John Barry Elementary School2828 N Kilbourn Ave Chicago, IL 60641
This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report will roll-up each assessed item with identical rank and total the quantity into a single line, regardless of item location (for location data, see the detailed report) . Assessors rate each facility item by visual observation only; they do not test the operation of equipment or perform destructive testing of walls, ceilings or floors. Each facility item is ranked on a 7-point scale: rank 7 means the item is in new or in good condition and no work is required while rank 1 means the item has failed and has lead to an immediate life safety condition¹. The remaining ranks choices generally mean that the item requires regular maintenance (rank 5 or 6) or full replacement (rank 2, 3 or 4). For additional detail and definition on rank values as they relate to each assessed item, please visit the "CPS Guide to Biennial Facility Assessments" found on the Facilities Standards webpage under CPS Policies and Guidelines at http://www.cps.edu/About_CPS/Policies_and_guidelines/Pages/facilitystandards.aspx. Definitions for Quantity, Unit, Cost and Campus Total can be found at the end of this report.
Facility Assessment Report
Building Name Year Constructed Building Area (Sq Ft) Assessed Need Number of Floors
Campus Summary
Main 1927 64,300 $4,005,8102
Annex 1996 14,400 $996,6651
Leased-Pre K 1995 13,767 $606,4211
SITE $399,115
Campus Total $6,008,01092,467
Building: Main
Category: Building Exterior
Item - Type Quantity Unit Rank Cost Group
Entrance
Entrance Control - Audio 6EA1 $497
Entrance Control - Audio and Video 6EA1 $702
Exterior Doors - Exterior Steel Door 6EA17 $8,169
Exterior Doors - Exterior Wood Door 4EA2 $7,645
Exterior Doors - Transom Lite 5EA1 $822
Exterior Doors - Transom Lite 6EA11 $3,446
Exterior Stairs - Concrete 5LF25 $2,740
Exterior Stairs - Concrete 6LF293 $23,958
Exterior Stairs - Steel or Aluminum 6LF15 $58
Exterior Stairs - Stone 6LF252 $28,472
Power Door Operator and Controls 6EA2 $0
Ramp Handrail - Wood_Ramp Handrail 6LF65 $563
Ramps - Concrete 6LF115 $17,277
Ramps - Wood Ramp 6LF30 $4,507
Stair Handrail - Steel_Stair Handrail 6LF101 $875
Fire Escape
Fire Escape 6LF90 $56,858
Page 1 of 25BARRY Assessment Date: 10/20/2015
John Barry Elementary School2828 N Kilbourn Ave Chicago, IL 60641
Building: Main
Category: Building Exterior
Item - Type Quantity Unit Rank Cost Group
Fire Escape
Foundation
Foundation - Concrete 5LF250 $137,984
Foundation - Concrete 7LF1,153 $0
Superstructure - Concrete 7SF64,300 $0
Lighting
Exterior Lighting - Parapet or Roof Mounted 6EA17 $9,121
Exterior Lighting - Wall Mounted 6EA10 $2,887
Roof System
Cell Tower 6EA1 $736
Chimney - Brick Chimney- Concrete/ Mortar Liner 6LF90 $85,921
Coping - Terra Cotta 5LF1,103 $185,142
Coping - Terra Cotta 6LF210 $6,745
Downspouts - Exterior Downspouts 6LF65 $2,160
Downspouts - Interior Downspouts 6LF245 $8,142
Parapet - 16" - 30" Height 5LF903 $156,233
Parapet - 16" - 30" Height 6LF210 $8,390
Parapet - Parapet > 30" 5LF200 $49,344
Roof - Asphalt Shingle 6SF1,260 $5,784
Roof - Modified Bitumen 4SF27,510 $754,134
Roof - Modified Bitumen 6SF2,766 $26,026
Roof Structure - Concrete 7SF2,766 $0
Roof Structure - Steel with Clay Tile Arch 7SF27,510 $0
Walls
Cheek-Wall - Concrete 5SF104 $2,452
Cornice - Terra Cotta 6LF1,118 $38,769
Exterior Walls - Brick 6SF38,500 $258,759
Windows
Guard - Guards wire guard 6SF1,920 $24,518
Lintels - Steel 6LF30 $871
Lintels - Terra Cotta 6LF370 $0
Windows - Sash Aluminum Double-pane 6SF7,700 $57,477
Building Exterior Subtotal: $1,978,187
Page 2 of 25BARRY Assessment Date: 10/20/2015
John Barry Elementary School2828 N Kilbourn Ave Chicago, IL 60641
Building: Main
Category: Electrical System
Item - Type Quantity Unit Rank Cost Group
Emergency System
Automatic Transfer Switch 6EA1 $408
Emergency A/C Power - Auditoium and Aisle Lighting 6SF3,040 $1,608
Emergency A/C Power - Corridors and Stairs 6SF12,150 $3,649
Emergency A/C Power - Gym 6SF2,800 $1,041
Emergency A/C Power - Lunchrooms 6SF1,150 $428
Emergency Battery Packs - Auditoium and Aisle Lighting 6EA2 $405
Exit Signs - Auditoium 2EA6 $3,273
Exit Signs - Corridors and Stairs 2EA20 $10,910
