Upload
others
View
3
Download
0
Embed Size (px)
Citation preview
JENNER WIND POWER PROJECTS
JULY 2019
Dear Stakeholder,
Attached you will find the latest newsletter for the Jenner Wind Power Project Expansion (JWPPE). As you may know
from earlier consultation efforts, the 122.4 MW Jenner Wind Power Project (JWPP) has received a permit from the Alberta
Utilities Commission (the AUC), which is being amended with proposed changes to turbine technology and other project
infrastructure through a Letter of Enquiry recently submitted to the AUC. The JWPPE will add a further 180.6 MW
connecting to the Alberta Interconnected Electric System grid at the same location as the JWPP.
As a result of the Renewable Electricity Program (REP) process, a portion of the JWPPE was selected for a long-term
contract by the Alberta Electric System Operator (AESO). The 71.4 MW portion of the JWPPE that was selected for the
AESO REP will be called the Jenner Wind Power Project 2 (“JWPP2”). The remaining 109.2 MW of the JWPPE that was
not selected for a long-term contract will be built to sell power directly into the Alberta power pool or to a credible third-
party and will be called the Jenner Wind Power Project 3 (“JWPP3”).
To keep the relevant AUC permit applications for JWPP2 and JWPP3 separate, the existing 180.6 MW JWPPE AUC
application will be split into two applications; a 71.4 MW application for JWPP2, and a 109.2 MW application for
JWPP3. The applications will be submitted under two new companies; Jenner 2 Limited Partnership and Jenner 3 Limited
Partnership, both of which were created to own the assets of each project. The new companies are both subsidiaries of
Jenner Wind Limited Partnership. Potentia Renewables Inc. is the ultimate parent entity of all project entities mentioned
above. Both projects’ AUC applications will include studies that take into consideration the potential impacts of the
other (and the JWPP), including sound levels and shadow flicker. It is anticipated that the two AUC application proceedings will run in parallel.
A representative of the JWPP2 and JWPP3 projects will be contacting you to arrange a time for individual meetings to
discuss any questions or concerns that you may have about either of the projects. These questions and comments
will be compiled into reports that will be submitted to the AUC with each application.
We look forward to discussing these exciting projects with you, to answering (and addressing where possible) any
questions or concerns that you might have, and to working with you to maximize their positive impact on the community
and the Province while minimizing any negative impacts.
We appreciate your time and your input.
Sincerely,
Hemanth Shankar
Jenner 2 Limited Partnership and
Jenner 3 Limited Partnership
• COMMUNITY FUND AND INVOLVEMENT
• AESO RENEWABLE ELECTRICITY PROGRAM
• PROJECT & LAYOUT UPDATE
• TURBINE MODEL CHANGE
• DECOMMISSIONING & RECLAMATION
• UPDATED SCHEDULE
• UPDATED MAP WITH NOISE CONTOUR
• LOCAL BENEFITS
• OWNERSHIP
• VIEWSCAPES
IN THIS NEWSLETTER,YOU WILL FIND INFORMATION ON:
PROJECT UPDATESOn December 17, 2018, a portion of the JWPPE (71.4 MW) was selected for a contract under Round 3 of the Alberta Electric System Operator (AESO) Renewable Electricity Program (REP). As a result of the AESO REP 3 contract, the JWPPE will be split into two phases – the Jenner Wind Power Project 2 (JWPP2) and Jenner Wind Power Project 3 (JWPP3). JWPP2 has a nameplate capacity of 71.4 MW and is contracted under the REP. JWPP3 has a nameplate capacity of up to 109.2 MW and does not have a REP contract. Combined, the two phases will be referred to as the JWPPE in this newsletter and in the attached Map.
The original design of the JWPPE proposed 53 wind turbine locations and an application was submitted to the Alberta Utilities Commission (AUC) in 2017. PRI put the application into abeyance (on hold) in January 2018 to address stakeholder concerns. The existing JWPPE AUC application will now be amended and split into two applications; a 71.4 MW application for the JWPP2, and a 109.2 MW application for the JWPP3. Both applications will also reflect changes to turbine technology, slight adjustments to turbine locations and other minor modifications.
INTRODUCTIONPotentia Renewables Inc. (PRI) would like to thank you for your continued interest in the Jenner Wind Power Project Expansion (JWPPE). We greatly value our relationship with the local community, and we are committed to engaging and consulting with stakeholders.
You recently received a newsletter about the Jenner Wind Power Project (JWPP) and are receiving this JWPPE newsletter because you live on or own land near the JWPPE and we want to provide you with an update on the changes to this project.
JULY 2019 • NEWSLETTER
PAGE 1JULY 2019 • NEWSLETTER
PUBLIC CONSULTATION AND PROVIDING YOUR INPUTWe wish to minimize potential negative impacts on the environment and the community from the JWPP2 and JWPP3. PRI will continue discussions with local landowners and stakeholders to develop the JWPP2 and JWPP3 in a way that respects community members’ needs and reduces environmental impacts.
We will continue to engage with occupants, residents, and landowners within 800 metres of the JWPP2 and JWPP3 to gather input through one-on-one consultation. During the one-on-one consultation process, we will document the information you provide and attempt to address any questions or concerns you may have about the projects. We would love to hear from you. Please contact us at the information provided below.
