Page 1 12 December 2016 7ème RDV Business du Nucleaire Civil CCI Marseille Provence Page 1 © 2016, ITER Organization ITER Besoins Previsonnels et Appels d’Offres Françoise Flament Head of Procurement and Contracts Division ITER Organization The views and opinions expressed herein do not necessarily reflect those of the ITER Organization

ITER Besoins Previsonnels et Appels d’Offres · 2016-12-13 · ITER Besoins Previsonnels et Appels d’Offres Françoise Flament Head of Procurement and Contracts Division ... At

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: ITER Besoins Previsonnels et Appels d’Offres · 2016-12-13 · ITER Besoins Previsonnels et Appels d’Offres Françoise Flament Head of Procurement and Contracts Division ... At

Page 1

12 December 2016 – 7ème RDV Business du Nucleaire Civil – CCI Marseille Provence Page 1

© 2016, ITER Organization

ITER Besoins Previsonnels et Appels

d’Offres

Françoise Flament

Head of Procurement and Contracts Division

ITER Organization

The views and opinions expressed herein do not necessarily reflect those of the ITER Organization

Page 2: ITER Besoins Previsonnels et Appels d’Offres · 2016-12-13 · ITER Besoins Previsonnels et Appels d’Offres Françoise Flament Head of Procurement and Contracts Division ... At

Page 2

12 December 2016 – 7ème RDV Business du Nucleaire Civil – CCI Marseille Provence Page 2

© 2016, ITER Organization

• The ITER Project is currently the 21st century major challenge for the scientific world, but

also for industry involved in cutting edge technologies;

• The world’s largest international science collaboration;

• The seven ITER members – China, Europe, India, Japan, Korea, Russian and the USA -

together represent 35 nations and more than half of the world population;

• ITER goal is to demonstrate the viability of fusion power in producing 10 times the power

it consumes. It is a major step towards the commercial scale for safe and sustainable

energy.

Page 3: ITER Besoins Previsonnels et Appels d’Offres · 2016-12-13 · ITER Besoins Previsonnels et Appels d’Offres Françoise Flament Head of Procurement and Contracts Division ... At

Page 3

12 December 2016 – 7ème RDV Business du Nucleaire Civil – CCI Marseille Provence Page 3

© 2016, ITER Organization

Outline

1. ITER Organization Industrial Strategy

2. Procurement Opportunities

Page 4: ITER Besoins Previsonnels et Appels d’Offres · 2016-12-13 · ITER Besoins Previsonnels et Appels d’Offres Françoise Flament Head of Procurement and Contracts Division ... At

Page 4

12 December 2016 – 7ème RDV Business du Nucleaire Civil – CCI Marseille Provence Page 4

© 2016, ITER Organization

ITER Council

Procurement Arrangements

Domestic Agencies (DA’s)

Management Advisory Committee (MAC)

Science & Technology Advisory Committee (STAC)

7 Members: China (CN-DA) Europe (EU-DA) India (IN-DA) Japan (JA-DA) Korea (KO-DA) Russian Fed.(RF-DA) United States (US-DA

ITER Organization (IO)

ITER Project Organization

Page 5: ITER Besoins Previsonnels et Appels d’Offres · 2016-12-13 · ITER Besoins Previsonnels et Appels d’Offres Françoise Flament Head of Procurement and Contracts Division ... At

Page 5

12 December 2016 – 7ème RDV Business du Nucleaire Civil – CCI Marseille Provence Page 5

© 2016, ITER Organization

ITER is a crucial step towards the fusion power plants of tomorrow:

• ITER will be the first facility to test the integrated fusion technologies and

cutting-edge materials necessary for the commercial production of electricity;

• ITER Organization and the Domestic Agencies, together with Industry, are

combining the best Tokamak scientific knowledge and the best Industrial

know-how;

• Progress is visible, not only in the building erection but also at factories for

the fabrication of the components. This is tangible evidence of the

relationship already built up between ITER Project and Industry.