Exit Signs - Gym 2EA8 $4,626
Exit Signs - Lunchroom 2EA6 $3,273
Security System - CCTV 6SF64,300 $19,309
Security System - Intrusion Detection 6SF64,300 $16,551
Main Service
Independent Electrical Service for emergency power 6EA1 $2,921
Main Electrical Service - 1200 A 120/208/3PH 6EA1 $5,078
PA System 6SF64,300 $21,148
Power Distribution
Lighting and Power Panels - 100 A 6EA9 $2,692
Lighting and Power Panels - Above 100 A 6EA4 $1,988
Main Distribution Panels - 400 - 600 amp 6EA4 $2,111
Main Distribution Panels - Greater than 600 amp 6EA1 $730
Electrical System Subtotal: $102,149
Building: Main
Category: Safty System
Item - Type Quantity Unit Rank Cost Group
Fire Alarm
Fire Alarm Panel 6EA1 $6,406
Fire Alarm Strobe Lights 6SF64,300 $22,987
Fire Alarm_System 6SF64,300 $31,263
Safty System Subtotal: $60,656
Building: Main
Page 3 of 25BARRY Assessment Date: 10/20/2015
John Barry Elementary School2828 N Kilbourn Ave Chicago, IL 60641
Building: Main
Category: Mechanical System
Item - Type Quantity Unit Rank Cost Group
Air Handling Systems
Air Handling Unit- Built Up- Single Zone w/ Air Tunnel- Steam Coils - 15001 - 25000 cfm 5EA2 $88,525
Air Handling Unit- Package Single Zone- Indoor- Steam Coils - 4000-8000 cfm 5EA2 $52,885
Air Intake 5EA1 $7,471
Air Intake 7EA3 $0
Auxiliaries - 15001 - 25000 cfm 5EA2 $29,798
Reheat Boxes - Reheat Boxes with Steam Coil 6EA13 $13,665
Return Duct Work - Indoor- Vertical Shaft and Ducts 7LF200 $0
Zone Dampers 6EA33 $27,490
Boiler Systems
Boiler Auxiliary- Scotch Marine- Steam Low Pressure Boiler - 151 - 200 HP 5EA2 $34,033
Chemical Feeder 6EA1 $1,078
Combustion Dampers 6EA2 $818
Condensate Pump 6EA2 $4,042
Feed Water Pumps and Tank 6EA1 $2,545
Non Condensing- Fire Tube- Scotch Marine- Steam- Low Pressure Boiler - 151 - 200 HP 5EA2 $34,033
Piping - Condensate Pipe- Steel 6LF400 $755
Piping - Steam Pipe- Steel 6LF400 $755
Steam Traps 5EA70 $92,043
Gas Booster
Gas Booster 6EA2 $998
Heating Devices
Fin Tube - Steam 6LF80 $755
Radiators - Steam 5EA33 $55,285
Unit Heater - Steam 6EA1 $278
Wall Heater - Electric 5EA12 $6,439
Wall Heater - Electric 6EA4 $556
Temperature Control
Electric Thermostat 6EA2 $0
Pneumatic System 6SF16 $8
Thermostats - Pneumatic 5EA16 $0
Thermostats - Pneumatic 6EA15 $0
Ventilation
Exhaust Fans- Indoor - 500 - 1500 CFM 6EA3 $1,777
Exhaust Fans- Roof Mounted - 1501 - 8000 CFM 4EA1 $6,392
Exhaust Fans- Roof Mounted - 1501 - 8000 CFM 6EA1 $592
Page 4 of 25BARRY Assessment Date: 10/20/2015
John Barry Elementary School2828 N Kilbourn Ave Chicago, IL 60641
Building: Main
Category: Mechanical System
Item - Type Quantity Unit Rank Cost Group
Mechanical System Subtotal: $463,017
Building: Main
Category: Plumbing System
Item - Type Quantity Unit Rank Cost Group
Hot Water
Gas Heater - 150000 - 300000 BTU/HR 5EA1 $2,249
Piping
Domestic Piping-Cold Water from Risers to Fixtures 6SF64,300 $12,873
Domestic Piping-Cold Water Horizontal Lines 6SF64,300 $15,631
Domestic Piping-Cold Water Risers 6SF64,300 $11,953
Domestic Piping-Hot Water from Risers to Fixtures 6SF64,300 $10,114
Domestic Piping-Hot Water Horizontal Lines 6SF64,300 $11,953
Domestic Piping-Hot Water Return Lines 6SF64,300 $9,195
Domestic Piping-Hot Water Return Risers 6SF64,300 $9,195
Sanitary Piping 6SF64,300 $58,847
Storm Piping 6SF64,300 $56,089
Vent Piping 6SF64,300 $43,216
Pumps
Pumps - Sump-Simplex 5EA2 $11,253
Plumbing System Subtotal: $252,570
Building: Main
Category: Classrooms
Item - Type Quantity Unit Rank Cost Group
Art Room (1 room)
AC Units 6EA1 $496
Casework 6LF20 $505
Ceiling - Lay-in 5SF32 $255
Ceiling - Lay-in 6SF690 $2,072
Doors - Transom Window 6SF9 $152
Doors - Wood Doors inclu hw 6EA2 $602
Floor - Wood 6SF722 $5,090
Lighting - Lay-in 7EA12 $0
Marker Board 7LF30 $0
Page 5 of 25BARRY Assessment Date: 10/20/2015
John Barry Elementary School2828 N Kilbourn Ave Chicago, IL 60641
Building: Main
Category: Classrooms
Item - Type Quantity Unit Rank Cost Group
Art Room (1 room)
Walls - Plaster/Drywall 6SF928 $2,561
Computer Lab (1 room)
AC Units 6EA2 $991
Casework 6LF20 $505
Ceiling - Lay-in 6SF720 $2,162
Doors - Transom Window 6SF9 $152
Doors - Wood Doors inclu hw 6EA2 $602
Floor - Wood 6SF720 $5,076
Lighting - Lay-in 7EA12 $0
