KEMENTERIAN ENERGI
& SUMBER DAYA MINERAL
INVESTMENT IN PV MINI GRID TO BOOST
ELECTRIFICATION IN REMOTE RURAL AREAS
MINISTRY OF ENERGY AND MINERAL RESOURCES
DIRECTORATE GENERAL OF NEW, RENEWABLE ENERGY AND ENERGY CONSERVATION
Maritje Hutapea
Director of Various of New Energy and Renewable Energy
Off-Grid Power Conference at Intersolar 2017, 31 Mei 2017
KEMENTERIAN ENERGI
& SUMBER DAYA MINERAL
NATIONAL ELECTRIFICATION RATIO
NATIONAL ELECTRIFICATION RATIO IN 2016 (%)
KEMENTERIAN ENERGI
& SUMBER DAYA MINERAL
23%
25% 30%
22% 5%
46% 31%
18%
194
MTOE
~ 400
MTOE
New and Renewable Energy
Oil
Gas
Coal
2025 2013
2013 2025
Power Plant Capacity 51 GW 135 GW
Energy Consumtion 0,8 TOE/kapita 1,4 TOE/kapita
Electricty Consumtion 776 KWh/kapita 2.500 KWh/kapita
Energy Intensity 334 SBM/billion rupiah
Decrease every year1%
Energy Elastisity 1,35 < 1
NRE
Oil
Gas
Coal
6
NATIONAL ENERGY POLICY (GOVERNMENT REGULATION NO 79/2014)
KEMENTERIAN ENERGI
& SUMBER DAYA MINERAL
2025 Geothermal 7.2 GW
Hydro 21 GW
Bioenergy 5.5 GW
Solar 6.4 GW
Wind 1.8 GW
Other NRE 3.1 GW
Totall 45 GW
8,66
10,80 11,73
12,94
15,81
18,48
24,66
29,28
35,74
41,01
45,04
2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025
PLTP PLT Bioenergi PLTA Mini Hidro PLTS PLT Bayu PLT Laut Total
NEW AND RENEWABLE ENERGY TARGET BY 2025
2015 2025
Total Installed Capacity 55 GW 135 GW
NRE Power Plant Capacity 8.7 GW (15.7%)
45 GW (33%)
KEMENTERIAN ENERGI
& SUMBER DAYA MINERAL
TYPES OF RENEWABLE ENERGY POWER PLANT :
THE MINISTRY OF ENERGY AND MINERAL RESOURCES’S
REGULATION NUMBER 12 YEAR 2017 : “UTILIZATION OF
RENEWABLE ENERGY SOURCE FOR ELECTRICITY SUPPLY”
Solar PV Wind Hydro
Biomass Biogass Municipal
Waste
Geothermal
PT PLN (Persero) is obligated to buy
KEMENTERIAN ENERGI
& SUMBER DAYA MINERAL
No. Renewable
Energy Sources
Method of Appointment
Tariff
Regional Grid BPP > National BPP
Regional Grid BPP ≤ National BPP
1. Solar PV Auction in capacity quota with minimum 15 MW Maximum 85% x Regional Grid BPP
100% x Regional Grid BPP
2. Wind Auction in capacity quota with minimum 15 MW Maximum 85% x Regional Grid BPP
100% x Regional Grid BPP
3. Hydro
Reference Price Maximum 85% x Regional Grid BPP
100% x Regional Grid BPP
Direct Selection Price determined by direct selection process
a. Capacity ≤ 10 MW: Capacity Factor minimum 65% b. Capacity > 10 MW: Capacity Factor depends on Regional Grid system requirements
4. Biomass Reference Price (for 10 MW or less)
Maximum 85% x Regional Grid BPP
100% x Regional Grid BPP
Direct Selection (for more than 10 MW) Price determined by direct selection process
5. Biogas Reference Price (for 10 MW or less)
Maximum 85% x Regional Grid BPP
100% x Regional Grid BPP
Direct Selection (for more than 10 MW) Price determined by direct selection process
6. Municipal Waste
Reference Price Maximum 100% of Local Generation BPP
Mutual agreement between PLN and IPP
7. Geothermal Reference Price Maximum 100% x Regional Grid BPP
Mutual agreement between PLN and IPP
BPP = Production Cost of Electricity Regional Grid BPP and National BPP will be determined by the Minister based on the proposal of PT PLN (Persero)
THE MINISTRY EMR REGULATION No. 12/2017 : TARIFF
KEMENTERIAN ENERGI
& SUMBER DAYA MINERAL
THE MINISTRY EMR REGULATION NO. 38/2016: THE ACCELERATION PROGRAM