Page 6: ITER Besoins Previsonnels et Appels d’Offres · 2016-12-13 · ITER Besoins Previsonnels et Appels d’Offres Françoise Flament Head of Procurement and Contracts Division ... At

Page 6

12 December 2016 – 7ème RDV Business du Nucleaire Civil – CCI Marseille Provence Page 6

© 2016, ITER Organization

PF Coil Facility

ITER Headquarters

Contractors area

Tokamak Complex Construction underway

Assembly Hall Construction underway

400 kV switchyard

Cryostat Workshop

Headquarters extension

Storage Area 2 Storage Area 3

Storage Area 1

Batching Plant

Cryoplant Construction underway

Preparatory works

Cooling systems

Preparatory works

Control Building

Cleaning Facility Construction underway Preparatory works

Magnet Conversion Power

Transformers

ITER Worksite

Service Building

Page 7: ITER Besoins Previsonnels et Appels d’Offres · 2016-12-13 · ITER Besoins Previsonnels et Appels d’Offres Françoise Flament Head of Procurement and Contracts Division ... At

Page 7

12 December 2016 – 7ème RDV Business du Nucleaire Civil – CCI Marseille Provence Page 7

© 2016, ITER Organization

The ITER Organization is looking for schedule and cost-effective solutions:

ITER Organization and Domestic Agencies, together with Industry look for efficient,

competitive and innovative solutions through:

o High safety performance;

o Key performance in the execution of the contracts, in terms of schedule as well

as cost;

o Partnerships and sub-contracting strategies answering best to the IO’s needs;

o Early warning for the identification of risks and opportunities along contract

execution;

o Involvment of SMEs;

o Whenever possible, economy of scale.

Page 8: ITER Besoins Previsonnels et Appels d’Offres · 2016-12-13 · ITER Besoins Previsonnels et Appels d’Offres Françoise Flament Head of Procurement and Contracts Division ... At

Page 8

12 December 2016 – 7ème RDV Business du Nucleaire Civil – CCI Marseille Provence Page 8

© 2016, ITER Organization

Nuclear Safety and Licensing Requirements:

• ITER is a nuclear facility (Installation Nuclear de Base #174) for which the

ITER Organization is the Nuclear Operator: French nuclear regulation applies,

in particular the Order dated 7 February 2012 concerning nuclear facilities;

• This Order applies to all Contractors dealing with structures, systems and

components in relation with nuclear safety requirements;

• Evidence of compliance with the regulation must be provided to the ITER

Organization and French Safety Authorities.

Page 9: ITER Besoins Previsonnels et Appels d’Offres · 2016-12-13 · ITER Besoins Previsonnels et Appels d’Offres Françoise Flament Head of Procurement and Contracts Division ... At

Page 9

12 December 2016 – 7ème RDV Business du Nucleaire Civil – CCI Marseille Provence Page 9

© 2016, ITER Organization

ITER Organization Procurement Rules:

• The IO Procurement Procedure is based on International Public Procurement Rules,

ensuring competition, fair treatment and transparency;

• Contracts are placed through the Call-for-Tender process starting by the Call for

Nomination published through the Domestic Agencies.

The award criteria are of two types:

o Best value for the IO,

o Lowest technically compliant offer.

Various Procedures in place:

o Call for tender,

o Competitive Dialogue,

o Call for Expertise,

o Restricted Tender,

o Request for Quotation.

Page 10: ITER Besoins Previsonnels et Appels d’Offres · 2016-12-13 · ITER Besoins Previsonnels et Appels d’Offres Françoise Flament Head of Procurement and Contracts Division ... At

Page 10

12 December 2016 – 7ème RDV Business du Nucleaire Civil – CCI Marseille Provence Page 10

© 2016, ITER Organization

JAPAN: Connection of segments for the first inboard

Toroidal Field Coil structure was completed in November

2015, marking a significant achievement for TF coil

procurement.

INDIA: is responsible for the fabrication and assembly of

the 30 x 30 meter ITER cryostat. Pictured, six 60° base

plates for Tier-1 of the Cryostat Base Section are

temporarily assembled at the factory in order to check

tolerances. The base plates were delivered to ITER in

December 2015.

S. KOREA: At Hyundai Heavy Industries, where two of

nine vacuum vessel sectors are under construction,

welding is carried out on the upper section of the inner

shell for Sector # 6 ─ now 40% complete.

