Engineers in Action. Joe Alvarez EIA Engineer. Building a better future for tomorrow. Kumurana Project status: Limestone Channels and abandoned mine sealing. Limestone Delivery. Channels:~358m tons Abandoned Mine:~135m tons. Limestone Channels. Limestone delivery - PowerPoint PPT Presentation
Citation preview
Joe AlvarezEIA EngineerKumurana Project status:Limestone Channels and abandoned mine sealingEngineers in ActionBuilding a better future for tomorrow
Limestone DeliveryChannels:~358m tonsAbandoned Mine:~135m tons
Limestone ChannelsLimestone deliveryRequired Volume for channles:2027m3
Amount of Limestone Delivered:~358 Metric tons for the channels [About 14% of the total limestone delivery]
Required:108m3Delivered: ~135m tonsRequired:213m3Delivered: ~262.5m tonsRequired:132m3Delivered: ~27m tonsLEGENDDelivery completed
Partial Delivery
No delivery
Required:348m3Delivered: ~67.5m tonsMap source EWB-OU
Limestone Channels ContdInstallationThe installation of limestone into the channels is pendingTaking advantage of trucksCommunity support to install the limestoneWater analysis coordination with CIMA and Universidad Tomas Frias
Limestone Channels ContdConstructions issuesProject issuesAccessibility issuesDistance [about 100miles/trip]Heavy Rain/HailWorking with the governmentBureaucracy at the governmentNo continuous of flow workBorrowed trucks
Accessibility issues
Rain
Bureaucracy
Abandoned Mine sealingLimestoneDelivered 108m3 of limestone delivery-completeLimestone installation is pendingOxidation pond90% completedSome improvements needed to finishInaccessible with a heavy equipment to continue digging and finish. [wetlands]Wall sealingConstruction starts when the worksite area becomes accessibleEstimated length of conclusion of the wall about 2-3 weeks