January 28, 2014 Town Meeting re: NH Middle School Project

Embed Size (px)

Citation preview

  • 8/13/2019 January 28, 2014 Town Meeting re: NH Middle School Project

    1/30

    North Haven Middle School

    Building Committee

    January 28, 2014

  • 8/13/2019 January 28, 2014 Town Meeting re: NH Middle School Project

    2/30

    North Haven Middle School -

    Current status

    NEASC (New England Association of Schools &

    Colleges, Inc.) accreditation report concludes

    that the facility is limiting the Towns ability to

    meet the needs of a contemporary academicprogram

    This report resulted in the town taking action

    on the building to maintain the accreditation

    DTC hired to do a study of the facility before

    the building committee was formed

  • 8/13/2019 January 28, 2014 Town Meeting re: NH Middle School Project

    3/30

    North Haven Middle School -

    Current status

    Constructed in 1960

    The building and systems are failing beyond

    useful life

    Detailed NEASC report can be found on the

    North Haven Middle School website (lower

    right hand corner full article)

    3

  • 8/13/2019 January 28, 2014 Town Meeting re: NH Middle School Project

    4/30

    CommitteeBackground

    Formed in August 2013

    First meeting held on August 20th

    A brief overview of 4 options was presented tothe committee

    Committee members approved at townmeeting on September 23rd

    Meetings started on October 7th 8:15am atthe BOE board room and are bi-weekly(subject to change)

    4

  • 8/13/2019 January 28, 2014 Town Meeting re: NH Middle School Project

    5/30

    Committee Members

    Gary Johns (committee chairman) Dyann Vissicchio (committee vice-chair)

    Michelle Spader (committee secretary)

    Goldie Adele

    Michael Brandt Miriam Brody

    Lou Coppola,Sr.

    David Mikos Bruce Morris

    Walter Nester, Jr.

    Joseph Porto5

  • 8/13/2019 January 28, 2014 Town Meeting re: NH Middle School Project

    6/30

    Other Attendees

    Dr. Robert Cronin - Superintendent North HavenPublic Schools

    Kristine Carling - Director of Business and Operations

    Phil Diana - BOE Buildings and Ground Supervisor

    Jeff DonofrioAttorney of the Town Phil Piazza - Principal North Haven Middle School

    Edward Swinkoski - Director of Finance

    Diversified Technology Consultants (DTC); ShayAtluru, Rick Morse

    Perkins Eastman Architects - Joe Costa, Fritz Morris

    6

  • 8/13/2019 January 28, 2014 Town Meeting re: NH Middle School Project

    7/30

    Middle School Options

    Option 1 - Renovate the existing school

    Total cost: $67,588,276 Net cost: $45,507,417

    Option 2 - Renovate Gateway Campus

    Total cost: $71,988,187 Net cost: $54,522,823

    7

  • 8/13/2019 January 28, 2014 Town Meeting re: NH Middle School Project

    8/30

    Middle School Options

    Option 3 - Construct new school on Bailey

    Road

    Total cost: $65,892,568 Net cost: $50,775,361

    Note: This option includes a potential expansion of

    the ball fields between the Middle and HighSchool. The additional net cost increases to

    $55,577,383

    Option 4Hybrid/Renovate (Common areasas new and build new academic wing)

    Total cost: $64,730,579 Net cost: $46,908,642

    8

  • 8/13/2019 January 28, 2014 Town Meeting re: NH Middle School Project

    9/30

    Decision process in selecting Option

    Options reviewed individually

    Listened to concerns of residents

    All decisions in the elimination process wereunanimous

    9

  • 8/13/2019 January 28, 2014 Town Meeting re: NH Middle School Project

    10/30

    Order In Which Options Were

    Eliminated

    Option 2 Gateway Campus

    Option 1 Renovate Existing School

    Option 3 Construct New School on Bailey Road

    10

  • 8/13/2019 January 28, 2014 Town Meeting re: NH Middle School Project

    11/30

    Reasons Option 2 Gateway was Eliminated

    11

    Gateway Property Conveyance Process

    Gateway

    FacilitiesPlanningBoard ofRegents

    President

    Board of

    Regents

    OPMDeemed

    surplus

    Decide to

    Vacate

    1-3 years

    2013-2015

    BOR

    evaluation

    1 year

    2016

    Recommend

    for release

    1 year

    2017

    State of CT

    Evaluation

    1 2+ years

    2018

    Possible

    acquisition

    by Town

    2019

    New School Opens: ~2022

    Acquisition cost for Gateway is unknown!!!

