46
Kamala Hydroelectric Project Pre-Feasibility Report KAMALA HYDRO ELECTRIC POWER COMPANY LTD. (KHEPCL) Kamala Hydroelectric Project (1800 MW) Arunachal Pradesh Pre-Feasibility Report - July 2018

KAMALA HYDRO ELECTRIC POWER COMPANY LTD. (KHEPCL) · Hydro Electric Power Company Ltd.), a joint venture between Jindal Power Ltd and Hydro Power Development Corporation of Arunachal

  • Upload
    others

  • View
    4

  • Download
    0

Embed Size (px)

Citation preview

Page 1: KAMALA HYDRO ELECTRIC POWER COMPANY LTD. (KHEPCL) · Hydro Electric Power Company Ltd.), a joint venture between Jindal Power Ltd and Hydro Power Development Corporation of Arunachal

Kamala Hydroelectric Project Pre-Feasibility Report

KAMALA HYDRO ELECTRIC POWER

COMPANY LTD. (KHEPCL)

Kamala Hydroelectric Project (1800 MW)

Arunachal Pradesh

Pre-Feasibility Report

- July 2018

Page 2: KAMALA HYDRO ELECTRIC POWER COMPANY LTD. (KHEPCL) · Hydro Electric Power Company Ltd.), a joint venture between Jindal Power Ltd and Hydro Power Development Corporation of Arunachal

Kamala Hydroelectric Project Pre-Feasibility Report

Contents

1 INTRODUCTION ......................................................................................................... 4

General 4

Project Background ..................................................................................................... 4

Location & Accessibility ............................................................................................... 5

Details of Alternate Sites Considered ........................................................................... 5

2 SALIENT FEATURES OF THE PROJECT ................................................................ 10

3 JUSTIFICATION OF PROJECT FROM POWER SUPPLY ANGLE .......................... 14

3.1 Hydro Potential and Its Development ................................................................... 14

3.2 Power Demand and Supply Scenario in the Country ............................................ 15

3.3 Hydro Power Potential of the North-East .............................................................. 16

3.4 Hydropower Potential of Arunachal Pradesh ........................................................ 17

3.5 Necessity and Justification for Implementing the Project ....................... 18

3.6 Employment Generation ....................................................................... 18

4 GEOGRAPHICAL FEATURES AND TOPOGRAPHY ............................................... 19

Land requirement ....................................................................................................... 20

5 ENVIRONMENTAL AND ECOLOGICAL ASPECTS ................................................. 21

Introduction ................................................................................................................ 21

5.1.1 Meteorology .......................................................................................... 21

5.1.2 Soils ...................................................................................................... 22

5.1.3 Water Quality ........................................................................................ 22

5.1.4 Ambient Air Quality ............................................................................... 23

5.1.5 Vegetation ............................................................................................. 23

5.1.6 Fauna ................................................................................................... 23

5.1.7 Fisheries ............................................................................................... 24

Prediction of Impacts ................................................................................................. 24

5.1.8 Impacts on Water Environment ............................................................. 24

5.1.9 Impacts on Air Environment .................................................................. 26

5.1.10 Impacts on Noise Environment ............................................................. 27

5.1.11 Impacts on Land Environment ............................................................... 29

5.1.12 Impacts on Biological Environment ....................................................... 31

5.1.13 Impacts on Socio-Economic Environment ............................................. 34

Environmental Management Plan .............................................................................. 35

5.1.14 Environmental Measures during Construction Phase ............................ 35

5.1.15 Muck Disposal....................................................................................... 36

5.1.16 Restoration Plan for Quarry Sites .......................................................... 37

5.1.17 Compensation for Acquisition of Forest Land ........................................ 38

5.1.18 Wildlife Conservation ............................................................................ 38

5.1.19 Greenbelt Development ........................................................................ 38

5.1.20 Sustenance of Riverine Fisheries .......................................................... 38

5.1.21 Public Health Delivery System .............................................................. 39

Page 3: KAMALA HYDRO ELECTRIC POWER COMPANY LTD. (KHEPCL) · Hydro Electric Power Company Ltd.), a joint venture between Jindal Power Ltd and Hydro Power Development Corporation of Arunachal