Privacy Commitment: PRI is committed to protecting your privacy. Collected personal information will be protected under the provincial Personal Information Protection Act. As part of the regulatory process for new generation projects, PRI may be required to provide your personal information to Alberta Utilities Commission (AUC). For more information about how PRI protects your personal information, visit our website at www.jennerwind.com or contact us directly via phone toll-free at 1-833-536-6371.
CONTACT US
COMMUNITY FUND AND INVOLVEMENT We’re pleased to announce that for a third consecutive year, we sponsored the Buffalo Rodeo and the Jenner Rodeo. We’re always interested in supporting other local events and activities in the community. Please email your sponsorship and donation requests to: [email protected] for consideration.
For additional information about the JWPP2 and JWPP3 or to arrange a personal consultation, please contact our consultation agent from Scott Land & Lease:
Jason PigeonSenior Consultation Agent
P: 403-473-6661E: [email protected]
For more information about Potentia Renewables Inc. (PRI) and the JWPP2 and JWPP3, please visit: www.jennerwind.com
Potentia Renewables Inc. 200 Wellington Street WestSuite 1102, Toronto, ON M5V 3C7
P: 1-833-536-6371 E: [email protected]
OWNERSHIPThe JWPP2 and JWPP3 are currently owned by Jenner Wind Limited Partnership, which is a wholly owned subsidiary of PRI.
As a result of the recent updates described in this newsletter, PRI created two new special purpose legal entities for the JWPP2 and JWPP3. JWPP2 is now owned by Jenner 2 Limited Partnership, and JWPP3 is now owned by Jenner 3 Limited Partnership. The JWPP, JWPP2 and JWPP3 continue to be wholly owned by Jenner Wind Limited Partnership.
An updated organization chart is shown on the right.
Image shows generic wind turbines, not the Goldwind 4.2MW turbine.
WIND POWER PROJECTS
JENNER WIND POWER PROJECTS
Power Corporation of Canada
Power Energy Corporation
Potentia Renewables
Inc. (PRI)
Jenner Wind Limited
Partnership
Power Corporation of Canada
Power Energy Corporation
Potentia Renewables
Inc. (PRI)
JWPP
JWPPE
Jenner 1 Limited Partnership
Jenner 2 Limited Partnership
Jenner 3 Limited Partnership
JWPP
JWPP2
JWPP3
Jenner Wind Limited Partnership
BEFORE AFTER
COMPONENT
Previous Turbine for JWPPE
New Turbine for JWPP2
New Turbine for JWPP3
CHANGESGOLDWIND
3.4 MWGOLDWIND
4.2 MWGOLDWIND
4.2 MW
Total Proposed Project Nameplate Capacity 180.2 MW 71.4 MW 109.2 MW Slight change to total nameplate
capacity for both projectsTurbine Nameplate Capacity 3.4 MW 4.2 MW 4.2 MW Change in generation capacity
Number of Turbines 53 17 26 Reduced number of turbines
Tower Hub Height 110 m 110 m 110 m None
Rotor Diameter 137 m 155 m 155 m Increased rotor diameter
Number of Blades 3 3 3 None
Rotational Speed 5.2 – 13.2 rpm 6 – 10 rpm 6 – 10 rpm Change in rotational speed
Cut-In Wind Speed* 2.5 m/s 2.5 m/s 2.5 m/s None
Cut-Out Wind Speed** 22.0 m/s 26.0 m/s 26.0 m/s Increase in cut-out speed
* Cut-in wind speed is the minimum wind speed where the turbine blades begin to rotate. **Cut-out speed is the speed that the turbine blades are brought to rest to avoid damage from high winds.
Table 1: Comparison of Turbine Specifications
TURBINE MODEL CHANGEWe’ve changed the turbine model to improve the financial competitiveness of the projects and to ensure that we are using the most recent commercially-available technology. Both JWPP2 and JWPP3 will now use the Goldwind 4.2 MW turbine which has similar characteristics to the previous Goldwind 3.4 MW turbine. The Goldwind 4.2 MW has a higher nameplate capacity but the tower hub height is the same as the Goldwind 3.4 MW. The Goldwind 4.2 MW turbine is also being used at the JWPP. The Goldwind 4.2 MW turbine can operate up to 4.3 MW under specific conditions. A comparison table of the current and previous turbine models is below.
The Goldwind 4.2 MW turbine has the same noise characteristics operating at 4.2 MW or 4.3 MW. We have completed noise modelling and determined that the new turbine, in combination with other noise sources (including the JWPP turbines and substation) complies with AUC Rule 012: Noise Control. The figures included with this newsletter show the updated sound contours using the Goldwind 4.2 MW turbines with a hub height of 110 metres and a rotor diameter of 155 metres (see Map insert). Additional details for each residence within 1.5 kilometres of the JWPP2 and JWPP3 are available upon request.
