Upload
others
View
7
Download
0
Embed Size (px)
Citation preview
1
ITRC Fall Meeting 2007
Enhanced Attenuation: Chlorinated Organics
Judie Kean, (Fl )and Kimberly Wilson (SC) October 24, 2007
San Antonio, Texas
2
Background Information
Æ Project Name: Enhanced Attenuation/Monitored Natural Attenuation
Æ Team Name: Enhanced Attenuation: Chlorinated Organics (EACO)
Æ Year Project Began: December 2003 (Proposal) Æ First Team Meeting: March 2004 Æ Program Advisor: Steve Hill, REGTECH, INC
3
Team Logo
Enhanced Attenuation
ITRC Team
4
TEAM SLOGAN
PARTNERING WITH NATURE!!!!
5
Team Membership EACO TEAM 2007
26%
3%3%
6%3%
53%
6%
State MembersStakeholderDODDOEUSGSIndustryAcademia
State Representatives
CALIFORNIAFLORIDA
MAINESOUTH CAROLINA
NEVADANEW JERSEYNEW MEXICO
PENNSYLVANIAWASHINGTON
We have the best team!!!
6
Problem Statement Æ Original Team Problem Statement
è Chlorinated solvents and organic contamination exist nationwide and worldwide. There is little guidance available regarding when to transition from active remedies, such as source control, to a Monitored Natural Attenuation (MNA) remedy and from a MNA remedy to active remediation. Additional guidance is needed for the development of remedial strategies to enhance attenuation processes, by either increasing the attenuation capacity of the aquifer or decreasing the flux of contaminants.
è Promulgation of applicable scientific protocol and decision tools
can encourage regulators and the entire environmental market to promote innovative approaches to site closure reducing overall costs and timeframe No change in problem statement
7
TEAM CLOSURE 10/1/2008
PROJECT END • July 2010
PROJECT START December 2003
Enhanced Attenuation: Monitored Natural Attenuation
PROJECT TRANSITION
• Begin June 2010 • Evaluate the Current nature of the Tech-Reg and revise if necessary, or • Develop a ‘Status of the Technology” statement and end the project.
PRODUCT IMPLEMENTATION FINAL PHASE
• Begin June 2008 • End May 2010
PRODUCT IMPLEMENTATION INITIAL PHASE
PRODUCT DEVELOPMENT
• Develop Implementation Strategy April 2008
• Insert Date Expected to Start
See next slides
January 2004
TEAM FORMATION
PROPOSAL DEVELOPMENT
December 2003
• Develop Implementation Strategy – Fall 2007
• Organize Implementation Session with POCs – 2008
• Develop Team Project Summary Statement - April 2008
8
Information “Building Blocks”
Enhanced Attenuation Fact Sheet-Early 2005
Regulator Survey-White Paper/Presentations-10/05
Database-Designed and Implemented-11/05
Decision Framework-Document, Presentations-10/06
Technical Regulatory Document-White Paper 07-08
Internet Training-2008
Resource Guide-05-06
Decision Framework-Short 1 page Handout- 11/06
9
Value of Team Products
è The six products before the Tech-Reg Document were considered “building blocks” to the final Technical Regulatory Document.
è Distribution of information early in the team working timeframe for
outreach and feedback. è Help regulators and industry move chlorinated organic sites
through the remedial process more efficiently, with a possible long term cost savings.
10
Outreach Status DATE Workshop/Conference/Paper Comments
Dec-05 SERDP Abstract Poster Presentation-EA
May-06 Battelle Conference-Monterey(2006) White Paper/ Presentation/Panel
Sep-06 DNAPL Conference-Pittsburg White Paper/ Presentation-Survey
Nov-06 Florida Remediation Conference EA-Decision Framework
Dec-06 SERDP Abstract Poster Presentation-Decision
Feb-07 Florida Contractor's Workshop EA-Decision Framework
Feb-07 American Bar Association Year in Review Journal 2006-EA
Mar-07 Oak Ridge Site Seminar* EA-Decision Framework
Apr-07 Hanford Site Seminar* EA-Decision Framework
Apr-07 Remediation Journal-Article Enhanced Attenuation
Apr-07 Savannah River Site Seminar* EA-Decision Framework
May-07 Florida Waste Cleanup Workshop EA-Decision Framework
May-07 State of Washington Conference EA-Decision Framework
May-07 Battelle Conference Baltimore Training Session--ITRC Decision
Jun-07 New Jersey Water Environmental Assoc EA-Decision Framework
Jul-07 Battelle Conference-Monterey(2008) Abstract Submitted
Jul-07 Battelle Conference Monterey (2008) Training Session Proposal Submitted
NOTE: * participants include DOE, contractors, regulators, and public stakeholders
11
Product Schedule-Challenges
Product Scheduled
Date Actual Date Comments
Survey 7/15/2005 10/20/2005 ITRC Web site down for 3 months
Fact Sheet 2005 2005 No problems
Resource Guide 5/30/2006 9/1/2006 Designed as Web Based/Problems/Removed Links
Database 6/30/2006 6/30/2006 Design Complete/Capture of
various Site Information
Decision Framework--Summary 12/15/2006 2/28/2007 POC late comments
Decision Framework-1 page No Date No Date Team Detailed Info
Tech-Regulatory Document 9/24/07 9/25/2007 To POCs and DOD, DOE internal
review complete
12
Collaboration with Other ITRC Projects
Æ Work with other existing or past ITRC Projects/Teams
è Working with In-Situ Bioremediation of DNAPL team regarding technical information. The DNAPL team provides good “backup” of technical overview information.