Kamala Hydroelectric Project Pre-Feasibility Report

5.1.22 Maintenance of Water Quality ............................................................... 40

5.1.23 Control of Noise .................................................................................... 40

5.1.24 Control of Air Pollution .......................................................................... 41

6 RESETTLEMENT AND REHABILITATION PLAN .................................................... 43

7 PROJECT SCHEDULE & COST ESTIMATES .......................................................... 44

7.1.1 Project Cost .......................................................................................... 44

7.1.2 Implementation Schedule ...................................................................... 44

Compensation for Provision of Flood Moderation ....................................................... 45

8 ANALYSIS OF PROPOSAL ...................................................................................... 46

Page 4: KAMALA HYDRO ELECTRIC POWER COMPANY LTD. (KHEPCL) · Hydro Electric Power Company Ltd.), a joint venture between Jindal Power Ltd and Hydro Power Development Corporation of Arunachal

Kamala Hydroelectric Project Pre-Feasibility Report

1 INTRODUCTION

General

The state of Arunachal Pradesh is endowed with vast hydropower potential. Brahmaputra river is the

primary river basin in the state and offers significant irrigation and power benefits. One of the major

tributaries of the Brahmaputra is river Subansiri which contributes about 7.9% of the flows of river

Brahmaputra. River Kamla is a major tributary of river Subansiri.

Kamala Hydroelectric Project (formerly Subansiri Middle Hydroelectric Project) is proposed for

development on Kamla river. The project is located just upstream of Tamen village in Lower

Subansiri District; Tamen is about 55km from Ziro, the district headquarter. The project is conceived

as a multipurpose project with the twin objectives of power generation and flood moderation. To

meet these objectives a 216m high concrete gravity dam is envisaged which is designed to provide

storage for power generation and is also provided with a 15m exclusive cushion above the full

reservoir level to facilitate flood moderation. The main power plant, comprising eight generating

units of 216 MW, each, is housed in an underground cavern located in the left bank about 500m

downstream from the dam. Two additional generating units of 36 MW each are proposed in a dam

toe surface powerhouse on the right bank. These units will utilize the mandatory environmental

release from the dam. The total installed capacity of the project is 1800 MW - 1728 MW in the

underground powerhouse and 72 MW in the surface powerhouse.

Power generated from the project is planned to be brought to a pooling point through a 400kV

double circuit transmission line. The power is proposed to be ultimately transmitted to the National

Grid.

Project Background

The project was initially identified and planned by the Brahmaputra Board in consultation with CWC

and GSI and was subsequently assigned to NHPC for development (a more detailed description of

this is given in a subsequent section). As a first step, NHPC carried out a Feasibility Study and

confirmed the general suitability of the identified area to develop the project. A comprehensive field

investigation program was ensued by NHPC and a Detailed Project Report was prepared wherein a

221m high Concrete Faced Rockfill Dam was proposed along with an underground powerhouse

arrangement with an installed capacity of 1600 MW. The Report was however not submitted for

statutory clearances as the Government of Arunachal Pradesh decided to get the project

implemented through private participation.

Page 5: KAMALA HYDRO ELECTRIC POWER COMPANY LTD. (KHEPCL) · Hydro Electric Power Company Ltd.), a joint venture between Jindal Power Ltd and Hydro Power Development Corporation of Arunachal

Kamala Hydroelectric Project Pre-Feasibility Report

Development rights of the project have subsequently been accorded by the Government of

Arunachal Pradesh to Kamala Hydro Electric Power Company Limited (KHEPCL) (formerly Subansiri

Hydro Electric Power Company Ltd.), a joint venture between Jindal Power Ltd and Hydro Power

Development Corporation of Arunachal Pradesh Ltd. The concession period of the project is for 40

years on Build, Own, Operate and Transfer (BOOT) basis.

KHEPCL has engaged SNC-Lavalin Engineering India Pvt. Ltd. (SLEI) to act as its engineering

consultant for updation and preparation of the DPR.

