess the costs and benefits of policy options in aggregate

•  Focuses on international, national and state/territory actors

Hypothetical Statement: The GST needs to be increased

From a top down perspective, the policy maker might consider: •  How might this influence total government revenue?

•  What might be the administrative cost of the change?

•  How might this influence Commonwealth and State financial relations?

•  How might business groups (e.g. the Business Council of Australia) react?

Page 24: Introduction to SDD and SDD’s project methodologycdn.nsw.ipaa.org.au/docs/Course-Readings---Dip-Gov... · This will be a twelve week project for SDD involving five staff (three

24

Department of the Prime Minister and Cabinet

Statements can be tested using multi-disciplinary perspectives – applying different problem-solving frames to a single issue

2

Policy Problem

Institutional •  Map institutions and their

functions •  Explore connections and

disconnections between institutions

Administrative •  Map the processes that

exist around a problem •  Consider issues of system

capability

Legal •  Consider the rules,

regulations and sanctions that may apply to a problem

•  Explore whether there are too many rules or not enough

Anthropological •  Examine the social and

cultural conditions that underpin a problem

•  Seek to understand the history of a group of people

Economic •  Explore the operation

of markets and incentives

•  Identify market failures and consider interventions and their consequences

Hypothetical Statement: There is a lack of financial services in remote Indigenous communities

Institutional •  Which financial institutions have a presence in remote

communities and what services are they providing?

Legal •  Are there any legal obligations on financial institutions to

provide services in remote locations?

•  Are appropriate regulatory and law enforcement arrangements in place to prevent fraud associated with financial products?

Anthropological •  How do particular remote Indigenous communities

currently save and trade money? How have they saved and traded resources in the past?

Administrative •  What processes do people undertake to access, save and

spend Centrelink payments?

Economic

•  What is the market failure leading to a lack of financial services in communities?

•  What incentives might lead to the provision and use of these services?

Statements that are proved valid from a number of disciplinary perspectives are more likely to be correct and hold significant weight in a policy development process

Page 25: Introduction to SDD and SDD’s project methodologycdn.nsw.ipaa.org.au/docs/Course-Readings---Dip-Gov... · This will be a twelve week project for SDD involving five staff (three

25

Department of the Prime Minister and Cabinet

Statements can be tested using a multi-cohort perspective, exploring the views of majority and minority groups

3

Policy Problem

Majority Group

Majority Perspective

A majority perspective would ask whether the proposed policy provides an overall benefit to the community. ‘The greatest good for the greatest number’

Minority Perspective A minority group perspective would ask what impact the policy has on groups in the community, and whether particular groups are advantaged or disadvantaged more than others by the policy.

Age group

Ethnic group

Income bracket

Family type

Geographic group

Hypothetical Statement: We should create more jobs in service industries to reduce unemployment

From a majority group perspective, the policy maker might consider: •  Are the majority of Australians now employed in

service industries?

•  Will increasing employment in service industries have the maximum flow-on effect for GDP?

•  Will inflation increase?

When considering various minority groups the policy maker might consider:

•  Will this measure assist older Australians?

•  Will this largely affect employment figures in lower income brackets?

•  Are there more casual / part-time workers in service industries?

•  Will this measure work to improve unemployment rates in the bush?

Page 26: Introduction to SDD and SDD’s project methodologycdn.nsw.ipaa.org.au/docs/Course-Readings---Dip-Gov... · This will be a twelve week project for SDD involving five staff (three

26

Department of the Prime Minister and Cabinet

Iteration is an important component of our approach—we will revise our answer many times before the final version

First answer statement First draft of your deck Successive revisions Final version

SDD experience tells us there will be MANY iterations This is normal – if the solution to the problem was known, we wouldn’t be working in this space!

Structure

Cabinet In Confidence 

Strategy and Delivery

First Draft of deck

2 July 2010

Cabinet-In-Confidence

Cabinet In Confidence 

Strategy and Delivery

Final Version of Deck

24 September 2010

Cabinet-In-Confidence

Answer

Situation

Complication

Resolution

Page 27: Introduction to SDD and SDD’s project methodologycdn.nsw.ipaa.org.au/docs/Course-Readings---Dip-Gov... · This will be a twelve week project for SDD involving five staff (three

27

Department of the Prime Minister and Cabinet

Case study exercise: Statement Generation

Exercise 3—Statement generation

Task: Have a first attempt at the answer by

converting the issue tree into a statement tree.

Then decide what analysis might be necessary

to prove each statement correct or incorrect

Tips: •  Turn your issue tree from questions into

statements •  Use the first three steps of the STAIR

method •  Be creative about the way you can prove

each statement correct or incorrect—this is

the time to decide what the real work you will

do is, and how you will do it

•  There are many different ways to prove your

point, think of qualitative and quantitative

methods Time: This is the most important part of

problem solving, it should take about 45

minutes today, but may take a week in a

normal project

State...

