Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
iPCHG-DESG E 4'FqJFjOG
Sheet I of 1Record of Lead Review
0000063016R3
Document: Phase 1 Additional Creep Test Plan Revision 0
The signature below of the Lead Reviewer records that:- the review indicated below has been performed by the Lead Reviewer;- appropriate reviews were performed and errors/deficiencies (for all reviews performed)
have been resolved and these records are included in the design package;- the review was performed in accordance with EGR-NGGC-0003.
-] Design Verification ReviewF-- Design ReviewI Alternate CalculationLI Qualification Testing
LI Engineering Review 2 Owner's Review
L- Special Engineering Review
LI YES LI N/A Other Records are attached.
John Hollidav .. , Pil 08/10/09Lead Reviewer aJ (printlsign) Discipline Date
Item I Deficiency ResolutionNo.
NONE1.
2.
3.
FORM EGR-NGGC-0003-2-10This form is a QA Record when completed and included with a completed design package.Owner's Reviews may be processed as stand alone QA records when Owner's Review iscompleted.
EEGR-NGGC-0003 Rev. 10
ATTACHMENT Z45R3 Page 1 of3
C-PCHG-DESG ENGINEERING CHANGE 0000063016R3
Celebrating 35 YearsNovember 25, 2008 1973 2008
Progress Energy Florida, Inc.15760 W. Powerline Street (SA2C)Crystal River, Florida 34428-6708
Attention: Ms. Debbie Hanna
Reference: Proposal for Additional ServicesCrystal River Nuclear PlantSteam Generator Replacement Restoration of the ContainmentOpeningPhase II-Additional Creep TestingCrystal River, FloridaS&ME Project No. 1439-08-208Contract 373812
Dear Ms. Hanna:
S&ME, Inc. (S&ME) is pleased to submit this proposal for additional services for thereferenced project. This proposal is in response to a verbal request from John Holliday ofProgress Energy during a conference call on November 19, 2008. This proposaldescribes our understanding of the additional scope of services, outlines the projectschedule and presents the associated compensation for our services.
PROJECT INFORMATION AND SCOPE OF SERVICES
Our understanding of the scope of work is based upon our discussion with ProgressEnergy and Sargent and Lundy duringa conference call on November 19, 2008. Theinitial Phase II scope included the testing of two different concrete mixtures for potentialuse to restore the containment opening. The Phase II testing is non-safety related anddoes not include creep testing. Phase III testing is to include the testing of the selectedfinal concrete mix. Phase III testing is safety related and will include creep testing. Inorder to obtain an indication of how the two Phase II mixes will perform during creeptesting and to provide additional information to the project team prior to mix selection,S&ME has been requested to have short term creep tests performed on the two proposedPhase II mixes. In general, the testing will be performed as follows:
Creep tests will be performed in general accordance with ASTM C 512. Initial curilngwill be performed in the autogenous chambers for approximately 4 days, and thenspecimens will be express shipped to CTLGroup for scheduled arrival at an age of. fivedays. Once the specimens arrive, gage points will be installed to measureddeformation (three readings per specimen). Specimens will be tested in the drying stateonly, to measure total creep and shrinkage.
S&ME, INC. /1413 Topside Road / Louisville, TN 3 7 777/p 865.970.0003 f 865.970.2312 / www.smeinc.comATTACHMENT Z45R3 Page 2 of 3
"P 15CýHG-DESG ENGINEERING CHANGE 0000063016R3Proposal for Additional Services S&ME Project No.: 1439-08-208Crystal River Nuclear Plant/Phase II Additional Creep Testing November 25, 2008
Two creep specimens and two shrinkage specimens will be tested for each mix. Inaddition, one specimen will be tested for compressive strength at 5 days and twospecimens will be tested for modulus of elasticity at 5 days.
For the creep test, six readings will be taken on the first day:1) Before loading (out of frame)2) Before loading (in frame)3) Preload (200 psi)4) .Initial load (2000 psi)5) 10 minutes after initial load6) 2-6 hours after initial load
Readings will be taken approximately every day for the first week with subsequentreadings taken on 14, 21, and 28 days after loading, with the exception of weekends andholidays. Data will be reduced and a brief summary report will be prepared.
COMPENSATION
S&ME proposes a cost of $7,350.00 per short-term creep test as defined above, for a totaladditional cost of $14,700.00.
SCHEDULE
The schedule for performing this additional scope of work will be dependent on thetiming of the authorization to proceed. However, it is anticipated that the mixes would beperformed and specimens cast during the first or second week of December.
AUTHORIZATION
It is anticipated that the authorization for this additional work would come through theissuance of an amendment existing Contract 373812 between Progress Energy and S&MEto add this scope and pricing and, if needed, to increase the original Not-to Exceed value ofthe contract.
Should you have any questions after reviewing this proposal or if we may be of additionalservice, please do not hesitate to contact us at your convenience.
Sincerely,
S&ME, INC.
.l B. Pearson Michael R. StomerMaterials Engineer Vice President
ATTACHMENT Z45R3 Page 3 of 3
PCHG-DESG ENGINEERING CHANGE 0000063016R16
0 0®
PLAN VIEW
CONTAINMENT OPENING
CORE BORE LOCATIONS
NOTES:
1. FIELD TO DRILL NINE (9) 4 INCH DIA. CORE BORES IN THECONCRETE CONSTRUCTION OPENING WALLS WITH 2'MINIMUM SPACING.
2. THE LOCATIONS CHOSEN SHALL BE IN GOOD CONCRETEWITH NO VISUAL CRACKING PRESENT.
3. THE CORE SHALL BE LOCATED AT THE APPROXIMATEDISTANCE HALF WAY BETWEEN THE LINER PLATE AND THEVERTICAL TENDONS.
4. IF REBAR OR MISC. STEEL IS ENCOUNTERED, DRILLADDITIONAL CORE AT NEW LOCATION. USE DRILL STOPSFOR CORE BORING.
5. DRILL CORE BORES IN ACCORDANCE WITH ASTM C-42 ANDAI-480.
6. AFTER DRILLING IS COMPLETE WIPE OFF SURFACE WATERFROM CORE SAMPLE AND ALLOW WATER TO EVAPORATE.
7. WHEN SURFACE IS DRY, BUTNO LATER THAN ONE HOUR,WRAP THE CORE SAMPLE IN PLASTIC.
8. PLACE EACH CORE SAMPLE IN SEPARATE PLASTIC BAGSAND SEALTHE BAGS TO PREVENT MOISTURE LOSS.
9. PROTECT THE WRAPPED CORE SAMPLES FROM EXPOSURETO DIRECT SUNLIGHT AND STORE AT ROOMTEMPERATURE.
10. MATCH MARK CORE SAMPLES WITH LOCATIONS SHOWN.
SIDE VIEW
CONTAINMENT OPENING
CORE BORE LOCATIONS
CRONTAINRENT OENING
CONTAINMENT OPENINGCORE BORE LOCATIONS
Z65R1 6 PAGE 1 OF 1
PCHG-DESG " .ENGINEERING CHANGE 10000063016R15
Purpose:The purpose of this Attachment is to evaluate the Liner Plate for the proposed lifting configuration shown inAttachment Z22R9 (Bechtel is responsible for the design of the rigging equipment).
Results:The liner plate is structurally acceptable for the lift configuration shown in Attachment Z22R9.
Methodology:The structural analysis of the liner plate for the lift configuration shown in Attachment Z22R9 is performed in thefollowing three steps:
1. Liner Plate and vertical reinforcement bending stress around horizontal (X) axis2. Liner Plate and horizontal strongback stress around vertical (Y) axis3. Local Liner Plate stress at lift points
Detailed Calculations:Attachment Z22R9 shows the different postions of the liner plate during the lifting process. Position 6 is the worstcase position to determine bending and local stresses.
Section 1: Liner Plate around Vertical (Y) Axis
DWliner.plate:= !5kip
see Attachment Z22R9 Page 2
Aliner:= 23.511-24.751f
Aliner = 581.625.ft2
Liner ileight= 24.75 ft
LinerWidth:= 23.5ft
DWliner_plateWw~idth -Liner Width
DWliner-plate POSITION 5,
wheight Lin= PueightLiner-Height LEG I CUI LOOSL. CR'AIE HAS LOAD
Ibf •Wwidth t638--
w
lbfWhcight = P I
ATTACHMENT Z64 Page 1 of 5
PCHG-DESG ENGINEERING CHANGE F0000063016R151
Bending about Verticial Axis
Iw:= 7ft + 3.75in + 7ft + 5.75in Iw= 14.792-ft
Conservatively consider simple beam
.23.5ft- 1waw'- 2 aW = 4.354. ftz
M- Wwidth' Iw
y: 8M Y= I7.457-kip'ft
Strongback and Liner Plate Section Modulus
Effective plate width considered as part of section modulus
Neutral Axis
A, := 0.375inmb
A2 := 2-1.19in2
b:= 6in
Y2:" 0.275in +3in + 1.5in
0.375.
2
AI.Y1 + A2.Y2
A1 + A2
n = 2.546-in
Y2
C = * ~ = A
xSt ron gback
n
3in
E~Z~b
Moment of InertiaLiner Plate
I1 = ,0.187 .in 42in-(3in) 3 (2 - 0.5)in-(3in - 0.5in) 3
12 1212 = 2.547-in
4 b.0.375in3
12
in:= 1 + A-2-(Y. - n) 2 + 11 + A,. n - 07i
~ ~ 2)in = 27.075-in4
inSh := -
n
Sh
Sh = 10.636-in 3
fb= 19.696.ksi < I 0.6-36ksi = 21.6-ksi OK
ATTACHMENT Z64 Page 2 of 5
I ATTACHMENT Z64
Page 2 of 5 1
I PCHG-DESG ENGINEERING CHANGE 10000063016R15
Bending about Horizontal Axis,
ah:= 6ft + 1.5in ah = 6.125.ft't Ih:= 18ft + 7.5in - ah Ih = 12.5:ft
Conservatively consider simple beam with distributed load on vertical stiffener only
2_ Wheight'lh 1.5ft
M : 8 2335ft.
S:= 0•542in3 Angle L3x2x1/4
MX =0.ý756-kip-ft
fb = 16.728.ksi < O.6.36ksi '=. 21.6;ksi ,OK
Local Plate StressesThe local plate stresses based upon the worst case load condition were determined byperforming a finite element analysis in GT STRUDL. The lift points were modeled assupports and a surface load was applied to the plate.
DWliner_platep := Aliner p = 25.79.psf
The stress profile in the liner plate is shown below:
L N
IUI
I P"
ATTACHMENT Z64 Page 3 of 5
PCHG-DESG ENGINEERING CHANGE 100000630116R15I
The locally stressed regions shown in the stress profile above are listed in detail inthe STRUDL output file, themaximum stresses are listed below:
MAXIMUM AND MINIMUM SUMMARY OF ABOVE RESULTS
RESULT* MAXIMUM SURFACE JOINT * MINIMUM SURFACE JOINT *
* SXX • 0.263025E+05 TOP 1684 , -0.263004E+05 BOTTOM 1684 *
SYY * 0.312231E+05 TOP 1684 *-0.312232E+05 BOTTOM 1684 *
* SXY 0.771544E+04 TOP 697 . -0.771544E+04 TOP 1684 *- - - - - - - -
Although two elements are shown to be overstressed, the stress profile shown above does not indicate-an even stressdistribution around the overstressed elements. The STRUDL output excerpt of the surrounding elements is shown below:
AVERAGE STRESSESJOINT SURFACE NUMBER OF ELEMENTS SXX1683 TOP 4 0.912358E+041683 BOTTOM 4 -0.912138E+04
SYY SXY0.175492E+05 -0.154991 E+04-0.175495E+05 0.1 54709E+04
16841684
TOPBOTTOM
44
0.263025E+05-0.263004E+05
0.312231 E+05-0.312232E+05
-0.771544E+040.771038E+04
1685 TOP 4 0.141190E+05 0.207881E+05 -0.574417E+041685 BOTTOM 4 -0.141198E+05 -0.207880E+05 0.574137E+04
The stresses in the adjacent elements are significantly below allowable weak axis bending stress (0.75*30ksi = 22.5ksi).Therefore, the 6"x6" mesh is not fine enough to adequately reflect the stress distribution in areas of materialdiscontinuities (the high stressed region is in the liner plate elements of 0.375" adjacent to thelstiffened liner plate with0.75" thickness. Taking average of three elements 481,482 and 483 and 1844, 1845, and 1846, theaverage stress willbe(0..... 1.1)! 3 - 1,.5 ,. . " . Note that the vertical load used in the finite element analysisis conservative, since the, sling attached to the lug at the liner plate will be at an angle and will exert. less vertical loadthan used in the analysis.
Therefore, the liner plate is structurally acceptable for the lift configuration shown in Attachment Z22R9.
(17.5+31.2+20.7)/3 = 23.1 ksi slightly over the allowable, however the verticalload used in the analysis is conservative as mentioned in Revision 14,therefore slight increase less than 3% of the allowable is acceptable.
I I. I I I I I ~ I I I I I I I '. I I I I I I I I I I I I
ATTACHMENT Z64 Page 4 of 5
!;:i,;',•
PCHGoDESG .,.ENGINEERING CHANGE 10000063016R15
STRUDL INPUT FILE: Liner Plate Lift RA2.txtSTRUDL 'LINER PLATE EVALUATION FOR LIFTING'UNITS FEET POUNDS DEGREESTYPE SPACE FRAMEMATERIAL STEEL ALLJOINT COORDINATEGEN 47 JOINTS CARTESIAN ID 1 1, X 0.0 0.5REPEAT 49 TIMES ID 47 Y 0.5GEN 49 MEM ID 2400 1 F 3 47 T 50 47REPEAT 14 TIMES ID INCR 49, FROM INC 3. TO INC 3STATUS SUPPORT 574 602 1749 1777JOINT RELEASE574 602 MOM X Y Z KFZ 5000 KFX 20001749 1777 MOM X Y Z KFZ 5000 KFX 2000MEM PROPERTIES2400 TO 3134 TABLE 'ULANGLE 'L3X2X1/4'CONSTANTSBETA 113.7 2400 TO 3134TYPE PLATEGEN46ELEMENTSID1 1 FROM1 1TO21TO49 1TO481REPEAT 48 ID 46 FROM INCR 47 TO INCR 47 TO INCR 47 TO INCR 47GEN 49 ELEMENTS ID 2255 1 FROM 46 47 T 47 47 T 94 47 T 93 47ELEMENT PROPERTIES1 TO 468 472 TO 495 499 TO 514 518 TO 541 545 TO 560 564 TO 587 591 TO 606 610 TO 633 637 TO 1618 TYPE 'SBHQ6' THICK 0.3751622 TO 1645 1649 TO 1664 1668 TO 1691 1695 TO1710 1714 TO 1737 1741 TO 1756 1760 TO 1783 1787TO 2303 TYPE 'SBHQ6' THICK0.375STOP LEFT SWIVEL HOIST CONNECTION1619 TO 1621 1665 TO 1667 1711 TO 1713 1757 TO 1759 TYPE'SBHQ6&THICK 1.125"$BOTTOM LEFT SWIVEL HOIST CONNECTION469 TO 471 515 TO 517 561 TO 563 607 TO 609 TYPE 'SB'Q6' THICK 1.125STOP RIGHT SWIVEL HOIST CONNECTION1646 TO 1648 1692 TO 1694 1738 TO 1740 1784 TO 1786 TYPE 'SBHQ6' THICK 1.125SBOTTOM RIGHT SWIVEL HOIST CONNECTION496 TO 498 542 TO 544 588 TO 590 634 TO 636 TYPE 'SBHQ6' THICK 1.125LOADING 1 'ELEMENT LOADS'ELEMENT LOADS1 TO 2303 SURFACE FORCE GLOBAL PZ -25.8STIFFNESS ANALYSISLOAD LIST IOUT BY MEMOUT DEC 2 Revised Maximum stress inPARAMETERSCALCULATE AVERAGE STRESSES AT TOP BOTTOM SURFACES 1 TO 2303 Page 4 under Rev. 15.
Prepared by: C.G..RanganathDate: 10/04/09
Preparer: Checker:
Jackson, Jabari Ranganath, CasabaPrepared By Checked By2009.10.03 03:03:43 -04;0'- 2009.10.03 05:52:48 -04'00'
Jabari Jackson, PE Casaba Ranganath, PE
ATTACHMENT Z64 Page 5 of 5
EC 63016R12 Z63R12 Page 1 of 5Evaluate the use of Hydrochloric Acid
Evaluation of 17% Hydrochloric Acid for Control Room Habitability
1.0 Purpose and Scope
1.1 Purpose
The purpose of this evaluation is to evaluate a potential new hazard at the CrystalRiver 3 Nuclear Plant (CR3). The hazard is from the temporary storage and use of1600 gallons of 17% hydrochloric acid. It is used to control PH levels in water usedfor containment building hydro-demolition activities associated with the station'sRefuel 16 Steam Generator Replacement Project. Of primary concern with theintroduction of any new hazardous material for CR3 is:
a) The explosion hazard from the new chemical; andb) The safety of the Main Control Room (MCR) operators from toxic vapor or
asphyxiation from the new chemical in the area. The toxic vapor could betransported to the MCR through the Control Complex HVAC system.
This evaluation will demonstrate that the use of a 17% solution of hydrochloric acidwill not pose a threat to the MCR operators by either explosion or hazardous levelsof vapor.
1.2 Scope
The evaluation described in Section 1.1 will be performed for the 1600 gallons of17% solution of hydrochloric acid that will be transported on site and temporallystored in a vented tank outside of CR3's protected area.
