Jacobs Design Innovation Institute (JDII)
JDII Background
CoE Advisory Board Document (April 2013):
“this is an ideal time to extend and grow the role of design in our educational model at all levels: undergraduate, graduate and continuing education”
JDII Genesis
$20 million pledged by Paul and Stacy Jacobs in May 2013. • Berkeley Alums, long-time supporters of CoE and the campus.• Goal is a 24,000 sq ft, 3.5-story building North of Soda Hall.
“In our interconnected innovation economy, it is not enough to provide our future engineering leaders with technical skills,… They must also learn how to work in interdisciplinary teams, how to iterate designs rapidly, how to manufacture sustainably, how to combine art and engineering, and how to address global markets.”
- Paul Jacobs, Clinton Global Initiative 2013.
JDII Background
Themes:• Real-world problems and needs• Innovation through building• Rapid prototyping• Interdisciplinarity• Design for sustainable manufacturing• Global markets
JDII BackgroundSynergies:• CITRIS Invention Lab• Mech. Eng. Workshop
(under JDII)• Cal Design Lab• BID Lab• Capstone design courses in CoE• BCNM, VCL, I-School, Architecture,…• Maker Movement• MOOCs, Flipped Classrooms,
Studio Model, Modular Curriculum
JDII PrioritiesUndergraduate Instruction:• Concentration in Design for Engineering Majors– Requirements TBD, a curriculum committee is working on
this (3 elective courses w/ core course)?
• Minor in Design for non-Engineering Majors– 5 courses, only one sharable with the Major
Goal of around 2000 student-courses per semester.
Hands-on, studio courses. Small groups around a workbench.The Studio/Classroom: Projectors + Critique space + Lots of vertical work surfaces
JDII PrioritiesMasters Degrees ?Courses for Professionals ? Research Space ?
TBD: Focus on undergrad education for now.
JDII Structure• Director position announced, 1FTE allocated. Search
includes both campus and external candidates.
• Staff:– Lab/safety officer– Academic program administrator– Finance, Special Projects ?? - still TBD
JACOBS HALL: Project Milestones(from Scott Shackleton)
• Design Task Force (Building & Program) Commenced – May 2013• Schematic Design – Completed Sept 10, 2013• Design Task Force Building Committee Complete – Sept 30, 2013• Design Development – Completed Nov 2013• Construction Design – Completed Feb 2014 • Construction starts – Mar/Apr 2014• Construction completed – July 2015
• First Classes held in Fall 2015
JDII from SE (LeRoy Ave.)
JDII from SE (LeRoy Ave.)
JDII from NW (Ridge Road)
JDII from NW (Ridge Road)
JDII from W (Etcheverry Plaza)
JDII from W (Etcheverry Plaza)
JDII cross section from W
Soda Hall F3
Woz F4
Etcheverry F2
Etcheverry F1
JDII South Elevation
South Façade – (Work in Progress)
JDII Level 5 Floor Plan
JDII Level 4 Floor Plan
Wozniak Terrace
Invention LabStudio Model
JDII Level 3 Floor Plan
Soda Hall
JDII Level 2 Floor Plan
Etcheverry Hall
JDII Level 2 Floor Plan (alt.)
Etcheverry Hall