Marker Board 7LF60 $0
Walls - Plaster/Drywall 6SF918 $2,534
Wireless System 7EA1 $0
Kindergarten (6 rooms)
AC Units 6EA7 $3,469
Casework 6LF89 $2,248
Ceiling - Lay-in 5SF733 $4,393
Ceiling - Lay-in 6SF3,222 $9,676
Doors - Transom Window 6SF54 $914
Doors - Wood Doors inclu hw 6EA8 $2,408
Floor - Terrazzo 6SF337 $737
Floor - Tile 6SF1,432 $3,133
Floor - Wood 6SF2,186 $15,411
Lighting - Lay-in 7EA67 $0
Marker Board 7LF165 $0
Storage/ Closet 6SF110 $798
Walls - Plaster/Drywall 5SF2 $10
Walls - Plaster/Drywall 6SF5,463 $15,077
Regular Classroom (12 rooms)
AC Units 6EA12 $5,947
Casework 6LF199 $5,026
Ceiling - Lay-in 5SF48 $383
Ceiling - Lay-in 6SF8,568 $25,730
Doors - Transom Window 5SF9 $381
Doors - Transom Window 6SF90 $1,524
Doors - Wood Doors inclu hw 5EA1 $1,174
Doors - Wood Doors inclu hw 6EA18 $5,418
Page 6 of 25BARRY Assessment Date: 10/20/2015
John Barry Elementary School2828 N Kilbourn Ave Chicago, IL 60641
Building: Main
Category: Classrooms
Item - Type Quantity Unit Rank Cost Group
Regular Classroom (12 rooms)
Floor - Wood 6SF8,616 $60,742
Lighting - Lay-in 7EA144 $0
Marker Board 7LF510 $0
Walls - Plaster/Drywall 5SF68 $347
Walls - Plaster/Drywall 6SF10,972 $30,282
Special Education (1 room)
AC Units 6EA1 $496
Casework 6LF20 $505
Ceiling - Lay-in 6SF471 $1,414
Doors - Transom Window 6SF9 $152
Doors - Wood Doors inclu hw 6EA1 $301
Floor - Tile 6SF471 $1,031
Lighting - Lay-in 7EA8 $0
Marker Board 7LF10 $0
Walls - Plaster/Drywall 6SF918 $2,534
Classrooms Subtotal: $225,415
Building: Main
Category: Rooms (Other Than Classrooms)
Item - Type Quantity Unit Rank Cost Group
Administrative Suites/Offices
AC Unit 5EA1 $1,826
AC Unit 6EA4 $1,982
Ceiling - Lay-in 6SF961 $2,886
Ceiling - Plaster/Drywall 5SF129 $1,182
Ceiling - Plaster/Drywall 6SF687 $2,377
Doors - Transom Window 6SF18 $305
Doors - Wood Doors inclu hw 5EA1 $1,174
Doors - Wood Doors inclu hw 6EA8 $2,408
Floor - Carpet 6SF531 $1,131
Floor - Tile 4SF129 $1,109
Floor - Tile 6SF1,117 $2,444
Lighting - Lay-in 7EA15 $0
Lighting - Pendent/Surface 4EA2 $1,081
Lighting - Pendent/Surface 7EA5 $0
Page 7 of 25BARRY Assessment Date: 10/20/2015
John Barry Elementary School2828 N Kilbourn Ave Chicago, IL 60641
Building: Main
Category: Rooms (Other Than Classrooms)
Item - Type Quantity Unit Rank Cost Group
Administrative Suites/Offices
Power Distribution 5EA6 $23,110
Power Distribution 6EA50 $106,244
Walls - Masonry 6SF643 $2,023
Walls - Plaster/Drywall 4SF650 $6,544
Walls - Plaster/Drywall 6SF4,115 $11,357
Auditorium & Theater
Balcony Seating 6EA90 $15,652
Ceiling - Plaster/Drywall 5SF20 $630
Ceiling - Plaster/Drywall 6SF3,020 $25,177
Doors - Wood Doors inclu hw 6EA4 $1,204
Floor - Carpet 5SF477 $2,449
Floor - Concrete Epoxy/ Painted 6SF2,563 $1,356
Lighting - Chandelier, Incandescent 7EA8 $0
Lighting - Pendent/Surface 7EA3 $0
Lighting - Wall Mounted 7EA11 $0
Main Floor Seating 6EA288 $50,088
Sound System 6EA1 $10,721
Stage 6SF405 $2,340
Stage Curtain 6EA2 $0
Stage Lighting System 6EA1 $8,077
Stage-Stairs - Wood 6LF10 $117
Storage/ Closet 6SF190 $1,378
Walls - Plaster/Drywall 5SF6 $68
Walls - Plaster/Drywall 6SF6,036 $28,743
Gymnasia
Ceiling - Plaster/Drywall 5SF25 $501
Ceiling - Plaster/Drywall 6SF2,775 $15,317
Doors - Transom Window 6SF16 $271
Doors - Wood Doors inclu hw 6EA2 $602
Floor - Wood 6SF2,800 $19,740
Lighting - Metal Halide/Sodium Vapor 7EA8 $0
Walls - Plaster/Drywall 6SF3,724 $10,278
Walls - Structural Glazed Tile 6SF1,540 $4,845
Kitchen
Ceiling - Plaster/Drywall 6SF592 $2,049
Doors - Wood Doors inclu hw 6EA1 $301
Page 8 of 25BARRY Assessment Date: 10/20/2015
John Barry Elementary School2828 N Kilbourn Ave Chicago, IL 60641
Building: Main
Category: Rooms (Other Than Classrooms)
Item - Type Quantity Unit Rank Cost Group
Kitchen
Floor - Tile Ceramic/ Porcelain 6SF592 $1,253
Lighting - Pendent/Surface 7EA4 $0
Walls - Plaster/Drywall 5SF4 $20
Walls - Plaster/Drywall 6SF746 $2,059
Walls - Structural Glazed Tile 6SF250 $787
Library
AC Unit 6EA3 $1,487
Casework 6LF60 $1,515
Ceiling - Lay-in 5SF40 $319
Ceiling - Lay-in 6SF1,963 $5,895
Doors - Side-lite 6SF60 $1,003
Doors - Transom Window 6SF27 $457
Doors - Wood Doors inclu hw 6EA5 $1,505
Floor - Carpet 6SF1,271 $2,708
Floor - Tile 6SF732 $1,602