Acceptance Criteria:a) Toxicity (One of the following conditions must be met)
The concentration of vapor in the MCR caused by hazardous chemicalrelease cannot be more than the Immediately Dangerous to Life andHealth (IDLH) toxicity limit. Also, the concentration of oxygen inside theMCR cannot drop below 19.5%, causing asphyxiation (Ref 2, pg. 4). InReg. Guide 1.78 (Ref 2, pg. 6), it states "the use of IDLH values astoxicity limits is considered appropriate since it provides an adequatemargin of safety as long as control room operators use protectivemeasures within 2 minutes after the detection of hazardous chemicals;they therefore would not be subjected to prolonged exposures at theIDLH concentration levels."
ii. More than two minutes must elapse between the time of detection andthe time when the concentration inside the MCR reaches the IDLH limit(Ref. 2, pg. 6). Note that detection can be by either automatic systems orthrough nasal detection.
Note: CR3 has not adopted Reference 2.2. The use of its acceptance criteria isjudged an acceptable industry practice.
EC 63016R12 Z63R12 Page 2 of 5Evaluate the use of Hydrochloric Acid
b) Explosions cannot cause an over-pressure of more than 1 psi at CR3 Reference[1] at page 1.
2.0 References2.1 CR3 Calculation No. M07-0005, Revision 0, Evaluation of Proposed New Chemical
Hazards to the Crystal River Site.2.2 USNRC Regulatory Guide 1.78, "Evaluating the Habitability of a Nuclear Power Plant
Control Room During a Postulated Hazardous Chemical Release," Rev 1, December2001.
2.3 NUREG-0570 "Toxic Vapor Concentrations in the Control Room Following aPostulated Accidental Release," James Wing, June 1979.
2.4 MSDS for Hydrochloric Acid, Science Lab.2.5 FSAR, Rev 31.32.6 CR3 Technical Specification thru amendment 235, Section 3.7.12.2.7 CR3 Technical Specification Bases, Rev 80, Section 3.7.12.
3.0 Definitionis)
The IDLH limit is a toxic gas exposure limit. From Reg. Guide 1.78, this the concentration ofa toxic gas that is "likely to cause death or immediate or delayed permanent adverse healtheffects if no protection is afforded within 30 minutes. [This limit] can be tolerated for 2minutes without physical incapacitation of an average human" (Ref. 2.2, pg. 6). Because 2minutes is the required time for a control room operator to don a respirator after detection,the IDLH is considered the maximum acceptable toxic gas concentration for a control roomoperator.
4.0 Input Data
Hazardous Chemical 17% in Solution Hydrochloric Acid (hydrogen chloride)* 1,600 Gallons stored on site Limitation* Storage conditions are 14.7 psia and 100 OF (max) Limitation* Hydrogen chloride has an IDLH limit of 210 mg/m3 or 50 ppm Ref. 2.1* Odor threshold of 0.25 to 10 ppm Ref. 2.4
5.0 Assumptions
The Reference 1 Chemical Hazards Evaluation has the following relevant assumptions:o The gas vapors that maybe released as vapors will obey the ideal gas law. This
assumption is consistent with common engineering practices for gasses atatmospheric pressures and temperatures.
o All chemical vapors are assumed to be at atmospheric temperature soon afterthey are released.
o Atmospheric pressure is assumed to be 14.7 psia.o The storage tank will be under observation by equipment operators or other
watch at least once each hour.
6.0 Evaluation
In regard to protection from toxic gas releases, other major sources of toxic gas have beenremoved from the site. The most significant sources remaining are ammonia at CR Units 4/5
EC 63016R12 Z63R12 Page 3 of 5Evaluate the use of Hydrochloric Acid
(Ref. 2.1) and the potential to use chlorine and sulfur dioxide for short periods of time at theHelper Cooling Towers. The use of administrative limits for toxic gas at CR3 has resulted innasal detection being adequate for operator protection and eliminated the need for automaticdetection and isolation. The operator donning self-contained breathing apparatus within 2minutes of nasal detection will ensure they are not exposed to debilitating levels of toxic gas.
Regulatory Guide 1.78 states "For chemicals that are gases at 100 OF and normal atmosphericpressure but are liquids with vapor pressure in excess of 10 torr, consideration should be givento the rate of flashing and boiloff to determine the rate of release to the atmosphere and theappropriate time duration of the release. For lighter-than-air gases, the buoyancy effect shouldbe considered in determining the dispersion characteristics". As noted in the attached E-mailfrom Sargent & Lundy it was concluded that 17% concentration hydrochloric acid solution is nota hazard to the Crystal River site.
The worst case scenario is the catastrophic failure of the tank holding the hydrochloric acid. Thestorage tank is an atmospheric tank and Reference [2.4] outlines that the acid solution is non-flammable and non-explosive. The catastrophic failure of the tank would cause the acid to poolin the retaining area built up around the area. And not cause the instantaneous formation of agas cloud that could move with little dissipation towards the control room ventilation intakes.
A tank failure would result in a plume release that would form over time. The plume would resultfrom the evaporation of the chemical over time. Reference [2.1] describes a plume release andhow a liquid puddle evaporates and how the vapor dissipates as it travels with the wind. Areleased liquid quickly spreads by gravity from its initial shape into a pancake on the ground.
The continuous source of the plume, pools with boiling points greater than the ambienttemperature, is the evaporation rate of the liquid. Reference [2.4] establishes that forhydrochloric acid concentrations less than 20%, the boiling point of the fluid is higher thanwater. Reference [2.4] establishes that the vapor density of the acid is 1.267 as compared to airat 1. With this density the evaporating gas plume will tend to initially gather at the surface of thepool and not spread upward. It is of additional note that the storage tank is located more than 40feet below the elevation of the control room ventilation intakes.
The above establishes that, under ambient heat conditions, by observation a reasonable time(over one hour) exists for station personnel to identify a failure of the acid holding tank beforesignificant accumulation of hydrochloric acid vapor. Moreover, vapor accumulation will becontinuously disbursed into the environment limiting the vapor concentration (i.e. the vapors willtend not to gather over long periods and then move as an intense vapor cloud).
The ventilation system for the control room circulates the air inside the MCR with air taken fromthe intake. As a result, the concentration of a toxic chemical in the MCR is different than theconcentration at the inlet Reference [2.1]. Reference [2.4] provides that hydrochloric acid has astrong pungent order with an odor threshold of 0.25 to 10 ppm. The IDLH established forhydrochloric acid is 50 ppm (see reference 2.2) providing ample time for an operator to don self-contained breathing apparatus within 2 minutes of nasal detection thus ensuring that they arenot exposed to debilitating levels of toxic gas.
Reference [2.4] identifies materials that should not come in contact with Hydrochloric Acid. Awalk down of the tank, retaining container, and general area revealed no metal substances or
EC 63016R12 Z63R12 Page 4 of 5Evaluate the use of Hydrochloric Acid
other substances that would interact with the acid are in the immediate area if the tank were tofail.It should also be noted that CR3 has approved the storage of hydrochloric acid in thewarehouse and subsequent use in the plant.
> Cat ID 1120310 - Hydrochloric Acid Concentrated, Liquid Form, Reagent Grade,> Cat ID 1120312 - Hydrochloric Acid Concentrated, Liquid Form, Reagent Grade, 35
Gallon Drum,> Cat ID 1120321 - Hydrochloric Acid, 20 Baume (32% concentration), Supplied in 55
gallon drums is approved.
7.0 Recommendations:A watch placed over the transportation vehicle established when chemical arrives on site withpositive controls established with the control room.
Establish a periodic surveillance of the acid tank for leaks of other failures.
Bechtel Safety coordinator should sign off on work order tasks ensuring all required MSDSmeasures are in place including but not limited to:
Personnel safety (fumes, contact with liquid)Monitoring ability (confirm <5ppm in air)Protection from rain, direct sunlight / heat (a tarp with wood supports, w/ventilation)Physical protection of the tank (jersey barriers, bollards, traffic control)Spill mitigation (dykes, plastic sheet, isolation from oxidizers and other acids))Fire protection (hydrogen gas produced by reaction with metals)Waste disposal
Barriers between the tank and vehicular traffic should be established.
8.0 Conclusion
This evaluation demonstrates that with the storage and use of a 17% solution of hydrochloricacid does not create a hazard to the MCR operators by either explosion or hazardous levels ofvapor.
Prepared by: Anthony CarrReviewed by: Bob Reynolds
EC 63016R12 Z63R12 Page 5 of 5Evaluate the use of Hydrochloric Acid
From: [email protected]: Carr, AnthonyCc: Jopling, Daniel L.; Reynolds, Robert B.; [email protected]; Caraballo, Daniel;MATTHEW.M. [email protected]; [email protected]: Hydrochloric AcidDate: Monday, September 28, 2009 4:41:19 PM
Tony,Regulatory Guide 1.78 states that chemicals with vapor pressures less than 10 torr at 100 OFare not a threat to a site and do not need to be analyzed further. From Perry's ChemicalEngineers Handbook, the vapor pressure of 17% concentration hydrochloric acid solution inwater is less than 1 torr at 100 OF. Therefore 17% concentration hydrochloric acid solution is nota hazard to the Crystal River site. The maximum concentration where the yapor pressure ofhydrochloric acid is less than 10 torr at 100 OF is 26%.
Chris SwardProject ManagerSargent & Lundy312-269-7426
PCHG-DESG ENGINEERING CHANGE 000063016R5
ATTACHMENT Z62
Pages 2-4 contain the calculated volume of grease required for each tendon conduit after thetendon has been installed. Per IWL-3221.4 the absolute difference between the amount of greaseremoved and the amount replaced shall not exceed 10% of the tendon net duct volume.
The tendon lengths used in these calculations are based on those contained in Attachment X61.
Calculation By: John Holliday q
Checked By: R. Kopicki R/actaq
ATTACHMENT Z62R5 Page 1 of 4
PCH ESG ENGINEERING - . ..
. .. ..~ 7 -- . .r- "---_ _ ........ ....... I/-~~~~~ ~~ -*ý41~s i .I$i'T-Z
-~1 -77 Z
.-. .. ... .. . . . . ... ..... .
- .. ...... . ... . ..... .. E o d
-,( ,, AY 175 -, --- 1 -ý4-Z -" V ,-
ATTACHMENTr Z62R5 Pae2o4
P G - ~E S ,• | ,i.E -_ ' -0 16 R 5
v
, , r_ __ _ __ _ __ _ _
- -~ ~ *-- - -*
77- rE
o7..
ATTAC. •EN -6, --
-•... ..- x . . j-.d----• -.... . . . . ... .. " ' ...... •- -1- -!'-•,_7 7. = • - . .
-..-, - /, _ __\ ,
I ATTACHMENTZ62R5 • -- , .. . ....... ; + . Page 3 of 4
S PGENGINEERING CHANGE 000063016R5
-- = 5K T Z- --- n-)* - . , . ... , .--
)7 144,, A .
I -1
-S V. 6- AA
; 'f7
AT.._TACHM NT 4. ,.
- , . . .. . .. . . . . . . . . r_.. . . . . . _- " k- - "- - - - Y .. . . . . .- -.. .. . . . .
-TTAC---N Z-21.5._,. a4-4 -4 . ....
AT A HMN.6 R . .. . .. . . . .. . . . . .. . .. . . ................. __-•,~.Pa e.4_-o_ .
PCHG-DESG ENGINEERING CHANGE 000063016R5
ATTACHMENT Z61
Pages 2 thru 13 contain the calculated lengths of the vertical and hoop tendons affected by theSGR. These lengths have been used in Attachment Z62 to calculate the volume of greaserequired for each tendon. These calculations are based on the original Prescon drawings:
5EX7-003-P 10-A, P3, P16, P40 and P41
Note 1: The slight curvatures that the vertical tendons have at elevation 235' have been ignoredsince their impact on the tendons overall length is negligible (Ref. Drawings P40 and P41)
Note 2: Pages 3, 5, 7, 9, 11 and 14 contain information on how each tendon length was reducedto 1 '-0" segments that were equivalent to either the straight portion of the tendon or the curvedsection and were used in preliminary calculations to evaluate projected tendon elongationsduring retensioning and are for information only.
Calculation By: John Hollida
Checked By: R. Kopicki
ly O-c q
.ýkt)-Te ~ ~ ~ ~ ~ ~ ~ ~ 64 qý AL,5l-o4oc6L'T4WA ~ Wr i
ATTACHMENT Z61 R5 Page 1 of 14
Io I - z 0
7-7
.4
-- , ,, . . . .. ,,
9~7-n
'Z4R
Page 2 of 1C:
PCHG-DESG ENGINEERING CHANGE
0 6
0 ; 00. lots)
Iý -
ATTACHMENT Z61 R5 Page 3 of 14
* PCUADES
~~cV4-
*~%~ ~z~o~)
6 A
.- *~ 4v
5. - 17.4;71
!A7 re=i
q~7p
4 77-
7G
ATTACHMENT Z61 R5 Page 4 of 14
H H GG ENGINEERING CHANGE-
6 O,,,- - _
00-F 6O~G~5J
~7i1
r~~T -t e r,
ATTACHMENT Z61 R5 Page 5 of 14
_53CHG-DESG-
ENGINEERING
i-
( •
7 71
'1kI
i~1~72~-
'7
I _ _______
-1741o1 465 ~6.)
fG1046 0.6.,&.0
C;1 -r
-~V
I
d/4V
~..-m7J~ y/
ATTA I CHMENT Z[i ikiý oll Page 6 of114
PCHG-DESG ENGINEERING CHANGE 04 0630
r qI
v~kK
ii~I32
.-- ~
I
'7
Ki~II~ A(i AA'
ATTACHMENT Z61 R5 Page 7 of 14
~ 4 ~ JG~ESG
14\/V~-
ENGINEERING CHANGE O O6~
- I -t
I I
-r
Is.(~0)
(.z 1~i~Z5~-j- ~
TI*~
715
14
-,1
'904 4'
g7~61~
"'c-
-4 5-9 14
-~ 0"f
ATTACHMENT Z61 R5 9e 8 of 14'
-,P4F 6~G
7
-ENGINEERING CHANGE -00
67 F7
.1I N
1t4v
I.
-±IzfV~ci~ ~ 14.fl S~tf1uA~r~
ATTACHMENT Z61 R5 Page 9 of 14
'•_PCHG)DESBG
S-,4" r -- i-
vv
ENGINEERING CHANGE 600 '61oo@ 5
9- 97
~2 \~ ~4~ec ~rrc,7.z~3
ATTACHMENT Z61 R5 Page 10 of 14
LtPESG
eU4\jI )ESG
ENGINEERING CHANGE .
" i • .:•-"--'O~55
4-
ATTACHMENT Z61 R5 Page 11 of 14
PCHG-DESG ENGINEERING
V,-•I. ", Z " .. ... ,-
CHANGE
TP il T4
0 5CO
I.
I
.-2"... -- • . r . -- ;
ATTACHMENTZ61R5 Page 12 of 14
PCHG-DESG GE GC E
(~fPNGINEERING CHANGE R5,
~0'.~-
N'
I.
S I o~c'~A
;-511i~
~ ______
~
~
L/L~ -6r~, 54
0-
2 .0•- •oI•9,,.I•,.
N(
I
ATTACHMENT Z61 R5 Page. 13 of 14
PCHG-DESG0
" ,-ENGINEERING CHANGE i •
: .+ , . . . /' ... .K
- I -
-- -----.--.1-.----.-,----- -
61 1/I.Z I
x
~-~~'1*
* -.
- -I /
- - -- I -
~0
10 -'
I
Page 14 of 14ATTACHMENT Z61 R5
PCHG-DESG ENGINEERING CHANGE 0000063016R5
EC 63016
The following 6 pages are for reference only. Their purpose is to provide QC with a suggested format for
recording examination results based on the requirements of IWL-5250 for the replacement concrete in
the access opening and a 2' wide strip around the perimeter of the opening.
John Holliday 9/3/09
ATTACHMENT Z60R5 Page 1 of 7
PC HG-DESG ENGINEERING CHANGE 000006301i
PRE-ILRTBASELINE DETAILED VISUAL (VT-ic) EXAMINATION OF CONCRETE SURFACES IN AND AROUND ACCESS OPENING
61R56
25'-0" Wide Access OIeninR
Page I of
6 spaces at 2'-0" each = 12'-0" 2,-os'6 spaces at 2'-0" each = 12'-0"
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
. 44 '7 29+ 316 17 18 '19 20 21 . "'22 *' -23', 24 25i ".27 '.' 28 29 30
31 32 33 34 35 . .42 4r " 4
4 4ý
46 47 48 '49 .50 51 52 53 54 55'56 7 58 5 60•5 .....58 59',
61 62. :-63* 64. 65 66 6' 6 8 6 70 7ý1 73 7 75
d ' -8 976 77 78& 9 8 8:1.8 ~ 84 5 86 87 8 8 9
9
N
m
m%4
91 , 192 g3• -9S .96,• 99. ÷ .
