19
Engineering Department EN 1 IT3853-EN Design, Supply of Ventilation Units and Smoke Extraction Systems for Building 192 Bidder’s conference – 29 th April 2013 Magali Mendez/ EN-CV IT3853-EN Bidders Conference – 29.04.2013

IT3853-EN Design , Supply of Ventilation Units and Smoke Extraction Systems for Building 192

  • Upload
    gasha

  • View
    28

  • Download
    1

Embed Size (px)

DESCRIPTION

IT3853-EN Design , Supply of Ventilation Units and Smoke Extraction Systems for Building 192 Bidder’s conference – 29 th April 2013 Magali Mendez/ EN-CV. IT3853-EN Bidders Conference – 29.04.2013. Building 192. Summary of estimated flows . - PowerPoint PPT Presentation

Citation preview

Page 1: IT3853-EN Design , Supply of Ventilation Units and Smoke Extraction Systems for Building  192

Engineering DepartmentEN

1

IT3853-EN

Design, Supply of Ventilation Units and Smoke Extraction Systems for Building 192

Bidder’s conference – 29th April 2013

Magali Mendez/ EN-CV

IT3853-EN Bidders Conference – 29.04.2013

Page 2: IT3853-EN Design , Supply of Ventilation Units and Smoke Extraction Systems for Building  192

Engineering DepartmentEN

Building 192

Page 3: IT3853-EN Design , Supply of Ventilation Units and Smoke Extraction Systems for Building  192

Engineering DepartmentEN

Page 4: IT3853-EN Design , Supply of Ventilation Units and Smoke Extraction Systems for Building  192

Engineering DepartmentEN

Summary of estimated flows

Basement

Forced air m³/h Smoke extraction m³/h Fresh air (for smoke extraction system) m³/h Return air m³/h

zones: OP/CF/CO Zone: BT zones:

OP/CF/CO Zone: BT zones: OP/CF/CO Zone: BT Stairs zones:

OP/CF/CO Zone: BT

12 000 4 000 14 000 5 000 8 400 3 000 1 800 12 000 4 000

Ground floor

Forced air m³/h Smoke extraction m³/h Fresh air m³/h Return air m³/h

zone: HT Zone: OP zone: HT Zone: OP zone: HT Zone: OP   zone: HT Zone: OP

3 000 6 200 0 0 3 500 0   3 000 6 200

Page 5: IT3853-EN Design , Supply of Ventilation Units and Smoke Extraction Systems for Building  192

Engineering DepartmentEN

AHUs to be supplied and installed by the contractor

Identification

 

Function location Flow rate[m3/h]

Fresh air intake [m3/h]

UACV1-00258

Modified Basement 192-001 16'000 1'500

UACV1-00259

NewR-Zone OPR-Zone HT

192-001 9'200 1'700

Page 6: IT3853-EN Design , Supply of Ventilation Units and Smoke Extraction Systems for Building  192

Engineering DepartmentEN

Exhausts fans for smoke extraction to be supplied and

installed by the contractorIdentification Function location Flow rate

[m3/h]

UUV1-00532 Fresh air for smoke extraction – Basement Roof 192 11'400

UUV1-00533 Fresh air for smoke extraction – stairs Roof 192 1'800

UUV1-00534 Fresh air for smoke extraction –Ground floor Zone HT Roof 192 3’500

UAT2-00028 Smoke extraction – Basement Roof 192 19'000

Chapter 7.2.4 of the rule EN 13501-4

Page 7: IT3853-EN Design , Supply of Ventilation Units and Smoke Extraction Systems for Building  192

Engineering DepartmentEN

The Supply

• Design • Dismantling of the existing installation• Design and studies of Smoke extraction and

HVAC systems• Packing• Shipping to Bldg.192• Installation• Tests• Commissioning• Documentation

Page 8: IT3853-EN Design , Supply of Ventilation Units and Smoke Extraction Systems for Building  192

Engineering DepartmentEN

The HVAC and smoke extraction systems (summary)

• Ducts for ventilation system• Exhaust fans, fresh air fans, ducts • Dampers, fire dampers• Stainless steel pipework, supporting, metal

structures,• Instrumentation, controls cubicle, cabling.

Page 9: IT3853-EN Design , Supply of Ventilation Units and Smoke Extraction Systems for Building  192

Engineering DepartmentEN

Specification of the Supply: Electricity

Page 10: IT3853-EN Design , Supply of Ventilation Units and Smoke Extraction Systems for Building  192

Engineering DepartmentEN

Specification of the Supply: Electricity

Included in the supply

Erratum: limit of the supply includes the

power cubicle, revised version of this

document to be provided by CERN

Erratum: limit of the supply includes the

power cubicle, revised version of this

document to be provided by CERN

Page 11: IT3853-EN Design , Supply of Ventilation Units and Smoke Extraction Systems for Building  192

Engineering DepartmentEN

Specification of the Supply: Controls

Page 12: IT3853-EN Design , Supply of Ventilation Units and Smoke Extraction Systems for Building  192

Engineering DepartmentEN

Specification of the Supply: Controls

Clarification on the information required for CERN to prepare the PLC control system software

The contractor shall allow in the schedule a minimum four weeks for the programming of the PLCs by CERN. In order to start the programming of the control system, CERN requires the following four documents to be finalised - submitted and approved:1. P&IDs - with the correct GMAO and tag references.2. Electrical Schematics3. I/O List4. Functional DescriptionIt is therefore essential that the above documentation and drawings are submitted, revised as required and finalised in accordance with the schedule, such that the preparation of the controls does not impact the scheduled testing and commissioning period.

Page 13: IT3853-EN Design , Supply of Ventilation Units and Smoke Extraction Systems for Building  192

Engineering DepartmentEN

Building 192

Technical RoomSpace

constraints

Page 14: IT3853-EN Design , Supply of Ventilation Units and Smoke Extraction Systems for Building  192

Engineering DepartmentEN

Roof installations

Fresh air for smoke

extraction- Ground floor

HT zone

Fresh air for smoke

extraction- Stairs

Air conditioning

Smoke extraction- Basement

Fresh air for smoke

extraction-Basement

Page 15: IT3853-EN Design , Supply of Ventilation Units and Smoke Extraction Systems for Building  192

Engineering DepartmentEN

Ground floor

Page 16: IT3853-EN Design , Supply of Ventilation Units and Smoke Extraction Systems for Building  192

Engineering DepartmentEN

Basement

Page 17: IT3853-EN Design , Supply of Ventilation Units and Smoke Extraction Systems for Building  192

Engineering DepartmentEN

Specification of the Supply

Page 18: IT3853-EN Design , Supply of Ventilation Units and Smoke Extraction Systems for Building  192

Engineering DepartmentEN

Schedule

Page 19: IT3853-EN Design , Supply of Ventilation Units and Smoke Extraction Systems for Building  192

Engineering DepartmentEN

Thanks for your attention!

Questions?