RUSSIA completes its share of toroidal field conductor

in June 2015. The milestone marks the end of a five-

year campaign to manufacture 28 production lengths

(more than 120 tons of material).

USA: General Atomics (GA) has launched fabrication of

the 1,000-ton superconducting Central Solenoid. The

component It will be among the most powerful magnets

ever built with each of the six modules containing the

equivalent energy of 1,000 cars racing 150 km/h.

A major milestone was achieved on 6 April with the

winding the first Central Solenoid module.

CHINA: Tooling and testing activities are underway to

prepare for the fabrication of ITER poloidal field coil

number 6 (PF6) at the ASIPP facility in China, which is

under contract with the European Domestic Agency to

produce and deliver this second-smallest ring-shaped

ITER magnet (350 tons, 10 m in diameter). Manufa

ctu

ring is in p

rogre

ss a

ll

ove

r th

e w

orld

The Project is moving forward in all Members’ countries!

Page 11: ITER Besoins Previsonnels et Appels d’Offres · 2016-12-13 · ITER Besoins Previsonnels et Appels d’Offres Françoise Flament Head of Procurement and Contracts Division ... At

Page 11

12 December 2016 – 7ème RDV Business du Nucleaire Civil – CCI Marseille Provence Page 11

© 2016, ITER Organization

The Project is moving forward in all Members’ countries!

INDIA

Tier-1

Cryostat

Base

Section

delivered

to IN-DA

Workshop

at ITER

Site

EUROPE

Start of

B1 civil

works in

Tokamak

Building

RUSSIA,

CHINA,

JAPAN

Fabricatio

n of all

Toroidal

Field

Conductor

s

completed

EUROPE

Installation

of Water

Detritiation

System

tanks in

Tritium

Building

Achie

vin

g

Cri

tica

l M

ilesto

ne

s

Page 12: ITER Besoins Previsonnels et Appels d’Offres · 2016-12-13 · ITER Besoins Previsonnels et Appels d’Offres Françoise Flament Head of Procurement and Contracts Division ... At

Page 12

12 December 2016 – 7ème RDV Business du Nucleaire Civil – CCI Marseille Provence Page 12

© 2016, ITER Organization

EUROPE

Completion

of first EU

Toroidal

Field Coil

winding

pack

JAPAN

Completion

of

performance

tests for

tungsten

Divertor

Outer

Vertical

Target

EUROPE

Installation

of Water

Detritiation

System

tanks in

Tritium

Building

USA

Complete

Central

Solenoid

Module 1

Winding

Ach

ievin

g C

ritica

l

Mile

sto

ne

s

The Project is moving forward in all Members’ countries!

Page 13: ITER Besoins Previsonnels et Appels d’Offres · 2016-12-13 · ITER Besoins Previsonnels et Appels d’Offres Françoise Flament Head of Procurement and Contracts Division ... At

Page 13

12 December 2016 – 7ème RDV Business du Nucleaire Civil – CCI Marseille Provence Page 13

© 2016, ITER Organization

Outline

1. ITER Organization Industrial Strategy

2. Procurement Opportunities

Page 14: ITER Besoins Previsonnels et Appels d’Offres · 2016-12-13 · ITER Besoins Previsonnels et Appels d’Offres Françoise Flament Head of Procurement and Contracts Division ... At

Page 14

12 December 2016 – 7ème RDV Business du Nucleaire Civil – CCI Marseille Provence Page 14

© 2016, ITER Organization

Business Opportunities

ELM

Coils

(3 per

sector)

Upper VS

Coil

ELM Feeders

Lower VS Coil

27 ELM (Edge Localized Mode)

water-cooled “picture frame” coils

fabricated of Mineral Insulated

Conductor (MIC).

- 9 lower, 9 equatorial, and

9 upper coil

- 6 turns/coil

- 1 flow path/coil

2 VS (Vertical Stability) “ring coils”

fabricated of MIC.