  • 8/13/2019 January 28, 2014 Town Meeting re: NH Middle School Project

    12/30

    Reasons Option 2 Gateway was Eliminated

    State has not deemed Gateway to be a

    surplus property as they are the current

    owners of the building

    Remediation cost for auto body shop which

    exists in both gyms

    Unknown state reimbursement rate so far in

    the future

    Risk of losing NEASC accreditation with

    timeline so far out

    12

  • 8/13/2019 January 28, 2014 Town Meeting re: NH Middle School Project

    13/30

    Reasons Option 2 Gateway was Eliminated

    State would not pick up any cost of the

    demolition or remediation of the current

    Middle School site. 100% of the cost would be

    towns responsibility because it is not on thesame property as the option chosen

    13

  • 8/13/2019 January 28, 2014 Town Meeting re: NH Middle School Project

    14/30

    Reasons Option 1 Renovate Existing

    School was Eliminated

    Riskiest option in terms of added costs (whenthey open up ceilings and walls and find

    additional problems such as PCBs)

    Since there is no swing space to move thestudents into, trailers would be used as

    classrooms

    Complete renovation has the most risk Most disruption to staff and students

    14

  • 8/13/2019 January 28, 2014 Town Meeting re: NH Middle School Project

    15/30

    Reasons Option 1 Renovate Existing

    School was Eliminated

    Longer time line renovating a portion of the

    building at a time

    Increased risk of exposure to airbornematerials even though they are isolated with

    barriers

    15

  • 8/13/2019 January 28, 2014 Town Meeting re: NH Middle School Project

    16/30

    Reasons Option 3 New School on

    Bailey Road was Eliminated

    Bailey Road resident concerns of building scale

    Close proximity to Bailey Road

    Traffic concerns One story building not likely

    Displaces existing baseball & soccer fields until

    middle school is demolished for 2-3 years New State of CT School Security Commission

    Report cites security concerns with having

    building so close to the main road 16

  • 8/13/2019 January 28, 2014 Town Meeting re: NH Middle School Project

    17/30

    Option 3 New School Bailey Road

    17

    Bailey Road

  • 8/13/2019 January 28, 2014 Town Meeting re: NH Middle School Project

    18/30

    Option 4 Hybrid selected(Concept selected but not designed at this time)

    No impact to existing fields When completed an additional field will be

    created

    Uses existing bus loop No change in proximity to High School

    Reuse of existing auditorium, caf, music

    room and gyms which will be renovated

    Less disruption and less need for a lot of swing

    space (summers to renovate common areas)18

    O ti 4 H b id

  • 8/13/2019 January 28, 2014 Town Meeting re: NH Middle School Project

    19/30

    19

    Option 4 HybridExpected Occupancy date of July 2017

    N th H Middl S h l

  • 8/13/2019 January 28, 2014 Town Meeting re: NH Middle School Project

    20/30

    North Haven Middle School

    State Reimbursement as of Today

    Renovate as New 39.64%New School Construction 29.64%

    Application to State due 06/30/2014

    Reimbursement rates are declining year

    after year

    No guarantee that current reimbursement

    rate will carry forward unchanged

    Project will comply with new school security

    standards that are effective July 201420

  • 8/13/2019 January 28, 2014 Town Meeting re: NH Middle School Project

    21/30

    North Haven Middle School

    Project Schedule - Next Steps

    Town Meeting 1/28/14

    Approval of Concept

    Appointment of New Committee

    Approval to Hire Architect NHMS Building Committee Meeting 1/30/14

    Organization of New Committee

    RFQ Review and Approval RFQ Available for Pick Up 1/31/14

    Statements of Qualifications Due 2/10/14

    Review Qualifications 2/11/14 21

  • 8/13/2019 January 28, 2014 Town Meeting re: NH Middle School Project

    22/30

    North Haven Middle School

    Estimated Project Schedule - Next Steps

    Provision of RFP & Interviews 2/11/14

    RFP Due 2/25/14

    Interviews of Selected Firms 2/26/14

    Selection/Recommendation of Firm 2/27/14

    Contract Execution 3/3/14

    Design Presented to NHMS Building Committee Early May

    Cost Estimated/Design Presented to BOE & BOF Mid May

    22

    h ddl h l

  • 8/13/2019 January 28, 2014 Town Meeting re: NH Middle School Project

    23/30

    North Haven Middle School

    Estimated Project Schedule - Next Steps

    Modified Design Presented to NHMS Building

    Committee, BOE & BOF End May

    Communication of Design to Public Early May Mid June

    Final Referendum Approval Late June File EDO 49

    with State of Connecticut 6/30/14

    Begin Next Phase of Design & Construction Documents 7/1/14

    Hire Construction Manager 8/15/14

    23

  • 8/13/2019 January 28, 2014 Town Meeting re: NH Middle School Project

    24/30

    If funding is not approved to

    proceed with Option 4, we are

    faced with making costly

    renovations to the existingMiddle School in order to not

    lose accreditation

    24

  • 8/13/2019 January 28, 2014 Town Meeting re: NH Middle School Project

    25/30

    Cost of Renovations to Existing Middle School

    HVAC Component: $750,000

    Replace all existing units only

    Does not include classrooms

    Electrical systems $1,250,000

    Presently all electrical and data systems are maxedout. No new services can be installed until all main

