5 primary buildings◦ Converse◦ Robinson◦ Hackett◦ Todd◦ Merrill

The Swimming Pool

Completed Projects

Cunningham Intermediate School

Gaston Primary School

Fitness Center

McNeel

Aldrich

Memorial

Projects in Progress

Fran FruzenIntermediate School

Update as of January 29, 2014

North-East Exterior Front ViewNorth-West Exterior Front View

Architect Renderings

West Exterior ViewSouth-West Exterior View

Architect Renderings

South-East Exterior ViewNorth-East Exterior View

Architect Renderings

Site Layout

Sidewalk

4-6 Entrance

7/8 Entrance

Plaza

DumpsterEnclosure

HardSurfacePlay

Storage Building16 x 16

Site Plan

First Floor

First Floor= 70,242 SFSecond Floor= 30,214 SFTotal= 100,456 SF

Second Floor

First Floor= 70,242 SFSecond Floor= 30,214 SFTotal= 100,456 SF

Site Clearing/Demolition: March/April 2014

Bid Date: April 17, 2014

Construction Start: April 30, 2014

Construction Complete: July 31, 2015

Timeline

Tennis CourtsBig Field between 6th and 4th

ScoreboardsNew Storage for FootballPropane Tank outside of Swimming Pool

Athletic Fields