PAGE 2 JENNER WIND POWER PROJECTSJULY 2019 • NEWSLETTER
AESO RENEWABLE ELECTRICITY PROGRAM (REP)In December 2018, the AESO completed Round 3 of the REP. Three projects, totalling 400 MW of proposed generation capacity,were each selected for 20-year renewable energy support agreements. The JWPP2 (71.4 MW) was among the projects selected for a contract. The weighted average price in REP Round 3 was approximately $40/MWh. More information on the AESO REP can befound at: https://www.aeso.ca/market/renewable-electricity-program/.
The JWPP3 was not selected for an AESO REP contract, but we are currently reviewing other power purchase opportunities and selling power directly to the Alberta power pool or to a credible third-party.
DECOMMISSIONING AND RECLAMATIONIn September 2018, Alberta Environment and Parks issued the Conservation and Reclamation Directive for Renewable Energy Operations. The JWPP2 and JWPP3 will follow the requirements outlined in this document for decommissioning plans to reclaim land to equivalent land capability both following construction and at the end of the project’s life.
• Creation of up to 300 construction and 5-15 permanent local jobs in operations and maintenance;
• Contract opportunities during construction in excavation and civil works, aggregate supply, etc.;
• Contract opportunities for local businesses in snow clearing, road maintenance, fencing, reclamation, etc.
• Increased local spending on goods and services during the development, construction, and operational phases;
• Property tax payments;
• Landowner lease payments; and
• Community funding commitments throughout the operation of the projects
LOCAL BENEFITSThe JWPP2 and JWPP3 will benefit the local community in a variety of ways, including the following:
LAYOUT UPDATEFor the JWPP2 and JWPP3, we have changed to a new turbine model with a higher nameplate capacity. Due to this change in turbine model, there will be an overall reduction in the number of turbines and the amount of infrastructure required for the JWPP2 and JWPP3. JWPP2 has a nameplate capacity of 71.4 MW and was selected for a REP contract. JWPP3 has a nameplate capacity of up to 109.2 MW and does not have a REP contract. Four turbines that were removed from the JWPP have been moved into JWPP3. The JWPP2 will have 17 turbines, and the JWPP3 will have 26 turbines, bringing the total number of turbines for both projects to 43 instead of 53. The change in turbine model reduces the overall project footprint and the potential impact to the land and environment.
The new layout has been modified in response to stakeholder feedback, environmental constraints, wind resource, and the new turbine model. We are updating our environmental reports and they will be submitted to Alberta Environment and Parks. A few turbines and infrastructure (i.e., access roads and collector lines) were added, removed, or moved within 500 metres of their previous location. Updated shadow flicker and viewscapes of the new turbines and turbine layout are shown on the Map inserts. The Map inserts include the
turbines from the JWPP to provide you with a complete picture of the overall development.
The JWPP2 and JWPP3 will share the Halsbury Substation and the 949L transmission line with the JWPP. The transmission line and substation have already received approval from the AUC. We will be seeking a Special Areas Board (SAB) Development Permit for the JWPP2 and the JWPP3.
Goldwind 2.5 MW turbines, Rattlesnake Wind Farm, TX, USA
PAGE 3JULY 2019 • NEWSLETTERJENNER WIND POWER PROJECTS
JWPP3 SCHEDULETIMELINE PROJECT MILESTONE
Consultation on JWPP2 amendmentsQ2 2019
Q4 2019 Detailed engineering and procurementExpected AUC approvalQ1 2020
Q1 2020 Site mobilization and construction start
Q2 2021 Commercial operation
Submit application to the AUCQ3 2019
Schedule subject to change. Schedule subject to change.
TIMELINE PROJECT MILESTONEConsultation on JWPP3 amendmentsQ2 2019
Q4 2019 Detailed engineering and procurementExpected AUC approvalQ1 2020
Q1 2020 Site mobilization and construction start
Q4 2021 Commercial operation
Submit application to the AUCQ3 2019
JWPP2 SCHEDULE
COMPONENT
Previous Turbine for JWPPE
New Turbine for JWPP2
New Turbine for JWPP3
CHANGESGOLDWIND
3.4 MWGOLDWIND
4.2 MWGOLDWIND
4.2 MW
Total Proposed Project Nameplate Capacity 180.2 MW 71.4 MW 109.2 MW Slight change to total nameplate
capacity for both projectsTurbine Nameplate Capacity 3.4 MW 4.2 MW 4.2 MW Change in generation capacity
Number of Turbines 53 17 26 Reduced number of turbines
Tower Hub Height 110 m 110 m 110 m None
Rotor Diameter 137 m 155 m 155 m Increased rotor diameter
Number of Blades 3 3 3 None
Rotational Speed 5.2 – 13.2 rpm 6 – 10 rpm 6 – 10 rpm Change in rotational speed
Cut-In Wind Speed* 2.5 m/s 2.5 m/s 2.5 m/s None
Cut-Out Wind Speed** 22.0 m/s 26.0 m/s 26.0 m/s Increase in cut-out speed
* Cut-in wind speed is the minimum wind speed where the turbine blades begin to rotate. **Cut-out speed is the speed that the turbine blades are brought to rest to avoid damage from high winds.