Location & Accessibility

The project is located on river Kamla, a major right bank tributary of Subansiri river in Lower

Subansiri District of Arunachal Pradesh and falls in the Lower Himalaya region. Kamla river valley is

almost entirely hilly and mostly covered by dense forests.

The dam site as proposed in the present DPR is located around 4km upstream of Tamen village.

Tamen village is around 55km from Ziro, the headquarter of Lower Subansiri district. Ziro is about

130km from North Lakhimpur, the headquarter of Lakhimpur district. A paved road in good

condition goes from North Lakhimpur to Ziro and further to Daporijo via Tamen. North Lakhimpur is

connected to Guwahati by road as well as by air; the airport is at Lilabari, about 5 km from North

Lakhimpur.

The dam site is approachable through a black-topped road on left bank of Kamla; an unmetalled

road also exists on the right bank at a higher elevation. Both these roads take off from the Tamen-

Daporijo road near Tamen village. The roads are being maintained by Border Road Organization

(BRO).

The project location map is shown in Figure 1-1.

Details of Alternate Sites Considered

The project has been studied previously by Brahmaputra Board (pre-feasibility level), NHPC

(feasibility and DPR level) and KHEPCL (preliminary assessment). While the project development

stretch was kept unchanged in these studies, the location and type of the dam varied from concrete

gravity dam to a CFRD and back to a concrete gravity dam.

A brief synopsis of the schemes considered in these studies is given below.

Page 6: KAMALA HYDRO ELECTRIC POWER COMPANY LTD. (KHEPCL) · Hydro Electric Power Company Ltd.), a joint venture between Jindal Power Ltd and Hydro Power Development Corporation of Arunachal

Kamala Hydroelectric Project Pre-Feasibility Report

Studies by Brahmaputra Board

Brahmaputra Board started investigating the project in 1996. Two alternative dam sites were

identified on river Kamla, and were designated as Site-A and Site-B. The former was located 3.5km

upstream of Tamen while the latter was identified some 12.5km upstream of Tamen.

Brahmaputra Board in consultation with CWC and GSI considered Site-A as a better option from

geological, topographical and construction material point of view and decided to focus further

investigations at this site. Subsurface explorations were initiated and two exploratory bore holes,

one each on either bank at the proposed dam site, were drilled. However, before any further

progress could be made, the project was transferred to NHPC for preparation of Feasibility and

Detailed Project Reports.

Studies by NHPC

NHPC first carried out a feasibility level study of the project and then initiated detailed field

investigations and studies for preparation of the DPR. The Feasibility Study Report indicates that

NHPC did not consider the Brahmaputra Board axis (Site-A) as suitable citing presence of thick

overburden on the right bank and abundance of mica schist bands and shear zones in the rockmass

on the left bank. Instead, after detailed inspection of the area, NHPC identified two other axes

(located about 450m and 500m upstream of the Site-A axis selected by Brahmaputra Board) and

initiated detailed investigations at these axes. Narrower valley section and relatively better quality of

rock exposures at road level were cited as positive features of the selected area. These axes were

designated as A-5 (450m upstream of Site-A) and A-6 (500m upstream of Site-A).

A concrete gravity dam was planned near A-5/ A-6 axis and the powerhouse was proposed

underground inside the left bank of Kamla river. The powerhouse comprised 8 units of

200 MW, totalling an installed capacity of 1600 MW. Two alternatives with different FRL’s (and thus

different dam heights) were studied. Although the design head for the alternatives were different,

the installed capacity and number of units was kept unchanged by keeping different power

discharges. Size of the water conductor system was accordingly adjusted.