- 4 turns/coil

- 4 flow paths/coil

Coils are installed behind blanket, which limits space, access and repair

Successful studies have demonstrated the feasibility of long conductor lengths and

of winding pack design

Vacuum Vessel - In-Vessel Coils (1/3)

Page 15: ITER Besoins Previsonnels et Appels d’Offres · 2016-12-13 · ITER Besoins Previsonnels et Appels d’Offres Françoise Flament Head of Procurement and Contracts Division ... At

Page 15

12 December 2016 – 7ème RDV Business du Nucleaire Civil – CCI Marseille Provence Page 15

© 2016, ITER Organization

Manufacturing, Testing and Assembly constraints

Due to very high constraints the procurement strategy was refined in order to

cope better with the progress made on R&D and design

improvement/simplification such as:

o Reliance on long conductor unit lengths to eliminate the need for internal

conductor joints within coil;

o Change of winding pack design to simplify manufacture;

o Redesign of coil attachment to vacuum vessel stubs.

Overall procurement strategy

o Due to the difference in technology, the ITER Organization will place

separate contracts for the conductors and the coils production.

Business Opportunities

Vacuum Vessel - In-Vessel Coils (2/3)

Page 16: ITER Besoins Previsonnels et Appels d’Offres · 2016-12-13 · ITER Besoins Previsonnels et Appels d’Offres Françoise Flament Head of Procurement and Contracts Division ... At

Page 16

12 December 2016 – 7ème RDV Business du Nucleaire Civil – CCI Marseille Provence Page 16

© 2016, ITER Organization

3 main manufacturing contracts:

o Ongoing: Conductors: prototypes, supply for ELM and VS coils and feeders +

spares (Award submitted to MAC approval);

o Q2-2017: VS Coils and feeder tooling, trials on full-size mock-up(s) + in-situ

manufacture/installation;

o Q4-2017: ELM coils: prototypes, supply + 3 spares (one of each type).

4 phases:

o Phase I: Documentation and process qualification

o Phase II: Prototyping

o Phase III: First series

o Phase IV: Production

Business Opportunities

Vacuum Vessel - In-Vessel Coils (3/3)

Page 17: ITER Besoins Previsonnels et Appels d’Offres · 2016-12-13 · ITER Besoins Previsonnels et Appels d’Offres Françoise Flament Head of Procurement and Contracts Division ... At

Page 17

12 December 2016 – 7ème RDV Business du Nucleaire Civil – CCI Marseille Provence Page 17

© 2016, ITER Organization

Q3-2017: Design, qualification, manufacturing, installation and commissioning of

the PSS-N control logic for detection and mitigation actions:

o Scope transferred from DAs to the IO: 66 Plant Safety Systems for Nuclear

(PSS-N) as part of 46 Procurement Arrangements;

o Covers all aspects of the manufacturing, including nuclear licensing,

environmental and product qualification, optimization of space allocation;

o But it excludes some PSS-N, especially those allocated to buildings, REMS and

Ex-Vessel Remote Handling Transfer Cask System.

Control Systems and Instrumentation (1/3)

Page 18: ITER Besoins Previsonnels et Appels d’Offres · 2016-12-13 · ITER Besoins Previsonnels et Appels d’Offres Françoise Flament Head of Procurement and Contracts Division ... At

Page 18

12 December 2016 – 7ème RDV Business du Nucleaire Civil – CCI Marseille Provence Page 18

© 2016, ITER Organization

Connecting thousands of plant system I&C

client cubicles via network panels located in

28 buildings.

Bill of Material:

• 173 cubicles

• 175 passive network panels

• 300 km multi-core single mode

• 170 km multi-pair copper cables

Network Infrastructure supply, installation and test

– Combined with the Electrical Construction Contract

Control Systems and Instrumentation (2/3)

Page 19: ITER Besoins Previsonnels et Appels d’Offres · 2016-12-13 · ITER Besoins Previsonnels et Appels d’Offres Françoise Flament Head of Procurement and Contracts Division ... At

Page 19

12 December 2016 – 7ème RDV Business du Nucleaire Civil – CCI Marseille Provence Page 19

© 2016, ITER Organization

On-going: Services for plant system I&Cs integration with central I&C system:

o Support Plant I&C SAT (Site Acceptance Test);

o Integration with Central I&C infra (provision of network, replacement of PSH

(~210), transfer local data, configuration of SUP, etc.);

o Plant I&C verification and validation for integration.