Lighting - Lay-in 7EA34 $0
Walls - Plaster/Drywall 5SF6 $31
Walls - Plaster/Drywall 6SF2,728 $7,529
Lunch & Multipurpose Room
AC Unit 3EA1 $6,086
Ceiling - Lay-in 5SF16 $128
Ceiling - Lay-in 6SF1,290 $3,874
Chalk Board 4LF6 $551
Doors - Transom Window 6SF18 $305
Doors - Wood Doors inclu hw 5EA2 $2,348
Doors - Wood Doors inclu hw 6EA2 $602
Floor - Terrazzo 6SF107 $234
Floor - Tile 6SF1,199 $2,623
Lighting - Lay-in 7EA25 $0
Serving Line 6LF14 $833
Storage/ Closet 6SF7 $51
Walls - Plaster/Drywall 6SF2,117 $5,843
Mechanical/ Service Rooms
Boiler Room 5SF2,544 $41,036
Coal Room 5SF1,100 $17,743
Interior Stairs 6LF50 $451
Page 9 of 25BARRY Assessment Date: 10/20/2015
John Barry Elementary School2828 N Kilbourn Ave Chicago, IL 60641
Building: Main
Category: Rooms (Other Than Classrooms)
Item - Type Quantity Unit Rank Cost Group
Mechanical/ Service Rooms
Janitor's Closet 5SF100 $1,613
Janitor's Closet 6SF90 $645
Mechanical/ Service Rooms 5SF686 $11,065
Storage Room 5SF9,100 $146,787
Restroom
Accessories 6SF2,189 $20,190
Ceiling - Lay-in 6SF111 $333
Ceiling - Plaster/Drywall 6SF2,078 $7,191
Doors - Transom Window 6SF144 $2,438
Doors - Wood Doors inclu hw 6EA19 $5,719
Floor - Tile Ceramic/ Porcelain 5SF1 $21
Floor - Tile Ceramic/ Porcelain 6SF2,189 $4,633
Floor Drain 6EA8 $8,473
Hand Dryer 6EA16 $3,681
Lavatory 6EA16 $5,114
Lighting - Lay-in 7EA1 $0
Lighting - Pendent/Surface 7EA33 $0
Lighting - Wall Mounted 7EA2 $0
Partitions 5EA21 $15,768
Partitions 6EA19 $5,642
Urinals 4EA1 $7,669
Urinals 6EA19 $6,384
Walls - Masonry 6SF2,592 $8,154
Walls - Plaster/Drywall 5SF2 $10
Walls - Plaster/Drywall 6SF3,780 $10,432
Walls - Structural Glazed Tile 6SF882 $2,857
Water Closet 6EA41 $13,775
Rooms (Other Than Classrooms) Subtotal: $770,558
Building: Main
Category: Building Interior
Item - Type Quantity Unit Rank Cost Group
Corridor
Ceiling - Lay-in 5SF80 $714
Ceiling - Lay-in 6SF8,242 $24,751
Page 10 of 25BARRY Assessment Date: 10/20/2015
John Barry Elementary School2828 N Kilbourn Ave Chicago, IL 60641
Building: Main
Category: Building Interior
Item - Type Quantity Unit Rank Cost Group
Corridor
Ceiling - Plaster/Drywall 6SF554 $3,430
Doors - Wood Doors include hw 6EA11 $3,311
Drinking Fountains - Single Fountain 6EA8 $2,206
Floor - Terrazzo 6SF1,406 $11,802
Floor - Tile/Sheet 6SF7,470 $4,059
Lighting - Lay-in 7EA104 $0
Lighting - Pendent/Surface 7EA13 $0
Lighting - Wall Mounted 7EA4 $0
Stairs - Terrazzo 6LF19 $176
Student Lockers - One Tier 6EA466 $43,261
Walls - Plaster/Drywall 6SF6,436 $28,531
Walls - Structural Glazed Tile 6SF1,340 $4,216
Safety
Camera Viewing Station 6EA2 $1,365
Security Cameras 6EA12 $2,328
Stairs
Ceiling - Plaster/Drywall 5SF126 $1,898
Ceiling - Plaster/Drywall 6SF346 $2,533
Floor - Terrazzo 6SF536 $4,499
Handrails 6LF248 $2,149
Stairs - Terrazzo 6LF108 $1,002
Walls - Plaster/Drywall 5SF28 $174
Walls - Plaster/Drywall 6SF3,932 $10,852
Building Interior Subtotal: $153,259
Total Building Cost $4,005,810
Building: Annex
Category: Building Exterior
Item - Type Quantity Unit Rank Cost Group
Entrance
Entrance Control - Audio 6EA1 $497
Exterior Doors - Exterior Steel Door 6EA6 $2,883
Power Door Operator and Controls 6EA1 $0
Page 11 of 25BARRY Assessment Date: 10/20/2015
John Barry Elementary School2828 N Kilbourn Ave Chicago, IL 60641
Building: Annex
Category: Building Exterior
Item - Type Quantity Unit Rank Cost Group
Foundation
Foundation - Concrete 7LF560 $0
Superstructure - Metal Deck/ Concrete Topping 7SF14,400 $0
Lighting
Exterior Lighting - Wall Mounted 6EA9 $2,599
Roof System
Chimney - Metal Flue 6LF5 $791
Downspouts - Exterior Downspouts 6LF44 $1,462
Roof - Metal 6SF18,000 $241,184
Roof Structure - Steel / Metal Deck/ Concrete Topping 7SF14,400 $0
Walls
Canopy - Metal 6SF70 $1,504
Exterior Walls - Brick 6SF5,775 $38,814
Windows
Guard - Guards perforated 6SF1,470 $18,772
Lintels - Steel 6LF277 $8,041
Windows - Casement Aluminum Double-pane 6SF1,470 $10,973
Building Exterior Subtotal: $327,519
Building: Annex
Category: Electrical System
Item - Type Quantity Unit Rank Cost Group
Emergency System
Automatic Transfer Switch 6EA1 $408
Emergency A/C Power - Corridors and Stairs 6SF1,300 $390
Exit Signs - Corridors and Stairs 2EA6 $3,273