AW"'1.02- :1I03!': 105
T
-19''110 '11 11 11 11 15 16 17 118 "119 120107 109 \4~:10 il 11 417
.E
0
ba
N
121 1:22--'4~4>,
-.1-24125S
12 6 127 . ,128& 129. ,6,430ý- 4 4' •.2" 14 44-4
'-4-" 'C4-4*34.7 135
13 '3 38: 139 140 141 14,13 144 145- , '4:46ý -1IX 7' 18 149 150136 443 I A 4.14
151 152 153 415 ~15 16 1", 5 19 1~.: 161 1'62 163 164" 16515 '1 4 5 1 4ý, ,'5 :15'
166 167, 168* 16J7 - 171. 172'ý 17, 1174,ý 1'1:75~ 1761 177' P8 179 180
181 182 18 -184 18ý5' 186: 187- 1988' 8 9, 11 12 13 '9 195
ý196 1"9§7 198 f 200 201: 20 0 0-4 205, 26, >207 208 210
211 212 213 214 215 216 217 21 8 219 220 221 222 223 224 225
9i4V4
-C
9
'ULa
N4'FAW'
L
14Z
Elevation View Looking From Outside Containment
NOTE: Darker shaded area represents the replaced concrete within the access opening
ATTACHMENT Z60R5 Page 2 of 7
PCHG-DESG ENGINEERING CHANGE 00
Pame 1 of
During-ILRTnLETAII cn wJICI IAI Itrriel iVAiAIIMATIfIk rnif nhllfl'DCTi CIDIrAfl: INJ Afdti• ADe%"IIn AdICCC eDlOIlkMIl
00063016R5
4 25'-0" Wide Access Opening
21-0"1 6 spaces at 2'-0" each = 12'-0" 1,-o" 6 spaces at 2'-0" each = 12'-0" 2O
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
16 17 18' 19 20 22 .22,823, 4,25 '2 29:: 30
31 32 33 34 '5 36. 37 38ý- "39 -I40. ' `4A2 +•' 44 4
46 47 48 49. , 50,ý 0 5 52 53 54, •55 56 57 58 59'ý 605Lý.~~ ~~ 56'`ý7 5 -9 6
61 62 63 64 "65 66, 67 68 -69 '"',0 71 ,72, 73.. .74 75
76 77. 178' i79 80 81 82. 83 84, 85 846 "'8 88.89.9085A87',.-.- 88- if :89 90g
91 92', 9i3 94 .'95~, ~.96 -97 98 99.:,-:..'100r'101"? 102 103 i4 105
93 +• , .'101': i 2 10i+ 1
0N
f-hII
UwGD
N4''U
GDU'U
wCL
0
41
1%
9
107106 ,108 i09A'+ii
.44'4 .4113 +++
115 ,16 -7,A-4
1<'' "1-912120
------
121 122 244 125. V27+ "128 -129 *30 i4 44
4' '4 7
<~131~'-'44
'182133-+!
134 135
136 137 138 139 140 14 1 '4 2 +143 '144 1 6 4,7' 48 149 1504, 4 4 , + 4 , ,,,+• ;
151 152 1 154 i 15 156 6 162
166 167' 1168 .16' 1 7 17 173' 174 '175 176, -17.7 178 1.79 180
18 182 1 83 1.-8 85 1861 118 88 189 190, 1918 928• 193,19§4 195
A 19 20 201 2:0600721196 197 198 1203 20 -;,102' .203 204. 2"005" .2 207 . 08- 209 210
211 212 213 214 215 216 217 218 219 220 221 222 223 224 225
m
9
m-&n
CL
v pFloluntinn ViauwLookine From Outside ContainmentblblUGIVII g IblI
NOTE: Darker shaded area represents the replaced concrete within the access opening
ATTACHMENT Z60R5 Page 3 of 7
PCHG-DESG ENGINEERING CHANGE 0000063Page I of
Post-ILRTDETAILED VISUAL WVT-1C) EXAMINATION OF CONCRETE SURFACES IN AND AROUND ACCESS OPENING
016R5
Elevation View Looking From Outside Containment
NOTE: Darker shaded area represents the replaced concrete within the access opening
ATTACHMENT Z60R5 Page 4 of 7
Page of
HI
mz
N0)C)
Pre-ILRT: Record of IWL Concrete Examinations at Containment Access Opening-u0I
mCOG)
PANEL #
- I I - - I
5min5 - I -
__________ + -+ A
PANEL#
- I - I - I - I -
PAN EL#
mz0zmm
zG)I
zG)m
- ~- r - * - -
- I - -
___ 4- i
- I - - I - I -
-cCDwJ
2
PANEL# PANEL # PANEL#
Page of
H
mz.- t
N0)
C.•
During-ILRT: Record of IWL Concrete Examinations at Containment Access Opening-00G)0mc,)G)- I - I ---- - I - P - U - I -
- ~~~ ~I-' - -
+ I +
- U - I - I - U -
PANEL#
- - - I - I -
rnLI - I -
PANEL#
-- - I -
PANEL#
_______ I I
- I - I - I - I -
CD
0)h
-.4
PANEL# PANEL# PANEL#
Page of
r
-1-
mz
N0')
Post-ILRT: Record of IWL Concrete Examinations at Containment Access OpeningG)
G)m - I - -
~ ----
- -
- I - - -
PANEL # PAN EL # PANEL #
- .hhhh.h!IImEhm.~ - Im I -
i - I - i I -
CD-40
-4
PANEL # PANEL # PANEL #
f•
PCHG-DESG , ENGINEERING CHANGE 0000063016R3PAkc~L2-I~
-a P H-L,4\ er
-A L u P"rT I - t- d (,gA Pp
PA46T~ ~s ~4ATC4~* ~c ~'FEC--co()
$0
A
4-
0-r-m"e-0
UO
44Y4
(fEf. .ýTTPCOW qwr s
It\ **-~i-' p
~
RASj$A,-
Ott pcý
- -l_______________ 7
5~-,c s,
24
. .. . . d .• I "
.... , • : .r7+be.;-- ~2L~A~-
ATTCHcN R P oATTACHMENT Z59R3 Page 1lof 5
9,. ;-PCHG-DESG ENGINEERING CHANGE: 0000063.016R3
9pt L~
F6~-~y "~~N ~,o ~ ~ Lp~r ~,
14'.:C 7c 7
447 4
4. -A,,
-- LS-T3 i L-r Z~
&-5 -- 6.0
ATTACHMENT-Z59R3 Page 2of 5
PCHG-DESG ENGINEERING CHANGE 0000063016R3I e
Holliday, John ATTAc A+Asntý
From:Sent:To:Subject:Attachments:
Brian Giometti [[email protected]]Tuesday, June 30, 2009 3:41 PMHolliday, JohnRail EQ ReactionsRISA-3D Graphic.pdf; Rail Support - No Roller.pdf
John-
Here are the reactions on the rail during the design earthquake. The values increased a bit from when we last spoke,however this really the best we can do. I've also attached a sketch of the actual lateral support which will be used toprevent tangential movement during the earthquake. Let me know if you have any more questions.
Brian GiomettiProject Engineer
Precision Surveillance Corporation3468 Watling Street I East Chicago I IN 1 46312P: (219) 397-5826 1 F: (219) 397-5867http://www.psctendon.com
1
ATTACHMENT Z59R3 Page 3 of 5
H0
mz-HN01Co Bevel tube to align to radius
mzG)zmm
zG)
I"/
zG)m
Tube capped w/2"x4" end plate
S12x5OCrane Rail
- TU 4"x4"xI'4
TU 2"x4"x1 4"
00000
0
0')
Co,
.Vil Y4.
I
ftPCHG-DESG ENGINEERING CHANGE 0000063016R3
Z yA
-- /
".
\
47.7
/o,/,,,j'
47.7
Results for LC 8, DL+OL+0.7(ELX+ELY)Reaction units are k and k-ft
Precision Surveillance Cor
Brian Giometti
CR-N 10 1 o3-1 03
CR3 - BT3-120 & BT4-180 USF Design - Rev 1
CR-Ni 013-103 BT3-120.BT4-180
ATTACHMENT Z59R3 Page 5 of 5
PCHG-DESG ENGINEERING CHANGE 0000063016R5
CONTAINMENT IWL REPAIR PLAN
FOR THE CRYSTAL RIVER UNIT 3
STEAM GENERATOR REPLACEMENT MODIFICATION
Progress Energy Florida
Rev. 2
Prepared By: ---4<- CCasaba Ranganath
Reviewed By: ) -J_ nHolliday
Approved By:Dan Jopling
Da-OtDate
Date-OqDate
Date
ATTACHMENT Z58R5 Page 1 of 27
PCHG-DESG ENGINEERING CHANGE 0000063016R5
Progress Energy Florida
CONTAINMENT IWL REPAIR PLAN FOR THE CRYSTAL RIVER UNIT 3
STEAM GENERATOR REPLACEMENT MODIFICATION
TABLE OF CONTENTS
Page
1.0 PU R PO S E ....................................................................................................................... I
2.0 BAC KG RO UND .............................................................................................................. 1
3.0 ACTIVITIES TO BE PERFORMED 2................................................................................. 2
4.0 APPLICABLE CODE EDITION, ADDENDA, AND CODE CASES ............... 3
5.0 M A TER IA L ...................................................................................................................... 3
6.0 QUALITY CONTROL REQUIREMENTS ................................................................... 7
7.0 REBAR SPLICE QUALITY CONTROL REQUIREMENTS ........................................ 9
8.0 PRESTRESSING SYSTEM QUALITY CONTROL ................................................... 10
9.0 DETENSIONING, REMOVAL, REPLACEMENT AND RETENSIONING OF
PRESTRESSING TENDONS ........ 6 .......................................................................... 10
10.0 EXAMINATION OF PRESTRESSING SYSTEM ..................................................... 12
11.0 EXAMINATION AND TESTING ................................................................................ 14
12.0 ACCEPTANCE CRITERIA ....................................................................................... 15
13.0 CUTTING, REMOVAL AND REINSTALLATION OF STEEL REINFORCEMENT ........ 16
14.0 DEMOLITION AND PLACEMENT OF CONCRETE ................................................ 16
15.0 PRESSURE TESTING AND PRESERVICE EXAMINATION ................................... 18
16.0 INTERFACE REQUIREMENTS ............................................................................. 19
17.0 HANDLING, STORING AND SHIPPING REQUIREMENTS ..................................... 19
18.0 RECORDS AND REPORTS .................. .......................................... 19
19.0 REFERENCES .............................................................................................................. 21
20.0 BIBLIOGRAPHY ..................................................................................................... 23
ATTACHMENT Z58R5 Page 2 of 27
IPCHG-DESG ENGINEERING CHANGE 0000063016R5
Progress Energy Florida
CONTAINMENT IWL REPAIR PLAN FOR THE CRYSTAL RIVER UNIT 3
STEAM GENERATOR REPLACEMENT MODIFICATION
REVISION SUMMARY
REVISION NUMBER DESCRIPTION
0 INITIAL ISSUE
1 SECTION 3.1 ADDITIONAL ACTIVITIES.
SECTION 5.1: ADDED DIV. 2 AFTER SECTION III.
SECTION 5.11: ADDED A LINE REGARDING SHEATHING JOINT.
SECTION 9.2: REVISED TENDON CUTTING SEQUENCE.
SECTION 10.1: CLARIFIED THE TENDONS THAT REQUIRE
EXAMINATION OF THEIR END ANCHORAGE COMPONENTS
AND SURROUNDING CONCRETE.
REWORDED BULLET 4 FIRST ITEM.
SECTION 11.3: DELETED THE SECOND BULLET.
SECTION 14.3: DELETED THE LAST BULLET.
SECTION 15.3: REWORDED EXAMINATION REQUIREMENTS
FOR CONCRETE SURROUNDING BEARING PLATES.
SECTION 18.4: ADDED ADDITIONAL RECORDS REQUIRED TO
BE MAINTAINED.
MADE EDIOTRIAL CORRECTIONS IN SECTION 19.0 AND OTHER
SECTIONS.
2 REVISED SECTION 9.2 BULLET 1 AND 2 TO CHANGE VERTICAL
ADJACENT TENDONS FROM 34V8, 34V9, AND 34V10 TO 34V12
AND 34V1 3 REVISED THE PROCESS USED TO REMOVE THESE
TENDONS.
ATTACHMENT Z58R5 Page 3 of 27
PCHG-DESG ENGINEERING CHANGE 0000063016R5
CONTAINMENT IWL REPAIR PLAN FOR THE CRYSTAL RIVER UNIT 3
STEAM GENERATOR REPLACEMENT MODIFICATION
1.0 PURPOSE
1.1 The purpose of this IWL Repair plan is to identify essential requirements
pertaining to the provision of a temporary access opening in the Crystal
River 3 concrete containment structure in support of the Steam Generator
Replacement (SGR) Project. Major activities include hydro-demolition of
concrete, cutting, removal and reinstallation of steel reinforcement,
removal and reinstallation of tendons, sheathing, and corrosion protection
medium, and placement of concrete. The repair/replacement plan
implements the requirements of ASME B&PV Code, Section Xl,
Subsection IWL (Reference 19.2), 10CFR50.55a (Reference 19.3) and
the Crystal River Unit 3 Section Xl Repair and Replacement Program
(Reference 19.17). This document does not include requirements for any
activities associated with removal or reinstallation of the containment liner
plate.
2.0 BACKGROUND
2.1 Steam Generator Replacement (SGR) at Crystal River 3 (CR3) will
require creation of an access opening through the containment shell to
facilitate removal of the existing steam generators and installation of new
ones. Creation and restoration of the access opening will require the
removal and reinstallation of the concrete, rebar, tendons, tendon
sheathing and liner plate within the boundaries of the opening and de-
tensioning and re-tensioning of selected vertical and horizontal tendons
adjacent to the opening. Additionally, a new reinforcing cage comprised
of 2 layers of #11 rebar at 11" center to center spacing, in both the hoop
and vertical directions is to be installed in the opening. The new #11 rebar
are not spliced; these are supported as shown on Drawing 421-350
(Reference 19.31). Related activities may include installing temporary
anchorages to the outer surface of the concrete containment.
2.2 The post-tensioning system used on Crystal River Unit 3 was tested and
supplied by the Prescon Corporation of Corpus Christi, Texas. Each
tendon consisted of 163 7-mm diameter low relaxation wires and
Page 1 of 24
ATTACHMENT Z58R5 Page 4 of 27
PCHG-DESG ENGINEERING CHANGE 0000063016R5
CONTAINMENT IWL REPAIR PLAN FOR THE CRYSTAL RIVER UNIT 3
STEAM GENERATOR REPLACEMENT MODIFICATION
developed a minimum ultimate tendon force of 2,333.5 kips. The low
relaxation tendon wire conforms to the applicable portions of ASTM
A 421-65 (Reference 19.7), type BA with a minimum ultimate tensile
strength of 240,000 psi. The end anchorage of each wire was a "BBRV"
buttonhead type. The details of the tendon system are shown in FSAR
Figure 5-24 and Figure 5-25 (Reference 19.15).
2.3 The creation of the temporary construction opening will affect the
containment wall, vertical and horizontal tendons and sheaths within the
boundaries of the opening. The following tendons within the opening will
be removed and replaced with new tendons:
o 34V8 thru 34V17 (10 verticals)
o 53H27 thru 53H35 and 42H27 thru 42H34 (17 hoops).
2.4 The following vertical and horizontal tendons immediately adjacent to the
opening will be de-tensioned and then re-tensioned:
o 45V22 thru 45V24, 34V1 thru 34V, 34V18 thru 34V24 and 23V1 thru
23V3 (20 verticals).
o 42H22 thru 42H26, 53H23 thru 53H26, 42H35 thru 42H39, and 53H36
thru 53H39 (18 hoops)
3.0 ACTIVITIES TO BE PERFORMED
3.1 The following activities are addressed in this repair plan:
* Degreasing, de-tensioning and removal of tendons.
* Hydro-demolition of concrete.
o Cutting, removal and reinstallation of steel reinforcement.
* Installation of new additional reinforcing bars.
* Cutting, removal and installation of tendon sheathing.
* Installation and subsequent removal of temporary attachments to the
concrete.
" Concrete material tests.
" Placement of concrete.
Page 2 of 24
ATTACHMENT Z58R5 Page 5 of 27
PCHG-DESG ENGINEERING CHANGE 0000063016R5
CONTAINMENT IWL REPAIR PLAN FOR THE CRYSTAL RIVER UNIT 3
STEAM GENERATOR REPLACEMENT MODIFICATION
o Surface preparation required prior to installation of new components
of the tendon system.
* Surface preparation required prior to placement of new concrete and
curing of concrete.
* Installation, tensioning, de-tensioning and re-tensioning of additional
tendons around opening, and re-greasing of tendons.
o Performance of examinations and system pressure test.
4.0 APPLICABLE CODE EDITION, ADDENDA, AND CODE CASES
4.1 The 2001 Edition with addenda up to and including the 2003 Addenda of
ASME Section XI will be used for repair/replacement activities applicable
to Subsection IWL.
4.2 For those repair/replacement activities performed in accordance with the
requirements of ASME Section III, Division 2, the applicable code edition
will be the 2001 Edition with addenda up to and including the 2003
Addenda.
4.3 Design of the concrete containment structure (concrete, tendons and
steel reinforcement) was performed in accordance with "Building Code
Requirements for Reinforced Concrete," ACI 318-63 (Reference 19.5).
Design of the new No. 11 reinforcing will also be in accordance with ACI
318-63.
4.4 The original structural concrete work was performed in accordance with
"Specifications for Structural Concrete for Buildings," ACI 301-66
(Reference 19.4). Structural concrete repair activities will also be in
accordance with ACI 301-66.
5.0 MATERIAL
5.1 Material will conform to the requirements of the original design
specification or ASME Section III Division 2 (Reference 19.1), with the
following exception: Portland cement that is used to restore concrete to
the access opening will be Type I cement, conforming to ASTM C 150
Page 3 of 24
ATTACHMENT Z58R5 Page 6 of 27
PCHG-DESG ENGINEERING CHANGE 0000063016R5
CONTAINMENT IWL REPAIR PLAN FOR THE CRYSTAL RIVER UNIT 3
STEAM GENERATOR REPLACEMENT MODIFICATION
(Reference 19.13). This is a change from the original design, which used
ASTM C150 Type II Portland cement, modified for moderate heat of
hydration. Reconciliation of the differences between Type I and Type II
cement is addressed in Section B.6.10 of EC 63016 (Reference 19.28).