Table 1: Comparison of Turbine Specifications
TURBINE MODEL CHANGEWe’ve changed the turbine model to improve the financial competitiveness of the projects and to ensure that we are using the most recent commercially-available technology. Both JWPP2 and JWPP3 will now use the Goldwind 4.2 MW turbine which has similar characteristics to the previous Goldwind 3.4 MW turbine. The Goldwind 4.2 MW has a higher nameplate capacity but the tower hub height is the same as the Goldwind 3.4 MW. The Goldwind 4.2 MW turbine is also being used at the JWPP. The Goldwind 4.2 MW turbine can operate up to 4.3 MW under specific conditions. A comparison table of the current and previous turbine models is below.
The Goldwind 4.2 MW turbine has the same noise characteristics operating at 4.2 MW or 4.3 MW. We have completed noise modelling and determined that the new turbine, in combination with other noise sources (including the JWPP turbines and substation) complies with AUC Rule 012: Noise Control. The figures included with this newsletter show the updated sound contours using the Goldwind 4.2 MW turbines with a hub height of 110 metres and a rotor diameter of 155 metres (see Map insert). Additional details for each residence within 1.5 kilometres of the JWPP2 and JWPP3 are available upon request.
PAGE 2 JENNER WIND POWER PROJECTSJULY 2019 • NEWSLETTER
AESO RENEWABLE ELECTRICITY PROGRAM (REP)In December 2018, the AESO completed Round 3 of the REP. Three projects, totalling 400 MW of proposed generation capacity,were each selected for 20-year renewable energy support agreements. The JWPP2 (71.4 MW) was among the projects selected for a contract. The weighted average price in REP Round 3 was approximately $40/MWh. More information on the AESO REP can befound at: https://www.aeso.ca/market/renewable-electricity-program/.
The JWPP3 was not selected for an AESO REP contract, but we are currently reviewing other power purchase opportunities and selling power directly to the Alberta power pool or to a credible third-party.
DECOMMISSIONING AND RECLAMATIONIn September 2018, Alberta Environment and Parks issued the Conservation and Reclamation Directive for Renewable Energy Operations. The JWPP2 and JWPP3 will follow the requirements outlined in this document for decommissioning plans to reclaim land to equivalent land capability both following construction and at the end of the project’s life.
• Creation of up to 300 construction and 5-15 permanent local jobs in operations and maintenance;
• Contract opportunities during construction in excavation and civil works, aggregate supply, etc.;
• Contract opportunities for local businesses in snow clearing, road maintenance, fencing, reclamation, etc.
• Increased local spending on goods and services during the development, construction, and operational phases;
• Property tax payments;
• Landowner lease payments; and
• Community funding commitments throughout the operation of the projects
LOCAL BENEFITSThe JWPP2 and JWPP3 will benefit the local community in a variety of ways, including the following:
LAYOUT UPDATEFor the JWPP2 and JWPP3, we have changed to a new turbine model with a higher nameplate capacity. Due to this change in turbine model, there will be an overall reduction in the number of turbines and the amount of infrastructure required for the JWPP2 and JWPP3. JWPP2 has a nameplate capacity of 71.4 MW and was selected for a REP contract. JWPP3 has a nameplate capacity of up to 109.2 MW and does not have a REP contract. Four turbines that were removed from the JWPP have been moved into JWPP3. The JWPP2 will have 17 turbines, and the JWPP3 will have 26 turbines, bringing the total number of turbines for both projects to 43 instead of 53. The change in turbine model reduces the overall project footprint and the potential impact to the land and environment.
The new layout has been modified in response to stakeholder feedback, environmental constraints, wind resource, and the new turbine model. We are updating our environmental reports and they will be submitted to Alberta Environment and Parks. A few turbines and infrastructure (i.e., access roads and collector lines) were added, removed, or moved within 500 metres of their previous location. Updated shadow flicker and viewscapes of the new turbines and turbine layout are shown on the Map inserts. The Map inserts include the
turbines from the JWPP to provide you with a complete picture of the overall development.
The JWPP2 and JWPP3 will share the Halsbury Substation and the 949L transmission line with the JWPP. The transmission line and substation have already received approval from the AUC. We will be seeking a Special Areas Board (SAB) Development Permit for the JWPP2 and the JWPP3.
Goldwind 2.5 MW turbines, Rattlesnake Wind Farm, TX, USA
PAGE 3JULY 2019 • NEWSLETTERJENNER WIND POWER PROJECTS
JWPP3 SCHEDULETIMELINE PROJECT MILESTONE
Consultation on JWPP2 amendmentsQ2 2019
Q4 2019 Detailed engineering and procurementExpected AUC approvalQ1 2020
Q1 2020 Site mobilization and construction start
Q2 2021 Commercial operation
Submit application to the AUCQ3 2019
Schedule subject to change. Schedule subject to change.