Security System - CCTV 6SF14,400 $4,324
Security System - Intrusion Detection 6SF14,400 $3,707
Main Service
Independent Electrical Service for emergency power 6EA1 $2,921
Main Electrical Service - 800 A and Less than 120/208/3PH 6EA1 $3,398
PA System 6SF14,400 $4,736
Power Distribution
Lighting and Power Panels - 100 A 6EA2 $598
Page 12 of 25BARRY Assessment Date: 10/20/2015
John Barry Elementary School2828 N Kilbourn Ave Chicago, IL 60641
Building: Annex
Category: Electrical System
Item - Type Quantity Unit Rank Cost Group
Power Distribution
Lighting and Power Panels - Above 100 A 6EA1 $497
Main Distribution Panels - 400 - 600 amp 6EA1 $528
Electrical System Subtotal: $24,780
Building: Annex
Category: Safty System
Item - Type Quantity Unit Rank Cost Group
Fire Alarm
Fire Alarm Panel 6EA1 $6,406
Fire Alarm Strobe Lights 6SF14,400 $5,148
Fire Alarm_System 6SF14,400 $7,001
Sprinkler System
Sprinkler Heads 7SF14,400 $0
Sprinkler Piping 7SF14,400 $0
Wet Sprinkler System 7SF14,400 $0
Safty System Subtotal: $18,555
Building: Annex
Category: Mechanical System
Item - Type Quantity Unit Rank Cost Group
Air Handling Systems
Air Handling Unit-Package Single Zone- Indoor- Hot Water Coils - 4000-8000 cfm 5EA1 $26,442
Air Intake 6EA1 $5,765
Boiler Systems
Boiler Auxiliary- Non Condensing Hot Water - 2001 - 3000 MBH 5EA2 $89,093
Chemical Pot Feeder 6EA1 $725
Combustion Dampers 6EA2 $818
Glycol Feed System 6EA1 $539
Hot Water Pump 6EA2 $748
Non Condensing- Water Tube- Flexible Tube- Force Draft- Hot Water Boiler - 2001 - 3000 MBH
5EA2 $120,265
Water Fill System 6EA1 $1,168
Page 13 of 25BARRY Assessment Date: 10/20/2015
John Barry Elementary School2828 N Kilbourn Ave Chicago, IL 60641
Building: Annex
Category: Mechanical System
Item - Type Quantity Unit Rank Cost Group
Heating Devices
Cabinet Heaters - With Hot Water Coil 6EA2 $709
Unit Heater - Electric 6EA2 $556
Mechanical Plumbing
Hydronic Supply and Return - Galvanized 6LF600 $46,392
Temperature Control
Electric Thermostat 6EA14 $0
Unit Ventilation
Unit Ventilators- Floor Mounted- Hot Water w/ DX Cooling Coil & w/ Self Contained
Compressors
5EA12 $118,569
Ventilation
Exhaust Fans- Roof Mounted - 1501 - 8000 CFM 6EA1 $592
Exhaust Fans- Roof Mounted - 500 - 1500 CFM 6EA3 $1,777
Mechanical System Subtotal: $414,159
Building: Annex
Category: Plumbing System
Item - Type Quantity Unit Rank Cost Group
Hot Water
Gas Heater - Less than 150000 BTU/HR 6EA1 $310
Piping
Domestic Piping-Cold Water Horizontal Lines 6SF14,400 $3,501
Domestic Piping-Hot Water Horizontal Lines 6SF14,400 $2,677
Domestic Piping-Hot Water Return Lines 6SF14,400 $2,059
Sanitary Piping 6SF14,400 $13,179
Storm Piping 6SF14,400 $12,561
Vent Piping 6SF14,400 $9,678
Plumbing System Subtotal: $43,965
Building: Annex
Category: Classrooms
Item - Type Quantity Unit Rank Cost Group
Page 14 of 25BARRY Assessment Date: 10/20/2015
John Barry Elementary School2828 N Kilbourn Ave Chicago, IL 60641
Building: Annex
Category: Classrooms
Item - Type Quantity Unit Rank Cost Group
Regular Classroom (10 rooms)
Ceiling - Lay-in 5SF56 $447
Ceiling - Lay-in 6SF8,664 $26,018
Ceiling - Plaster/Drywall 5SF4 $37
Doors - Steel Doors incl hw 7EA10 $0
Floor - Tile 6SF8,724 $19,087
Lighting - Lay-in 6EA90 $10,708
Marker Board 7LF294 $0
Walls - Concrete Block 6SF6,218 $18,228
Walls - Plaster/Drywall 5SF5 $26
Walls - Plaster/Drywall 6SF4,113 $11,351
Special Education (1 room)
Ceiling - Lay-in 6SF367 $1,102
Doors - Steel Doors incl hw 7EA1 $0
Floor - Tile 6SF367 $803
Lighting - Lay-in 6EA4 $476
Marker Board 7LF10 $0
Walls - Concrete Block 6SF200 $586
Walls - Plaster/Drywall 5SF5 $26
Walls - Plaster/Drywall 6SF632 $1,744
Classrooms Subtotal: $90,639
Building: Annex
Category: Rooms (Other Than Classrooms)
Item - Type Quantity Unit Rank Cost Group
MDF_IDF
Doors - Steel Doors incl hw 7EA1 $0
Finishes 4SF1 $28
Finishes 6SF60 $428
Ventilation and Cooling 6EA1 $1,855
Mechanical/ Service Rooms
Boiler Room 6SF340 $2,436
Janitor's Closet 5SF50 $807
Mechanical/ Service Rooms 6SF290 $2,078
Page 15 of 25BARRY Assessment Date: 10/20/2015
John Barry Elementary School2828 N Kilbourn Ave Chicago, IL 60641
Building: Annex
Category: Rooms (Other Than Classrooms)
Item - Type Quantity Unit Rank Cost Group
Restroom