5.2 Replacement concrete that is to be used to restore the containment
access opening will be chemically, mechanically and physically
compatible with the existing concrete. The replacement concrete will be
supplied, placed, inspected and tested in accordance with Specification
CR3-C-0003 (Reference 19.19). The specification requirements assure
that the replacement concrete will have the physical properties required
by calculation S06-0006 (Reference 19.26).
It is noted that the original concrete design for the containment wall
specified ASTM C150 Type II Portland cement and a minimum concrete
compressive strength of 5,000 psi.
5.3 Requirements relating to concrete materials, including cement,
pozzolans, coarse aggregate, fine aggregate, admixtures and mixing
water, are identified in Specification CR3-C-0003 (Reference 19.19).
These will conform. to the applicable ASTM standards as listed in that
specification.
5.4 The original No. 8 deformed reinforcing bars conform to the requirements
of ASTM A 615-68 (Reference 19.11) Grade 40. Damaged or misplaced
reinforcement will be replaced by Grade 60 bars conforming to the
requirements of the latest revision of ASTM A615 as specified in
EC 63016 (Reference 19.28). New No. 11 reinforcing bars also will meet
the requirements of the latest revision of ASTM A615 as specified in
EC 63016 (Reference 19.28). The yield strength and tensile strength of
the new and replacement bars will meet or exceed the minimums
specified for original (Grade 40) bars in ASTM A615-68. Material
property requirements reconciliation is documented in the EC 63016.
o New reinforcing steel intended to be spliced by welding will meet the
requirements of Paragraph CC-2333.1 of ASME Section III, Division 2
(Reference 19:1) as specified in the EC 63016.
Page 4 of 24
ATTACHMENT Z58R5 Page 7 of 27
PCHG-DESG ENGINEERING CHANGE 0000063016R5
CONTAINMENT IWL REPAIR PLAN FOR THE CRYSTAL RIVER UNIT 3
STEAM GENERATOR REPLACEMENT MODIFICATION
5.5 All mechanical splices will be BarGrip XL - Nuclear / Type 2 Series cold-
swaged steel coupling sleeves for #8 size rebar, as manufactured by
BarSplice Products, Inc, Dayton OH. Couplings will be manufactured
from seamless steel tubing that conforms to ASTM A 519
(Reference 19.10) Grade 1018. Mechanical splices are classified as
"Safety Related" (Q). Detailed requirements applicable to the mechanical
splices are provided in EC 63016 (Reference 19.28).
5.6 The original low relaxation tendon wire conforms to the applicable
portions of ASTM A 421-65 (Reference 19.7), type BA and was supplied
with a minimum ultimate tensile strength of 240,000 psi. Relaxation test
data are shown in Table 5-1 and Figure 5-26 of the CR3 FSAR
(Reference 19.15). When extrapolated to 40 years, the data in FSAR
Figure 5-26 indicates that the maximum relaxation is less than 2%. The
design is based on a relaxation of 4%.
5.7 The replacement tendons are 163 7mm diameter low relaxation wires that
conform to the requirements of ASTM A421-98a, Type BA and will be
supplied with a minimum ultimate tensile strength of 240,000 psi1. The
wire meets the requirements of Supplement I for Low-Relaxation Wire.
Material property requirements reconciliation is documented in EC 63016
(Reference 19.28).
5.8 Tendon Anchor Heads (163 wire stressing washer) material will meet the
requirements of ASTM A 514 (Reference 19.9) Grade Q per Precision
Surveillance Corporation (PSC) Drawing CR-N1009-502, "163 Wire
Stressing Washer," which replaces Drawing 5EX7-003 Sheet A8
(Reference 19.35) for the new anchor heads for the replacement tendons
34V8 thru 34V17 and 42H27 thru 42H34 and 53H27 thru 53H35. This
'ASTM A421-65 does not specify a minimum tensile strength for 7 mm Type BA wire (anote to the applicable table states that BA wire is not normally supplied with a diameter of0.276 in, which is equal to 7 mm). ASTM A421-98a specifies a minimum tensile strength of235 ksi for 7 mm Type BA wire. However, the CR3 tendon purchase specification requires
that the 7 mm wire have a minimum tensile strength of 240 ksi.
Page 5 of 24
ATTACHMENT Z58R5 Page 8 of 27
PCHG-DESG ENGINEERING CHANGE 0000063016R5
CONTAINMENT IWL REPAIR PLAN FOR THE CRYSTAL RIVER UNIT 3
STEAM GENERATOR REPLACEMENT MODIFICATION
material has been evaluated and found to be suitable for replacing the
original material identified as Armco SSS-100, ASTM A514 Grade E
material. Material property requirements reconciliation is documented in
EC 63016 (Reference 19.28).
5.9 Tendon grease cap gaskets, studs, nuts and washers will be furnished
per original Prescon Drawing 5EX7-003, Sheet A-9D (Reference 19.37)
(for hoop and upper vertical ends) and Drawing 5EX7-003, Sheet A-9C
(Reference 19.36) (for the lower vertical ends).
5.10 Tendon grease cans will be fabricated from HR-LC steel per original
Prescon Drawing 5EX7-003, Sheet A-9D (Reference 19.37).
5.11 Replacement tendon sheathing will be fabricated from ASTM A513
(Reference 19.8), Type 5 resistance welded tubing with a 5" internal
diameter and 5%" outside diameter as specified in EC 63016
(Reference 19.28). Use of this material (which is essentially identical to
the sheathing in the dome and basemat) in lieu of the original 22 gage
galvanized duct provides the semi-rigid, watertight conduit needed to
accommodate installation of the new tendons prior to concrete placement.
Tendon sheathing is not Safety Related. Existing and new tendon
sheathing will be joined by couplings as shown on Drawing 421-350
(Reference 19.31).
5.12 Sheathing couplings will be sealed with Belzona 1211 E-Metal as
specified in EC 63016 (Reference 19.28) and where shown on Drawing
421-350 (Reference 19.31).
5.13 Existing shims (load bearing plates inserted between tendon anchor
heads and bearing plates) will be cleaned, examined and reused unless
found to be damaged or severely corroded. New shims needed during
reactor building restoration will be drawn from the CR3 warehouse
inventory that is stocked for use during periodic tendon in-service
inspection activities. The stocked shims are fabricated from Armor Plate
HY-80 Type 1 (MIL-S-16216). The substitution of this material for the
original Modified Armco VNT (proposed ASTM A633-E) was previously
evaluated in PEERE 987 (Reference 19.38).
Page 6 of 24
ATTACHMENT Z58R5 Page 9 of 27
PCHG-DESG ENGINEERING CHANGE 0000063016R5CONTAINMENT IWL REPAIR PLAN FOR THE CRYSTAL RIVER UNIT 3
STEAM GENERATOR REPLACEMENT MODIFICATION
5.14 Corrosion protection medium, which is injected into the tendon sheathing
after stressing, will be Visconorust 2090-P4 or latest compatible
formulation by Viscosity Oil Company. The corrosion protection medium
will be certified to conform to the specifications given in ASME Section III,
Division 2, Table CC-2442-1. This material is fully compatible with the
original corrosion protection medium, a Visconorust 2090-P formulation,
per the evaluation documented in EC 63016 (Reference 19.28).
5.15 Replacement tendons will be protected from corrosion after fabrication at
PSC's manufacturing facility by coating them with Visconorust 1601
Amber by Viscosity Oil Company. This material is fully compatible with
Visconorust 2090-P4 per the evaluation documented in Section B.6.8.b of
EC 63016 (Reference 19.28).
5.16 Welding filler material is classified as "Safety Related"(Q) and will be
controlled accordingly. Welding filler material, which will conform to the
applicable requirements of the Corporate Welding Manual
(Reference 19.18), will be traceable to purchase orders.
5.17 Use of materials of a specification, grade, type, class, or alloy, and heat-
treated condition other than that originally specified will be evaluated for
suitability for the specified design and operating conditions in accordance
with ASME Section Xl, IWA-4311 and documented in EC 63016
(Reference 19.28). Any changes to the original material examination and
testing requirements will be reconciled to the requirements of the original
construction specifications (See References 19.20, 19.21 & 19.22).
6.0 QUALITY CONTROL REQUIREMENTS
6.1 Concrete material qualification testing and control requirements will be in
accordance with Specification CR3-C-0003 (Reference 19.19).
6.2 The new concrete mix will be designed for high early strength and a low
creep coefficient. In addition, the reinforced concrete patch will be
designed to ensure stiffness compatibility with the original concrete. The
proportions for the replacement concrete mix design will be as
Page 7 of 24
ATTACHMENT Z58R5 Page 10 of 27
PCHG-DESG ENGINEERING CHANGE 0000063016R5
CONTAINMENT IWL REPAIR PLAN FOR THE CRYSTAL RIVER UNIT 3
STEAM GENERATOR REPLACEMENT MODIFICATION
determined by the test program specified in EC 63016 Attachment Z13RO
(Reference 19.29).
6.3 A batch plant will be setup 'and qualified on site to furnish concrete in
accordance with ASTM C 94 (Reference 19.12). During concrete
operations, an independent testing laboratory will provide inspectors at
the batch plant to certify the mix proportions of each batch produced at
the plant and sample and test the concrete ingredients per Specification
CR3-C-0003 (Reference 19.19). The inspectors will verify that delivery
tickets conforming to the requirements of CR3-C0003 are prepared for
each load of concrete.
6.4 Concrete delivery trucks will comply with the requirements of ASTM C 94
(Reference 19.12).
6.5 Inspectors at the construction site will inspect reinforcing steel and form
placement, perform slump tests, prepare test cylinders, check air content,
and record weather conditions in accordance with the requirements of
Specification CR3-C-0003 (Reference 19.19). Test cylinders will be
cured, capped and. tested in accordance with CR3-C-0003. Evaluation
and acceptance of test results will be in accordance with ACI 318
(Reference 19.5) 'and Article CC-5232 of ASME Section III, Division 2
(Reference 19.1).
6.6 Placing, consolidating and curing of fresh concrete will conform to
applicable requirements of ACI 301 (Reference 19.4) as detailed in
Specification CR3-C-0003 (Reference 19.19).
6.7 Special requirements will be implemented for cold and hot weather
concreting. These include requirements for insulation, form cooling and
additional test cylinders as detailed in CR3-C-0003 (Reference 19.19).
6.8 Certified mill test reports will be provided for each heat of reinforcing steel
covering chemical composition and ASTM specification requirements for
mechanical properties. Bars will provide identification as to manufacturer,
size, type, and grade or yield strength.
Page 8 of 24
ATTACHMENT Z58R5 Page 11 of 27
PCHG-DESG ENGINEERING CHANGE 0000063016R5
CONTAINMENT IWL REPAIR PLAN FOR THE CRYSTAL RIVER UNIT 3
STEAM GENERATOR REPLACEMENT MODIFICATION
6.9 Reinforcing steel will be procured as safety-related material from a
manufacturer/supplier with a qualified QA Program as specified in
EC 63016 (Reference 19.28). The manufacturer/supplier will be
responsible for performing material tests in accordance with the purchase
order and the requirements of ASTM A615 (Reference 19.11).
7.0 REBAR SPLICE QUALITY CONTROL REQUIREMENTS
7.1 The No. 8 reinforcing removed from the opening area will be spliced to
stub bars by swaged sleeves where possible and otherwise by welding.
To eliminate buckling that can result if a bar is connected by swaged
sleeves at both ends (swaging causes a small increase in bar length),
separate bars will- be spliced to each stub and spliced together by lapping
as shown on Drawing 421-351 (Reference 19.32).
7.2 Swaged sleeve splices will be tested and installed in accordance with
manufacturer's instructions and the requirements of ASME Section III
(Reference 19.1), Division 2, CC-4333 as specified in EC 63016
(Reference 19.28) and shown on Drawings 421-350 and 421-351
(References 19.31 & 19.32). The manufacturer of the swaging system
will provide training on the use of its equipment. The quality control (QC)
requirements in Sections CC-2300, CC-4330 and CC-5320 of ASME
Section III, Div. 2 (Reference 19.1) will apply with the following exception
as specified in EC 63016 (Reference 19.28). Since the swaged couplings
will be quite close to the face of the concrete in the opening, it will not be
possible to cut out production splices and have a sufficient length of stub
reinforcing remaining to remake these. Therefore, all testing will be on
sister splices. The mix of sister splice reinforcing grade combinations
(Grade 40 to Grade 40 and Grade 40 to Grade 60) will be consistent with
that of the production splices.
7.3 Welding of reinforcing bars, welder qualification and examination of welds
will be in accordance with Corporate Welding Manual (Reference 19.18)
procedures incorporating the applicable requirements of AWS D1.4
(Reference 19.14).
Page 9 of 24
ATTACHMENT Z58R5 Page 12 of 27
PCHG-DESG ENGINEERING CHANGE 0000063016R5
CONTAINMENT IWL REPAIR PLAN FOR THE CRYSTAL RIVER UNIT 3
STEAM GENERATOR REPLACEMENT MODIFICATION
7.4 Lap splices will conform to applicable ACI 318 (Reference 19.5)
requirements as specified in EC 63016 (Reference 19.28) and detailed on
Drawings 421-350 and 421-351 (References 19.31 & 19.32).
8.0 PRESTRESSING SYSTEM QUALITY CONTROL
8.1 Tendons and other Quality Related pre-stressing system materials
procured for this repair activity will be handled, stored and shipped per
the requirements of MCP-NGGC-0402 "Material Management (Storage,
Issue and Maintenance)" (Reference 19.24) and ANSI N45.2.2 - 1972
"Packaging, Shipping, Receiving, Storage and Handling of Items for
Nuclear Power Stations" (Reference 19.6).
8.2 Anchorheads, wire and completed tendons will be inspected during
manufacture. In addition, Section B.6.25 of EC 63016 (Reference 19.28)
specifies that replacement tendons and associated hardware shall be
inspected at the plant receiving area prior to receipt and acceptance.
9.0 DETENSIONING, REMOVAL, REPLACEMENT AND RETENSIONING OF
PRESTRESSING TENDONS
9.1 Degreasing, de-tensioning, removal of existing tendons, surface
preparation required prior to installation of new items, installation of new
tendons, tensioning and regreasing of tendons will follow the standard
practice specified in procedures in the PSC Field and Quality Control
Procedure Manual (Reference 19.34) that is incorporated into EC 63016
(Reference 19.28).
9.2 Tendons will be de'-tensioned in the following sequence as developed in
Calculation S06-0005 (Reference 19.25).
During the period after reaching cold shutdown (Mode 5) and prior to
the start of hydrodemolition of the concrete, vertical tendons 34V12
and 34V1 3, which are within the opening area, will be ram de-
tensioned and removed. These tendons will be detensioned with a
hydraulic ram, the buttonheads removed with a hand grinder, coiled
Page 10 of 24
ATTACHMENT Z58R5 Page 13 of 27
PCHG-DESG ENGINEERING CHANGE 0000063016R5
CONTAINMENT IWL REPAIR PLAN FOR THE CRYSTAL RIVER UNIT 3
STEAM GENERATOR REPLACEMENT MODIFICATION
and then saved as a contingency to ensure that replacement vertical
tendons of sufficient length are available in the event that a new
replacement tendon is identified as being too short. Additional
tendons that will be removed from within the access opening will be
accomplished by sequential cutting of button heads at one end using
a plasma arc or similar approved process. Tendon locations are
shown on Drawing 421-347 (Reference 19.30).
o During the period after reaching cold shutdown (Mode 5) and prior to
the start of hydrodemolition of the concrete, after removal of the two
vertical tendons 34V12 and 34V13 stated in the first bullet, the 17
hoop and remaining 8 vertical tendons WITHIN the boundaries of the
containment wall access opening will be removed.
* The following additional tendons outside the boundaries of the
containment wall access opening will be de-tensioned (but not
removed): (I) After the new SGs have been rigged into their
respective cubicles inside the D-Rings thereby ensuring that adequate
prestress will be maintained when loads are imposed on the wall
during generator movements and (11) Prior to placement of new
concrete in the opening area:
A. Nine (9) hoop tendons above and nine (9) below the boundaries of
the containment wall access opening (Total 18), and
B. Ten (10) vertical tendons on each side of the containment wall
access opening (Total 20).
9.3 After the tendons that are not to be removed have been de-tensioned, the
degreased tendons will be protected from the elements as specified in
procedures in the PSC Field and Quality Control Procedure Manual
(Reference 19.34) that is incorporated into EC 63016 (Reference 19.28).
9.4 Prior to installation of new tendons, waffle assemblies will be pulled
through the sheathing to clean out residual corrosion protection medium
as well as accumulations of water and debris that may have entered
following tendon removal and during hydro-demolition of the concrete.
Page 11 of 24
ATTACHMENT Z58R5 Page 14 of 27
PCHG-DESG ENGINEERING CHANGE 0000063016R5
CONTAINMENT IWL REPAIR PLAN FOR THE CRYSTAL RIVER UNIT 3
STEAM GENERATOR REPLACEMENT MODIFICATION
9.5
9.6
9.7
Tendons will be installed and tensioned/re-tensioned in accordance with
procedures in the Field and Quality Control Procedure Manual
(Reference 19.34) that is incorporated into EC 63016 (Reference 19.28)
and following the sequence shown on Drawing 421-352 (Reference
19.33). To offset friction loss and provide adequate force at the center of
each tendon, end force is initially raised to 80% of guaranteed ultimate
tensile strength (GUTS). It is then reduced to 70% (± a tolerance) for
lock-off.
