6
January 2019 MONTHLY PROGRESS REPORT PROJECT: SEASIDE SCHOOL DISTRICT 2016 GO BOND PROJECT MONTH OF: JANUARY 2019 PREPARED FOR: SEASIDE SCHOOL DISTRICT PREPARED BY: MEGAN PRITCHARD, DAY CPM PROJECT COORDINATOR OWNER’s REPRESENTATIVE: DAY CPM ARCHITECT: BRIC ARCHITECTURE INC. CM/GC: HOFFMAN CONSTRUCTION COMPANY OF OREGON

January 2019 MONTHLY PROGRESS REPORTfiles.seasidesd.schoolinsites.com/construction/SSDGOUpdateJan2019.pdfPROJECT DASHBOARD BUDGET SCHEDULE SCOPE COMMUNITY Monthly Rating JANUARY 2019

  • Upload
    others

  • View
    7

  • Download
    0

Embed Size (px)

Citation preview

Page 1: January 2019 MONTHLY PROGRESS REPORTfiles.seasidesd.schoolinsites.com/construction/SSDGOUpdateJan2019.pdfPROJECT DASHBOARD BUDGET SCHEDULE SCOPE COMMUNITY Monthly Rating JANUARY 2019

January 2019

M O N T H L Y P R O G R E S S R E P O R T

PROJECT: SEASIDE SCHOOL DISTRICT 2016 GO BOND PROJECT

MONTH OF: JANUARY 2019

PREPARED FOR: SEASIDE SCHOOL DISTRICT

PREPARED BY: MEGAN PRITCHARD, DAY CPM PROJECT COORDINATOR

OWNER’s REPRESENTATIVE: DAY CPM

ARCHITECT: BRIC ARCHITECTURE INC.

CM/GC: HOFFMAN CONSTRUCTION COMPANY OF OREGON

Page 2: January 2019 MONTHLY PROGRESS REPORTfiles.seasidesd.schoolinsites.com/construction/SSDGOUpdateJan2019.pdfPROJECT DASHBOARD BUDGET SCHEDULE SCOPE COMMUNITY Monthly Rating JANUARY 2019

2

PROJECT DASHBOARD

BUDGET SCHEDULE SCOPE COMMUNITY

Monthly Rating

JANUARY 2019 MILESTONES

FEBRUARY 2019 TARGET MILESTONES

Developed Early In-Water work approach for access road between Heights and HS/MS

Review with ODF&W the Early In-Water work approach for access road construction up to the HS/MS

Working with the City on the East Hills Reservoir site agreements and utility coordination

Continue working with the City on the East Hills Reservoir site agreements and utility coordination

Finished up Exterior Subcontractors for VE opportunities, saving over $900,000

Meet with Interior Subcontractors for VE opportunities for cost savings

Heights Elementary Addition and Renovation program meetings

Finalize Design approach for Elementary School, begin Cost Estimate

Hire Real Estate Brokerage Firm Finalize contract with Real Estate Brokerage Firm

ON TARGET CAUTION BEHIND

Page 3: January 2019 MONTHLY PROGRESS REPORTfiles.seasidesd.schoolinsites.com/construction/SSDGOUpdateJan2019.pdfPROJECT DASHBOARD BUDGET SCHEDULE SCOPE COMMUNITY Monthly Rating JANUARY 2019

3

EXECUTIVE SUMMARY

DESIGN:

BRIC Architecture is finishing up Schematic Design of Seaside Heights designs to meet

Elementary education program needs, including classroom types and arrangements,

gymnasium and covered play areas, building security and project budget.

While not part of the District Bond, the City of Seaside’s engineering firm of Murray Smith

is designing the East Hills Reservoir tank, pump station, and future north and south piping

connections.

Working Hoffman Construction subcontractors on cost savings options for the HS/MS,

Seaside Heights, and developing schedules for work beginning in Summer 2019 through

Summer 2020.

Page 4: January 2019 MONTHLY PROGRESS REPORTfiles.seasidesd.schoolinsites.com/construction/SSDGOUpdateJan2019.pdfPROJECT DASHBOARD BUDGET SCHEDULE SCOPE COMMUNITY Monthly Rating JANUARY 2019

4

CITY OF SEASIDE:

Permitting - Seaside Public Works has been smooth:

o Received Electrical Permit from Clatsop County

o Received Building and responded to permit review comments

o Final Building permit anticipated in early March

Water System - Public Works and Murray Smith

o City is working with Murray Smith on East Hills Reservoir Design and Cost

o Bidding/Permitting planned for early Summer 2019, with onsite work beginning

late Summer 2019. Fabrication of reservoir tank sections will occur offsite, then

delivered for erection and welding in the Fall

o Working up agreements with the City for site access and land use

CONSTRUCTION:

Work proceeding at HS/MS:

o Underground site utilities

o Concrete mat foundation and east ‘basement’ walls complete

o Foundation work for HS Auxilary and MS Gyms under way

o Concrete block walls started in late January

o Rough-in building plumbing and electrical also in progress

Scheduling of work – Summer 2019 will be very busy:

o Heights will be closed to all community access for the summer

o Domestic water, storm water management, electrical, data, gas and sewer line

work will be extended to the HS/MS and Reservoir concurrent with road

construction to the HS/MS, reservoir.

o Heights Addition work scheduled to start in June

Page 5: January 2019 MONTHLY PROGRESS REPORTfiles.seasidesd.schoolinsites.com/construction/SSDGOUpdateJan2019.pdfPROJECT DASHBOARD BUDGET SCHEDULE SCOPE COMMUNITY Monthly Rating JANUARY 2019

5

PROJECT BUDGET: Bidding:

o Bid Package 4 (P-4): Subcontractor bids have come in higher than

estimated due to saturated construction market in western Oregon.

o Hoffman, BRIC and DAY meetings with subcontractors in December and

January to find cost savings in exterior building materials and systems.

Interior materials will be reviewed in February and March.

Priority is to maintain high quality building exterior due to coastal

weather conditions

Take a hard look at interior cost savings including finishes

Reviewing options for deferring work which can be built in the

future which does not impact education

Meetings with subcontractors have been collaborative and

successful

Page 6: January 2019 MONTHLY PROGRESS REPORTfiles.seasidesd.schoolinsites.com/construction/SSDGOUpdateJan2019.pdfPROJECT DASHBOARD BUDGET SCHEDULE SCOPE COMMUNITY Monthly Rating JANUARY 2019

6

BUDGET:

END OF REPORT

$99,546,749 $7,989,461

$6,469,722

$1,412,165

$10,612,152 $5,222,958

$1,284,142

$579,676

$-0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

CONSTRUCTION PROFESSIONAL

SERVICES:

OWNER/ DISTRICT

ADMIN COST

CONSULTANT

COSTS/NON-PROF &

TECH SERVICES

OWNER

CONTINGENCY:

Project Risk

ContingencyBudget Actual Spent

PROJECT BUDGET $123,277,093

$-

$5,000,000

$10,000,000

$15,000,000

$20,000,000

$25,000,000

$30,000,000

$35,000,000

$40,000,000

$45,000,000

$50,000,000

J F M A M J J A S O N D J

COMPARISON: to 1/2018 THRU 1/2019 CUMMULATIVE FORECAST TO

ACTUAL SPENT

46,226,284 17,519,585