JMB MEETING UPDATES19th January 2019
STATUS UPDATE
NO UPGRADING ITEM STATUS DATELINE
Other upgrading;
Badminton/Basketball court
3. Ventilation – Installation of Exhaust Fan Completed -
4. Benches Completed -
Signages
5. Tower A exit to Jalan Laksamana Boulevard- To add exit signage
Completed -
6. Installation of 2nos of Electric Charging Point for hybrid car
Completed -
NO UPGRADING ITEM STATUS DATELINE
Suites
1. Propose Suites Upgrading – Installation of Big 10 ft fan
Completed
2. Propose Suites Upgrading - Loading/unloading bay path way
Awarded. Included in signages contract.
-
STATUS UPDATE
13. WIFI Service in Common Area and Lifts Others are completed.Pending installation in Cabana Lift only.
June 2018
10. WIFI Service in Common Area and Lifts Completed. Aug 2018
11. Water dispenser Delivered. -
12. Mosquito repellant bulb Delivered. July 2018
13. Missing Links Roof at E-deck Completed. Jan 2019
14. Child care and multipurpose room furnishings Pending handover to JMB. 22 Jan 2019
15. Upgrading of fencing 100% Completion with additional works added. Pending small openings.
Feb 2019
16. Signages Upgrading Awarded – 90 % complete 31 Jan 2019
17. Security Upgrading Awarded. 31 Jan 2019
NO UPGRADING ITEM STATUS DATELINE
Changing Room
7. Installation of Changing Room Fittings(hanger, towel racks and locker)
Completed. July 2018
9. Benches Completed. -
OFFICE TOWER SIGNAGE
To be installed in 3rd week of January 2019.
FIT-OUT WORKS
• Items included under this project are as follows;No. Location Item
1. Fit-out for childcare centre • Indoor Play area• Reading nook(Please refer to Perspective)
2. Cabana Lobby • Arm chair and coffee table
3. Games Room • Storage Cabinet to be fixed
4. Multipurpose Room / Function Room (E-deck Tower A & B)
• Foldable rectangular table• Block Curtain• Additional Banquet Chair
5. Pantry at Multipurpose / Function Room (Sky-lounge Tower A, B & Suites)
• Cabinet and wash basin
6. Mailroom at Suites • To provide metal strips at corner to avoid crack/damages to the glass.
FIT-OUT FOR CHILDCARE CENTRE Proposal for Childcare Fit-out concept – COMPLETED. HANDOVER TO JMB ON 3RD WEEK OF JAN 2019.
Actual On-Site Images
OTHER UPGRADING;No. ITEMS/UPGRADES STATUS1. Cleaning of external Facade Yes Tower started. External perimeter
to be conducted in November
2018.2. E-Deck
2.1 Door upgrade Yes Doors delivered on 14th
September 2018. Installation
pending BOMBA certificate to
obtained by 14th October 2018
(1month)
Doors currently pending
installation by workers. Target
installation on 4th Week of Jan 19.
OTHER UPGRADING;No. ITEMS/UPGRADES STATUS
SUITES3. Car Park Gantry repositioning Yes Awarded. Completed.4. Loading Bay Pending award.
5. Mailroom – mirror to be changed
to stainless steel
Yes Completed
6. Wheelchair friendly at entrance Yes Completed.7. Fire Doors to include vision panel
(glass) (Edeck)
Yes Same as no. 2
8. Car Stopper to be painted to
prevent tripping near lift
entrance.
Completed.
OTHER UPGRADING;No. ITEMS/UPGRADES STATUS
RESIDENCES
14. Fire Doors to include vision panel
(glass) (Edeck)
Yes Same as No.3
15. Corridor to badminton court – Better
lighting and signages required
Yes Completed.
COMMON AREA DEFECTS UPDATE
Note : The defects lodged into the Novade will be deleted/rejected due to the following reason : (1) Duplicate case (2) Lodged without photo evidence (3) Lodged with wrongly location.
OVERALL PROGRESS
CLOSED/ COMPLETED
1878(83.7%)
WIP/ NEW
367(16.3%)
PREVIOUS DEFFECT RECTIFICATION WORK PROGRESS
01 NOVEMBER 2018 - 30 NOVEMBER 2018
CLOSED/ COMPLETED
2027(86.7%)
WIP/ NEW
311(13.3%)
CURRENT DEFECTS RECTIFICATION WORK PROGRESS
01 DECEMBER 2018 - 31 DECEMBER 2018
PREVIOUS CURRENT PREVIOUS CURRENT PREVIOUS CURRENT PREVIOUS CURRENT PREVIOUS CURRENT PREVIOUS CURRENT PREVIOUS CURRENT PREVIOUS CURRENT PREVIOUS CURRENT PREVIOUS CURRENT
Nov-19 Dec-19 Nov-19 Dec-19 Nov-19 Dec-19 Nov-19 Dec-19 Nov-19 Dec-19 Nov-19 Dec-19 Nov-19 Dec-19 Nov-19 Dec-19 Nov-19 Dec-19 Nov-19 Dec-19
CLOSED/
COMPLETED250 255 603 620 190 206 282 307 21 21 439 446 21 27 47 120 25 25 1878 2027
WIP/ NEW 9 9 21 13 122 108 136 118 2 2 26 20 27 21 15 11 9 9 367 311
LODGED 259 264 624 633 312 314 418 425 23 23 465 466 48 48 62 131 34 34 2245 2338
DEFECTS RECTIFICATION WORK RECORD
DESCRIPTION
TEEGA TOWER
(OFFICE)TEEGA SUITE TOWER A TOWER B CABANA CAR PARK
CONDOMINIUM
E-DECKRETAIL
SERVICE
APARTMENT
E-DECK
TOTAL
DEFECTS
COMMON AREA DEFECTS UPDATE
Note : The defects lodged into the Novade will be deleted/rejected due to the following reason : (1) Duplicate case (2) Lodged without photo evidence (3) Lodged with wrongly location.