Tendon elongation will be measured during stressing and will be
compared to predicted values provided by Engineering. Deviations from
the predicted values will be evaluated against the acceptance limits
specified in ASME Section III, Division 2 (Reference 19.1).
Tendon regreasing will be completed within 30 days of Mode 2 Entry.
Corrosion protection medium will be replaced following procedures in the
PSC Field and Quality Control Procedure Manual (Reference 19.34) that
is incorporated into EC 63016 (Reference 19.28).
10.0 EXAMINATION OF PRESTRESSING SYSTEM
10.1 The pre-stressing system will be examined in accordance with PSC Field
and Quality Control Procedure Manual (Reference 19.34) procedures,
EC 63016 (Reference 19.28), and work order instructions. Required
examinations and associated tests are summarized below.
* Prior to Detensioning
o End anchorage components, including bearing plates,
anchorheads, shims and buttonheads will be examined for
signs damage and corrosion (Detensioned / Retensioned
Tendons only).
o Concrete adjacent to bearing plates will be examined for
cracking and other indications of damage or degradation
(Detensioned/Retensioned and removed / replaced tendons).
o After De-Tensioning
Page 12 of 24
ATTACHMENT Z58R5 Page 15 of 27
PCHG-DESG ENGINEERING CHANGE 0000063016R5
CONTAINMENT IWL REPAIR PLAN FOR THE CRYSTAL RIVER UNIT 3
STEAM GENERATOR REPLACEMENT MODIFICATION
o End anchorages will be examined for indications of broken
wires which, if found, will be extracted, examined and / or
tested in accordance with ASME Section Xl, Paragraph IWL-
2523.2 to determine the cause of failure.
o Wires that protrude from the anchor head as well as visible
areas of the wire bundle between the anchor head and the
bearing plate will be examined for corrosion or pitting which, if
found will be evaluated by the IWL Responsible Engineer.
o Prior to Tendon Installation
o Tendon wires, button heads, anchor heads and bearing plates
will be examined for signs of damage, pitting and corrosion.
* Prior to Concrete Placement
o Sheath and couplings will be examined for alignment, and
signs of damage including kinks, dents, oval areas, and holes.
Verify the attachments are secure.
o Sheath and coupling sealant will be examined for holes and
tears as well as to verify complete joint coverage.
o Following Re-Tensioning
o End anchorage components including bearing plates,
anchorheads, shims and buttonheads will be examined for
signs of damage and corrosion.
o Concrete adjacent to bearing plates will be examined for
cracking and other indications of damage or degradation
Acceptance standards for the above examinations and tests will be as
listed in the PSC Field and Quality Control Procedure Manual (Reference
19.34) procedures, EC 63016 (Reference 19.28), and work order
instructions as specified in ASME Section Xl, Article IWL-3000 and as
established by the IWL Responsible Engineer.
10.2 Examination and test results that do not meet acceptance standards are
evaluated and dispositioned by the IWL Responsible Engineer in
accordance with the requirements of ASME Section Xl, Article IWL-3000.
Page 13 of 24
ATTACHMENT Z58R5 Page 16 of 27
PCHG-DESG ENGINEERING CHANGE 0000063016R5
CONTAINMENT IWL REPAIR PLAN FOR THE CRYSTAL RIVER UNIT 3
STEAM GENERATOR REPLACEMENT MODIFICATION
11.0 EXAMINATION AND TESTING
11.1 Personnel performing the examinations and tests required under this plan
will be trained, qualified and certified in accordance with the CR3 Quality
Assurance Program (Reference 19.16) or under approved vendor quality
assurance programs. In addition, personnel performing reactor building
.concrete examinations will be approved by the IWL Responsible Engineer
in accordance with the requirements of ASME Section Xl, IWL-2320(a).
Personnel training and certification programs will incorporate applicable
requirements of the following documents.
* ASME Section Xl (Reference 19.2), Sub-Sections IWA and IWL
0 Specification CR3-C-0003 (Reference 19.19)
o AWS D1.4 (Reference 19.14).
11.2 Concrete materials, including mixing water, and production concrete will
be sampled and tested to ensure conformance to the requirements of
Specification CR3-C-0003 (Reference 19.19) and the ASTM standards
cited therein. Additional tests will be performed to verify that the selected
design mix meets the unit weight, air content, bleeding, slump, strength
and creep coefficient requirements specified in CR3-C-0003.
11.3 Construction examinations and tests will be performed as required by
EC 63016 (Reference 19.28).' These examinations, except those
associated with the pre-stressing system that are covered in Section 10.0,
are summarized below. Instructions specific to each of these
examinations are as delineated directly or by reference in EC 63016.
* Detailed visual examination of reinforcing stubs (after the No. 8 bars
are cut and concrete has been removed from the opening) as
required by ASME Section Xl, IWL-4220(c) and, if determined
necessary by the IWL Responsible Engineer, repair in accordance
with IWL-4230.
Page 14 of 24
ATTACHMENT Z58R5 Page 17 of 27
PCHG-DESG ENGINEERING CHANGE 0000063016R5
CONTAINMENT IWL REPAIR PLAN FOR THE CRYSTAL RIVER UNIT 3
STEAM GENERATOR REPLACEMENT MODIFICATION
" Visual examination of welded and swaged sleeve reinforcing
splices.
" Load testing of welded and swaged sleeve reinforcing
demonstration splices.
o Load testing of swaged sleeve sister splices.
" Other NDE of welded reinforcing splices as specified by the IWL
Responsible Engineer.
* Visual examination of the concrete surfaces at the bottom, top and
sides of the opening prior to concrete placement (Sections A5.2.10,
D.2.2.4-2 and D.2.2.5-1 of EC 63016 - Reference 19.28).
o Visual examination of reinforcing curtain alignment, lap splices, ties
and supports prior to concrete placement (Sections A5.2.10,
D.2.2.4-2 and D.2.2.5-1 of EC 63016 - Reference 19.28).
0 Batch plant certification examinations and tests per ASTM C94
(Reference 19.12) requirements.
11.4 The new concrete will be visually examined before, during and after the
pressure test as required by ASME Section Xl, Article IWL-5250
(Reference 19.2). These examinations will follow the applicable
requirements of Procedure EGR-NGGC-0015 (Reference 19.23) and
will satisfy the ASME Section Xl, Article IWL-2230 requirement for post-
repair pre-service examination.
12.OACCEPTANCE CRITERIA
12.1 The results of the tests and examinations identified in this plan will be
evaluated against the acceptance standards included (directly or by
reference) in EC 63016 (Reference 19.28), and Specification CR3-C-
0003 (Reference 19.19) as well as in the codes, standards and
procedures cited in Sections 10.0 and above.
Page 15 of 24
ATTACHMENT Z58R5 Page 18 of 27
PCHG-DESG ENGINEERING CHANGE 0000063016R5
CONTAINMENT IWL REPAIR PLAN FOR THE CRYSTAL RIVER UNIT 3
STEAM GENERATOR REPLACEMENT MODIFICATION
13.0CUTTING, REMOVAL AND REINSTALLATION OF STEEL REINFORCEMENT
13.1 The No. 8 steel reinforcement will be cut and removed from the opening
area as specified in EC 63016 (Reference 19.28). Steel will be cut in a
manner that ensures adequate stub length for later reattachment using
swaged sleeve or welded splices as applicable to the stub location. Steel
removed from the opening area will be cleaned, examined and stored for
reuse if determined by the IWL Responsible Engineer to be in acceptable
condition.
13.2 The original layer of No. 8 reinforcing bars will be restored following
installation of tendon sheathing. Restoration work will be done in
accordance with the instructions in EC 63016 (Reference 19.28). The
restored layer will include new Grade 60 bars conforming to the
requirements of ASTM A615 (Reference 19.11) and may include Grade
40 bars that were removed and stored for reuse. The new and reused
bars will be spliced to the stub reinforcing protruding from the periphery of
the opening as described in Section 7.0 of this plan.
13.3 Two layers of new reinforcing (No. 11 bars @ 11" each way) will be
installed in the opening area as shown on Drawings 421-350 and
421-351 (References 19.31 & 19.32). The new reinforcing will be
procured to the requirements of ASTM A615 (Reference 19.11), for
Grade 60 deformed carbon steel bars. This new reinforcing, which is
safety related (Q) is provided to increase the stiffness of the concrete in
the opening area as discussed in Calculation S06-0006 (Reference
19.26).
14.0 DEMOLITION AND PLACEMENT OF CONCRETE
14.1 Concrete will be removed from the opening by high pressure water jets
(hydrodemolition) as described in EC 63016 (Reference 19.28).
Demolition will begin after tendons passing through the opening area
have been removed and will be generally continuous except for
interruptions to allow removal of the No. 8 reinforcing steel curtain and
Page 16 of 24
ATTACHMENT Z58R5 Page 19 of 27
PCHG-DESG ENGINEERING CHANGE 0000063016R5
CONTAINMENT IWL REPAIR PLAN FOR THE CRYSTAL RIVER UNIT 3
STEAM GENERATOR REPLACEMENT MODIFICATION
tendon sheathing. Water jet pressure will be reduced during removal of
the final 6 in of concrete to minimize the potential for liner damage.
14.2 New concrete will be placed following the installation of the new No. 11
reinforcing curtains, new tendon sheathing #8 reinforcing curtain and
formwork (Per Section D.2.2.1-4i of EC 63016, Reference 19.28, new
tendons can be pulled through the sheathing either prior to concrete
placement or after concrete strength has reached 3,000 psi). Concrete
will be batched, mixed, conveyed, placed and consolidated in accordance
with the requirements of Specification CR3-C-0003 (Reference 19.19)
and the ASTM and ACI standards referenced therein.
14.3 The opening area will be prepared for concrete placement as specified in
EC 63016 (Reference 19.28) and Specification CR3-C-0003 (Reference
19.19). Preparation activities will include the following.
* Roughening, cleaning and soaking the top, bottom and sides of the
opening to improve bond between new and existing concrete.
o Cleaning debris, oil, grease and deleterious material from the liner,
tendon sheathing and the reinforcing steel.
o Examining the concrete surfaces, liner, reinforcing steel, tendon
sheathing and formwork to ensure readiness for concrete
placement.
14.4 The outer formwork will be installed after splicing of the No. 8 reinforcing
curtain and cleaning and inspection of the opening area are complete.
The formwork will be supported by form ties welded to liner stiffening
angles and spaced, as specified in Calculation S06-0007 (Reference
19.27), to ensure proper support of both the formwork and the liner during
concrete placement. Ties will consist of standard threaded rod and
helical insert elements as shown on Drawing No. 421-351 (Reference
19.32).
14.5 Concrete will be placed and consolidated in continuous horizontal layers
as specified in Specification CR3-C-0003 (Reference 19.19). Overall
placement rate will be limited as specified in CR3-C0003 to ensure that
Page 17 of 24
ATTACHMENT Z58R5 Page 20 of 27
PCHG-DESG ENGINEERING CHANGE 0000063016R5
CONTAINMENT IWL REPAIR PLAN FOR THE CRYSTAL RIVER UNIT 3
STEAM GENERATOR REPLACEMENT MODIFICATION
form pressure does not exceed design limits for the liner (as derived in
calculation S06-0007 - Reference 19.27) or the formwork. Delays in
concrete placement due to consolidation activities will be minimized to
ensure that there are no cold joints.
15.OPRESSURE TESTING AND PRESERVICE EXAMINATION
15.1 A reactor building pressure test will be performed after de-tensioned and
replaced tendons have been re-tensioned. The test will be conducted as
specified in EC 63016 (Reference 19.28), which incorporates the
applicable requirements of ASME Section Xl, Article IWL-5000
(Reference 19.2). The IWL Responsible Engineer will authorize
performance of the test.
15.2 The pressure test Will be conducted at the design basis accident
pressure, P, = 54.2 psig (calculated peak containment DBA pressure), as
specified in Reference 19.2, prior to returning reactor building to service.
15.3 The surface of all containment concrete placed during repair/replacement
activities will be visually examined in accordance with the requirements
developed in EC 63016 (Reference 19.28), which incorporates the
requirements of ASME Section Xl, Article IWL-5250 (Reference 19.2).
The examinations will be done (1) prior to the start of pressurization, (2)
at test pressure, and (3) following completion of depressurization. In
addition, concrete surrounding the bearing plates of all new and de-
tensioned / re-tensioned tendons will be examined per ASME Section XI,
Subsection IWL Section 2524.1 (Reference 19.2) following the completion
of depressurization. The preservice examination required by IWL-2230
will be conducted in accordance with procedure EGR-NGGC-0015
(Reference 19.23).following completion of depressurization 2. If the results
of the post-test and preservice examinations do not meet the acceptance
standards developed by the IWL Responsible Engineer in accordance
2 A single examination can satisfy the requirements of both IWL-5250 and IWL-
2230.
Page 18 of 24
ATTACHMENT Z58R5 Page 21 of 27
PCHG-DESG ENGINEERING CHANGE 0000063016R5
CONTAINMENT IWL REPAIR PLAN FOR THE CRYSTAL RIVER UNIT 3
STEAM GENERATOR REPLACEMENT MODIFICATION
with IWL-31 10, corrective action will be taken as required by IWL-3113
and IWL-5260.
16.0 INTERFACE REQUIREMENTS
16.1 The ANII will be notified prior to starting the repair/replacement activity
and will be kept informed of progress so that necessary inspections may
be performed.
17.0 HANDLING, STORING AND SHIPPING REQUIREMENTS
17.1 Materials procured for this repair activity will be handled, stored and
shipped per the requirements of MCP-NGGC-0402 "Material
Management (Storage, Issue and Maintenance)" (Reference 19.24) and
ANSI N45.2.2 - 1972 "Packaging, Shipping, Receiving, Storage and
Handling of Items for Nuclear Power Stations" (Reference 19.6).
17.2 Constituent concrete materials will be handled and stored in accordance
with the requirements in Specification CR3-C-0003 (Reference 19.19).
18.0 RECORDS AND REPORTS
18.1 The preparation, submittal, and retention of records and reports of
examinations, tests, and repair/replacement activities will be in
accordance with the CR3 Quality Assurance Program (Reference 19.16)
and the requirements of ASME Section XI, Article IWA-6000
(Reference 19.2).
18.2 Records and reports indicated in this section will be filed and maintained
for the service lifetime of the containment in accordance with the CR3
Quality Assurance Program (Reference 19.16) and in a manner that will
allow access by the Regulator and the Authorized Inspector.
18.3 A report for repair/replacement activities will be prepared on ASME
Section Xl Form NIS-2 upon completion of all required activities
associated with this repair/replacement plan. Upon completion, Form
NIS-2 will be submitted to the Inspector for signature.
Page 19 of 24
ATTACHMENT Z58R5 Page 22 of 27
PCHG-DESG ENGINEERING CHANGE 0000063016R5
CONTAINMENT IWL REPAIR PLAN FOR THE CRYSTAL RIVER UNIT 3
STEAM GENERATOR REPLACEMENT MODIFICATION
18.4 The following records will be maintained in accordance with the CR3
Quality Assurance Program (Reference 19.16)
* Record index,
,, Records and reports of repair/replacement activities,
* Rebar welding procedures and weld qualification records,
o Inspection/examination reports,
* Deficiency evaluations, if any, as required by ASME Section Xl,
Paragraphs IWA-4160 and IWL-331 0.
o Changes made to material, design, or configuration, if any, as
required by ASME Section XI, Paragraph IWA-431 1.
o Repair/Replacement Program and Repair/Replacement Plan,
o Reconciliation documentation,
o Owner's Report for Repair/Replacement Activities, Form NIS-2,
* Nondestructive examination (NDE) procedures and records,
including NDE personnel qualifications/certifications,
* Pressure test procedures and test records,
0 Concrete test reports.
Page 20 of 24
ATTACHMENT Z58R5 Page 23 of 27
PCHG-DESG ENGINEERING CHANGE 0000063016R5
CONTAINMENT IWL REPAIR PLAN FOR THE CRYSTAL RIVER UNIT 3
STEAM GENERATOR REPLACEMENT MODIFICATION
19.0 REFERENCES
19.1 ASME B&PV Code, Section III, Division 2 "Rules for Construction of
Nuclear Power Plant Components." 2001 Edition with 2002 and 2003
Addenda
19.2 ASME B&PV Code, Section Xl, "Rules for Inservice Inspection of Nuclear
Power Plant Components," 2001 Edition with addenda up to and including
the 2003 Addenda.
19.3 1OCFR 50.55a, "Codes and Standards"
19.4 ACI 301-66, "Specifications for Structural Concrete"
19.5 ACI 318-63, "Building Code Requirements for Structural Concrete"
19.6 ANSI N45.2.2 - 1972 "Packaging, Shipping, Receiving, Storage and
Handling of Items for Nuclear Power Plants"
19.7 ASTM A 421, "Standard Specification for Uncoated Stress Relieved Steel
Wire for Prestressed Concrete," 1965 and 1998.
19.8 ASTM A 513-69, "Standard Specification for Electric Resistance Welded
Carbon and Alloy Steel Tubing"
19.9 ASTM A 514-05, "Standard Specification for High-Yield-Strength,
Quenched and Tempered Alloy Steel Plate, Suitable for Welding
19.10 ASTM A 519-06, "Standard Specification for Seamless Carbon and Alioy
Steel Mechanical Tubing"
19.11 ASTM A 615-68, "Standard Specification for Deformed and Plain Billet -
Steel Bars for Concrete Reinforcement."
19.12 ASTM C 94-07, "Standard Specification for Ready-Mixed Concrete"
19.13 ASTM C 150, "StandardSpecification for Portland Cement," 1967 & 2007
19.14 AWS D1.4 2005, "Structural Welding Code - Reinforcing Steel," 6th
Edition.