Test...

Analyse...

Iterate...

Resolve...

Page 28: Introduction to SDD and SDD’s project methodologycdn.nsw.ipaa.org.au/docs/Course-Readings---Dip-Gov... · This will be a twelve week project for SDD involving five staff (three

28

Department of the Prime Minister and Cabinet

Focus on scoping STAIR approach to problem solving and policy development Inclusively engaging stakeholders Compellingly communicated Dedicated project management

Page 29: Introduction to SDD and SDD’s project methodologycdn.nsw.ipaa.org.au/docs/Course-Readings---Dip-Gov... · This will be a twelve week project for SDD involving five staff (three

29

Department of the Prime Minister and Cabinet

Stakeholders are often thought to be the senior people in key decision-making roles, but in reality they are a subset of our stakeholders A stakeholder is anyone who has an interest in, has influence on, or is impacted by the outcomes of a decision or action Stakeholder management can be thought of as the planning and execution of how we engage with stakeholders

Good stakeholder management means we engage effectively with people with an interest in, or an influence on, our project

Stakeholder management links to and supports other parts of the SDD methodology: •  STAIR approach – helps form and test the answer •  Evidence-based approach – helps gather evidence and ensure

representativeness •  Systems thinking – helps manage complexity

Page 30: Introduction to SDD and SDD’s project methodologycdn.nsw.ipaa.org.au/docs/Course-Readings---Dip-Gov... · This will be a twelve week project for SDD involving five staff (three

30

Department of the Prime Minister and Cabinet

The complexity of the issues, the tight deadlines and our iterative approach put a higher premium on good stakeholder engagement

Good stakeholder management is important

for good policy

Identifying and working closely with content experts delivers a higher quality product

Working with the key decision-makers to build their support is critical to getting any proposals accepted

Engaging with opponents mean that their concerns can either be addressed or rebutted

BUT

Our issues are often complex

So we need to engage more deeply

We work to tight deadlines

So we need to engage more frequently

We take an iterative approach

So our answers can change significantly and rapidly

SO

We need to place a higher premium on good stakeholder management and ensure that we do it in a systematic and effective way We also need to do it in the right way to ensure that we build the relationship of trust that underpins the use of a STAIR approach

Page 31: Introduction to SDD and SDD’s project methodologycdn.nsw.ipaa.org.au/docs/Course-Readings---Dip-Gov... · This will be a twelve week project for SDD involving five staff (three

31

Department of the Prime Minister and Cabinet

Who are our stakeholders and why do we engage with them?

Who stakeholders are may range

from project sponsor to end

users

The purposes of engagement

will vary

The nature of the engagement will depend on how the project

is set up

•  Goals •  Audience •  Timeframe •  Subject

1.  Increase the quality of inputs (evidence) for our work

•  Need varying perspectives on complex problems to get a comprehensive understanding of issues (and solutions)

2.  Communication and selling of ideas •  Demonstrate breadth of input

(inclusiveness) •  Get people onside •  Get commitment of resources •  Achieve consensus where we can •  Where we can’t get consensus, clearly

identify the points of difference – and propose options

•  Project sponsor •  Within PM&C •  Within the Commonwealth •  States and Territories •  Implementers, workforce •  Interest groups, end users •  Any others affected by a

decision

Page 32: Introduction to SDD and SDD’s project methodologycdn.nsw.ipaa.org.au/docs/Course-Readings---Dip-Gov... · This will be a twelve week project for SDD involving five staff (three

32

Department of the Prime Minister and Cabinet

There are a range of tools that we use

It is important to note there is no set way, or mandated tools to do stakeholder management as each project will have a unique set of stakeholders

Govt funders

Teacher pay

Classroom conditions

Unions

Co-located nurses

Health system

Disadva-ntagedchildren

Parents

Example: Schools

Stakeh-older

Issue

inform

consult

collaborate

empower

listen

Decide in favour of A

B becomes hostile

B does XXX

YYYXXX??End results

Potential consequences

Initial decision

B does XXX, but A does YYY

ZZZYYY

Stakeholder 1

Stakeholder 2

Stakeholder 3

Stakeholder 4

Issue 1 Position Position Position Position

Issue 2 Position Position Position Position

Issue 3 Position Position Position Position

Issue 4 Position Position Position Position

Potential trade-off

Decision trees Understand the consequences of decisions

Stakeholder framework Understand where tradeoffs can be made

Stakeholder heat map Understand support and challenges

Venn diagram Understand how interests overlap

Network map Understand connections and nodes of influence

Stakeholder engagement ladder Decide on the appropriate level of engagement

Degree of buy in -

Importance

of stakeholders

Attention needed – manage risk

Limit input – filter unneeded information

Champions – actively involve

Supporters – keep engaged

Page 33: Introduction to SDD and SDD’s project methodologycdn.nsw.ipaa.org.au/docs/Course-Readings---Dip-Gov... · This will be a twelve week project for SDD involving five staff (three