Q2-2018: CODAC Servers supply, installation and maintenance

o Servers and storage systems in Main Control Room (MCR) and Back-up

Control Room (BCR);

o Network active components for Central I&C network infrastructure;

o Supply, installation, testing and maintenance.

Control Systems and Instrumentation (3/3)

Page 20: ITER Besoins Previsonnels et Appels d’Offres · 2016-12-13 · ITER Besoins Previsonnels et Appels d’Offres Françoise Flament Head of Procurement and Contracts Division ... At

Page 20

12 December 2016 – 7ème RDV Business du Nucleaire Civil – CCI Marseille Provence Page 20

© 2016, ITER Organization

Connectors and Vacuum Feedthrough for ITER Instrumentation

o Connectors for instrumentation connect instrumentation cables

to patch panels and vacuum feedthroughs;

o Vacuum feedthroughs enable the instrumentation cables to

cross the vacuum walls of the ITER cryostat and other vessels.

They shall be leak tight;

o Both are fitted to 40 pins connections and are designed for

high vacuum operation, some are operated at 80 K, others are

operated at room temperature;

o Needs: 240 of these items by 2017 and 2018 becoming the

standard applicable to all ITER systems.

Page 21: ITER Besoins Previsonnels et Appels d’Offres · 2016-12-13 · ITER Besoins Previsonnels et Appels d’Offres Françoise Flament Head of Procurement and Contracts Division ... At

Page 21

12 December 2016 – 7ème RDV Business du Nucleaire Civil – CCI Marseille Provence Page 21

© 2016, ITER Organization

Signed: Award for the Supply of Diagnostics Port Plug Structures - approved by the ITER

Council Management Advisory Committee – Contract signed 28 October 2016.

Ongoing: Structural engineering electromagnetics and thermo-mechanics services (CFT).

Ongoing: High Performance Engineering (CFT).

Q2-2017: Engineering Framework contract for Diagnostics Remote Handling.

o Design for mechanical structures interfaces of Diagnostics components with remote

handling. Nuclear environment with safety relevant components;

o Technical expertise to design and specify solutions that can be handled remotely.

Ongoing: Manufacturing and testing of components for Diagnostics (PQA Q1 2017).

Ongoing: Magnetic Diagnostic Flux loops cable assemblies final design, support and

manufacturing (CFT).

Diagnostics (1/2)

Page 22: ITER Besoins Previsonnels et Appels d’Offres · 2016-12-13 · ITER Besoins Previsonnels et Appels d’Offres Françoise Flament Head of Procurement and Contracts Division ... At

Page 22

12 December 2016 – 7ème RDV Business du Nucleaire Civil – CCI Marseille Provence Page 22

© 2016, ITER Organization

Q3-2017: First Wall manufacturing, test and delivery of all the Diagnostics First Wall

(DFW) modules for ITER nuclear components.

o DFWs are large stainless steel blocks bolted to the Diagnostic Shield Modules. They

are designed to handle the radiant and nuclear heating from the plasma. In addition,

the DFWs provide custom viewing apertures for the respective diagnostics.

Diagnostics (2/2)

Page 23: ITER Besoins Previsonnels et Appels d’Offres · 2016-12-13 · ITER Besoins Previsonnels et Appels d’Offres Françoise Flament Head of Procurement and Contracts Division ... At

Page 23

12 December 2016 – 7ème RDV Business du Nucleaire Civil – CCI Marseille Provence Page 23

© 2016, ITER Organization

• The Atmosphere Detritation Systems form an important tritium dynamic confinement

barrier. It is based on oxidation and scrubber column technology;

• Japanese Domestic Agency and ITER Organization signed an Agreement establishing a

joint procurement approach for the ITER Detritiation System.

The Procurement Strategy is under finalization, based on a phased approach:

o Mid-2017: Component qualification for system isolation, valves, transducers,

blowers and control;

o > 2018: Final design of the components and system design, and the contract

management, manufacturing of the systems.