19.15 Crystal River 3 Final Safety Analysis Report, Revision 31.2, Chapter 5.
19.16 NGGM-PM-0007, CR3 Quality Assurance Program.
19.17 CR3 ASME Section Xl Inservice Inspection Program / Interval 4 / Repair
& Replacement Program, Revision 13.
Page 21 of 24
ATTACHMENT Z58R5 Page 24 of 27
PCHG-DESG ENGINEERING CHANGE 0000063016R5.
CONTAINMENT IWL REPAIR PLAN FOR THE CRYSTAL RIVER UNIT 3
STEAM GENERATOR REPLACEMENT MODIFICATION
19.18 NGGM-PM-0003, Corporate Welding Manual.
19.19 Specification CR3-C-0003, "Concrete Work for Restoration of the SGR
Opening in the Containment Wall"
19.20 Specification SP-5569, "Furnishing and Delivering of Structural Concrete",
23 June 71.
19.21 Specification SP-5583, "Tendons and Associated Conduit - Reactor
Building", 18 Sep 68.
19.22 Specification SP-5618, "Placement of Structural Concrete", 14 Apr 72.
19.23 Procedure EGR-NGGC-0015, "Containment Inspection Program"
19.24 Procedure MCP-NGGC-0402 "Material Management (Storage, Issue and
Maintenance)"
19.25 Calculation S06-0005, Rev. 0, "Containment Shell Analysis for Steam
Generator Replacement - Shell Evaluation During Replacement
Activities"
19.26 Calculation S06-0006, Rev. 1, "Containment Shell Analysis for Steam
Generator Replacement - Evaluation of Restored Shell."
19.27 Calculation S06-0007, Rev. 2, "Containment Liner Evaluation for SGR"
19.28 Engineering Change Package 0000063016, Rev. 3 "Containment
Opening."
19.29 Laboratory Testing Requirements for Concrete Proportioning (See
Attachment Z13RO of EC 63016R3)
19.30 Drawing 421-347, Sheet 1, "Reactor Building Temporary Access Opening
for SGR - Vertical & Horizontal Tendon Positions"
19.31 Drawing 421-350, "Reactor Building Temporary Access Opening for SGR
Restoration," Sheet 1 of 3.
19.32 Drawing 421-351, "Reactor Building Temporary Access Opening for SGR
Restoration," Sheet 2 of 3.
19.33 Drawing 421-352, "Reactor Building Temporary Access Opening for SGR
Restoration," Sheet 3 of 3.
Page 22 of 24
ATTACHMENT Z58R5 Page 25 of 27
PCHG-DESG ENGINEERING CHANGE 0000063016R5
CONTAINMENT IWL REPAIR PLAN FOR THE CRYSTAL RIVER UNIT 3
STEAM GENERATOR REPLACEMENT MODIFICATION
19.34 Precision Surveillance Corporation, "Post Tensioning System Field and
Quality Control Procedure Manual for Progress Energy Florida Inc.,
Crystal River Nuclear Unit 3, Steam Generator Replacement Project,
Containment Building Tendon Installation", Revision 0, 29 Aug 08.
19.35 Drawing 5EX7-003-A-08, Revision 3, (Dwg key #S-001529)
19.36 Drawing 5EX7-003-A-09C, Revision A, (Dwg key #S-001532)
19.37 Drawing 5EX7-003-A-09D, Revision 1, (Dwg key #S-001533)
19.38 PEERE 987, Rev. 0, "Plant Equipment Equivalency Replacement
Evaluation."
20.0 BIBLIOGRAPHY
20.1 ASME QAI-1 - 2005, "Qualifications for Authorized Inspection"
20.2 ACI 309R, "Guide for Consolidation of Concrete"
20.3 ASTM C 29-07, "Standard Test Method for Bulk Density ("Unit Weight")
and Voids in Aggregate"
20.4 ASTM C 31 - 08, t"Standard Practice for Making and Curing Concrete
Test Specimens in the Field"
20.5 ASTM C 33, "Standard Specification for Concrete Aggregates," 1967 &
2003.
20.6 ASTM C 39-05, "Standard Test Method for Compressive Strength of
Cylindrical Concrete Specimens"
20.7 ASTM C 40-04, "Standard Test Method for Organic Impurities in Fine
Aggregates for Concrete".
20.8 ASTM C 127-07, "Standard Test Method for Density, Relative Density
(Specific Gravity), and Absorption of Coarse Aggregate".
20.9 ASTM C 128-07a, "Standard Test Method for Density, Relative Density
(Specific Gravity), and Absorption of Fine Aggregate".
20.10 ASTM C 136-06, "Standard Test Method for Sieve Analysis of Fine and
Coarse Aggregates".
Page 23 of 24
ATTACHMENT Z58R5 Page 26 of 27
PCHG-DESG ENGINEERING CHANGE 0000063016R5
CONTAINMENT IWL REPAIR PLAN FOR THE CRYSTAL RIVER UNIT 3
STEAM GENERATOR REPLACEMENT MODIFICATION
20.11 ASTM C 143 - 08, "Standard Test Method for Slump of Hydraulic-Cement
Concrete"
20.12 ASTM C 231 - 08, "Standard Test Method for Air Content of Freshly
Mixed Concrete by the Pressure Method"
20.13 ASTM C 1064 - 08, "Standard Test Method for Temperature of Freshly
Mixed Hydraulic-Cement Concrete"
20.14 Procedure NEP-229, Rev. 4, "Guidance for Implementation and Use of
ASME Section Xl Repair/Replacement Program Documents"
20.15 Procedure SP-182, Rev. 16, "Reactor Building Structural Integrity Tendon
Surveillance Program"
20.16 Drawing 5EX7-003-A-09, Revision 5, (Dwg key #S-001 530)
20.17 Drawing 5EX7-003-A-09A, Revision 5, (Dwg key #S-001 531)
20.18 Title 10, CFR Part 50, Appendix J, "Primary Reactor Containment
Leakage Testing for Water-Cooled Power Reactors'
20.19 NRC Regulatory Guide 1.163, Performance-Based Containment Leak-
Test
20.20 NEI 94-01, Revision Ij, Industry Guideline for Implementing Performance-
Based Option of 10 CFR Part 50, Appendix J
20.21 ANSI/ANS 56.8-1994, Containment System Leakage Testing
Requirements
Page 24 of 24
ATTACHMENT Z58R5 Page 27 of 27
PCHG-DESG ENGINEERING CHANGE 0000063016R3
CONTAINMENT LINER IWE REPAIR PLAN
FOR THE CRYSTAL RIVER UNIT 3
STEAM GENERATOR REPLACEMENT
MODIFICATION
Progress Energy Florida
Rev. 18/5/09
Prepared By:
Reviewed By:
Casaba Ranganath
John Hlia
Date:
Date:
Date:Approved By:
Dan Jopling
ATTACHMENT Z57R3 Page 1 of 14
PCHG-DESG ENGINEERING CHANGE 0000063016R3
Progress Energy Florida
CONTAINMENT LINER IWE REPAIR PLAN FOR THE CRYSTAL RIVER UNIT 3
STEAM GENERATOR REPLACEMENT MODIFICATION
TABLE OF CONTENTS
Page
1.0 PU RPO SE ....................................................................................................................................... 1
2.0 BACK GR OUND ............................................................................................................................ 1
3.0 APPLICABLE CODE EDITION, ADDENDA AND CODE CASES ...................................... 1
4.0 M ATERIAL ................................................................................................................................... 2
5.0 REMOVAL AND INSTALLATION/REPAIR OF THE LINER PLATE .......................... 3
6.0 EXAMINATION AND TESTING ......................................................................................... 4
7.0 PRESSURE TESTING ........................................................................................................... 7
8.0 PROTECTIVE COATING SYSTEM ..................................................................................... 8
9.0 SUPPORT OF LINER DURING CONCRETE PLACEMENT ........................................... 8
10.0 HANDLING, STORAGE AND SHIPPING REQUIREMENTS ...................... ........................ 8
11.0 RECORDS AND REPORTS ................................................................................................... 8
12.0 INTERFACE REQUIREMENTS ................................................................................................ 9
13.0 REFERENCES ............................................................................................................................ 10
14.0 BIBLIO GRAPHY ........................................................................................................................ 11
TC-I
ATTACHMENT Z57R3 Page 2 of 14
PCHG-DESG ENGINEERING CHANGE 0000063016R3
Progress Energy Florida
CONTAINMENT LINER IWE REPAIR PLAN FOR THE CRYSTAL RIVER UNIT 3
STEAM GENERATOR REPLACEMENT MODIFICATION
REVISION SUMMARY
REVISION DESCRIPTION
0 INITIAL ISSUE
ADDED EXCEPTION IN SECTION 3.1.
ADDED REFERENCE TO IWA-4200 IN SECTION 3.2.
CHANGED REFERENCE 13.1 TO 13.15 IN SECTION 7.1
DELETED REFERENCE TO NRC IN SECTION 11.3.
ADDED REFERENCE 13.28.
TC-2
ATTACHMENT Z57R3 Page 3 of 14
PCHG-DESG ENGINEERING CHANGE 0000063016R3
CONTAINMENT LINER IWE REPAIR PLAN FOR THE CRYSTAL RIVER UNIT 3
STEAM GENERATOR REPLACEMENT MODIFICATION
1.0 PURPOSE
1.1 The purpose of this IWE Repair/Replacement plan is to identify essential
requirements pertaining to the cutting, removal, handling and reinstallation of the
containment liner plate and the installation and subsequent removal of temporary
attachments to the liner or stiffener angles in support of the Steam Generator
Replacement (SGR) Project at Crystal River 3 (CR3). The repair/replacement
plan implements the requirements of ASME B&PV Code, Section Xl, Subsection
IWE and the Crystal River Unit 3 Repair and Replacement Program.
1.2 This repair plan covers the following SGR project activities: Initial coating
inspection, welding of temporary attachments, liner cutting, welding to restore
liner plate and stiffeners, attachment of form ties, nondestructive weld
examination, removal of temporary attachments, coating repairs, and system
pressure test.
2.0 BACKGROUND
2.1 Steam Generator Replacement (SGR) at Crystal River 3 (CR3) will require
creation of an access opening through the containment shell to facilitate removal
of the existing generators and installation of new ones. Creation of this Reactor
Building access opening requires the removal of the Reactor Building wall
concrete and the pressure boundary steel liner. Creation of the access opening
will commence in Mode 5 with the hydrodemolition of the concrete within the
boundaries of the opening. After the Unit is defueled (No Mode) the exposed
liner plate will be cut and removed, thus creating the access opening. Related
activities may include installing temporary anchorages to the concrete
containment liner.
3.0 APPLICABLE CODE EDITION, ADDENDA, AND CODE CASES
3.1 The 2001 Edition with addenda up to and including the 2003 Addenda of ASME
Section Xl will be used for repair/replacement activities applicable to Subsection
IWE, except as noted in Section 3.2.
Page 1 of I I
ATTACHMENT Z57R3 Page 4 of 14
PCHG-DESG ENGINEERING CHANGE 0000063016R3
CONTAINMENT LINER IWE REPAIR PLAN FOR THE CRYSTAL RIVER UNIT 3
STEAM GENERATOR REPLACEMENT MODIFICATION
3.2 Except as noted hereinafter, items to be used for liner repair/replacement activities
will meet the following original construction codes as applicable. In accordance
with ASME Section XI, Article IWA-4200. The materials, details of fabrication,
welding and workmanship will conform to the requirements of the 1965 Edition
of the ASME B&PV Code, Section II1, Subsection B, "Nuclear Vessels Code for
Class B Vessels" (Reference 13.2) and American Standard ASA N 6.2.-1965,
"Safety Standard for Design, Fabrication and Maintenance of Steel Containment
Structures for Stationary Nuclear Power Reactors" (Reference 13.6).
4.0 MATERIAL
4.1 The 3/8" thick steel liner plate conforms to ASTM A 283, Grade C with a
minimum of 0.2% Cu (Reference 13.27), which has a P1 material grouping per
ASME Section IX (Reference 13.4). Replacement material, if required to repair
liner damage, will conform to the current edition of the same standard. EC 63016
(Reference 13.23) provides the reconciliation, as required by ASME Section XI
(Reference 13.5), Paragraph IWA-4224. 1, for use of the later edition of the
standard.
4.2 Stiffener angles conform to ASTM A 36 (Reference 13.12) or ASME
(Reference 13.1) SA 36, "Specification for Structural Steel". Replacement
material, if required to repair damaged angles, and plate used to reconnect angles
(per Drawing 421-351, Reference 13.25) will conform to the current edition of the
same standards. EC 63016 (Reference 13.23) provides the reconciliation, as
required by ASME Section XI (Reference 13.5), Paragraph IWA-4224.1, for use
of the later edition of the standards.
4.3 Certificates of compliance or typical certificates of analyses for the weld rod or
weld filler metal for the main liner welds are acceptable and will be maintained in
accordance with Section 1I of this plan.
4.4 Welding filler material for stiffener welds, liner seam welds, repair welds and
temporary attachment welds will be made using E7018 material. This material
will be procured and controlled in accordance with the applicable CR3 procedures
and will be traceable to purchase orders.
Page 2 of I 1
ATTACHMENT Z57R3 Page 5 of 14
PCHG-DESG ENGINEERING CHANGE 0000063016R3
CONTAINMENT LINER IWE REPAIR PLAN FOR THE CRYSTAL RIVER UNIT 3
STEAM GENERATOR REPLACEMENT MODIFICATION
5.0 REMOVAL AND INSTALLATION/REPAIR OF THE LINER PLATE
5.1 The steel liner plate cutting process will not be initiated prior to completion of
Reactor Vessel fuel off-load and plant entry into No Mode.
5.2 Welding and weld repair activities will be performed in accordance with the
Progress Energy Corporate Welding Manual (Reference 13.18) and ASME
Section III (Reference 13.2).
* The qualification of welding procedures and welders will be in
accordance with the Progress Energy Corporate Welding Manual
(Reference 13.18).
* Weld examination requirements are reconciled in ECED 70586
(Reference 13.24) as required by ASME Section XI (Reference 13.5)
Paragraphs IWA-422 1(c) and IWA-4411 (a).
5.3 Weld details for welded attachment to the liner for rigging requirements and
alignment are provided in CBI Drawing ER-4 (Reference 13.26).
5.4 When the liner section is reinstalled, the edges of the plates to be welded together
will be aligned to ensure that the offset of the butt joint does not exceed 25% of
the plate thickness.
5.5 Metal removal will be performed by thermal methods following contractor
procedures that will have been reviewed by Progress Energy for conformance to
the Corporate Welding manual (Reference 13.18).
" When thermal removal processes are used on P-No. I materials, surface
oxides will be removed by mechanical processing prior to welding on cut
surfaces. However, mechanical processing is not required when the thermal
metal removal process is qualified/evaluated in accordance with the
requirements of ASME Section XI (Reference 13.5) Article IWA-4461.4.1.
* Metal cutting and removal processes include oxyacetylene cutting, carbon arc
gouging, plasma cutting, metal disintegration machining (MDM), and
Electrical Discharge Machining (EDM).
5.6 Defect removal, if required, will be accomplished in accordance with the
requirements of ASME Section XI (Reference 13.5) Article IWA-4420.
Page 3 of 11
ATTACHMENT Z57R3 Page 6 of 14
PCHG-DESG ENGINEERING CHANGE 0000063016R3
CONTAINMENT LINER IWE REPAIR PLAN FOR THE CRYSTAL RIVER UNIT 3
STEAM GENERATOR REPLACEMENT MODIFICATION
5.7 The liner plate will be re-installed to its original configuration using full
penetration butt-welds that utilize low hydrogen electrodes and welding from two
sides, in accordance with the original construction Specification SP-5566
(Reference 14.2). Alternatively, the full penetration weld can be made from one
side with backing on the outside of the liner shell. Liner weld details are shown
on Drawing No. 421-351 (Reference 13.25). Liner stiffeners will be welded using
details shown on Drawing 68-3871-17 (Reference 13.27).
5.8 Welding procedures and qualifications will incorporate instructions designed to
control porosity. These instructions will cover allowable welding currents,
removal of slag and flux and welding techniques to control porosity.
5.9 Uphill welding of vertical welds will be required, except that downhill cover
passes or backgouged root does not need to be qualified, but should be noted in
the Welding Procedure Specification as a nonessential variable. Downhill cover
passes or backgouged root can be welded by downhill welding.
5.10 Note that Reactor Vessel refueling operations cannot begin until after the liner
plate repair welds are completed and examined in accordance with Paragraph 6.3
below.
6.0 EXAMINATION AND TESTING
A. Weld Examination
6.1 Liner welds made as part of repair/replacement activities will be examined in
accordance with the applicable requirements of ASME Section XI
(Reference 13.5), Subsection IWE and Article IWA-4000 as well as ASME
Section VIII (Reference 13.3).
6.2 The requirements of ASME Section XI (Reference 13.5) Article IWA-4500 will
be used for examination and testing of welds. Personnel performing
nondestructive examinations (NDE) will be qualified and certified using a written
practice prepared in accordance with ASME Section XI (Reference 13.5) Article
IWA-2311 and ANSI/ASNT CP-189 (Reference 13.9). As stipulated in ASME
Section XI (Reference 13.5) Article IWA-23 10(a), certifications based on ASNT
SNT-TC-IA (Reference 13.10) are valid until recertification is required.
