Engineers in Action. Joe Alvarez EIA Engineer. Building a better future for tomorrow. Kumurana Project status: Limestone Channels and abandoned mine sealing. Limestone Delivery. Channels:~358m tons Abandoned Mine:~135m tons. Limestone Channels. Limestone delivery - PowerPoint PPT Presentation

Citation preview

  • Joe AlvarezEIA EngineerKumurana Project status:Limestone Channels and abandoned mine sealingEngineers in ActionBuilding a better future for tomorrow

  • Limestone DeliveryChannels:~358m tonsAbandoned Mine:~135m tons

  • Limestone ChannelsLimestone deliveryRequired Volume for channles:2027m3

    Amount of Limestone Delivered:~358 Metric tons for the channels [About 14% of the total limestone delivery]

  • Required:108m3Delivered: ~135m tonsRequired:213m3Delivered: ~262.5m tonsRequired:132m3Delivered: ~27m tonsLEGENDDelivery completed

    Partial Delivery

    No delivery

    Required:348m3Delivered: ~67.5m tonsMap source EWB-OU

  • Limestone Channels ContdInstallationThe installation of limestone into the channels is pendingTaking advantage of trucksCommunity support to install the limestoneWater analysis coordination with CIMA and Universidad Tomas Frias

  • Limestone Channels ContdConstructions issuesProject issuesAccessibility issuesDistance [about 100miles/trip]Heavy Rain/HailWorking with the governmentBureaucracy at the governmentNo continuous of flow workBorrowed trucks

  • Accessibility issues

  • Rain

  • Bureaucracy

  • Abandoned Mine sealingLimestoneDelivered 108m3 of limestone delivery-completeLimestone installation is pendingOxidation pond90% completedSome improvements needed to finishInaccessible with a heavy equipment to continue digging and finish. [wetlands]Wall sealingConstruction starts when the worksite area becomes accessibleEstimated length of conclusion of the wall about 2-3 weeks