Atmosphere Detritiation System (1/2)

Page 24: ITER Besoins Previsonnels et Appels d’Offres · 2016-12-13 · ITER Besoins Previsonnels et Appels d’Offres Françoise Flament Head of Procurement and Contracts Division ... At

Page 24

12 December 2016 – 7ème RDV Business du Nucleaire Civil – CCI Marseille Provence Page 24

© 2016, ITER Organization

Final manufacturing design, fabrication and installation of 8 modules, including scrubber

columns, recombiners, balance of systems

(valves, pipes, instrumentation and control).

Protection Important

Component (PIC)

systems

Tritium Plant

Atmosphere Detritiation System (2/2)

Page 25: ITER Besoins Previsonnels et Appels d’Offres · 2016-12-13 · ITER Besoins Previsonnels et Appels d’Offres Françoise Flament Head of Procurement and Contracts Division ... At

Page 25

12 December 2016 – 7ème RDV Business du Nucleaire Civil – CCI Marseille Provence Page 25

© 2016, ITER Organization

The Hot Cell Complex and the Radwaste Facility (RWF) consists of three buildings: Hot

Cell Building, Radwaste and Personnel Access Control Buildings. Together they provide

a secure environment for the processing, repair or refurbishment, testing and disposal of

ITER components that have become activated by neutron exposure.

The Procurement Strategy will be based on a phased approach:

o Q2-2017 : 1st Phase - Launch of the Tender related to the Preliminary Design of

the Hot Cell Complex Buildings and Equipment.

Hot Cell Complex

Page 26: ITER Besoins Previsonnels et Appels d’Offres · 2016-12-13 · ITER Besoins Previsonnels et Appels d’Offres Françoise Flament Head of Procurement and Contracts Division ... At

Page 26

12 December 2016 – 7ème RDV Business du Nucleaire Civil – CCI Marseille Provence Page 26

© 2016, ITER Organization

Q4-2017: Maintenance Tools & Equipment for Port Cell

o To develop the maintenance operations (either hands-on or RH-assisted) needed for replacing the

Pipe Forests in the TBM Port Cells using the appropriate maintenance tools & equipment as

developed by the ITER Organization;

o Such operations involve the cutting and welding of pipes made with a robotic arm and several

hands-on operations needed to position the maintenance tools in the correct locations.

Q2-2018: Demonstration of Remote Maintenance Operations

o To establish the RH replacement operations needed for refurbishing the Test Blanket Module

(TBM) Port Plug with two new TBM-Sets to be made in the Hot Cell;

o Development of appropriate metal gaskets;

o Small-scale mock-ups (local demonstration);

o Demonstration using a large-scale (~1) mock-up of the TBM Port Plug.

Plasma Operations

Page 27: ITER Besoins Previsonnels et Appels d’Offres · 2016-12-13 · ITER Besoins Previsonnels et Appels d’Offres Françoise Flament Head of Procurement and Contracts Division ... At

Page 27

12 December 2016 – 7ème RDV Business du Nucleaire Civil – CCI Marseille Provence Page 27

© 2016, ITER Organization

Q1-2017 : CP/3 – Procurement of TCWS Valves

Types of Cooling Water System valves : Manual, Motorized, Pressure Relief and

Control Valves; Butterfly, Gate, Globe, Ball, Plug, Diaphragm….; Valves actuators

(hydraulic, pneumatic, motor operated);

Applicable Standards: ASME B16.34 , ASTM, ESP / ESPN, Machinery Directive and

EMC Directive.

Business Opportunities

Preliminary BoQ

Quantity (units) Manual Valve 2100

Pressure Relief Valve 100 Control Valve 100

Valve Actuator 1200

Tokamak Cooling Water System (TCWS ) and Centralized Piping Tenders:

Page 28: ITER Besoins Previsonnels et Appels d’Offres · 2016-12-13 · ITER Besoins Previsonnels et Appels d’Offres Françoise Flament Head of Procurement and Contracts Division ... At

Page 28

12 December 2016 – 7ème RDV Business du Nucleaire Civil – CCI Marseille Provence Page 28

© 2016, ITER Organization

ITER Machine Assembly and Works (1/7)

ITER construction works include different kinds of works:

o Construction Management as-Agent (CMA): Site coordination and supervision of all

activities (contract signed);

o Plant installation: similar to industry plant but related to special technologies such as

high capacity electrical power supply, large scale tritium plant, large capacity cryogenic-

plant, custom-made special diagnostics, etc.;

o Tokamak assembly: Assembly of ultra heavy and extremely sophisticated machine

with very severe tolerances;

o Tokamak Complex: Assembly of mechanical and electrical components inside the

TKM Building but outside the machine.