Upon approval of the Feasibility Report, NHPC embarked on preparation of the DPR. Through

detailed investigations and studies, NHPC concluded that the site selected during the feasibility stage

(near Axis A-5/A-6) was not suitable for a concrete dam - as per NHPC’s assessment the site would

require extensive stripping of abutments for founding a concrete gravity dam. Changing the dam

type to rockfill was contemplated but it was concluded that the topography around this axis was not

conducive for a fill type dam. Investigations were started on another axis located about 250m

Page 7: KAMALA HYDRO ELECTRIC POWER COMPANY LTD. (KHEPCL) · Hydro Electric Power Company Ltd.), a joint venture between Jindal Power Ltd and Hydro Power Development Corporation of Arunachal

Kamala Hydroelectric Project Pre-Feasibility Report

upstream of A-6; this axis was designated as

A-11. The investigation works comprised surface geological mapping, detailed geological and

geophysical investigations, remote sensing studies, subsurface investigations through drilling and

drifting, in-situ and laboratory rock mechanic testing etc.

Based on subsurface investigations, the geological conditions at the two alternative axes i.e. A-6 and

A-11, when compared, suggested that while there was significant improvement in the rockmass on

the left bank at A-11 axis, the right bank did not show any improvement. In fact, the bedrock in the

river bed at A-11 was found to be highly fractured and sheared. In view of favourable rock conditions

on left bank, dam axis was located near axis A-11 (nearly 20m downstream of A-11).

This site near A-11 was not considered suitable for placing a concrete gravity dam as the shear zone

in the river bed and slumping/sheared rockmass on the right abutment would have required

considerable excavation and foundation treatment. Accordingly, NHPC considered a Concrete Face

Rockfill Dam (CFRD) at this site citing the following advantages:

Complete removal of overburden/slumped rock is not necessary for a CFRD

Rock condition at left bank is favourable for laying spillways and other appurtenant

structures

Puku nallah which meets river Kamla upstream of the dam axis provides topographical

advantage of positioning spillway and diversion tunnels on the left bank

Any special foundation treatment in the riverbed shear zone shall not be required in case of

CFRD

CFRD would be a better choice in highly seismic area

Diversion tunnels and water conductor system were proposed on the left bank with the

underground powerhouse located at the same location on the left bank as in the Feasibility Report.

The Full reservoir Level for the project was kept at El 460m and an exclusive flood cushion of 15m

above FRL was finalized through Integrated Flood Moderation Studies of the basin1. Rule curve

defined as a part of the Integrated Flood Moderation Studies of the Subansiri basin projects was

specified to regulate the reservoir level during monsoons. Adequate spillway capacity was ensured

by providing surface spillway bays and tunnel spillways, both located on the left bank.

Page 8: KAMALA HYDRO ELECTRIC POWER COMPANY LTD. (KHEPCL) · Hydro Electric Power Company Ltd.), a joint venture between Jindal Power Ltd and Hydro Power Development Corporation of Arunachal

Kamala Hydroelectric Project Pre-Feasibility Report

Studies by KHEPCL

The present study commenced with an independent review of all previous study reports

including the investigation results. A few reconnaissance visits were undertaken and the

project area was thoroughly assessed. Drifts and core logs from drill holes were examined.

As a first step, it was confirmed that the project should be developed on the left bank as

proposed in the previous studies. Accessibility, relatively better geology and availability of

substantial amount of investigation results clearly weighed in favor of a left bank

development.

Location of the dam axis was finalized after a detailed assessment of all the alternative axes

and also considering the type of dam that suited a given location. As discussed in

subsequent sections of the report, a concrete dam is considered more suitable from flood

management as well as other perspectives. The geology at the selected axis, near Axis

A-5/A-6, is considered suitable for a concrete dam.

Study of alternative powerhouse arrangements comprised a dam toe option and an

underground alternative. As described in the report, underground location inside the left

bank just downstream of the dam location is proposed.

Alternative/optimization studies have also been undertaken for other project components

to arrive at the proposed layout and designs.

Location of the dam axis was finalized after a detailed assessment of all the alternative axes and also

considering the type of dam that suited a given location. As discussed in subsequent sections of the

report, a concrete dam is considered more suitable from flood management as well as other

perspectives. The geology at the selected axis, near Axis A-5/A-6, is considered suitable for a

concrete dam.

