34
Maryland Avenue at Payne Avenue January 30, 2014 Luke Lortie, EIT 651.266.7123 Jerry Auge, PE 651.266.7117

January 30, 2014 Luke Lortie, EIT 651.266.7123 Jerry Auge, PE 651.266.7117

Embed Size (px)

Citation preview

Maryland Avenue at Payne Avenue

January 30, 2014

Luke Lortie, EIT651.266.7123

Jerry Auge, PE651.266.7117

Project Overview Alley Way Access Storm Water Treatment Right-of-Way Acquisition Update Arlington Hills Park Impacts Future of Vacant Parcels Project Schedule/Estimated Cost Update Project Phasing

Meeting Agenda

Received HSIP Funds to Address Safety Concern 44 Foot Roadway Width (55 Feet at

Intersection) 4 Lanes 11 Foot Lane Width Left Turn Lanes on Maryland Avenue 30 mph Speed Limit Sidewalks Alley Way Closures

Project Overview

Alley Way Access Current Alley Ways Pose a Safety ConcernoCurrently Located Very Close to Signalized

IntersectionsoSight Distance Issues

5 Accesses to be Closed

Closure Design OptionsoChain Link Fence; 5-Foot Boulevard; Hazard Markero Planted Shrubs; 5-Foot Boulevard; Hazard MarkeroBallards; No Greenspace Boulevard; Hazard Marker

Project Overview

Alley Way Access Option 1

Alley Way Access Option 2

Alley Way Access Option 3

County Recommends Ballard Option

Mid-Block Alley Way Required to Maintain At Least 2 Accesses to

Passable Streets

Southwest Quadrant Contains Only 1 Access After Proposed Closures

2 Proposed Mid-Block Alley Way Locations

Mid-Block Alley Way - West

Mid-Block Alley Way - East

Mid-Block Alley Way Profiles

*Current Alley Way Slope: 6% to 13%

Mid-Block Alley Way By Moving the Alley Way East, Slope Can Be

Drastically Reduced.

More Moderate Slope Allows for a Safer Alley WayoEasier to Navigate During Winter MonthsoEasier to Collect and Retain Storm Water Runoff

County Recommends East Alley Option

Storm Water Treatment Treatment Required for Watershed Dist. Permit

County Discussing Designs with Capitol Region Watershed District

Watershed Requires Volume Reduction of 1” Per Acre Impervious Surfaceo Proposed Impervious: 2.25 AcresoVolume Reduction of ~8,200 Cubic Feet

Storm Water Treatment Design Optionso InfiltrationoBiofiltrationo PondingoTree Boxes

County Looking at Linear Underground Filtration Along Vacated Parcels

Storm Water Treatment

Infiltration Trench

Biofiltration Trench

Right-of-Way Acquisition 33 Properties Impacted o1 Churcho1 Park Propertyo2 Private Commercial Propertieso1 Parking Loto2 Vacant Lotso26 Residential Properties

Properties to Be Acquired

Temporary Easements o22 Settled

Property Acquisitiono8 Signed Agreements o2 Tentative Settlementso1 Residential Not Settled

Right-of-Way Update

8 Propertieso7-Prior to Constructiono1-During Construction

County in Process of Letting Demo ContractoAs Properties Are AcquiredoDemolition February – April 2014

Building Demolition

Arlington Hills Park Impacts

Federal Funding Requires 4(F) Approval

oSection 4(F) Regulates the Use of Publicly Owned Parks, Refuges, and Historic Sites for Federal Highway Projects

oCounty, City, and Parks Require Separate Approval Processes

Arlington Hills Park Impacts

4(F) De Minimis Process

oRoad Project Impact to Features, Attributes, or Activities in Park

o30-Day Public Comment Period• Advertised in the Ramsey Review January 8 & 15,

2014

Arlington Hills Park Impacts

Public Comments – Added to Project Memorandum (Federal Funding Requirement)

FHWA Findingso Reviews Public Commentso Issues De Minimis Impact Findingo Requests City of St. Paul Approval

Arlington Hills Park Impacts

Future of Vacant Parcels Parcels Will Be Demoed and Graded oCurrent Parcels Do Not Meet City Requirementso Parcel Zoning to Be Determined by City of St. Paul

Sewer & Water Utilities Will Be Constructed to Vacant Parcels During Road Reconstruction

What’s the Future????

Residential/Commercial???Water ServicesSewer Service

Prevent the Excavation of Newly Constructed Roadway

Properties Acquired

Vacant Parcels

10 Vacated Parcels = ?? New Parcels

ROW Purchase Agreements Jan 2014-Mar 2014Design Plans at 90% January 2014Condemnation March 5, 2014Design Approval March 30, 2014Right-of-Way Certificate #1 March 17, 2014Advertise for Bids April 2014Bid Awarding May 2014Start of Construction June 2014Completion of Construction August 2014

Project Schedule - 2014

Federal $1,498,000County State Aid Highway $1,600,000Municipal State Aid $1,580,000

Total $4,688,000

Estimated Project Funding

To be Determinedo Private/Public Utility WorkoCommunity Inputo Project Duration

MnDOT 35E MNPass Projecto Potential Closures Affect Maryland Traffic Volume?

Future Open House Meeting

Project Phasing

E-Subscribe For Projects For the most up-to-date project information and

to receive project updates regularly throughout the duration of the project, visit the Ramsey County website at: http://www.co.ramsey.mn.us/pw/index.htm

Click on ‘Subscribe to Maryland and Payne Email Updates’ to receive

future email updates on the status of the project

January 30, 2014

Luke Lortie, EIT651.266.7123

[email protected]

Jerry Auge, PE651.266.7117

[email protected]

Questions?