Upload
rosalyn-britt
View
27
Download
0
Embed Size (px)
DESCRIPTION
JWST S&OC Contract. Peter Stockman TIPS March 20, 2003. S&OC Proposal. Original Proposal submitted November 2001 Proposed cost comparable to unsolicited proposal, (330M w fee over 10 years) - PowerPoint PPT Presentation
Citation preview
1
Space Telescope Science Institute
JWST S&OC
JWST S&OC Contract
Peter Stockman
TIPS March 20, 2003
2
Space Telescope Science Institute
JWST S&OC
S&OC Proposal
• Original Proposal submitted November 2001 Proposed cost comparable to unsolicited proposal, (330M w fee over
10 years)
Project internal estimate: 140M (based largely on SMEX & MIDEX PI missions, inexpensive flight ops systems)
Extended review of proposal assumptions with Project in spring
• Revised proposal submitted on schedule (16 Sept.) to meet 176M target. Reductions achieved by the following assumptions:
• Govt. provides groundstations -- probably DSN
• Govt. provides I&T test system as basis of flight operations ground system (STScI was to provide originally)
• Govt. provides SI, OTE, S/C flight ops analysts for launch + 1 yr
• Just-in-time development schedule (no phased development to support SI, OTE, S/C dev.)
• No operations or science I&T support for SI, OTE, S/C.
• Reduced support to Project and SIs but w. overguides
3
Space Telescope Science Institute
JWST S&OC
Status of negotiations (began Jan. 15)
• Contract negotiations began in mid January Project puts back: management oversight, Project support,
special studies, PRD Ops. (~ 5M) and fenced these costs off. Project poses a new Target of 159.5 (without fee) AURA can meet new Project target:
• STScI roles are reduced significantly compared to HST (and Chandra and SIRTF experience)
» SI support» Commissioning planning for SIs and spacecraft.» Calibration software» Calibration analysis
• Assumes TRW develops I&T system near that needed for flight ops.
• Reduced planning system capabilities: no linked observations, routine scheduling of parallel calibrations, manual planning of the weekly calendar
• Late GO funding for Cycle 1 (Grants office startup delayed)
• Contract will be revised after results of replan: reduced instrument complement?, delayed schedule.
4
Space Telescope Science Institute
JWST S&OC
Key Assumptions
• SI s: The three JWST instruments will have the capabilities and complexity outlined in the ASWG and Project Scientists recommendations. In particular:
- The NIRCam will be a wide field, infrared camera with a limited set of fixed-band filter combinations (<20) and several elements used exclusively for wavefront-sensing.
- The NIRSpec will be a multi-object, single-order spectrograph with addressable apertures and a small number of fixed-position gratings (< 6).
- The MIRI will have two elements: a camera with a small number gratings and potentially a fixed pupil mask and Lyot stop for coronagraphy; a slit spectrograph with R ~1500 and a small number of fixed-position gratings.
- All three instruments will have a single target acquisition mode (including PEAKUP and/or PEAKDOWN). All three instruments will have a small number of common readout schemes (<3) and a common data format.
5
Space Telescope Science Institute
JWST S&OC
More Key Assumptions
• The S&OC systems will not support parallel activities. These include parallel calibration, pure parallel or coordinated parallel observations and parallel modes within instruments. Level 2 requirement 3.2.15.4 is applicable to the Observatory.
• The Fine Guidance Sensor will be sufficiently capable to enable guide star availability and selection to be done in an automated fashion by the S&OC. This assumes a wide field, highly capable guider that can satisfy the Level II requirement (3.2.15.2.2) for the 95% probability of guide star acquisition.
6
Space Telescope Science Institute
JWST S&OC
Many Miscellaneous
• The peak flight to ground data rate will be 25 GB/day.
• Level 1 data products will be available at L+3 months. Level 2 data products will be available at L+6 months.
• Targets of Opportunity are not supported within the time period of this contract.
• Etc. (about 70 such assumptions)
7
Space Telescope Science Institute
JWST S&OC
Current Status
• Technical aspects of contract appear to be satisfactory to NASA
• 2-3 week period to acquire needed signatures
8
Space Telescope Science Institute
JWST S&OC
Replan Status
• Challenge was to meet: Stringent budget limits in FY04-07
Launch date as close as possible to 2010
Overall cost of 1.6B
• NASA HQ has settled on Option 4i Launch in August 2011
About 110M cut in US instruments (down from ~ 160M)
• No MIRI
• 1/4 of NIRCam FOV, 1/8 NIRSpect FOV
Reduced primary mirror area (but meets spec)
Reduced testing plan
Challenged Project to save 40-50M in other areas to help restore instruments.
9
Space Telescope Science Institute
JWST S&OC
SWG & Project Studies
• SWG considering merging NIRCam and Canadian FGS: Potential saving of accommodations (mass, computer)
Elimination of short wavelength tunable filter
Shared electronic and detector procurement
• Project finding it difficult to achieve matching savings
• Other possibilities: Loss or reduced short wavelength performance.
Increased role for ESA in MIRI
• Emergency meeting for SWG in April 10,11