TIMELINE PROJECT MILESTONEConsultation on JWPP3 amendmentsQ2 2019
Q4 2019 Detailed engineering and procurementExpected AUC approvalQ1 2020
Q1 2020 Site mobilization and construction start
Q4 2021 Commercial operation
Submit application to the AUCQ3 2019
JWPP2 SCHEDULE
• COMMUNITY FUND AND INVOLVEMENT
• AESO RENEWABLE ELECTRICITY PROGRAM
• PROJECT & LAYOUT UPDATE
• TURBINE MODEL CHANGE
• DECOMMISSIONING & RECLAMATION
• UPDATED SCHEDULE
• UPDATED MAP WITH NOISE CONTOUR
• LOCAL BENEFITS
• OWNERSHIP
• VIEWSCAPES
IN THIS NEWSLETTER,YOU WILL FIND INFORMATION ON:
PROJECT UPDATESOn December 17, 2018, a portion of the JWPPE (71.4 MW) was selected for a contract under Round 3 of the Alberta Electric System Operator (AESO) Renewable Electricity Program (REP). As a result of the AESO REP 3 contract, the JWPPE will be split into two phases – the Jenner Wind Power Project 2 (JWPP2) and Jenner Wind Power Project 3 (JWPP3). JWPP2 has a nameplate capacity of 71.4 MW and is contracted under the REP. JWPP3 has a nameplate capacity of up to 109.2 MW and does not have a REP contract. Combined, the two phases will be referred to as the JWPPE in this newsletter and in the attached Map.
The original design of the JWPPE proposed 53 wind turbine locations and an application was submitted to the Alberta Utilities Commission (AUC) in 2017. PRI put the application into abeyance (on hold) in January 2018 to address stakeholder concerns. The existing JWPPE AUC application will now be amended and split into two applications; a 71.4 MW application for the JWPP2, and a 109.2 MW application for the JWPP3. Both applications will also reflect changes to turbine technology, slight adjustments to turbine locations and other minor modifications.
INTRODUCTIONPotentia Renewables Inc. (PRI) would like to thank you for your continued interest in the Jenner Wind Power Project Expansion (JWPPE). We greatly value our relationship with the local community, and we are committed to engaging and consulting with stakeholders.
You recently received a newsletter about the Jenner Wind Power Project (JWPP) and are receiving this JWPPE newsletter because you live on or own land near the JWPPE and we want to provide you with an update on the changes to this project.
JULY 2019 • NEWSLETTER
PAGE 1JULY 2019 • NEWSLETTER
PUBLIC CONSULTATION AND PROVIDING YOUR INPUTWe wish to minimize potential negative impacts on the environment and the community from the JWPP2 and JWPP3. PRI will continue discussions with local landowners and stakeholders to develop the JWPP2 and JWPP3 in a way that respects community members’ needs and reduces environmental impacts.
We will continue to engage with occupants, residents, and landowners within 800 metres of the JWPP2 and JWPP3 to gather input through one-on-one consultation. During the one-on-one consultation process, we will document the information you provide and attempt to address any questions or concerns you may have about the projects. We would love to hear from you. Please contact us at the information provided below.
Privacy Commitment: PRI is committed to protecting your privacy. Collected personal information will be protected under the provincial Personal Information Protection Act. As part of the regulatory process for new generation projects, PRI may be required to provide your personal information to Alberta Utilities Commission (AUC). For more information about how PRI protects your personal information, visit our website at www.jennerwind.com or contact us directly via phone toll-free at 1-833-536-6371.
CONTACT US
COMMUNITY FUND AND INVOLVEMENT We’re pleased to announce that for a third consecutive year, we sponsored the Buffalo Rodeo and the Jenner Rodeo. We’re always interested in supporting other local events and activities in the community. Please email your sponsorship and donation requests to: [email protected] for consideration.
For additional information about the JWPP2 and JWPP3 or to arrange a personal consultation, please contact our consultation agent from Scott Land & Lease:
Jason PigeonSenior Consultation Agent
P: 403-473-6661E: [email protected]
For more information about Potentia Renewables Inc. (PRI) and the JWPP2 and JWPP3, please visit: www.jennerwind.com
Potentia Renewables Inc. 200 Wellington Street WestSuite 1102, Toronto, ON M5V 3C7
P: 1-833-536-6371 E: [email protected]
OWNERSHIPThe JWPP2 and JWPP3 are currently owned by Jenner Wind Limited Partnership, which is a wholly owned subsidiary of PRI.
As a result of the recent updates described in this newsletter, PRI created two new special purpose legal entities for the JWPP2 and JWPP3. JWPP2 is now owned by Jenner 2 Limited Partnership, and JWPP3 is now owned by Jenner 3 Limited Partnership. The JWPP, JWPP2 and JWPP3 continue to be wholly owned by Jenner Wind Limited Partnership.
An updated organization chart is shown on the right.
Image shows generic wind turbines, not the Goldwind 4.2MW turbine.
WIND POWER PROJECTS
JENNER WIND POWER PROJECTS
Power Corporation of Canada
Power Energy Corporation
Potentia Renewables
Inc. (PRI)
Jenner Wind Limited
Partnership
Power Corporation of Canada
Power Energy Corporation
Potentia Renewables
Inc. (PRI)
JWPP
JWPPE
Jenner 1 Limited Partnership
Jenner 2 Limited Partnership
Jenner 3 Limited Partnership
JWPP
JWPP2
JWPP3
Jenner Wind Limited Partnership
BEFORE AFTER
Author: J. McRaeReviewer: S. SchnickApprover: R. Istchenko
!²³
!²³!²³
²³ ²³
²³
!²³
!²³!²³!²³
")
!!