Page 29: ITER Besoins Previsonnels et Appels d’Offres · 2016-12-13 · ITER Besoins Previsonnels et Appels d’Offres Françoise Flament Head of Procurement and Contracts Division ... At

Page 29

12 December 2016 – 7ème RDV Business du Nucleaire Civil – CCI Marseille Provence Page 29

© 2016, ITER Organization

ITER Machine Assembly and Works (2/7)

Page 30: ITER Besoins Previsonnels et Appels d’Offres · 2016-12-13 · ITER Besoins Previsonnels et Appels d’Offres Françoise Flament Head of Procurement and Contracts Division ... At

Page 30

12 December 2016 – 7ème RDV Business du Nucleaire Civil – CCI Marseille Provence Page 30

© 2016, ITER Organization

Plant Installation: Electrical, I&C and Cabling Works

o Awarded: Electrical, I&C and cabling, mechanical works contract for Building 61

o Ongoing: Electrical, cable supply, Instrumentation and Control including:

• DC busbar and switching network (RF-DA);

• Tokamak in-vessel coil busbars and switches (KO-DA);

• Access Control and Security Equipment (IO);

• Power and Control Cables (IO or Construction Contractor);

• Cable Tray and Conduit (Construction Contractor);

• Process Instrumentation and Connections (DA’s Supply).

ITER Machine Assembly and Works (3/7)

Page 31: ITER Besoins Previsonnels et Appels d’Offres · 2016-12-13 · ITER Besoins Previsonnels et Appels d’Offres Françoise Flament Head of Procurement and Contracts Division ... At

Page 31

12 December 2016 – 7ème RDV Business du Nucleaire Civil – CCI Marseille Provence Page 31

© 2016, ITER Organization

ITER Machine Assembly and Works (4/7)

400 kV switchyard

Coil Power Converters Reactive Power

Compensators

Switching Networks and

Fast Discharge Units 66 kV switchyard

Location of main Electrical Distribution Components

Plant Installation: Electrical, I&C and Cabling Works

Page 32: ITER Besoins Previsonnels et Appels d’Offres · 2016-12-13 · ITER Besoins Previsonnels et Appels d’Offres Françoise Flament Head of Procurement and Contracts Division ... At

Page 32

12 December 2016 – 7ème RDV Business du Nucleaire Civil – CCI Marseille Provence Page 32

© 2016, ITER Organization

Plant Installation: Mechanical and Piping Works

o Pre-manufacturing and installation of platforms and structures;

o Installation of mechanical parts (plant system equipment), ducts and system

penetrations;

o Pre-manufacturing and Installation of pipework spools including system

supports to building;

o Installation of in-line instrumentation: at least provision up to the first root /

isolation valve, which will constitute the process boundary;

o Quality Control and Installation Tests, Pre-commissioning Activities;

o Assistance during Commissioning activities performed by Operators of

systems.

ITER Machine Assembly and Works (5/7)

Page 33: ITER Besoins Previsonnels et Appels d’Offres · 2016-12-13 · ITER Besoins Previsonnels et Appels d’Offres Françoise Flament Head of Procurement and Contracts Division ... At

Page 33

12 December 2016 – 7ème RDV Business du Nucleaire Civil – CCI Marseille Provence Page 33

© 2016, ITER Organization

Plant Installation: Support Contracts

o Lifting and Handling:

Perform lifting and handling operations upon request.– primarily for mobile crane hire

for use by all contractors Construction to provide scaffolding to works contractors;

(CFN launched);

o Scaffolding:

Design, erect and survey the scaffolding to reach the installation area;

o Construction Material Management – for on site transportation of material from

storage location to works location – new contract;

o Finishing civil works – for necessary changes to buildings after handover by F4E;

o Pre-commissioning/commissioning and maintenance.

