91
ISSA International Forum on Occupational Heath and Safety Management in the 21st Century Liam G O’Sullivan Transmission Construction Director - London 2012 Infrastructure (Electricity) Managing H&S behaviour by engagement - on the London 2012 Construction Programme - a view from 'the inside track'.......

ISSA International Forum on Occupational Heath and Safety

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: ISSA International Forum on Occupational Heath and Safety

ISSA International Forum on Occupational Heath and Safety Management in the 21st Century

Liam G O’Sullivan Transmission Construction Director - London 2012 Infrastructure (Electricity)

Managing H&S behaviour by engagement - on the London 2012 Construction Programme - a view from 'the inside track'.......

Page 2: ISSA International Forum on Occupational Heath and Safety

2 2

What I would like to share with you…. • Intro, about….. • Setting the scene • Some metrics • The challenge • The pictures, the evidence - we definitely where

there, we definitely were effective and we definitely left a defining lasting legacy!

• Collaboration and teamwork • A mature, developed and pioneering client • 7 years of our lives and that of our colleagues in

20mins, a few slides - do able - of course, we don't do failure!

• The occasion • The enjoyment • The outcome

Page 3: ISSA International Forum on Occupational Heath and Safety

3

By 2013, how many Olympic Games had London hosted?

Quiz Question …

Page 4: ISSA International Forum on Occupational Heath and Safety

6 6

Setting the scene - Introduction • Electricity Network operator for London & South East • Leading and developing the transmission and construction team and

professional/supply chain since July 2005, first involved as an SME from November 2004….! No escape!!

• Responsible for all aspects of 132kV project construction works – including raising the standards of traditional H&S management to be pioneering, UK & world leading and ‘best in class’…..for 2012 infrastructure and beyond…..embed back into our business…

• Performing the role as the ‘good corporate citizen’, perfect partner… • Achieving and sustaining enduring H&S standards, targets, training,

application & awareness (plus contract performance) while ensuring the network performs during the Games…..

• Promoting and driving ambitions, but importantly doing all (and more!) we could to ensure NO-ONE gets injured or hurt, no matter how inconsequential; or damage to systems/assets, and the public…

• Early works set the context for the ODA’s and IOC’s delivery ambitions wrt health, safety….. and the environment…..

Page 5: ISSA International Forum on Occupational Heath and Safety

7

Setting the scene…. • ‘’Health and safety management, the focus on

occupational health, healthy eating, and the impact of tools, processes and equipment has moved the whole area of construction site safety and awareness along way from humble beginnings - with an extremely positive effect on assuring the workforce is safe and with less incidents and accidents - so what next, where do we go from here?’’ Liam G O’Sullivan

• 3 million man hours, 3 consecutive 1m mhrs without incident

• One project - Kings Yard Primary Substation (KYPS) - 686,762 mhrs; Riddor LTI 1; Minors 8; Near misses 4; AFR 0.14 7

Page 6: ISSA International Forum on Occupational Heath and Safety

8

Our challenge

• To do it safe….. • To do it right….. • To do it on time….. • To do it to budget…..2012 WAS FIXED

• These are not in conflict - although they are

always seen as being…perhaps sometimes are deemed to be – they AINT!!

Page 7: ISSA International Forum on Occupational Heath and Safety

9

Unearthed Roman road Iron Age Settlement

Roman coin

An old friend

Page 8: ISSA International Forum on Occupational Heath and Safety

10

New Stratford City

Development

Athletes Village

New Kings

Yard PSS

Docklands Canary Wharf

Olympic Site Offices

Stratford O2 Arena

Olympic Park Site: Location

Page 9: ISSA International Forum on Occupational Heath and Safety

11

London 2012 Electricity Infrastructure Projects

• PLUG – Powerlines Undergrounding Tunnel Project • Overhead Line Removal Project • Hackney Reinforcement Project • Bow Substation Upgrade Project • Kings Yard Primary Substation : Section 22 Phase 1

and Phase 2 • Kings Yard Primary Substation • HV - 11kV Electrical Network (LVU) • LV Network • Operational Readiness • Various connections and disconnections for Olympic

Venues

Page 10: ISSA International Forum on Occupational Heath and Safety

12 12

New Hackney 132kV Substation

West Ham 132kV Substation

Eastway Tunnel Shaft

Stratford Network Rail Substation

New Bow 132kV Substation and tunnel shaft

Carpenters Road Tunnel Shaft

Powerlines Undergrounding Project

New Kings Yard 132kV Substation

Page 11: ISSA International Forum on Occupational Heath and Safety

13

Concept to reality - Powerlines • 13 kilometres of tunnel, 8 Wembley's full of muck…. • Over 200km of power cabling, London to Belfast and

back…. • 52 overhead pylons, beautiful they were…… • 80km of overhead line conductor, lots of scrap…… • 1000 days, 3 years of my life….. • 420 workers….lots of mates, & friends made along

the way…. • £280 million………a little project • Other power projects – £110million………