33

Department of the Prime Minister and Cabinet

Case study exercise: Stakeholder Mapping (Group exercise)

Exercise 4—Stakeholder mapping

Task: Identify important stakeholders for

the project and how you will engage

them using the ladder model

Tips: •  Think of this broadly, not just in terms

of the process of doing the project,

but also in terms of content—who will

be impacted by your

recommendations, which citizens

does the project affect

•  List both those that will be in favour

as well as those you will have to work

hard to convince

•  Discuss how you will engage each

group of stakeholders

Time: 30 minute group discussion

inform

consult

collaborate

empower

listen

Page 34: Introduction to SDD and SDD’s project methodologycdn.nsw.ipaa.org.au/docs/Course-Readings---Dip-Gov... · This will be a twelve week project for SDD involving five staff (three

34

Department of the Prime Minister and Cabinet

Focus on scoping STAIR approach to problem solving and policy development Inclusively engaging stakeholders Compellingly communicated Dedicated project management

Page 35: Introduction to SDD and SDD’s project methodologycdn.nsw.ipaa.org.au/docs/Course-Readings---Dip-Gov... · This will be a twelve week project for SDD involving five staff (three

35

Department of the Prime Minister and Cabinet

Storytelling is a critical element to SDD’s methodology

Why we tell stories

How we tell stories

Good stories should...

However, evidence must always drive the story

•  Increasingly, advice must look to persuade as well as inform

•  Stories are relatable and compelling

•  Presenting evidence in a story makes complex things easier to understand and more memorable

•  There is an appropriate blend of structure and flow, evidence and anecdote

•  Involves arguing why the recommended approach is more compelling than alternative recommendations

•  Emphasises what is new, different and innovative in our recommendations – because this is ultimately more interesting than the status quo and will stay with the reader

•  Situates the decision maker within the story

•  Provide an impetus to their action

•  Assist the decision maker visualise new possibilities and anticipate future reform directions

•  Open up vision and imagination

•  There is a fine balance between evidence dictating story and story dictating evidence – and it is imperative this is managed to ensure evidence always informs the story being told

•  And we don’t omit critical information to support a more compelling story

Page 36: Introduction to SDD and SDD’s project methodologycdn.nsw.ipaa.org.au/docs/Course-Readings---Dip-Gov... · This will be a twelve week project for SDD involving five staff (three

36

Department of the Prime Minister and Cabinet

Good analysis is not enough – it needs to be communicated compellingly to stand up against well communicated poor analysis

In a contestable environment, policy advice has to be persuasive. Good policy advice is compelling. It is embraced by Ministers, even if not immediately, and is impervious to the assaults of other players in the game, including those motivated by vested interests. Public policy advisers who appreciate this point pay as much attention to the construction and presentation of an argument as they do the quality of the analytical content and the soundness of its strategic perspective.

Ken Henry Secretary of the Treasury, 2007

Page 37: Introduction to SDD and SDD’s project methodologycdn.nsw.ipaa.org.au/docs/Course-Readings---Dip-Gov... · This will be a twelve week project for SDD involving five staff (three

37

Department of the Prime Minister and Cabinet

Though we use different formats, the approach to communication must always be clear and compelling

Slide decks Public policy papers Speeches

Cabinet submissions Briefs to PM Emails

SOME TIPS   Set out your argument in one line: what is the one idea you want people to take from

your work?   Write for an intelligent outsider. Write as if you’re talking to someone at a dinner party.   Stories stick: are there any stories that can enliven your work?

Page 38: Introduction to SDD and SDD’s project methodologycdn.nsw.ipaa.org.au/docs/Course-Readings---Dip-Gov... · This will be a twelve week project for SDD involving five staff (three

38

Department of the Prime Minister and Cabinet

Good writing is good story-telling: a template for our work

This template can be modified or embellished but it is the basic structure of many (perhaps most) stories, and of our policy work

We are here:

We want to go there:

Why do we want to go there?

How do we get there?

What difficulties lie along the way?

How will we know when we have got there? The Secretary: what will success look like?