Accessories 6SF1,106 $10,201
Ceiling - Plaster/Drywall 6SF1,106 $3,827
Doors - Steel Doors incl hw 7EA2 $0
Floor - Concrete Epoxy/ Painted 6SF509 $269
Floor - Epoxy/ Painted 6SF509 $269
Floor - Tile 6SF88 $193
Floor Drain 6EA5 $5,296
Hand Dryer 6EA4 $920
Lavatory 6EA8 $2,557
Lighting - Lay-in 6EA12 $1,428
Partitions 6EA12 $3,563
Urinals 6EA6 $2,016
Walls - Concrete Block 6SF3,266 $9,574
Water Closet 6EA14 $4,704
Rooms (Other Than Classrooms) Subtotal: $52,448
Building: Annex
Category: Building Interior
Item - Type Quantity Unit Rank Cost Group
Corridor
Ceiling - Lay-in 6SF1,564 $4,697
Ceiling - Plaster/Drywall 6SF258 $1,598
Doors - Steel Doors incl hw 7EA8 $0
Drinking Fountains - Single Fountain 6EA2 $551
Floor - Tile Ceramic/ Porcelain 6SF258 $719
Floor - Tile/Sheet 6SF1,564 $850
Lighting - Lay-in 6EA20 $2,380
Walls - Concrete Block 6SF4,577 $13,417
Safety
Security Cameras 6EA2 $388
Building Interior Subtotal: $24,600
Total Building Cost $996,665
Page 16 of 25BARRY Assessment Date: 10/20/2015
John Barry Elementary School2828 N Kilbourn Ave Chicago, IL 60641
Building: Leased-Pre K
Category: Building Exterior
Item - Type Quantity Unit Rank Cost Group
Entrance
Exterior Doors - Exterior Steel Door 6EA4 $1,922
Exterior Doors - Store Front 6EA9 $4,915
Exterior Doors - Transom Lite 6EA7 $2,193
Exterior Stairs - Concrete 6LF18 $1,472
Foundation
Foundation - Concrete 7LF640 $0
Superstructure - Slab on Grade 7SF13,767 $0
Lighting
Exterior Lighting - Wall Mounted 6EA19 $5,486
Roof System
Coping - Metal 6LF480 $15,417
Downspouts - Exterior Downspouts 6LF50 $1,662
Parapet - Parapet > 30" 6LF480 $30,682
Roof - Modified Bitumen 6SF10,000 $94,094
Roof Structure - Steel / Metal Deck/ Concrete Topping 7SF10,000 $0
Walls
Canopy - Fabric 6SF770 $11,826
Exterior Walls - Concrete Block 6SF3,800 $25,540
Exterior Walls - Stucco 6SF2,000 $9,581
Windows
Lintels - Steel 6LF175 $5,080
Skylite - Lexan 6SF80 $1,912
Storefront Windows 6SF1,053 $11,805
Building Exterior Subtotal: $223,586
Building: Leased-Pre K
Category: Electrical System
Item - Type Quantity Unit Rank Cost Group
Emergency System
Emergency Battery Packs - Corridors and Stairs 6EA12 $2,430
Exit Signs - Corridors and Stairs 6EA8 $1,198
Security System - CCTV 6SF13,767 $4,134
Security System - Intrusion Detection 6SF13,767 $3,544
Page 17 of 25BARRY Assessment Date: 10/20/2015
John Barry Elementary School2828 N Kilbourn Ave Chicago, IL 60641
Building: Leased-Pre K
Category: Electrical System
Item - Type Quantity Unit Rank Cost Group
Emergency System
UPS - Less than 30 KW 6EA1 $7,886
Main Service
Main Electrical Service - 800 A and 120/208/3PH 6EA1 $3,570
PA System 6SF13,767 $4,528
Power Distribution
Lighting and Power Panels - 100 A 6EA1 $299
Lighting and Power Panels - Above 100 A 6EA5 $2,485
Electrical System Subtotal: $30,074
Building: Leased-Pre K
Category: Safty System
Item - Type Quantity Unit Rank Cost Group
Fire Alarm
Fire Alarm Panel 6EA1 $6,406
Fire Alarm Strobe Lights 6SF13,767 $4,922
Fire Alarm_System 6SF13,767 $6,694
Sprinkler System
Sprinkler Heads 7SF13,767 $0
Sprinkler Piping 7SF13,767 $0
Wet Sprinkler System 7SF13,767 $0
Safty System Subtotal: $18,021
Building: Leased-Pre K
Category: Mechanical System
Item - Type Quantity Unit Rank Cost Group
Air Handling Systems
Roof Top Unit-Single Zone-Roof Mounted- Gas Heating and DX Cooling Coil - 5 - 10 tons 5EA4 $42,491
Roof Top Unit-Single Zone-Roof Mounted- Gas Heating and DX Cooling Coil - 5 - 10 tons 7EA2 $0
Temperature Control
Electric Thermostat 6EA6 $0
Ventilation
Exhaust Fans- Indoor - Less than 500 CFM 6EA9 $2,666
Page 18 of 25BARRY Assessment Date: 10/20/2015
John Barry Elementary School2828 N Kilbourn Ave Chicago, IL 60641
Building: Leased-Pre K
Category: Mechanical System
Item - Type Quantity Unit Rank Cost Group
Ventilation
Exhaust Fans- Roof Mounted - 1501 - 8000 CFM 6EA6 $3,554
Roof Mounted Duct Work 6LF20 $7,580
Mechanical System Subtotal: $56,292
Building: Leased-Pre K
Category: Plumbing System
Item - Type Quantity Unit Rank Cost Group
Hot Water
Electric Heater - Less than 20 KW 6EA3 $2,047
Piping
Domestic Piping-Cold Water Horizontal Lines 6SF10,000 $2,431
Domestic Piping-Hot Water Horizontal Lines 6SF10,000 $1,859