• But most of all, a great team effort, no serious

injuries; incidents, yes, but a relatively small number

Page 12: ISSA International Forum on Occupational Heath and Safety

14

Concept - Change and Integration

Page 13: ISSA International Forum on Occupational Heath and Safety

15

CONCEPT TO REALITY

–“ PLUG is probably the highest risk and toughest project we’ll do on the Olympics and sets a fantastic benchmark to every other project that follows. A great start.”

David Higgins, Chief Executive, Olympic Delivery Authority

• “ The completion - on time and on budget - of the work on the powerlines tunnelling is a tremendous achievement. It is important not just for the creation of the Olympic Park, but also as a crucial part of our ambitious regeneration plans. It demonstrates clearly the excellent progress being made to deliver a fantastic Olympics.”

• Olympics Minister Tessa Jowell

Page 14: ISSA International Forum on Occupational Heath and Safety

16

POWERLINES - PEOPLE

Page 15: ISSA International Forum on Occupational Heath and Safety

17

Health, Safety & Environment • Structured, communications & co-ordination • Health, Safety & Environment Plans • Matrix of responsibilities

– Pre-construction – Construction – Commissioning – Operation & maintenance

• Matrix of CDM regulation duty holders by contract • Monthly project H&S meetings with open invitation to

HSE Inspector/s • Construction site facilities – welfare and occupational

focus • Excavated material stored ready for profile use on

Olympic Park • Lorry movements minimised by use of conveyors for

tunnel muck shifting

Page 16: ISSA International Forum on Occupational Heath and Safety

18

RISK MANAGEMENT WORKSHOP

IDENTIFY ALLOCATE EVALUATE ANALYSE MITIGATE

REVIEW

• Continuous workshops prior to and during works commencing.

• IMT lead continuous weekly and monthly UKPN had held a number, and attended many combined risk review mtgs.

• Continuing combined review mtgs (monthly) and management of risks – risk review mtgs

Risk Management Process

Feedback and Review

Page 17: ISSA International Forum on Occupational Heath and Safety

19

Moments of laughter - ENJOYING THE JOB!!

Page 18: ISSA International Forum on Occupational Heath and Safety

20

Powerlines – Teamwork, People

Page 19: ISSA International Forum on Occupational Heath and Safety

21

What we started with!

Page 20: ISSA International Forum on Occupational Heath and Safety

22

The Park – as was!!

Page 21: ISSA International Forum on Occupational Heath and Safety

23

Carpenters Shaft Site – from above

Page 22: ISSA International Forum on Occupational Heath and Safety

24

Hackney Shaft – before being dug and sunk

Page 23: ISSA International Forum on Occupational Heath and Safety

25

Difficulties of the shaft sites – live assets!

Page 24: ISSA International Forum on Occupational Heath and Safety

26

WHAT ELECTRICAL ENERGY CAN DO….

Page 25: ISSA International Forum on Occupational Heath and Safety

27

WHAT ELECTRICAL ENERGY CAN DO

• These overalls were being worn by one of our contractors during excavation in a busy central London street.

• Although made of special flame retardant fabric, they were still extensively damaged by the fault energy after damaging a LOW Voltage cable.

Page 26: ISSA International Forum on Occupational Heath and Safety

28

Typical shaft set up – finished article

Page 27: ISSA International Forum on Occupational Heath and Safety

29

Shaft sinking – mainly caisson, but under pinning also!

Shaft Sinking – Caisson Method

Jacking Frame

Made Ground

Gravel

Thanet Sand

Hydraulic Ram

Bentonite Annulus

Shaft Segments

Choker Ring

Lambeth Group

Page 28: ISSA International Forum on Occupational Heath and Safety

30

Carpenters Road, EDFE2 Shaft site

Page 29: ISSA International Forum on Occupational Heath and Safety

31

Shaft site – from above

Page 30: ISSA International Forum on Occupational Heath and Safety

32

Bow, EDFE2B Shaft post construction and substation basement construction

Page 31: ISSA International Forum on Occupational Heath and Safety

33

Carpenter’s Road Shaft – EDFE 2

Page 32: ISSA International Forum on Occupational Heath and Safety

34

Carpenter’s Road Shaft – one of the 1st, making good progress!

Page 33: ISSA International Forum on Occupational Heath and Safety

35

Oops - Carpenter’s Road Shaft – not supposed to happen!!