!!
!!
!!
!!
!!
!!
!!
!!
!!
!!
!!
!!
!!
!!
!!
!!
!!
!!
!!
!!
!!
!!
!!
!!
!
!
!
!
!
!
!
!
!!!!
!!
!!!!
!!
!! !!
!!
!!
!!
!!
!!
!!
!!!! !!
!!!!
!! !!!!
!!
!!
!!
!!
!!
!!
!! !!
!! !!
!!!!
!! !!!!
!!
!!!!
!!
!!!!
!!
!!
!!
!!
!!!!
!!!!
!!!!!!
!!!!
!!
!!
!!!!
!!
!!
!!!!
!!
!!
!!
!!
!!!!
!!!!!!
!!
²³
²³²³
²³ ²³
²³
²³
²³²³²³
²³
²³²³
²³ ²³
²³
²³
²³²³²³
²³²³
²³²³²³
²³²³²³ ²³
²³²³
²³²³
²³
²³
²³²³
²³
²³
²³
²³²³
²³
²³
²³
²³
²³
²³
²³
²³
²³
²³
²³
²³²³
²³
²³²³
²³
²³²³
²³
²³
²³
²³²³
²³
²³
³³
³
³³
³
³³
!(
!(
!(
!(
#*
#*
#*
#*
#*
#*
#*
#*#*#*#*#*#*#* #*
#*#*
Halsbury 306S Substation
Primary Laydown Area
Secondary Laydown Area
Jenner 275S Substation
Location 4
Location 3
Location 1
Location 2
Township Road 212
Rang
e Roa
d 91
Township Road 220A
Township Road 204
Township Road 210
TownshipRoad 215
Rang
e Roa
d 90
Township Road 203A
Township Road 205A
TownshipRoad 220B
Township Road 214
Township Road 222
Range Road 103
Rang
e Roa
d 75
Rang
e Roa
d 92
Range Road 84A
Rang
e Roa
d 80
Rang
e Roa
d 82
UV884
UV555
UV884
29
35 36
40
4142
49 51
5459
747576
77 788184
86 8889
91
929394
95
96
2 4
7 813 15
19 2022 2325
262831
3337
47
1
356 910
1114171821
24
3032 3438
39
55 5758 61
6467
7172
828385
87
RGE 9 W4M
RGE 9 W4M
RGE 8 W4M
RGE 7 W4MRGE 8 W4M
RGE 7 W4M
TWP 2
0TW
P 22
TWP 2
1
TWP 2
1TW
P 22
TWP 2
0
±0 1 2 3 4 5 60.5
Kilometres
Jenner Wind Power Project 2 (JWPP2) - 71.4 MWJenner Wind Power Project 3 (JWPP3) - 109.2 MW
Owners:
Projects:
Figure Description:
Jenner 2 Limited PartnershipJenner 3 Limited Partnership Project Lands
!! Current JWPP Turbine Location!! Proposed JWPP2 Turbine Location!! Proposed JWPP3 Turbine Location 1
Collector System (34.5 kV)Underground Collector SystemOverhead Double Circuit Collector sharedbetween JWPP and JWPP3
JWPP Overhead CollectorSingle CircuitDouble Circuit
JWPP2 Overhead CollectorSingle CircuitDouble Circuit
JWPP3 Overhead CollectorSingle CircuitDouble Circuit
Access RoadsNew RoadUpgraded Road
Other InfrastructureAUC Approved Halsbury 306S SubstationLocation 2
Proposed Permanent Laydown Area includingO&M Building Location
Proposed Temporary Laydown Area 2
Numbered HighwayMunicipal RoadLocal Road
")Existing Jenner 275S Substation Location (not toscale) 2
! ! Approved 949L Transmission Line (240 kV) 2
Cumulative Nighttime Permissible Sound LevelContour (40 dBA) 3
#* Third-party Facility (Sound Source)²³ Residence
Township Line
J J!( Viewscape Location and Field of ViewShadow Flicker (Expected Hours per Year) 4
²³ No shadow flicker expected!²³ Up to 5 hours!²³ Between 5 hours and 10 hours
This layout provides an overview of the JWPP2 and JWPP3 projects. This layout also includes the Jenner Wind Power Project (JWPP) to demonstrate the cumulative impact of all projects.
Legend
1 Turbines 74, 77, 84, and 89 and their associated infrastructure havebeen moved from JWPP to JWPP3.2 Infrastructure that will be shared with the JWPP.3 Cumulative nighttime permissible sound level contour considers theJWPP, JWPP2, JWPP3 and third-party infrastructure.4 Shadow Flicker considers JWPP, JWPP2 and JWPP3.
Scale: 1:125,000 at 8.5" × 11"Projection: UTM Zone 12NDatum: NAD 83
Date: 2019-07-05Version: 9Prepared By: WSP
"
"
"
"
"
"
"
"
")
JWPP2 & JWPP3CalgaryBrooks Regina
Cranbrook
Swift CurrentMoose JawMedicine Hat
Lethbridge
Location:
2
VIEWSCAPEWe’ve provided updated viewscapes that include the JWPP, JWPP2 and JWPP3 below. These viewscapes show what the projects combined (303 MW) will look like. The viewscapes are taken from four locations around the JWPP, JWPP2 and JWPP3. Higher resolution images are available upon request.