Page 4 of I I
ATTACHMENT Z57R3 Page 7 of 14
PCHG-DESG ENGINEERING CHANGE 0000063016R3
CONTAINMENT LINER IWE REPAIR PLAN FOR THE CRYSTAL RIVER UNIT 3
STEAM GENERATOR REPLACEMENT MODIFICATION
6.3 After the liner plate has been welded back to its original configuration the
following Non-Destructive Examinations (NDE) will be performed, in accordance
with the applicable sections of ASME Section VIII (Reference 13.3) and ASME
Section XI (Reference 13.5) Subsections IWA and IWE, on the liner plate butt
welds around the perimeter of the Opening:
o 100% visual examination
o 100% vacuum box leak testing
o 100% magnetic particle testing (Double sided welds will receive magnetic
particle examinations of the final layer on both sides of the liner shell. Welds
with backing will receive Magnetic Particle Examinations after the first and
final layers).
6.4 Magnetic particle examination methods and acceptance criteria will be in
accordance with Appendix 6 of ASME, Section VIII (Reference 13.3).: The basis
for using magnetic particle in lieu of spot RT is addressed in ECED 70586
(Reference 13.24).
6.5 Results of magnetic particle examination, leak testing by vacuum box methods,
and visual inspection will be recorded as part of construction records.
6.6 Temporary fit-up devices that have been welded to the liner plate or liner
stiffeners to aid in aligning and supporting the reinstallation of the liner plate will
be either:
a. Removed (by grinding) and all removal areas inspected and tested per the
requirements of ASME Section XI (Reference 13.5), Division I, Subsection
IWA and IWE. This alternative will apply to all temporary fit-up devices
welded to the inside face of the liner.
b. Cut off approximately 'A" from the liner plate or stiffener. This alternative
method will eliminate grinding of the liner plate or stiffener plate and
additional NDE examinations. This alternative may be selected for the
concrete side of the liner provided that the welds have been made as safety-
related welds and all applicable NDE examinations for safety-related welds
to the IWE liner as per SP-0215 have been completed.
Page 5 of I 1
ATTACHMENT Z57R3 Page 8 of 14
PCHG-DESG ENGINEERING CHANGE 0000063016R3
CONTAINMENT LINER IWE REPAIR PLAN FOR THE CRYSTAL RIVER UNIT 3
STEAM GENERATOR REPLACEMENT MODIFICATION
6.7 All containment pressure boundary repair full penetration liner welds will be
tested using a soap film and vacuum box. The testing will be performed utilizing
a pressure differential of not less than 4 psig. The rate of inspection will not
exceed two feet of weld per minute. The box will overlap a minimum of six
inches over the previously tested section. All detectable leaks will be corrected.
6.8 Results of nondestructive examinations will be evaluated in accordance with
Section 9.2.6 of Procedure EGR-NGGC-00 15 (Reference 13.19).
B. Pre-Service and Related Examination
6.9 Personnel performing visual examinations as required by'ASME Section XI
(Reference 13.5), Subsection IWE will be qualified and certified in accordance
with a written practice approved by the Responsible Engineer as specified in
Subsection 9.1.13 of EGR-NGGC-0015 (Reference 13.19). The written practice
will conform to the applicable requirements of ASME Section XI (Reference
13.5), Article IWA-2300 as amended by IOCFR50.55a (Reference 13.7).
6.10 Prior to removal of the liner coating, the affected liner surface will be visually
examined in accordance with ASME Section XI, (Reference 13.5) Table
IWE-2500-1. Examination results will be evaluated for acceptability by the
Responsible Engineer.
6.11 Both surfaces of the liner and the L3x2x ¼" stiffeners on the back side will be
visually examined for dents, warping, deformation, punctures or other damage
that may affect their ability to serve their safety-related function as components of
the containment pressure boundary. The Responsible Engineer will evaluate
examination results for acceptability and specify repairs as deemed necessary.
Any damage to the 3/8" thick liner plate that occurs during hydrodemolition
and/or just prior to cutting the plate is acceptable if the reduced thickness of the
plate is > 3/16". If the original liner plate is to be reinstalled, damaged areas will
be evaluated for potential repair and/or replacement actions prior to concrete
placement. Repairs to the removed liner section will be made in accordance with
the requirements of ASME Section XI (Reference 13.5), Article IWA-4000 and
this repair plan. Prior to returning the liner to service, the suitability of the
repaired item will be evaluated in accordance with ASME Section XI (Reference
Page 6 of I 1
ATTACHMENT Z57R3 Page 9 of 14
PCHG-DESG ENGINEERING .CHANGE 0000063016R3
CONTAINMENT LINER IWE REPAIR PLAN FOR THE CRYSTAL RIVER UNIT 3
STEAM GENERATOR REPLACEMENT MODIFICATION
13.5), Article IWA-4160. If the liner repair is determined to be deficient,
appropriate corrective provisions will be implemented and included in the repair
documentation.
6.12 Preservice examination of the liner will be performed in accordance with ASME
Section XI (Reference 13.5), IWE-2200, after re-coating is complete but prior to
returning the liner to service. CR3 requirements for preservice examination are
specified in Section 6.5 of the CR3 ASME Section XI Repair & Replacement
Program (Reference 13.14). The Responsible Engineer will evaluate pre-service
examination results for acceptability as specified in ASME Section XI (Reference
13.5), Article IWE-31 10.
7.0 PRESSURE TESTING
7.1 After liner repairs are completed and prior to returning the Reactor Building to
service, the restored containment structure will be subjected to an integrated
leakage rate test (ILRT) that satisfies the Type A Test requirements of 1 OCFR50,
Appendix J (Reference 13.8). The ILRT, which will be performed in accordance
with the Technical Specification Containment Leakage Rate Testing Program
(Reference 13.15) and the requirements of SP-178 "Containment Leakage Test-
Type A Including Liner Plate" (Reference 13.17) will satisfy the ASME Section
XI (Reference 13.5), Article IWE-5221 requirement for a post-repair leakage test.
The measured leakage from this test will be included in the summary report
required by I OCFR50 Appendix J (Reference 13.8), Section V.B. The acceptance
criteria of IOCFR50 Appendix J, Section III.A.5(b) will be met. Details of the test
procedure and acceptance criteria are given in test procedure SP- 178 (Reference
13.17).
7.2 Surface areas that were repaired or replaced will be visually examined (VT-I)
prior to the start of reactor building pressurization for the Type A Test and
following the completion of de-pressurization. This examination will satisfy the
requirements of ASME Section XI (Reference 13.5), Article IWE-5240.
Page 7 of I 1
ATTACHMENT Z57R3 Page 10 of 14
PCHG-DESG ENGINEERING CHANGE 0000063016R3
CONTAINMENT LINER IWE REPAIR PLAN FOR THE CRYSTAL RIVER UNIT 3
STEAM GENERATOR REPLACEMENT MODIFICATION
7.3 Documentation will be provided for all tests. This documentation will be
included in the modification records for permanent retention (See Section 11 of
this Plan).
8.0 PROTECTIVE COATING SYSTEM
8.1 After repair of the liner plate is completed, all exposed surfaces of the liner will
undergo surface preparation and reapplication of coating in accordance with the
requirements of Specification CPL-XXXX-W-005 (Reference 13.22) and
Procedure MNT-NGGC-0009 (Reference 13.20).
9.0 SUPPORT OF LINER DURING CONCRETE PLACEMENT
9.1 The liner will serve as the inner form during placement of concrete in the opening.
It will be attached to the outer form by ties welded to the vertical stiffener angles
as shown on Drawing 421-351 (Reference -13.25). Form ties are sized and spaced
to minimize deformations of both the liner and the outer form as specified in
Calculation S06-0007 (Reference 14.1).
10.0 HANDLING, STORING AND SHIPPING REQUIREMENTS
10.1 Materials procured for this repair activity will be handled, stored and shipped per
the requirements of MCP-NGGC-0402 "Material Management (Storage, Issue
and Maintenance)" (Reference 13.21) and ANSI N45.2.2 - 1972 "Packaging,
Shipping, Receiving, Storage and Handling of Items for Nuclear Power Stations"
(Reference 13.11).
11.0 RECORDS AND REPORTS
11.1 The preparation, submittal,-and retention of records and reports of examinations,
tests, and repair/replacement activities will meet the requirements of ASME
Section XI (Reference 13.5), Article IWA-6000 as incorporated into the CR3
Quality Assurance Program (Reference 13.13) and NEP 229 (Reference 13.15).
11.2 Records and reports indicated in this section will be filed and maintained for the
service lifetime of the Reactor Building in accordance with the CR3 Quality
Page 8 of 11
ATTACHMENT Z57R3 Page 11 of 14
PCHG-DESG ENGINEERING CHANGE 0000063016R3
CONTAINMENT LINER IWE REPAIR PLAN FOR THE CRYSTAL RIVER UNIT 3
STEAM GENERATOR REPLACEMENT MODIFICATION
Assurance Program (Reference 13.13) and ASME Section XI (Reference 13.5),
Article IWA-63 10.
11.3 Following the completion of liner repair and replacement activities, reports
required by the CR3 ASME Section XI Repair & Replacement Program
(Reference 13.14) and NEP-229 (Reference 13.16) will be prepared and submitted
to the ANII for review and approval as specified in those documents.
12.0 INTERFACE REQUIREMENTS:
12.1 As specified in NEP-229 (Reference 13.16), which incorporates the requirements
of ASME Section XI (Reference 13.5), Article IWA-4170, the ANII will be
notified prior to starting the repair/replacement activity and will be kept informed
of progress so that necessary inspections may be performed.
Page 9 of I 1
ATTACHMENT Z57R3 Page 12 of 14
PCHG-DESG ENGINEERING CHANGE 0000063016R3
CONTAINMENT LINER IWE REPAIR PLAN FOR THE CRYSTAL RIVER UNIT 3
STEAM GENERATOR REPLACEMENT MODIFICATION
13.0 REFERENCES
13.1 ASME B&PV Code, Section I1, "Materials, Part A - Ferrous Material
Specifications", Current Edition.
13.2 ASME B&PV Code, Section III, Subsection B, "Nuclear Vessels Code for
Class B Vessels," 1965.
13.3 ASME B&PV Code, Section VIII, "Unfired Pressure Vessels", 19651 Edition.
13.4 ASME B&PV Code, Section IX, "Welding and Brazing Qualifications", Current
Edition.
13.5 ASME B&PV Code, Section XI, 2001 Edition with addenda up to and including
the 2003 Addenda.
13.6 ASA N6.2-1965, "Safety Standard for Design, Fabrication and Maintenance of
Steel Containment Structures for Stationary Nuclear Power Reactors".
13.7 Code of Federal Regulations; Title 10, "Energy"; Part 50, "Domestic Licensing of
Production and Utilization Facilities"; Section 50.55a, "Codes and Standards".
13.8 Code of Federal Regulations; Title 10, "Energy"; Part 50, "Domestic Licensing of
Production and Utilization Facilities"; Appendix J, "Primary Reactor
Containment Leakage Testing for Water-Cooled Power Reactors".
13.9 ANSI/ASNT CP- 189, "Standard for Qualification and Certification of
Nondestructive Testing Personnel".
13.10 ASNT SNT-TC- 1 A-2006, (Recommended Practice No. SNT-TC- 1 A), "Non-
Destructive Testing," 2006 Edition.
.13.11 ANSI N45.2.2 - 1972 "Packaging, Shipping, Receiving, Storage and Handling of
Items for Nuclear Power Stations".
13.12 ASTM A36-05, Standard Specification for Carbon Structural Steel.
13.13 CR3 Quality Assurance Program.
Reactor Building Liner Specification SP-5566 (Reference 14.9) cites ASME Section VIII for certain weld
related items but does not identify a Code year. This specification was first completed in Jul 68 (and issued
in Oct 69). At the time that the specification was under development, the 1965 Edition of the ASME Boiler
and Pressure Vessel Code was current. Since SP-5566 is silent as to Code year, it is presumed that the 1965
Edition of Section VIII is the appropriate reference.
Page 10 of I1
ATTACHMENT Z57R3 Page 13 of 14
PCHG-DESG ENGINEERING CHANGE 0000063016R3
CONTAINMENT LINER IWE REPAIR PLAN FOR THE CRYSTAL RIVER UNIT 3
STEAM GENERATOR REPLACEMENT MODIFICATION
13.14 CR3 ASME Section XI Inservice Inspection Program / Interval 4 / Repair &
Replacement Program, Revision 13, 14,Aug 08.
13.15 Crystal River Unit 3 Operating License (Through License Amendment No. 229),
Specification 5.6.2.20, Containment Leakage Rate Testing Program.
13.16 Procedure NEP 229, "Guidance for Implementation and Use of ASME Section XI
Rcpair/Replacement Program Documents", Revision 4, 14 Aug 08.
13.17 Procedure SP- 178 "Containment Leakage Test-Type A Including Liner Plate"
13.18 NGGM-PM-0003, "Corporate Welding Manual"
13.19 Procedure EGR-NGGC-0015, "Containment Inspection Program"
13.20 Procedure MNT-NGGC-0009, "Application of Protective Coatings," Rev. 5.
13.21 Procedure MCP-NGGC-0402 "Material Management (Storage, Issue and
Maintenance)"
13.22 Specification CPL-XXXX-W-005, "Nuclear Power Plant Protective Coatings."
13.23 Engineering Change 63016, Containment Opening.
13.24 ECED 70586, "Containment Opening Liner Plate Owner Reconciliation"
13.25 Drawing No. 421-351, "Reactor Building Temporary Access Opening for SGR
Restoration, Sheet 2 of 3"
13.26 CBI Drawing ER-4, "Lift Frame on Door Sheet"
13.27 Drawing No. 68-3871-17, CB&I, Shell Stretchout & Plate Details, Rev. 3.
13.28 SP-0125 "ASME Section XI Non-destructive Examination"
14.0 BIBLIOGRAPHY
14.1 Calculation S06-0007, Rev. 0, "Containment Liner Evaluation for SGR.
14.2 CR3 Specification SP-5566, "Reactor Building Liner and Penetrations and
Personnel Access Locks", Addendum C, Oct. 1969.
Page II of 11
ATTACHMENT Z57R3 Page 14 of 14
PCHG-DESG ENGINEERING CHANGE 000063016R003
PCHGDES ENINEEINGCHAGE 0006016R0A
IT+
Tr77
r"uc~m m' ir-Hi mlHl-¢ i
itEOR-f -
-- W/LKll4y BI ClIT[IL
FON RK GENERAL. MOMl
NOTE RENSPONSIBIENT FOR THE FINAL FORMWORK DESIGN ANDPLAUEN NT REMAINS WITH THE (ONTRA _TOR_
A'C 0005.50000 C• ORE• , -S ORE EOtNL OVCORSAe0t ~e e
Til 9 5 T~OO R E'SOE A tN i0000.p[ 1 [
ANA _7 T.O aTNHE0 SEOT GAEoN 1111 -1 1 STN 00)000
]I PEDVEOATNESE •OWOR THE U•ON •N•
050"1N 01PANELAO
N N CRYTON ALFRER, F
00000 SATE SEWIP IN
oec ANELTAOU
A - 1. NFRYSTAL-IV1R, .F
AND 9ORM
THESE 07WRG AR [EASE ONTE ,OLNIGDRM
--- t- - ET -
1 I- .-ly yC~T
- ______ -- 0-0 _________________________________________
PANEL LAYOUT FOR CONCRETE PLACEMENT ;II
ELEV. e.-1o 3111' RU
RATTACHMEN IOR Pa- 1 o
Page 1 of 9ATTACHMENT Z56R3
PCHG-DESG ENGINEERING CHANGE 000063016R003
m r rkr A tr~zz~~C
N
N
Ll 4]
- -
T 1 ii -
--- 4 71 ED~K-4~71Z
i iI II I
I II II I
I .
S - Aa .
I N
FCRMWORX GENERAL NOTES
NET EPSIDEIT FDAT OSA-ASMDNDSE A ND
SAEREPNDSILT DADA TAS FISNALS S TADER SDFSDY DANYTDD
DATAEDt
PLCMN REAN IHTECODNTR( O
A
ED BDM eA DEN -EA - Fn - -- .EN
FO AROGRES END N ERAGYANAM
OS SNAIM CR3 AD ST SLRT//EAR
LDAATA C CRYSTAL RIVER I F
AA,,• I VV•o E,, .o.. IrA•CRTYSTAL R[A-TER, E
!IANDANT DAT NDI D~IT
ANDESADDSNDD 1
N wM- ir-rTt wrT-- L
II II Li I• J I I II I[ II I• II i• IL I• I II___ ___I X-----------------,-,
.7'
-V
S
S-I
IPANEL LAYOUT SEVERE WEATHER X
ATTACHMENT ZRER3 PAgA 2 Af 9Page 2 of 9ATTACHMENT Z561R3
PCHG-DESG ENGINEERING CHANGE 000063016R003
PCHG-DESG ENGINEERING CHANGE 0E006301 6R003FORMWORK GENERAL NOTES
NGRONPOAONOIOTY FOR OCR FONAL FOATROAR WOCTK[•£1 ANDPNAD[ RA 6ITHE IRFRFA AOFTHENTAO FARýF -- l
.IO M ARARARLO AR RN R 0 0oAOAAI
MR.].CNC.. CR0.:
RE0000ON: I
A.
C S NS , FM OR TFIA M ART
LCE A SEVARE WITHECONTRAT OR
NOR PROGRESS ENERGYIOR MOO CR3 CRYSTAL RIVER
LOCATONL CRYSTAL ENTER, FLAA H, CR T- IT 2 o1
NA .N NT AT A.MO JIlRFNY 1- 1.A11 17 Tý
II
I
N
SEVERE WEATHER PROTECTION COVER ELEVATION1MT$ T
ATTACHMENT Z56R3 Page 3 of 9
PCHG-DESG ENGINEERING CHANGE 000063016R003
PCHG-DESG ENGINEERING CHANGE 000063016 R003
HIRE
~1~
MIMI 1 0 M 111 MlI - -I -I
- I~rui~rm~ ~I
I .