Page 34: ISSA International Forum on Occupational Heath and Safety

36

Carpenter’s Road Shaft – going, going, gone!!

Page 35: ISSA International Forum on Occupational Heath and Safety

37

Hackney EDFE4 - Shaft sinking excavation and trimming

Page 36: ISSA International Forum on Occupational Heath and Safety

38

Start again, but we got there!

Page 37: ISSA International Forum on Occupational Heath and Safety

39

Not all straight forward - problems encountered!

Page 38: ISSA International Forum on Occupational Heath and Safety

40

Complex and challenging sites!

Page 39: ISSA International Forum on Occupational Heath and Safety

41

Complex and challenging sites!

Page 40: ISSA International Forum on Occupational Heath and Safety

42

TBM – workhorse of the industry, refurb!

Page 41: ISSA International Forum on Occupational Heath and Safety

43

Pipe jack being lifted into position at Bow 2A shaft

Page 42: ISSA International Forum on Occupational Heath and Safety

44

TBM in pre launch, being lowered to position

Page 43: ISSA International Forum on Occupational Heath and Safety

45

TBM in pre launch

Page 44: ISSA International Forum on Occupational Heath and Safety

46

Shaft site – from above, machine breakthrough

Page 45: ISSA International Forum on Occupational Heath and Safety

47

Tunnel TBM Train

Page 46: ISSA International Forum on Occupational Heath and Safety

48

870m North drive

It’s about the journey!!

Page 47: ISSA International Forum on Occupational Heath and Safety

49

Murphy Express

It’s about the journey!!

Page 48: ISSA International Forum on Occupational Heath and Safety

50

The moment we all wait for – breakthrough!!

Page 49: ISSA International Forum on Occupational Heath and Safety

51

Tunnel Headhouse – part constructed

Page 50: ISSA International Forum on Occupational Heath and Safety

52

Tunnel Ventilation Control and Monitoring Equipment – MCC Rooms

Page 51: ISSA International Forum on Occupational Heath and Safety

53

Tunnel Ventilation Control and Monitoring Equipment

Page 52: ISSA International Forum on Occupational Heath and Safety

54

Concept - Bow GIS Substation Design

Page 53: ISSA International Forum on Occupational Heath and Safety

55

Bow GIS substation – we worked in all weathers!!

Page 54: ISSA International Forum on Occupational Heath and Safety

56

132kV GIS Switchgear being delivered to Bow GIS Substation

Page 55: ISSA International Forum on Occupational Heath and Safety

57

132kV GIS Switchgear being delivered to Bow

Page 56: ISSA International Forum on Occupational Heath and Safety

58 Learning Lunch Presentation, 220/03/10 © EDF Energy plc. All rights Reserved.

Hackney Reinforcement Key Milestones

• 3 x National Grid Supergrid

connections commissioned February 2010

• 132kV circuit transfers completed • Third circuit to Kings Yard –

commissioned September 2011

Page 57: ISSA International Forum on Occupational Heath and Safety

59

Network Reinforcement – Hackney GIS and EDFE4

Page 58: ISSA International Forum on Occupational Heath and Safety

60

Substation works completed…..

Page 59: ISSA International Forum on Occupational Heath and Safety

61

Bow traction transformers being offloaded into position

Page 60: ISSA International Forum on Occupational Heath and Safety

62

Bow Traction Substation - completed

Page 61: ISSA International Forum on Occupational Heath and Safety

63

132kV Cable manufacture – factory testing

Page 62: ISSA International Forum on Occupational Heath and Safety

64

Cable drums being delivered to site

Page 63: ISSA International Forum on Occupational Heath and Safety

65

Cables being spooled off into position

Page 64: ISSA International Forum on Occupational Heath and Safety

66

Cables being spooled off into position

Page 65: ISSA International Forum on Occupational Heath and Safety

67

Cables being spooled off into position

Page 66: ISSA International Forum on Occupational Heath and Safety

68

Tunnel – cabling part way

Page 67: ISSA International Forum on Occupational Heath and Safety

69

Cable installation in basements

Page 68: ISSA International Forum on Occupational Heath and Safety

70

Shaft steelwork and 132kV cable installations

Page 69: ISSA International Forum on Occupational Heath and Safety

71

Tunnel cable installation – project part way

Page 70: ISSA International Forum on Occupational Heath and Safety

72

Typical OHL towers we had to grapple with!