These contracts will be launched in 2017.

ITER Machine Assembly and Works (6/7)

Page 34: ITER Besoins Previsonnels et Appels d’Offres · 2016-12-13 · ITER Besoins Previsonnels et Appels d’Offres Françoise Flament Head of Procurement and Contracts Division ... At

Page 34

12 December 2016 – 7ème RDV Business du Nucleaire Civil – CCI Marseille Provence Page 34

© 2016, ITER Organization

o Fusion oriented specific technology:

− Specialized work related to superconducting magnet and extreme technology;

− No standardized proven assembly processes and methodologies, thus need to

develop appropriate processes innovatively;

− Large amount of in-situ engineering works necessary.

o Non-reversible assembly process:

− Repairs and/or reworks will be fundamentally difficult, almost impossible in most

cases. In addition, work spaces are often limited and accessibility is poor because

of the complexity of the machine and tight building space.

ITER Machine Assembly and Works (7/7)

Page 35: ITER Besoins Previsonnels et Appels d’Offres · 2016-12-13 · ITER Besoins Previsonnels et Appels d’Offres Françoise Flament Head of Procurement and Contracts Division ... At

Page 35

12 December 2016 – 7ème RDV Business du Nucleaire Civil – CCI Marseille Provence Page 35

© 2016, ITER Organization

Conclusion

o The ITER Council has endorsed the updated Integrated Schedule for the ITER

Project, which identifies the date of First Plasma as December 2025, and in

November the Overall Project Schedule (OPS);

o The updated Schedule represents the best technically achievable path forward to

First Plasma, which will mark the completion of the key assembly and

commissioning phases of the Tokamak and support facilities;

o In order to find economically efficient solutions to achieve the FP in 2015, the IO

is looking at all solutions that could bring flexibility as well as cost and schedule

performance.

o The IO will organize consultation with Industry during the 1st Quarter 2017.

o You are all invited to join the ITER Business Forum on 28-30 March 2017 in

Avignon.

Page 36: ITER Besoins Previsonnels et Appels d’Offres · 2016-12-13 · ITER Besoins Previsonnels et Appels d’Offres Françoise Flament Head of Procurement and Contracts Division ... At

Page 36

12 December 2016 – 7ème RDV Business du Nucleaire Civil – CCI Marseille Provence Page 36

© 2016, ITER Organization

o Read more on the ITER Organization’s Procurement Website:

www.iter.org - Procurement / General information

[email protected] - Point of contact

o On-line registration:

Self-presentation of the companies;

>1500 suppliers registered as of today;

Identification of the suppliers per business activities;

No prequalification at this stage;

But references need to be updated from time to time.

Page 37: ITER Besoins Previsonnels et Appels d’Offres · 2016-12-13 · ITER Besoins Previsonnels et Appels d’Offres Françoise Flament Head of Procurement and Contracts Division ... At

Page 37

12 December 2016 – 7ème RDV Business du Nucleaire Civil – CCI Marseille Provence Page 37

© 2016, ITER Organization

Doing Business in Vicinity of ITER:

W@I: Welcome Around ITER Partnership

o A strong regional network has been deployed to welcome international leaders,

high-tech companies, specialized laboratories and SMEs and provide them with

services matching their needs:

• Immigration and workers accommodation: Agence ITER France (AIF);

• Industrial partnerships, subcontracting, local support: C2I - ITER

Industrial Committee;

• Local recruitment and training: Pôle Emploi and PACA Mode d’ Emploi;

• Business setup: Welcome Office for International Companies (WOIC).

o More information: http://welcome-around-iter.com

Page 38: ITER Besoins Previsonnels et Appels d’Offres · 2016-12-13 · ITER Besoins Previsonnels et Appels d’Offres Françoise Flament Head of Procurement and Contracts Division ... At

Page 38

12 December 2016 – 7ème RDV Business du Nucleaire Civil – CCI Marseille Provence Page 38

© 2016, ITER Organization

Thank you for your attention