1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
1 Mobilisasi Alat Ls 1.00
2 Persiapan Ls 1.00
3 Pekerjaan Test Pile
* Test Pile BP1 dia. 80cm; L= 23 m ttk 1.00
* Test Pile BP1 dia. 60cm; L= 23 m ttk 1.00
* Axial Test BP 1 dia. 80cm( 2.5x350 Ton) = 700 Ton ttk 1.00
* Axial Test BP 1 dia. 60cm( 2.5x120 Ton) = 300 Ton ttk 1.00
* PDA Test ttk 6.00
REMARK
TIME SCHEDULE PEKERJAAN BORE PILEPROYEK HOTEL MERCURE MATRAMAN
INo Description Unit Qty
II III IV
* PDA Test ttk 6.00
* PIT test ttk 2.00
4 Pekerjaan Main Pile
* Borepile dia. 80 cm ; L=23 m ; 119 titik ttk 119.00 Produksi ± 4ttk/hari/ 1 alat
* Borepile dia. 60 cm ; L=23 m ; 76 titik ttk 76.00 Produksi ±4ttk/hari/ 1 alat
5 Pekerjaan continuos Pile
* Pile dia. 60 cm ; L= 17m ; 198 titik ttk 198.00
* Bentonite Pile dia. 50 cm L =17m , 198 titik ttk 198.00
6 Demobilization Ls 1.00
Jakarta, 10 Februari 2015
PT. Berdikari Pondasi Perkasa