Page 39: Introduction to SDD and SDD’s project methodologycdn.nsw.ipaa.org.au/docs/Course-Readings---Dip-Gov... · This will be a twelve week project for SDD involving five staff (three

39

Department of the Prime Minister and Cabinet

Two stories: very different and yet the same a) Health policy b) Lord of the Rings

We are here:

a)  Our health system is under pressure and faces mounting challenges

b)  Sauron wants his Ring of Power but Frodo has it

We want to go there:

a)  We need to build a health system for the 21st century

b)  Frodo must throw the Ring into Mount Doom

Why do we want to go there?

a)  Because a strong health system is essential to a strong, fair society

b)  Because it is good to save the world from evil

How do we get there?

a)  By an alliance with states, a stronger Commonwealth role, better hospitals, and a good map

b)  By an alliance with elves, dwarves and wizards, and a good map

Difficulties along the way?

a)  Potential cost blowouts, arguments with the states, a shrinking budget

b)  Black Riders, orcs, and a giant spider – all require rigorous policy responses

How will we know?

a)  Patients get excellent service at an acceptable cost; society is healthy

b)  The Ring destroyed, Middle Earth saved

Page 40: Introduction to SDD and SDD’s project methodologycdn.nsw.ipaa.org.au/docs/Course-Readings---Dip-Gov... · This will be a twelve week project for SDD involving five staff (three

40

Department of the Prime Minister and Cabinet

Storyboarding the titles and then preparing a simple ghost deck lets you check whether you have a good story

Page 41: Introduction to SDD and SDD’s project methodologycdn.nsw.ipaa.org.au/docs/Course-Readings---Dip-Gov... · This will be a twelve week project for SDD involving five staff (three

41

Department of the Prime Minister and Cabinet

Exercise 4—Ghost deck

Task: Put together a ghost deck to

describe your early narrative, and to

give an outline of what analysis you will

do throughout the project

Tips: •  This is not a final answer, it is a first

attempt at how you will describe the

problem and the solution

•  There are different methods to writing

a story, discuss a number of them, for

example ‘situation, complication,

resolution’ or ‘where are we, where to

we want to be, how do we get there’

Time: 1 hour, but leave some time to

discuss how you will present it to your

project sponsor and other stakeholders

to get their early input

Case study exercise: Ghost Deck

Page 42: Introduction to SDD and SDD’s project methodologycdn.nsw.ipaa.org.au/docs/Course-Readings---Dip-Gov... · This will be a twelve week project for SDD involving five staff (three

42

Department of the Prime Minister and Cabinet

Focus on scoping STAIR approach to problem solving and policy development Inclusively engaging stakeholders Compellingly communicated Dedicated project management

Page 43: Introduction to SDD and SDD’s project methodologycdn.nsw.ipaa.org.au/docs/Course-Readings---Dip-Gov... · This will be a twelve week project for SDD involving five staff (three

43

Department of the Prime Minister and Cabinet

Good project management is critical if we are going to find solutions to complex problems in tight timeframes

•  Our projects are often extremely complex

•  We work in multi-disciplinary teams with people from diverse backgrounds including other departments, other divisions and the private sector

•  We work to tight deadlines, our projects require rapid responses

•  We need input from a wide range of experts to get to the right answer

•  We need to engage a large number of stakeholders along the way to ensure agreement

•  Each project is unique—there is no set formula for getting to the right answer

There are a number of factors that mean our projects require dedicated project management

There is always more work that could be done on a difficult problem. Good project management ensures that we consciously choose what level of resourcing to invest – and that we get the best answer we can with that investment

Page 44: Introduction to SDD and SDD’s project methodologycdn.nsw.ipaa.org.au/docs/Course-Readings---Dip-Gov... · This will be a twelve week project for SDD involving five staff (three

44

Department of the Prime Minister and Cabinet

Project planning requires thinking through all the interactions and deliverables ahead of time

Project planning

•  Good project planning is more than just a Gantt chart (pictured)

•  The chart is a tool to help sequence and arrange all of the activities and considerations for a project

•  Good project planning requires

•  Consideration of resourcing

•  Booking meetings in calendars

•  Considering of the project ‘rhythm’—can it be achieved on time, how hard will the team be working

•  Agreeing on interim deliverables and dates

15. 05.22. 12. 19.Mar Apr

29.01. 08.

Meetings with Portfolio Secretaries

Work Stream

Other meetings

NP/IP Process Diagram & Checklists

Developing Transition Plan Scoping Deck

Drafting IP Circular

Drafting IP Concept Paper

Final Project Report for PM

Final Project Report for SCoSP

Consistent Script

Develop Transition Plan

Ongoing Support to DPG

Report for Treasury HoTs (Backpack)

SDD Drafting

SDD Consulting

Non-SDD Responsibility

Confirmed Meeting

Meeting TBCFinal Deliverable

SCoSP Meeting

Lisa Paul

Jeff Harmer

Jane Halton

?

Steering Group

COAGDeputy SOM

Reference Group

??

? ? ?

with Treasury

with Treasury

?

Interim Deliverable

Interim products and interim deadlines play a critical role in our project approach – we use them to drive our output and drive our stakeholder engagement . We know we will have to iterate, so let’s plan for it