8
UNCLASSIFIED UNCLASSIFIED DoD CIO Joint Regional Security Stacks COL Nora R. Marcos Commander DISA CONUS

Joint Regional Security Stacks - AFCEA International · PDF fileUNCLASSIFIED UNCLASSIFIED ... •Elimination of Army TDM circuits could save at least ... * SOURCE: WWOLS-R as of 4

  • Upload
    vungoc

  • View
    213

  • Download
    0

Embed Size (px)

Citation preview

UNCLASSIFIED

UNCLASSIFIED

D o D C I O

Joint Regional Security Stacks

COL Nora R. Marcos

Commander

DISA CONUS

UNCLASSIFIED

UNCLASSIFIED

JRSS* is the Operational Solution

Addresses immediate need to defend the cyber warfighting domain & resolve JIE ICD gaps

Shrinks attack surface from ~1000 disparate ingress points to 50 ingress points (U&C networks)

Achieves a standard network security architecture

Accelerates achieving a standardized Command and Control platform for the Joint Information Environment

JRSS suite fielded enables global synchronized network operations

“I never understood why the Services each spend money creating, maintaining, building, and operating a global communications backbone….We need a joint framework. Each Service could still address its own

needs..” Adm. Mike Rogers

2

JRSS

* JRSS = Security + Network Modernization + Cyber SA

UNCLASSIFIED

UNCLASSIFIED

Implementation Timeline

3

FY14 FY15 FY16 FY17 FY18 FY19

San Antonio Ops Decision (Sep 14)

JRSS v 1.0: CONUS/EUROPE/ SWA Focus

(50% Global Reqt)

Assumes FY15 Funding Available JRSS 1.5: USAF/USA Stand Down Legacy Capabilities

80% Global Reqt (50% in Europe, Africa, Pacific)

Assumes FY16 Funding Available

USN/USMC Migration 100% Global Reqt

JRSS Version 2.0 (DON Enhancements)

Reduced Attack Surface

DOD Installations Connected

Improved C2 and SA

Added Resiliency/Capacity Increased Sharing of Threat Data

100 Sites

300 Sites

400+ Sites

Expanding Cyber C2 Capabilities

1000+ Loosely Controlled Entry Points 50 Robust Entry Points

JFHQ DODIN Activated

UNCLASSIFIED

UNCLASSIFIED

DoD Circuit Infrastructure: Army (Contracted thru DISA)*

TO BE: Total Circuits AS IS: Total Circuits

17.6K Access Circuits

3.5K Access Circuits

Installation of IP Transport/MPLS: ~$80M / Year Cost Savings

• An estimated 80% of existing TDM circuits DS-3 and below can be moved to IP transport as it is enabled

• Army Leased TDM Circuits: $100M ARC • Does not include TDM circuits leased outside of DITCO

• Implementation of IP Transport & MPLS allows elimination of most TDM circuits (estimated @ 80%)

• Elimination of Army TDM circuits could save at least ~$80M or more ARC after FY16

• Elimination of some non-DITCO TDM circuits will result in even greater savings

4

* SOURCE: WWOLS-R as of 4 August 2014

UNCLASSIFIED

UNCLASSIFIED

AS IS

Security • 900+ Security Stacks and 41 Service gateways • Pockets of excellence in each Service

Network • Single threaded, lower bandwidth DISN access connections • 117K inefficient point to point circuits

Cyber Situational Awareness (SA) • Disparate and uncoordinated analysis

Security • Reduced attack surface • Merge best of breed solutions for each threat • DoD protection with MILDEP unique cyber control Network • Improved network resiliency & command and control • 23K point to point circuits (save $400M+ per year)

Cyber Situational Awareness (SA) • Improved Cyberspace Detection and Diagnosis • Supports tailored SA views for all commands

JRSS Operational View

TO BE BASE X

Base B Base A

DISN

BASE X

Base B Base A

DISN

5

UNCLASSIFIED

UNCLASSIFIED July August September 6

1. JMS build-out

2. JBSA Migration

3. Cyber security & accreditation rigor

4. JRSS test events

5. WBS/Master schedule development

6. On-boarding & Mission assignment

Status

Commander’s Assessment

JRSS OPS Update

D O T M L P F S

5 2 1 6 4 3

1. JMS 0.5 risk = Low; JMS 1.0 = High

2. JBSA migration; JMT/SMT readiness, risk = Low

3. Multiple C & A/CND challenges, risk = Low

4. Shared management / Remote Access risk = Low

5. WBS/ Master Schedule development, risk = Low

6. GSM-O contracting actions, risk = Low

1. JMS v.5 awaiting VM & MS license delivery

• JMS 1.0 awaiting funding

2. JBSA Migration

• Multiple ASIs to be conducted this week

3. IATO S: (IATT expires 22 Aug)

• FSO has reviewed; expected award ~ 20 Aug

4. Testing

• System Acceptance and Shared Man. Testing ongoing

5. WBS/Integrated Master Schedule

• Draft IMS template and WBS dictionary developed

6. PWS for JMT

• Est Award ~ 15 Sep

• Completed two Alpha sessions

1. JMS acquisition award, delivery & installation schedule

2. Migration Plan supporting documents

3. None

4. SAT, Shared management, ROC/ROL drills

• TTPs in development to support test plan

5. None

6. GSM-O contract modifications

• Funding for long term

Priorities

Dependencies

Lab Train

ing

JMT

Aw

ard

JMS 0

.5

Fun

ction

al (avail fo

r trng)

IATO

Co

mp

lete

RO

C/R

OLS

Arm

y/AF

acceptan

ce to

Migrate

Ft Sam

Read

iness

review

SAT Test

Shared

M

anTest

FSH M

igrate

UNCLASSIFIED

UNCLASSIFIED 7

JRSS/JBSA Migration Tasks

19 Sep: (T) Final Readiness Review – Army G6, Tenant Customers, NETCOM, 7th SC, 24th AF, JMT

16 Sep: (T) Service GO Readiness Review

11-15 Aug: JMT huddle on FSH-JBSA

Legend

Pending

Complete

In Progress

In Progress (at risk)

Behind Schedule

21 Aug: ASI – Base FW interface migration

11-22 Aug: IWC Army, develop EIP and prepare for NIPR path migration

11-28 Aug: JMT / operator training

7-12 Sep: EIP – Additional Base cleanup

20-28 Aug: Shared management event and training (ICW JMT / operator training)

8-11 Sep: ROC and ROLS (Rehearsal of Concept / Rehearsal of Live Systems)

12 Sep: Action Officer Readiness Review with NETCOM, 7th SC, 106th TSSB, FSH NEC, JMT

13-21 Aug: EIP-NETMOD cleanup (Migrate server farm route-points to CE router)

20 Sept: Migrate FSH Base FW/IPS to Kelly JRSS

7-19 Sep: Stage FSH base FW and IPS in Kelly JRSS

4 11 18 25 1 8 15 22 29 AUG

14 Aug: ASI: Cutting over NIPR Circuit

22-24 Aug: ASI – Server Farm Consolidation