    and branch circuits are upgraded

    Bathroom and plumbing: $2,250,000

    All bathrooms and fixtures replaced

    All drains, main distribution water lines and

    heating lines need replacement

    All valves associated with boiler functions 25

  • 8/13/2019 January 28, 2014 Town Meeting re: NH Middle School Project

    26/30

    Cost of Renovations to Existing Middle School

    Remove & replace entire roof: $3,500,000 to

    $4,450,000

    Remove existing roof

    Repair all drains

    Remove all trees hanging in proximity

    Possible abatement

    26

  • 8/13/2019 January 28, 2014 Town Meeting re: NH Middle School Project

    27/30

    Cost of Renovations to Existing Middle School

    Fire code & ADA Compliance: $750,000 to

    $1,250,000

    Replace fire control panels

    Replace all smoke detectors and branch wiring

    Meet all ADA requirements for classrooms

    building entrances, exits and all associated fixtures

    and equipment

    Ceilings & Grids: $500,000

    27

  • 8/13/2019 January 28, 2014 Town Meeting re: NH Middle School Project

    28/30

    Cost of Renovations to Existing Middle School

    The items mentioned on the previous slides

    only address the core mechanicals and

    electrical equipment of the school

    Does not address the other needs in all

    classroom areas and architectural concerns

    Without the passage of a new middle school

    the above items would have to be completed

    in the near future

    28

  • 8/13/2019 January 28, 2014 Town Meeting re: NH Middle School Project

    29/30

    Cost of Renovations to Existing Middle School

    We can assume that there will hidden or

    unforeseen costs associated with the repair

    All windows replaced

    All doors & hardware replaced

    All flooring replaced

    Upgrades to the Auditorium

    Upgrade all lockers

    29

    http://www.google.com/url?sa=i&rct=j&q=&esrc=s&source=images&cd=&cad=rja&docid=f1j6K6vr_1zQxM&tbnid=Wl6SPDD8I9XaSM:&ved=&url=http://sweetclipart.com/simple-blue-question-mark-1146&ei=Z-HRUpCRJ4vfkQe22ICACw&bvm=bv.59026428,d.eW0&psig=AFQjCNEsRssH-cwdk6r-xXpp9lDdKnwUlQ&ust=1389572839907728http://www.google.com/url?sa=i&rct=j&q=&esrc=s&source=images&cd=&docid=LVFcb6D0xJIUWM&tbnid=RtGvkoEfWzwyYM:&ved=&url=http://www.freeclipartnow.com/signs-symbols/roadside/question-mark.jpg.html&ei=i-DRUpCbKcjWkQftkYGYAw&bvm=bv.59026428,d.eW0&psig=AFQjCNE9FZ2FvB-To7U5S0wJH2FLvVbRIg&ust=1389572620163064http://www.google.com/url?sa=i&rct=j&q=&esrc=s&source=images&cd=&docid=LVFcb6D0xJIUWM&tbnid=RtGvkoEfWzwyYM:&ved=&url=http://www.freeclipartnow.com/signs-symbols/roadside/question-mark.jpg.html&ei=i-DRUpCbKcjWkQftkYGYAw&bvm=bv.59026428,d.eW0&psig=AFQjCNE9FZ2FvB-To7U5S0wJH2FLvVbRIg&ust=1389572620163064
  • 8/13/2019 January 28, 2014 Town Meeting re: NH Middle School Project

    30/30

    Questions

    30

    ?

    http://www.google.com/url?sa=i&rct=j&q=&esrc=s&source=images&cd=&cad=rja&docid=f1j6K6vr_1zQxM&tbnid=Wl6SPDD8I9XaSM:&ved=&url=http://sweetclipart.com/simple-blue-question-mark-1146&ei=Z-HRUpCRJ4vfkQe22ICACw&bvm=bv.59026428,d.eW0&psig=AFQjCNEsRssH-cwdk6r-xXpp9lDdKnwUlQ&ust=1389572839907728http://www.google.com/url?sa=i&rct=j&q=&esrc=s&source=images&cd=&docid=LVFcb6D0xJIUWM&tbnid=RtGvkoEfWzwyYM:&ved=&url=http://www.freeclipartnow.com/signs-symbols/roadside/question-mark.jpg.html&ei=i-DRUpCbKcjWkQftkYGYAw&bvm=bv.59026428,d.eW0&psig=AFQjCNE9FZ2FvB-To7U5S0wJH2FLvVbRIg&ust=1389572620163064http://www.google.com/url?sa=i&rct=j&q=&esrc=s&source=images&cd=&docid=LVFcb6D0xJIUWM&tbnid=RtGvkoEfWzwyYM:&ved=&url=http://www.freeclipartnow.com/signs-symbols/roadside/question-mark.jpg.html&ei=i-DRUpCbKcjWkQftkYGYAw&bvm=bv.59026428,d.eW0&psig=AFQjCNE9FZ2FvB-To7U5S0wJH2FLvVbRIg&ust=1389572620163064