Domestic Piping-Hot Water Return Lines 6SF10,000 $1,430
Sanitary Piping 6SF10,000 $9,152
Storm Piping 6SF10,000 $8,723
Vent Piping 6SF10,000 $6,721
Plumbing System Subtotal: $32,363
Building: Leased-Pre K
Category: Classrooms
Item - Type Quantity Unit Rank Cost Group
Pre School (2 rooms)
Casework 6LF15 $379
Ceiling - Lay-in 5SF52 $415
Ceiling - Lay-in 6SF9,873 $29,649
Floor - Tile 5SF65 $375
Floor - Tile 6SF9,925 $21,715
Lighting - Lay-in 7EA107 $0
Storage/ Closet 6SF1,569 $11,375
Walls - Concrete Block 6SF1,332 $3,905
Walls - Plaster/Drywall 6SF4,881 $13,471
Work Sink 6EA2 $758
Page 19 of 25BARRY Assessment Date: 10/20/2015
John Barry Elementary School2828 N Kilbourn Ave Chicago, IL 60641
Building: Leased-Pre K
Category: Classrooms
Item - Type Quantity Unit Rank Cost Group
Classrooms Subtotal: $82,041
Building: Leased-Pre K
Category: Rooms (Other Than Classrooms)
Item - Type Quantity Unit Rank Cost Group
Administrative Suites/Offices
Ceiling - Lay-in 5SF10 $80
Ceiling - Lay-in 6SF2,124 $6,378
Doors - Wood Doors inclu hw 6EA1 $301
Floor - Carpet 6SF1,699 $3,620
Floor - Tile 5SF6 $35
Floor - Tile 6SF429 $939
Lighting - Lay-in 6EA28 $3,331
Power Distribution 6EA50 $106,244
Walls - Plaster/Drywall 7SF3,160 $0
Lunch & Multipurpose Room
Ceiling - Lay-in 6SF360 $1,081
Floor - Tile 5SF15 $86
Floor - Tile 6SF345 $755
Lighting - Lay-in 7EA4 $0
Walls - Concrete Block 6SF240 $704
Walls - Plaster/Drywall 6SF590 $1,628
Mechanical/ Service Rooms
Janitor's Closet 6SF82 $587
Storage Room 6SF26 $186
Restroom
Accessories 6SF355 $3,274
Ceiling - Lay-in 6SF355 $1,066
Doors - Wood Doors inclu hw 5EA1 $1,174
Doors - Wood Doors inclu hw 6EA9 $2,709
Floor - Tile 5SF355 $1,601
Floor Drain 6EA10 $10,592
Lavatory 6EA10 $3,196
Lighting - Lay-in 7EA5 $0
Lighting - Pendent/Surface 6EA3 $372
Lighting - Pendent/Surface 7EA2 $0
Page 20 of 25BARRY Assessment Date: 10/20/2015
John Barry Elementary School2828 N Kilbourn Ave Chicago, IL 60641
Building: Leased-Pre K
Category: Rooms (Other Than Classrooms)
Item - Type Quantity Unit Rank Cost Group
Restroom
Walls - Concrete Block 6SF180 $528
Walls - Plaster/Drywall 5SF2 $10
Walls - Plaster/Drywall 6SF1,792 $4,946
Water Closet 5EA1 $1,344
Water Closet 6EA9 $3,024
Rooms (Other Than Classrooms) Subtotal: $159,791
Building: Leased-Pre K
Category: Building Interior
Item - Type Quantity Unit Rank Cost Group
Corridor
Ceiling - Lay-in 6SF389 $1,168
Drinking Fountains - Single Fountain 6EA1 $276
Floor - Tile/Sheet 6SF389 $211
Lighting - Pendent/Surface 7EA4 $0
Walls - Plaster/Drywall 6SF586 $2,598
Building Interior Subtotal: $4,253
Total Building Cost $606,421
SITE
Category: Site
Item - Type Quantity Unit Rank Cost Group
Civil/Drainage
Civil/ Drainage - Catch Basin 6EA10 $10,938
Civil/ Drainage - Site Manhole 6EA10 $14,927
Fencing
Fencing - Chain Link 5LF100 $6,099
Fencing - Chain Link 6LF1,275 $23,939
Landscape
Benches 6EA2 $860
Landscape - Grass 6SF16,971 $14,076
Landscape - Hardscape- Concrete 5SF7,500 $70,142
Page 21 of 25BARRY Assessment Date: 10/20/2015
John Barry Elementary School2828 N Kilbourn Ave Chicago, IL 60641
SITE
Category: Site
Item - Type Quantity Unit Rank Cost Group
Landscape
Landscape - Hardscape- Concrete 6SF3,600 $21,879
Parkway trees 6EA59 $38,943
Play Area - Asphalt/ Hardscape 6SF43,420 $104,933
Trash Receptacles 6EA2 $625
Parking Lot
Concrete Curbs 6LF175 $2,247
Interior Plantings 6LF60 $2,553
Surface - Asphalt 6SF13,650 $32,988
Playground
Equipment - School Age 5-12 6EA1 $3,546
Surface - Square Rubber Mats 5SF2,400 $24,230
Sidewalks
Sidewalks - Internal Walks 6LF250 $3,003
Sidewalks - Perimeter Sidewalks 6SF10,832 $21,531
Signage
Flag Pole - Flag Pole 6EA1 $1,657
Marquee - Free Standing Back lighted w/ LED 6EA1 $0
Site Subtotal: $399,115
Total Site Cost $399,115
Campus Total ² ³
² As stated above, Total Assessed Campus Need does not include the addition of features not already in a particular facility, such as programmatic improvements, school-wide ADA compliance, air conditioning, space reconfiguration or construction to alleviate overcrowding; these items are treated as separate capital needs. The Total Assessed Campus Need includes current deficiencies and is based on current unit cost estimates; it does not reflect a complete project cost.