LOCATION 1: TOWN OF JENNER LOOKING NORTHEAST
JULY 2019 • NEWSLETTER JENNER WIND POWER PROJECTS
JWPP
ON
LY12
2.4
MW
JWPP
+ J
WPP
2 +
JW
PP3
303
MW
WIND POWER PROJECTS
LOCATION 2: HIGHWAY 555 LOOKING WEST (NEAR TOWNSHIP ROAD 21-2)
JULY 2019 • NEWSLETTERJENNER WIND POWER PROJECTS
JWPP
ON
LY
122.
4 M
WVIEWSCAPEWe’ve provided updated viewscapes that include the JWPP, JWPP2 and JWPP3 below. These viewscapes show what the projects combined (303 MW) will look like. The viewscapes are taken from four locations around the JWPP, JWPP2 and JWPP3. Higher resolution images are available upon request.
JWPP
+ J
WPP
2 +
JW
PP3
303
MW
WIND POWER PROJECTS
LOCATION 3: JENNER HUTTERITE COLONY LOOKING EAST
JULY 2019 • NEWSLETTERJENNER WIND POWER PROJECTS
JWPP
ON
LY12
2.4
MW
VIEWSCAPEWe’ve provided updated viewscapes that include the JWPP, JWPP2 and JWPP3 below. These viewscapes show what the projects combined (303 MW) will look like. The viewscapes are taken from four locations around the JWPP, JWPP2 and JWPP3. Higher resolution images are available upon request.
JWPP
+ J
WPP
2 +
JW
PP3
303
MW
WIND POWER PROJECTS
LOCATION 4: JENNER CAMPGROUND LOOKING SOUTH
JULY 2019 • NEWSLETTERJENNER WIND POWER PROJECTS
JWPP
ON
LY12
2.4
MW
VIEWSCAPEWe’ve provided updated viewscapes that include the JWPP, JWPP2 and JWPP3 below. These viewscapes show what the projects combined (303 MW) will look like. The viewscapes are taken from four locations around the JWPP, JWPP2 and JWPP3. Higher resolution images are available upon request.
JWPP
+ J
WPP
2 +
JW
PP3
303
MW
WIND POWER PROJECTS
www.auc.ab.caUpdated January 2019
Step 5: Consultation and negotiation (if applicable)*The Commission supports ongoing efforts to reach a positive outcome for the applicant and all affected parties. The Commission encourages the applicant and those who have filed submissions to continue to attempt to resolve any outstanding issues. If all concerns can be satisfactorily resolved this may eliminate the need for a formal hearing. However, if there continues to be unresolved issues, those matters will typically be addressed at an AUC hearing.
The Commission will issue a notice of hearing if a person or business with standing continues to have legitimate unresolved concerns with the application. The notice of hearing will provide a hearing date and location in addition to a process schedule. The AUC conducts public hearings in its hearing rooms in Edmonton and Calgary and, where suitable venues exist, in communities closer to the project area.
Step 6: The public hearing process*The public hearing process provides an opportunity for those who have been unable to resolve their concerns with the applicant and have made a filing, to express their views directly to a panel of Commission members.
An AUC hearing is a formal, evidence-based, court-like proceeding. The public can attend the hearing in-person or listen in to hearings online through the AUC’s website.
Participants in a hearing can either represent themselves or be represented by a lawyer. In addition, participants may hire experts to assist in preparing and presenting evidence to support their position.
Persons who hire a lawyer or technical experts must be aware that while reimbursement for the costs of legal and technical assistance is available under Rule 009, recovery of costs is subject to the Commission assessing the value of the contribution provided by the lawyer and technical experts. People with similar interests
Contact information:
and positions are expected to work together to ensure that any expenditures for legal or technical assistance are minimized and costs are not duplicated.
Step 7: The decisionThe AUC generally issues a written decision approving, with or without conditions, or denying the application(s) that were considered in a hearing no more than 90 days after the hearing record is closed. AUC decision reports summarize the Commission’s findings and explain its reasons for those findings.
All AUC decision reports are available to any member of the public on the Commission’s website or by obtaining a printed copy from the AUC.
Step 8: Opportunity to appealA dissatisfied participant may file a permission to appeal in the Court of Appeal of Alberta within 30 days from the date the decision is issued.
An applicant or participant who is dissatisfied with the Commission’s decision can request the Commission to review its decision within 60 days, from the date the decision is issued, as specified in Rule 016: Review and Variance of Commission Decisions, which outlines the limited grounds or review.
Step 9: Construction, operation and complianceAn applicant that receives approval to build and operate a facility from the Commission must adhere to any conditions that were set out in that approval. If concerns about compliance with approval conditions and post-construction operations cannot be resolved with the applicant, they can be brought to the AUC’s attention for review.
Public involvement in needs or facilities applications
The Alberta Utilities Commission is committed to ensuring that Albertans whose rights may be directly and adversely affected by a utility
development project are informed of the application and have the opportunity to have
their concerns heard, understood and considered. If you believe you may be directly or adversely affected, you can become involved in the AUC’s
application and review process.