è Proposal submitted in regards to BioWalls. Working with Permeable Reactive Barriers Team Leader-Matt Turner
Æ Collaboration
è Review technical information-Tech Regulatory Document-Draft. è Attend teleconference calls when applicable
13
Project Success Stories è Presentations delivered - noted overall support from audience and regulator
representatives were pleased with the decision process. è POC “overview” of decision tree indicated favorable comments; “good to have
some guidance on direction for closure”. è Provided training/ presentation with DOE team at the Battelle conference in
2007. The ITRC received a check for $685.98, as part of our team participation.
Æ If none identified currently, what successes do you expect to be identified in the future? è Targeted—project managers, regulators, industry è Streamline approach for remediation of chlorinated organic sites, which will
help to develop “treatment train” remedial philosophy based on mass flux and attenuation capacity concepts.
è Speed closure timeframe and reduce overall long term site cleanup costs.
14
Enhanced Attenuation (EA)
Æ So……. what is EA and why should I care?!!
Enhanced = Improve/Augment Attenuation= Shrinking/Decrease
15
EA provides a “bridge” between Source
Treatments and MNA (& reverse)
Source Treatments
Monitored Natural Attenuation
Enhanced Attenuation Technologies
16
Challenges for Implementation of MNA
Æ Limited efforts to understand the balance between source loading and attenuation capacity, therefore longer remediation timeframes.
Æ Limited understanding of site specific natural attenuation processes.
Æ Little guidance for when to transition from active remedies to MNA and the reverse;
Æ Naturally occurring rates can be too slow when using MNA.
17
Enhanced Attenuation (EA)/Decision Flowchart (DF)- Benefits
è DF-Facilitates transition of contaminated sites through the remediation process. EA uses various technologies and techniques to stabilize the plume
è DF-Encourages a systematic approach to total site remediation
è DF-Encourages open communication between the regulated and the regulators, so that effective decision making is possible
è EA complements MNA and expands remediation opportunities
à Tailored intervention approach
è EA encourages energy efficiency and develops the best solutions for the environment
18
Site Data
Risk Criteria
Time Criteria
Performance
Monitoring
Performance
Monitoring
Cost Criteria
II. Evaluate Plume Stability·∙ Determine plume stability·∙ Describe how plume stability is currently evaluated·∙ Estimate long-term sustainability
Implement and Monitor
Enhancements
I. Source and/or Primary Plume Treatment·∙ Removal (e.g., excavation, thermal, vapor extraction, etc.)·∙ Destruction (e.g., chemical or biological oxidation or reduction, etc.)·∙ Containment
III.Evaluate Enhancement Options·∙ State goals·∙ Identify technologies
§ Increase attenuation§ Reduce loading
·∙ Evaluate options to meet goals
F. Approve and Implement MNA
A. Are the risks
acceptable?
B. Is the plume stable or shrinking?
C. Are conditions
sustainable?
D. Is the remediation time frame
acceptable?
E. Are the costs-benefits acceptable?
Are sustainable enhancements
viable?
Yes
Yes
Yes
Yes
Yes
Yes
No
No
No
No
No
No
Evaluate performance and implement contingencies if needed
Until Cleanup
Does risk require Active
Source Remediation?
Is the Plume Stable?
Is Enhanced Attenuation
Appropriate?
Is MNA Appropriate?
Monitor Natural Attenuation until
Site Closure!
D
ECIS
ION
FR
AM
EWO
RK