I-i ~I1II- F l_ 1-J
l[i R, t
i
il II R.
FORMWORK GENERAL NOTES
WTA RESPONAIDITY FOR THE FINAL FORAWORK DESIGN ANDPLA[LENENT rINlIS M1H THE (ONTRAC TOR
[HSES 10MPlNCS 33([ OISD OA TH1[ F01100113 DMMOIMCS:1N0/,'1RCM. FIR3:
I Im
WIESE DRAM NCREBASEDONTHE 10110M1NT
DRWG NUMB0(E1F011S (
-R1(3 W0 COD 1. 41A0
PROGRESS ENERGY
p10 (131 CR3 CRYSTAL RIVEROK N CRYSTAL EIVR, FE
1113 ,0( 40 .o 3 of
Is01.1~3.
~iH~ R,
-0 .M11(AP.ll(0
I 11103 0L
40 1 1' 1 N i I lm 1. ImaIlll IN Pll ! 1 I IIId : ,i I I I RI
W-4-m-- 4A, AW-Aw hi 11 (b M -.
L -1 Ii- Ii K_ jI ~ E ~]-
i ! cmR,
CONCRETE PLACEMENY ELEVATION
II01
ATTACHMENT Z56R3 Page 4 of 9
PCHG-DESG ENGINEERING CHANGE 000063016R003
SEVERE WEATHER PROTECTION COVER PLAN
FORINORK GENERAL NOTES
NOTT AL SP NSIBI Y FTOR TA FINAL FORMWfIRK DIX S" ANL
SES [IIALACS ACE BASED ON LIFE FLOtLOWIC DRASNCS:
SF ED:
N EL NWTNONFES -..- ANS7S
1.- AA NNAAN AlS1NE T
%IATN FNNCREIEPLACEMET I L.N I 5
L E LAO R I WEA p LAN A I AS
USA N,• CR 5TYh N L IVE
LOD ACAT CYTA
FAA LL- TISTLag 5 Af
THET PROGRESGS AENBAERGYTH OL0FGD
DRONN AISCR3 RYTBIERSDSATED. RSTL RVE.ERMIONA ITAAI ,FLI-A,
REWN1SS~LONS 4f
-De~f .1
CONCRETE PLACEMENT PLANSAOLA.'-
ATTACHMENT Z56R3
PCHG-DESG ENGINEERING CHANGE 000063016R003
PC HG-D ERG ENGINEERING CHANGE 00006301 RRRR3
_ 5 ALNA -E .
FORAIINNORK NEAOANDAL AOTNS
*otALASABO• PTAAAANTANAAJTlAIA,AA SD SSPBANTAS
H S . NE BAE O N THE F OEL Om yB DT BNA!BE= 1
EN/BC .Fl . . .- I ._____________
JELBABE BUNBERS: ____________________________
B2 BOB A I- L
ILA• I - I•m It S LS
A-, r m 'r
"' = I~m eew tm loON TI 1 - 111 I 1`1 (11cr 1.
ETyAINIII . AAL Any - - AnT An -
Ie M ~ "I.T,,. 11N 'l D
-T..N A INAL -'A." Any I.
DO~~ ~ TATCy L EKPL
(DA • EEL t ALAa exe m1/AN/N•
EHS E COANCRETSED PLACEMEOLIINT &SEV FRl E WT SECTIONS
ISAPRORES ENRG
'Ln I I IS
AKrRem CONCRE T E LCMN
THS RMSEVERE BAEDANTHER SECTI O ANGS
E. PROGNMBRESSE RG
•D~ ~ ~ - .117•J•Y 5o
~j YNrNANAA!NDNINC
LAN
CONCRETE PLACEMENT SECTIONTh~-A-
IIIIN
SEVERE WEATHER PROTECTION COVER SECTION
ATTACHMENT Z56R3 Page 6 of 9
PCHG-0ESG ENGINEERING CHANGE 000063016R003
PCHG-OESG ENGINEERING CHANGE 000063016 R003
/// \\ IF
NOT USED
DETAIL-2
30 o 0
8'--* o0 0
r--==. --*,A 0,m3 3
NAN3 3- 1 3 13
r= -
3/3*30ff0001138313333-~~
0100010-3'
\
i
\'\ DETAIL-3
DETAIL- I
\'
o 8073-81113313038.03
DETAIL-5
333 7 23 AI~30 3033
A3/0 13/33
FORMWOiRX GENERAL NOlES
30R7 3PIIN'S3331I3y FOR TH3 FINAL F30I33 DE3SIGN AN0PLAC[EKT R[ NAIHS WITH THE CONT RATOR,
3N3./3CH. IN I'- -
RE•ISI1N: 3
.Y i-IN. p •,,I1 1.1,ot su D. o I I " •1TI
H[m IN NET AINS A
B-1-1 NT01.-13-3,..11...1131- -1-33
3331313 3-43 1 I H 33d 33/N 31 .
DEESEDRAM RE BSED013 ON TEF9O" RMG1133303803,0FIRM:
AS33-33 PE TAILS. cm 11. 0/0/
SECTION-B3303.3-3
SECTION-C
SECTION-A @ BLOCKOUTDETAIL-4
r333173 ~ 1 13338/
POU CHT PLAN p
P4 U D~ UT Pl SECTION-Ei'l31.
ILA
F0R PROGRESS ENERGY"o ' CR3 CRYSTAL RIVER
LOCATION CRYSTAL RIVER, FL
10 133 " 3 7 of0
CUSTOM PANEL DETAIL ELEVATION-DA
ATTACHMENT Z56R3 Page 7 of 9
PCHG-DESG ENGINEERING CHANGE 000063016R003
FRoauwK GENERAL NOTES
NObTQ RESPONSIBILITY FOR TEH FINAL FORMWORK DESION ANLPLA[I[NT1 REMAINS WITH THE ONTNRA RTOR
II
Sf50 H( AOT• S IO RATES ON TAO FOOLOTNEI TATNECIT-:SIR /N -LT. TIR NM -.. T -1. I'ANF-
OR•NAN SUUBORS: _______________
RRMTEO: :=1Z=11=41.11
-.1 XT.M IT • K' - 1 _'IN S
ALL~RAAOSTAIT.
oFAN eAAMIT F eAE CART -s NT NT ININ -A- I1
AS~~~~~~~~~MR TNT S"T A RD RANRIANIAK LSI LI T SNTII
SESNPTAN MOCK POUR FORMING - N
PLAN & ELEVATIONNoN PROGRESS ENERGY
NT N• CR3 CRYSTA RIVEROT- N I CRYSTAL RIVER, FL .
IRA A N - MXAAS1 IN TK IýEI I
ATTACHMENT Z56R3L PageA8 of 9
-A
PCHG-OESG ENGINEERING CHANGE 000063016R003
PC HG-OR SG ENGINEERING CHANGE 000063016 R003
DETAIL-6
REVOTEOrR¶TOSOOErSt -0
i
FORUWORK GENERAL NOTIE
((01s oTESOETEST TO •iT•.[ O TOO TOLYTO OTTO T•OER[C•
TLE REEM6OTOy TOOR THT FWET FORROTEORK DTOTEN AnPLACEME[NT REtlAIM$ M#ICH Il CONTRAC10R
ITTISE OeA00NTE POT BESET TO TOE FOLLOSING ORTOTTEC:TENG/TCH, FEA ___R ______________DTAOENG NULSEBERS: _______________DATED:
.•I=S= :I
RTEES OTT
PLEEVT
C aOROPROGRTESSO ENSEaRGY R~
"1'A _00 TO REOSSOESO000000 SO
=L 0-ITION IR.E 000 FE
rA I 1 ==I2X• T OILY I
THS RAOT E AE O H TOTEO- TT/OtEE0
DRWN NMOCKPORRORIN
PLANON 1 LVTO
00.RTCRCRSARIE
TIC'TN" CR3CYSTAL RIVERF
-COSTOTO 1TOTE OR -8 8TON I'l-ET TREST
00 REC 0000 OSESO-~
MOCK POUR FORMING PLAN
MOCK POUR BULKHEADPANEL ELEVATION
RATTACHMENT Z56R3 Page 9 of 9
PCHG DESG ENGINEERING CHANGE 000063016R003
SS&IE
S&ME, INC. KNOXVILLE BRANCH
PHASE III ADDITIONAL TESTINGCuring Comparison
FORCRYSTAL RIVER UNIT 3 STEAM GENERATOR REPLACEMENT PROJECT
S&ME PROJECT NUMBER 1439-08-208Contract 373812, Amendment 4
Prepared for:Mr. John Holliday
PROGRESS ENERGY FLORIDA, INC.
15760 West Powerline StreetCrystal River, Florida 34428-6708
July 6, 2009
PREPARED BY:
REVIEWED BY:
QA BY:
APPROVED BY:
All work contained in this report was conducted in accordance with the requirements of the referenced procurementdocuments and the S&ME, Inc., Knoxville Branch Quality Assurance Manual, Volume I, Revision 4, dated December 5,2003.
ATTACHMENT Z55R3
S&ME, INC. / 1413 Topside Road / Louisville, TN 37777 /p 865.970.0003 f 865.970.2312 / %ww.smeinc.com
Page 1 of 5
PCHG DESG ENGINEERING CHANGE 000063016R003PHASE Ill ADDITIONAL TESTING - Curing Comparison July 6, 2009S&ME Project 1439-08-208
BACKGROUND
S&ME, Inc. (S&ME) has completed the Phase III Curing Comparison Testing for theCrystal River Unit 3 Steam Generator Replacement Project. The testing was performed asoutlined in Contract 373812, Amendment 4. To date, the concrete mixture testing for thisproject has included compression testing of cylinders at ages of 5 days and 28 days. Asrequired by the project specification the cylinders have been cured in autogenous curingcontainers for the first 5 days in an attempt to better represent the curing conditions of theconcrete that will be placed for the containment opening restoration. Autogenous curingcontainers are not planned to be used to cure the production cylinders cast during thecontainment opening restoration concrete placement. For this reason, Progress requestedthat a concrete mix be batched and cylinders cast for compressive strength testing usingboth forms of curing (autogenous containers and the curing method proposed forproduction) so that a comparison of the obtained compressive strengths could bedocumented.
TESTING
One batch of concrete was mixed using the materials and proportions used in the initialPhase III testing, adjusting admixture dosages to achieve the desired fresh properties.Twenty 6" x 12" cylinders were cast from the batch. Two cylinders were tested incompression at ages of 1, 2, 3, 5 and 28 days for the two different curing conditions. Thefirst curing condition involved placing the cylinders in autogenous curing containers untilthe time of test, for up to five days. For this curing condition, the cylinders that were tobe tested at 28 days were removed from the autogenous containers at an age of 5 days andplaced in a curing environment maintained at 73 ± 3°F, but without access to additionalcuring moisture until the time of test. The remaining ten cylinders were cured the entiretime in the 73 ± 3'F environment without access to additional curing moisture.
NOTICE OF ANOMALY/CORRECTIVE ACTION
During the comparison study, one Corrective Action Report (CAR) was issued (CAR-09-04). The CAR was issued to address exceeding the calibration interval on the sulfurcapping compound. The capping material was re-verified after this was discovered and wasfound to be within tolerance, therefore there was no impact to the test results. A copy of theCAR is attached.
RESULTS
A summary of the results of the Phase Ill Curing Comparison Testing is attached.
ATTACHMENT Z55R3 2 Page 2 of 5
PCHG *&ME Te~bnqRSumma ry 000063016R003
Client: Progress Energy Material: Concrete Mix IAProject: Crystal River Source: Laboratory MixS&ME Project No.: 1439-08-208 Quantity: 4.75 cubic footContract/P.O. No.: 373812 Date / Time Mixed: May 27, 2009, 9:45 am (Eastern)
S&ME Log No.: 09-044-001
Mixture Proportions (calculations based on one cubic yard)
Constituent Materials S&ME Log No. Weight (Ibs) Volume (ift)Type 1/1i Portland Cement (Holly Hill) 08-040-001 560 2.86
Class F Fly Ash (Proash) 08-034-001 140 0.93
No. 67 Stone (Maryville) 08-037-001 1613 9.23Natural Sand (Lilesville) 08-032-001 1515 9.23
Water N/A 262.5 4.21Target Air (2%) N/A --- 0,54
Totals 4,090 27.0
Actual Admixture Dosages (Admixtures dosed to achieve desired fresh properties.)
Constituent Materials S&ME Log No. Dosage Rate (oz/cwt)ADVA CAST 575 09-012-001 7.3
Recover 09-004-001 2
Target water/cementitious ratio 0.375
Theoretical Unit Weight (pcf) 151.5
Measured Plastic Properties
Property ASTM Designation Result
Slump (in) ASTM C 143-05a 7.75
Air content (%) ASTM C 231-04 2.3
Measured Unit Weight (pcf) ASTM C 138-01 151.1
Concrete Temperature (OF) ASTM C 1064-05 79Air Temperature (OF) N/A 75
Notes Concrete batching performed in accordance with ASTM C 192-06, except that final mixing time was extended by 2 minutes.
Compressive Strength, psi (ASTM C 39-0561) (Average of 2 cylinders per test age)
Age ,day(s) Autogenous Containers Alternative Proposed Curing
1 5,620 4,760
2 6,450 5,930
3 6,590 6,320
5 6,860 6,830
28 8,050 8,480
Notes Autogenous cured cylinders remained in the autogenous containers until time of test up to and including 5 days age.The 28-day autogenous cylinders were removed from the autogenous containers at 5 days and remained seated intheir plastic mold at 73+1-30 F.Production curing cylinders remained sealed in their molds at 73+1-3'F up to test age.
ATTACHMENT Z55R3 Page 3 of 5
1413 Topside Road Louilsvifle, Tennessee 37777 Phone: 865-970-0003 Fax., 865-970-2312
PCHG DESG , QUALITY ASn'U~XW 0MORANDOM 000063016R003
TO:
FROM:
CAR Files
John W. Coffey, Sr., Quality Assurance Manager Nuclear
DATE:
SUBJECT:
Projects
June 12, 2009
Closure of CAR-09-04
This memo is to close CAR-09-04
The calibration/verification of the capping compound was completed satisfactorly.
The concrete personnel were instructed to re-read ASTM C 617.
This CAR is now closed.
•o• W.Coffey, Sr.Quality Assurance ManagerNuclear Projects
ATTACHMENT Z55R3 Page 4 of 5
PCHG DESG ENGINEERING CHANGE 000063016R003
CORRECTIVE ACTION REPORT CAR NUMBER:CAR-09-04
PREPARED BY: John W. Coffey, Sr. DATE: 06-12-09REQUIRED ACTION DATE: June 12, 2009
ACTION ASSIGNED TO: Jason B. Burgess SIGNIFICANT CONDITIONORGANIZATION/PROJECT: 1439-08-208 ADVDERSE TO QUALITY
D3 YES I ENO
PART A - DESCRIPTION OF NONCONFORMANCE/PROBLEM: ASTM C 617, paragraph 5.1.4States in part that the calibration interval is not to exceed three months or upon receipt of each newshipment. Contrary to this the last calibration perform was on 01-09-09 with calibration due on 04-09-09however the next calibration was conducted on 06-12-09.
SINGATURES/DATEQUALITY XXý7ýNCEORI&7A'TOR
PART B -. ACTION AGENCY
I 1. ROOT CAUSE OF NONCONFORMANCE/PROBLEM: Due to an over sight by the concretelaboratory personnel the required due calibration date of 04-09-09 was passed and the re-calibrationwas performed on 06-12-09. A equipment use log was not assigned as a hold point prior to executionof the work task.
2. CORRECTIVE- ACTION-TO PRECLUDE-RECURRENCE:- The concrete-laboratory-personnel was--instructed to be more diligent on the calibration interval of three months of calibration/verification onthe capping compound. The concrete personnel were required to re-read the ASTM C 617 "StandardPractice for Capping Cylindrical Concrete Specimens",. QA will consider this QA Hold Point onupcoming tasks..
3. DATE CORRECTIVE ACTION TO BE COMPLETED: June 12,2009
4. SIGNATURES/DATE: 06-12-09DATEQA SUFMWSORI
PART C - QUALITY ASSURANCE
1. QA REVIEW/COMMENTS: Comparison was made between the calibration/verification record ofthe 0 1-09-09 and the 06-12-09 calibration/verification records. The average compressive strength ofthe verification on 01-09-09 was 5930 PSI and the average compressive strength of the 06-12-09verification is 5400 PSI. The required average compressive strength should be 5000 PSI. Thecapping compound is within the required strength.
2.3.4.S.6.
DATE CORRECTIVE ACTION VERIFIED:CORRECTIVE ACTION ACCEPTABLE:REPORTABLE PER 10 CFR 21:DATE CAR CLOSED: June 12, 2(SIGNATURE/DATE
June 12, 2009El YESC3 YES
E3 NO[] NO
.. T.L-TY ASSURANCE
Page 5 of 5
I . PCH'G-DESG 000063016R3
M~1~7
, -1 , . ---roL -FC, L-v2%t- ~ 5
~o~-t ~~44 N1Th.-/'7 LA c00~~~t'-r rot1 Accn-4-pAT C-4 Ccjkrrc-
46~
.-A~e . c
60.7
S-i- I
12 I-I
1~iT~2~ ~ 42rf - ~-
~
-S
ATTACHMENT Z54R3 *Page 1 of 1