It is the AUC’s goal to ensure that you understand its application and hearing processes, and your opportunities
for involvement in proceedings to consider utility development applications. For those interested in having an AUC staff member further explain the review process for an application or answer questions you may have about your involvement in utility development proceedings, please
contact us so that we can answer those questions directly or schedule a formal information session with you. The
“Have your say about a utility project” page on the AUC’s website will also provide you with further details which
could assist you in understanding the process and having your say in a utility development proceeding.
This brochure provides general information about public involvement in needs and utility facilities applications before
the AUC. Specific participation opportunities and requirements may differ depending on the type of application.
The Alberta Utilities Commission is an independent, quasi-judicial agency of the government of Alberta that
ensures the delivery of Alberta’s utility service takes place in a manner that is fair, responsible and in the public interest.
The AUC regulates the utilities sector, natural gas and electricity market to protect social, economic and
environmental interests of Alberta, where competitive market forces do not.
Phone: 310-4AUC (in Alberta)1-833-511-4AUC (outside Alberta)
Email: [email protected]
Information session
*Opportunity for public involvement
The AUC’s regulatory role in needs and facilities applications
The AUC uses an established process to review applications to protect social, economic and environmental interests of Alberta. It is also committed to ensuring that Albertans whose rights may be directly and adversely affected by a project have an opportunity to have their concerns heard, understood and considered.
Approvals from the AUC are required for the construction, operation, alteration and decommissioning of transmission lines and electric substations. These include: • Approval of the need for transmission upgrades.• Approval of the route and location of transmission facilities.
Sometimes a needs application is considered together with a facilities application in a single hearing; sometimes separate hearings may be held to consider each application. Approvals from the AUC are also required for power generation and gas utility pipeline facilities in Alberta.
Application process
Step 1: Public consultation prior to application
Step 2: Application filed to the AUC
Step 3: Public notice
Step 4: Public submissions to the AUC
Step 5: Consultation and negotiation
Step 6: The public hearing process
Step 7: The decision
Step 8: Opportunity to appeal
Step 9: Construction, operation and compliance
Step 1: Public consultation prior to application*Prior to filing an application with the AUC for the approval of a proposed utility development, the applicant must engage in a public consultation program in the area of the proposed project, so that concerns may be raised, addressed and if possible, resolved.
The application guidelines and requirements for facility applications can be found in Rule 007 and Rule 020.
Potentially affected parties are strongly encouraged to participate in the initial public consultation, as early involvement in discussions with an applicant may lead to greater influence on project planning and what is submitted to the AUC for approval.
The Alberta Electric System Operator will notify potentially affected stakeholders on the need for transmission development.
Step 2: Application filed to the AUCWhen the participant involvement requirements have been completed, the applicant files its application with the AUC through the eFiling System.
The application is then reviewed to ensure the required information in the applicable Commission rules is included. If the required information is not provided, the AUC may choose to close the application or to request more information from the applicant.
In the application, considerations should be made for the issues which came up during the public consultation and amendments made to the proposal. Any unresolved objections or concerns which arise during the public consultation must be identified in the application.
Step 3: Public noticeThe AUC generally issues a notice by mail directly to those who live, operate a business or occupy land in the project area who may be affected by the Commission’s decision of the proposed project. The notice for larger facility projects with potentially greater impacts may also be published in local newspapers.
The notice will specify a submission deadline. The information required by this deadline is general in nature as outlined in Step 4. For those participating in the AUC review process, referred to as a proceeding, additional opportunities to provide evidence and additional information will arise after this deadline.
Step 4: Public submissions to the AUC*Anyone with unresolved objections or concerns about the application can file a written submission to the AUC, preferably through the eFiling System, to have their concerns considered by the Commission before making a decision on the application. Your submission must include your contact information, where you reside or own property in relation to the proposed facility, your concern or interest in the application, an explanation of your position and what you feel the AUC should decide. Please be aware that any information and materials provided as part of an AUC
proceeding, except information granted confidentiality in advance, will become part of the public record and will be available through the eFiling System. While the AUC has the authority to treat some types of information as confidential, such treatment is rare and only available under limited circumstances to ensure that the AUC’s process is open and transparent.
Based on what is filed, the Commission will determine if those who file submissions have demonstrated that they have rights that may be directly and adversely affected and, if so, give them “standing”. Standing is the right to participate in the proceeding, which is the full review process and may include an oral hearing and is necessary to continue involvement as an intervener in the proceeding.
AUC eFiling SystemThe eFiling System is the tool that the AUC uses to manage applications and submissions in its proceeding-based review. The eFiling System gives access to all public documents associated with an application and is the way to provide your input to the AUC and monitor the related proceeding filings. Those who do not have access to the internet can send submissions, evidence and other material by mail or fax and the AUC will upload the submission on their behalf.
Cost assistance A person determined by the Commission to be a local intervener, can apply for reimbursement of reasonable costs. Details regarding recovery of participants’ costs are described in AUC Rule 009: Rules on Local Intervener Costs.www.auc.ab.ca *Opportunity for public involvement