Page 71: ISSA International Forum on Occupational Heath and Safety

73

Powerlines – OHL Removal

Page 72: ISSA International Forum on Occupational Heath and Safety

74

Working on the lines

Page 73: ISSA International Forum on Occupational Heath and Safety

75

Powerlines – OHL Removal

Page 74: ISSA International Forum on Occupational Heath and Safety

76

Powerlines – Tower being dismantled

Page 75: ISSA International Forum on Occupational Heath and Safety

77

Powerlines – OHL Removal, Towers being collapsed

Page 76: ISSA International Forum on Occupational Heath and Safety

78

Powerlines – OHL Removal, Towers being collapsed

Page 77: ISSA International Forum on Occupational Heath and Safety

79

Review of what we did POWERING THE GAMES

• Main tunnel works and 132kV and 25kV cabling complete and commissioned – on time/budget/safe!!!!

• West Ham GIS Substation, Bow GIS Substation, Bow NWR and Hackney AIS Substation commissioned – on time/budget/safe!!!!

• PKD OHL completely decommissioned and removed and c. 95% recycled

• Hackney 132kV GIS substation – building completed, 132kV GIS switchgear and ancillaries installed and commissioned

• NG incomers installed and commissioned by end of Jan 2010 • Kings Yard Primary Substation - commissioned • Kings Yard S22 Non Contestable Works, Phase 1 - 132kV and

auxiliary cables commissioned • Kings Yard S22 Non Contestable Works, Phase 2 - 132kV and

auxiliary cables commissioned • HV and LV network installed and commissioned – ahead of

time/budget/safe!!!!

Page 78: ISSA International Forum on Occupational Heath and Safety

80

Lines all gone!

Page 79: ISSA International Forum on Occupational Heath and Safety

81

Kings Yard Primary Substation

• Power-on October 2009 • Shortlisted for

- Institution of Civil Engineers – ‘London Civil Engineering Award’

- Royal Institute of British Architects – ‘London Area’ - Won 1st prize

- World Brick Awards - Vienna

What Powers the Park and POWERED the GAMES?

Page 80: ISSA International Forum on Occupational Heath and Safety

82

Kings Yard Primary Substation – Final Views

Page 81: ISSA International Forum on Occupational Heath and Safety

83

Kings Yard PSS – Construction Early Stages

Page 82: ISSA International Forum on Occupational Heath and Safety

84

Kings Yard PSS – Construction well underway

Page 83: ISSA International Forum on Occupational Heath and Safety

85

Kings Yard PSS – Construction well underway

Page 84: ISSA International Forum on Occupational Heath and Safety

86

Kings Yard Primary Substation

Page 85: ISSA International Forum on Occupational Heath and Safety

87

Kings Yard PSS – Transformer Deliveries

Page 86: ISSA International Forum on Occupational Heath and Safety

88

Kings Yard PSS – Transformer Installations

Page 87: ISSA International Forum on Occupational Heath and Safety

89 89

Key initiatives and actions • Founding member of SHELT, monthly UKPN and supply chain

programme SHE forums • PLT: cascaded - everyone has a voice & deserves to be listened to • Designers forums - risk assessments, lead teams and workshops • New procedures – scaffold licence, SSTI, RAMS assessment and

assurance, site and behaviour exchange inspections • Dedicated Site foremen and site managers – a departure from the

norm…. • Forums, quarterly workshops for infrastructure utilities workforce -

time to think, stop, act! • Site engagement tours - top to tail, broad and deep – engagement,

reward, consequence – lessons learnt and actually APPLIED!! • Going Live/Dig Safe Forums and Workshops….train the trainer…. • One vision, one team, one goal (set of)….. • Hazard spotter, best practice, ideas to action • Evidenced and rewarded by 3 consecutive 1 million man hours

without incident achievement awards……

Page 88: ISSA International Forum on Occupational Heath and Safety

90 90

The outcome • Communication is key!

• Leadership is vital!

• Engagement, empowerment and

support/coaching is absolutely essential

• Effective teamwork gets you the Gold, Silver AND bronze

• Infrastructure delivery was the backbone of the GAMES

Page 89: ISSA International Forum on Occupational Heath and Safety

91

So, back to the question……

• ….what next, where do we go from here?….

• "Act into a new way of thinking, not think of a new way of acting“….

• The Learning - by doing, by observation, and most importantly sharing….

• Do it ALL again, make it better….share and learn, not….

Page 90: ISSA International Forum on Occupational Heath and Safety

92

…be left in the dark……..

•The night view of London we would like to see all the time but especially in July, August and September 2012 when London hosted the next summer Olympics and the eyes of the entire world were on the Capital, London and we, UKPN, our industry, did us proud……!!

Page 91: ISSA International Forum on Occupational Heath and Safety

93

Thank you, any questions?

Liam O’Sullivan Programme Director, Low Carbon London

Programme Director, UKPN Business Transformation Programme

liam.o’[email protected] 07875115615