WORK IN PROGRESS BY AGING
PREVIOUS CURRENT PREVIOUS CURRENT PREVIOUS CURRENT PREVIOUS CURRENT PREVIOUS CURRENT PREVIOUS CURRENT PREVIOUS CURRENT PREVIOUS CURRENT PREVIOUS CURRENT PREVIOUS CURRENT
Nov-19 Dec-19 Nov-19 Dec-19 Nov-19 Dec-19 Nov-19 Dec-19 Nov-19 Dec-19 Nov-19 Dec-19 Nov-19 Dec-19 Nov-19 Dec-19 Nov-19 Dec-19 Nov-19 Dec-19
DEFECTS < 30
DAYS0 1 10 5 40 35 8 14 2 0 3 3 7 3 5 7 1 1 76 69
DEFECTS > 30
DAYS9 8 11 8 82 73 127 103 0 2 23 17 20 18 10 4 8 8 290 241
WORK IN PROGRESS (WIP) DEFECTS CATEGORY BY AGING
DEFECTS
AGING
TEEGA TOWER
(OFFICE)TEEGA SUITE TOWER A TOWER B CABANA CAR PARK
CONDOMINIUM
E-DECKRETAIL
SERVICE
APARTMENT
E-DECK
TOTAL
DEFECTS
COMMON AREA DEFECTS UPDATE
423
678
8681000
1208
1454
1671
1831 1878
2027
11631045
901810
742641
466343 367
311
0
500
1000
1500
2000
2500
Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18
NU
MB
ER
OF
DE
FE
CT
S
MONTH
COMMON AREA DEFECTS RECTIFICATION WORK PROGRESSMARCH 2018 - DECEMBER 2018
Completed/Closed Work In progress (WIP)
Variance
, σClosed :
217
WIP : -
175
Variance
, σClosed :
246
WIP : -
101
Variance
, σClosed :
160
WIP : -
123Variance
, σClosed :
208
WIP : -68
Variance
, σClosed :
132
WIP : -91
Variance
, σClosed :
190
WIP : -
144
Variance
, σClosed :
225
WIP : -
118
Variance
, σClosed :
149
WIP : -56
Variance
, σClosed :
47
WIP : 24
Defects / Month Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18
Completed/Closed 423 678 868 1000 1208 1454 1671 1831 1878 2027
Work In progress (WIP) 1163 1045 901 810 742 641 466 343 367 311
Closed/Completed Variance, s - 255 190 132 208 246 217 160 47 149
Work in Progress (WIP), s - -118 -144 -91 -68 -101 -175 -123 24 -56
ISKANDAR PUTERI CONNECTIVITYConnectivity – Current transport available in Puteri Harbour, Iskandar Puteri
FREE SHUTTLE SERVICE
• Complimentary shuttle service brought to you by UEM Sunrise & MediniIskandar Malaysia
• Current Status : 4 nos. of busses in operation.
• Timetable as per next page.
Note:-
• Timing for the public bus are base on the operator schedule (available in mobile apps HUGO)
ISKANDAR PUTERI BUS SCHEDULE
Note:-
• Timing for the public bus are base on the operator schedule (available in mobile apps HUGO)
ISKANDAR PUTERI BUS SCHEDULE
ISKANDAR PUTERI CONNECTIVITY• Proposed Route - Phase 2 Community Shuttle
M6/M7
Rumah Iskandar
Malaysia (RIM) –
Gelang Patah
Bukit Indah
Taman
Nusa Perdana
- Afinit Medini
- Somerset Medini
- 1 Medini
- Sunway Iskandar
- Sunway
International
School
- Imperia
- Teega
- Puteri Cove
- Ledang
Clubhouse
- Ujana
- Nusajaya Center
- Tesco
Iskandar Puteri Community
Shuttle Service
Route Operation Time
Route 1 (Morning & Evening only)
RIM - PHIFT
7:00am –7:00pm
Route 2 Edu City -PHIFT
Route 3(existing)
Terminal Larkin -PHIFT
6:30am –7:00pm
Route 4 Bukit Indah 6:45am –7:00pm
Note:-
• Awaiting permit approval from Land Public Transport Commission (SPAD) on the proposed route
ISKANDAR PUTERI CONNECTIVITYStarex Operation (3 nos)• Operation will start on 1st September 2018.• The trips will be increased from 4 trips per day to 6 trips per
day.• New time slot will be proposed as late as 10:30am from Teega
and 3:30pm from Jurong East• There will be 3 timing in the morning (Poster as per next
page)• Starex routing as follows;
TeegaEast
LedangJurong
East
ISKANDAR PUTERI CONNECTIVITY
BUS STOP IN FRONT OF TEEGA BUS STOP
1. Bus stop tensile roof completed.
2. Sitting area completed.
Proposed sitting design
TEEGA RETAIL LOTS
GROUND LEVEL
LOWER GROUND
Teega Handover Office
Tribus Café SUTL Sales Gallery
Note: 1. Occupied unit delineated in green2. Units in negotiation delineated in yellow3. Vacant unit delineated in red
SUTL-One Degree 15 Marina Puteri HarbourTarget to open: 1 October 2018
YSL FreshmartTarget to open: 1 December 2018The Tribus
Target to open: 1
December 2018