Page 9: KAMALA HYDRO ELECTRIC POWER COMPANY LTD. (KHEPCL) · Hydro Electric Power Company Ltd.), a joint venture between Jindal Power Ltd and Hydro Power Development Corporation of Arunachal

Kamala Hydroelectric Project Pre-Feasibility Report

Figure 1-1: Project Location Map

Project Area

Page 10: KAMALA HYDRO ELECTRIC POWER COMPANY LTD. (KHEPCL) · Hydro Electric Power Company Ltd.), a joint venture between Jindal Power Ltd and Hydro Power Development Corporation of Arunachal

Kamala Hydroelectric Project Pre-Feasibility Report

2 SALIENT FEATURES OF THE PROJECT

Location

State Arunachal Pradesh

District(s) Project components in lower

Subansiri district; Reservoir

in Lower Subansiri & Kurung

Kumey Districts

River Kamla

Dam Site 3 Km upstream of Tamen

Village

27o46’18”N, 93

o59’19”E

Hydrology

Catchment Area 7213 Km2

Probable Maximum Flood (PMF) 17416 Cumec

River Diversion Flood (1 in 25) 7520 Cumec

Ecological release 48.56 cumec

Reservoir

Maximum Water Level (MWL) El. 470.00m

Full Reservoir Level (FRL) El. 455.00m

Minimum Draw Down Level (MDDL) El. 430.00m

Gross Storage at MWL 2365.68 MCM

Gross Storage at FRL 1927.60 MCM

Gross Storage at MDDL 1304.04 MCM

Surcharge Storage 438.08 MCM

Live Storage 623.58 MCM

Area under Submergence at FRL 2775 Ha

Diversion Tunnels

Number 3 nos.

Diameter 13.5m, Circular

Length 915m to 1315m

Cofferdams

Type Rockfill with central clay core

Height of upstream cofferdam 64m

Height of downstream cofferdam 26m

Page 11: KAMALA HYDRO ELECTRIC POWER COMPANY LTD. (KHEPCL) · Hydro Electric Power Company Ltd.), a joint venture between Jindal Power Ltd and Hydro Power Development Corporation of Arunachal

Kamala Hydroelectric Project Pre-Feasibility Report

Dam

Type Concrete Gravity

Average river bed level El. 275.00m

Deepest foundation level El. 259.00m

Top of dam El. 475.00m

Height above deepest foundation 216m

Length of dam at top 628m

Spillway

o Main Spillway

Number of bays 7 nos.

Crest Elevation El. 370.00m

Opening Size 6.0m (W) x 10.5m (H)

Energy Dissipation Trajectory Bucket

o Auxillary Spillway

Number 1 no.

Crest Elevation El. 446.00m

Opening Size 6.0m (W) x 13.0m (H)

Power Intake

Number 4 nos.

Invert Elevation El. 406.00m

Size of Gate opening 6.0m (W) x 7.0m (H)

Headrace Tunnel

Number 4 nos. (Concrete lined)

Diameter & Shape 10m, circular

Length 515m to 815m

Design Discharge 308.5 cumec each

Pressure Shaft

Number 8 nos, steel lined

Diameter & Shape 5.7m, Circular

Length 270m each

Design Discharge 154.25 cumec each

Powerhouse (Main)

Page 12: KAMALA HYDRO ELECTRIC POWER COMPANY LTD. (KHEPCL) · Hydro Electric Power Company Ltd.), a joint venture between Jindal Power Ltd and Hydro Power Development Corporation of Arunachal

Kamala Hydroelectric Project Pre-Feasibility Report

Type Underground

Installed Capacity 1728 MW

Type of Turbine Vertical Axis Francis

Number of Units 8 x 216 MW

Cavern Size 302m (L) x 23m (W) x 56.5m

(H)

Turbine Centerline Elevation El. 275.00m

MIV Floor level El. 270.00m

Turbine Floor level El. 278.70m

Generator Floor level El. 283.70m

Operating Floor & Service Bay level El. 289.20m

Rated Net Head 154.17m

Annual Energy in 90% dependable year 6739.0 MU

Transformer Cavern

Size 297m (L) x 16.5m (W) x

25.5m (H)

Transformer floor level El. 289.20m

GIS floor level El. 301.20m

Collection Gallery

Size 212m (L) x 15m (W) x 65m

(H)