³ The overall condition of different items can change after an assessment date due to many variables, including newly occurring deficiencies, renovation or repairs and cost changes. These dollar figures in this report are estimates only and are based solely on the data that was collected as of the assessment date in the footer below.
¹ It is very rare for assessors to find a feature in this condition. If assessors do, they are required to report it immediately to CPS, and CPS addresses it immediately. Thus, no features will be ranked “1” in this report; by the time the report is compiled, they have been resolved.
$6,008,010
Page 22 of 25BARRY Assessment Date: 10/20/2015
John Barry Elementary School2828 N Kilbourn Ave Chicago, IL 60641
Definitions
● Quantity
● Unit
means a basic estimate for each item needing some level of repair or replacement. Cost does not include all expenses that would be necessary to complete a repair or replacement project. This is because,
depending on the item and on the overall scope of a construction project, repair/replacement projects can include additional costs such as destructive testing, environmental needs, discovered conditions, and
additional work triggered by building codes.
means, for each item, the total number (or amount) of that item that exists and was evaluated.
means the generally accepted standard unit of measure for each item. Some items, like doors, are measured individually and use the unit of measurement “EA” for “each.” Other items, like
chimneys, are measured in terms of linear feet (“LF”). Still other items, like flooring, are generally measured in square feet (“SF”).
● Cost
● For the same reason, the Total Campus Need listed at the end of this report reflects only a portion of what it would actually cost to repair/replace all of the listed features.
● Campus Total also does not reflect features that do not yet exist at a particular facility, such as: programmatic improvements, school-wide ADA compliance, air conditioning, space reconfiguration, or construction to
alleviate overcrowding; these are viewed as separate capital needs.
Page 23 of 25BARRY Assessment Date: 10/20/2015
John Barry Elementary School2828 N Kilbourn Ave Chicago, IL 60641
Classroom Summary
Smart-
Board
Power
Strip
Window
Stop
Operable
Window
Area
Glazed
Window
Area
Noise
Level
Elect.
Outlets
Data
Outlets
Voice
Outlets
Area (SF)Floor Plan
Room
Number
Room
Number
Intended UsageCurrent Usage Room
Location
Main
YNY40132131824722201201Regular ClassroomArt Room 2nd Floor
YNY401061174823720203203Regular ClassroomComputer Lab 2nd Floor
YNY40132131823715101101Regular ClassroomKindergarten 1st Floor
YNY40132131821717103103KindergartenKindergarten 1st Floor
YNY40132131821752104104Regular ClassroomKindergarten 1st Floor
NNY40132131823715106106Regular ClassroomKindergarten 1st Floor
YNY40421337Teacher lunch200Faculty LoungeKindergarten 2nd Floor
YNY40132131823719207207Science ClassroomKindergarten 2nd Floor
YNY40132131824722107107Regular ClassroomRegular Classroom 1st Floor
YNY40132131824674108108Regular ClassroomRegular Classroom 1st Floor
YNY40132131823718109109Regular ClassroomRegular Classroom 1st Floor
YNY40132131821725110110Regular ClassroomRegular Classroom 1st Floor
YNY40132131824725202202Regular ClassroomRegular Classroom 2nd Floor
YNY40132131823725204204Science ClassroomRegular Classroom 2nd Floor
YNY40132131821718205205Regular ClassroomRegular Classroom 2nd Floor
YNY40132131824721206206Regular ClassroomRegular Classroom 2nd Floor
YNY40132131823720208208Regular ClassroomRegular Classroom 2nd Floor
YNY40132131823720209209Science ClassroomRegular Classroom 2nd Floor
YYY40132131823730210210Regular ClassroomRegular Classroom 2nd Floor
YNY40132131823718211211Regular ClassroomRegular Classroom 2nd Floor
YNY407978621471100100Special Education 1st Floor
Annex
YNY40104102167186711Regular ClassroomRegular Classroom 1st Floor
YNY4010410216718711010Regular ClassroomRegular Classroom 1st Floor
YNY40104102167187122Regular ClassroomRegular Classroom 1st Floor
YNY40104102167186833Regular ClassroomRegular Classroom 1st Floor
YNY40104102167187844Regular ClassroomRegular Classroom 1st Floor
YNY40104102167187155Regular ClassroomRegular Classroom 1st Floor
NNY40104102167188066Regular ClassroomRegular Classroom 1st Floor
YNY40104102167187177Regular ClassroomRegular Classroom 1st Floor
YNY40104102167188088Regular ClassroomRegular Classroom 1st Floor
YNY40104102167186799Regular ClassroomRegular Classroom 1st Floor
YNN4000640367NABetween 4 & 6OfficeSpecial Education 1st Floor
Leased-Pre K
YNN40037232016,594N/A4362 B & APre SchoolPre School 1st Floor
Page 24 of 25BARRY Assessment Date: 10/20/2015
John Barry Elementary School2828 N Kilbourn Ave Chicago, IL 60641
Classroom Summary
Smart-
Board
Power
Strip
Window
Stop
Operable
Window
Area
Glazed
Window
Area
Noise
Level
Elect.
Outlets
Data
Outlets
Voice
Outlets
Area (SF)Floor Plan
Room
Number
Room
Number
Intended UsageCurrent Usage Room
Location
Leased-Pre K
YNN40032026013,331N/A4634 A/BPre SchoolPre School 1st Floor
Page 25 of 25BARRY Assessment Date: 10/20/2015