TO ELECTRIFY RURAL, BORDER AREA AND SMALL ISLAND
Undevelop rural areas
Remote areas
Border areas
Small islands
To provide electricity in
certain area until 50 MW;
Offer Business Area To Non PLN Business
Entity
Minimum Offered Working Area To Be
Electrified Is 1 (One) District
Small Scale Electricity Supply Business
Could Be Operate:
With Subsidy Funds
Without Subsidy Funds
Mechanism
KEMENTERIAN ENERGI
& SUMBER DAYA MINERAL
• Indonesia as tropical country has a relatively good of solar
radiation (4,8 kWh/m2/day throughout Indonesia)
• Indonesia comprises of 17.508 big and small island, and that
have some areas are difficult to be reached by national grid
• Around 2,519 villages are still darkness don’t have yet
access to the electricity
• The Goverment of Indonesia prioritize the use of Renewable
Energy
• The Implementation of Solar PV particularly in rural areas has
been prioritized to electrified remote villages
THE POTENSIAL OF PV DEVELOPMENT IN INDONESIA
KEMENTERIAN ENERGI
& SUMBER DAYA MINERAL
Solar PV (574 units; 24.765 kW)
Hydro/Micro Hydro (64 units; 4.322 kW)
NRE Micro Grid Infrastucture Development 2011-2016
574 units of NRE-based infrastructure;
42.680 kW of electricity made, successfully electrified
87.063 families.
Total Investment: Rp 2.458 trillion (USD 186,2 million)
Development by the Government in 2011 – 2016 by State Budget
KEMENTERIAN ENERGI
& SUMBER DAYA MINERAL
NOTE:
West
Kalimantan
Central
Kalimantan
South
Kalimantan
North Kalimantan
Maluku
North
Maluku
East Nusa Tenggara
West Nusa Tenggara
West Papua
Papua
South Sulawesi
Southeast
Sulawesi
Central
Sulawesi West
Sumatera
North Sumatera
Riau
Banten
DKI Jakarta
East
Kalimantan
North
Sula-
wesi Gorontalo
No NRE-Based PP Units Capacity (kW/ kWp)
1. Solar PV 58 3.430
2. Hydro/Micro 8 2.022
3. LTSHE* 59.678
Total 66 PLT EBT 5.452
Targeted to electrified 424
villages / 70.017 Families. (including the installation of LTSHE)
Microgrid Development Plan 2017
Development by the Government as planned in 2017 State
Budget
*) LTSHE: Lampu Tenaga Surya Hemat Energi (Energy Efficient Solar Lights)
KEMENTERIAN ENERGI
& SUMBER DAYA MINERAL
1
2
3 4
Lampu Tenaga Surya Hemat Energi (LTSHE)
2.519 Villages
“With No Electricity”
293.532 Household in 20 Provinces
Source: Badan Pusat Statistik, 2014
- By Government Budget (APBN) 2017
331,5 Billion 95.729
- By Government Budget (RAPBN) 2018
996,6 Billion
1
2
3
3.372 Billion 887.141 – (56.591)
2.753 Billion 692.064
3.801 Billiom 955.692
47,6 Million Household
381 Thousand
Household
2.099 Villages
34.958 Villages
Household without access to electricity 2.828.429
Total Government Budget11,25 T
197.803 +
(56.591)
“Solar Lamp”
ELECTRIFICATION PROGRAM FOR 2.519 VILLAGES (2017-2019)
KEMENTERIAN ENERGI
& SUMBER DAYA MINERAL
DOCUMENTATION 17
BORBAN, PAPUA (15 kWp)
BUGI, PAPUA (20 kWp) AIDIRU, PAPUA (30 kWp) BANGAI, PAPUA (15 kW)
BAMANA, WEST PAPUA (30 kWp) Siandau, North Kalimantan
DOCUMENTATION
KEMENTERIAN ENERGI
& SUMBER DAYA MINERAL
The Challenges of Microgrid Development in Indonesia
• Need to establish “Local Management Unit” to operate and
maintain the facility
• Lack of rural people capability to monthly payment for
operating and maintenance of the facility
• Need to engange local university and regional government to
facilitate training in technical issue