Maximum Surge Level El. 307.50m

Minimum Surge Level El. 273.40m

Gate operation level El. 309.00m

Gate Numbers and Size 8 nos, 8m (W) x 8m (H)

Tailrace Tunnels

Number 4

Diameter & Shape 10m, Circular shape

Lengths 415m to 555m

High Flood level El. 306.20m

Normal Tailwater Level El. 285.50m

Gate numbers & size 8 nos, 6m(W)x10m(H)

Pothead Yard

Type Outdoor

Elevation El. 430.00m

Size 150m (L) x 55m (W)

Page 13: KAMALA HYDRO ELECTRIC POWER COMPANY LTD. (KHEPCL) · Hydro Electric Power Company Ltd.), a joint venture between Jindal Power Ltd and Hydro Power Development Corporation of Arunachal

Kamala Hydroelectric Project Pre-Feasibility Report

Dam-Toe Scheme

o Intake Structure

Number 1 no.

Invert Level El 418.00m

Size of Gate Opening 3.25m (W) x 4m (H)

Design Discharge 48.56 cumec

o Penstock

Number, Diameter & length

Main Penstock 1 no., 4m dia, Circular, 166m

Unit Penstock 2 nos., 2.8m dia, Circular,

68m & 76m

o Powerhouse (Auxillary)

Type Surface

Size 30.5m (L)x19.5m

(W)x48.1m(H)

Installed Capacity 72MW

Type of Turbine Vertical Axis Francis

Number of units 2 x 36 MW

Turbine Centerline elevation El. 274.00m

Annual Energy in 90% dependable year 599.0 MU

Page 14: KAMALA HYDRO ELECTRIC POWER COMPANY LTD. (KHEPCL) · Hydro Electric Power Company Ltd.), a joint venture between Jindal Power Ltd and Hydro Power Development Corporation of Arunachal

Kamala Hydroelectric Project Pre-Feasibility Report

3 JUSTIFICATION OF PROJECT FROM POWER SUPPLY ANGLE

Hydro power is the richest renewable and environmentally benign source of energy. Hydroelectric

stations have the inherent ability of instantaneous starting, stopping and managing load variations,

which helps in improving reliability of the power system. Hydroelectric stations are the natural

choice for meeting peak demand. The generation cost is inflation free and, in fact, reduces over

time. A hydroelectric project has a useful life extending to well over 35 years and helps in conserving

scarce fossil fuels.

Development of hydro power projects also provides the added advantage of opening up avenues for

development of remote and backward areas of the state. Despite being recognised as a renewable

source of energy, the share of hydro power in the overall generating capacity in the country has

been steadily declining since 1963. The share of hydro power has declined from 44% in 1970 to

about 17.5% today.

Several constraints have affected the pace of hydro power development, including non-availability of

long term financing and viability of tariff. Many hydro projects have been adversely affected by

geological surprises, especially during underground excavation. Other problems arising out of the

inaccessible and remote location of the site, delays in land acquisitions and in resettlement of

families affected by the projects have also slowed the pace of hydro power development in the

country.

Government of India has now accorded high priority to the development of hydro potential and has

taken a number of policy initiatives to address the issues impeding hydro power development. In

accordance with the latest hydro power policy (2008), the Government of India is encouraging

substantial private investment in hydro power development.

In order to hasten the progress of hydroelectric generation, a large number of projects have been

identified and their viability has been confirmed through pre-feasibility studies. Many of these

projects have been awarded to private developers who are actively engaged in their

implementation.

3.1 Hydro Potential and Its Development

The total installed capacity in the country, as on 31st May, 2018, is 343898 MW of which

hydroelectric schemes contribute 45403 MW (13.2 %). All India and Region-wise installed capacity of

power utilities are given below in Tables 2-1 and 2-2.

Page 15: KAMALA HYDRO ELECTRIC POWER COMPANY LTD. (KHEPCL) · Hydro Electric Power Company Ltd.), a joint venture between Jindal Power Ltd and Hydro Power Development Corporation of Arunachal

Kamala Hydroelectric Project Pre-Feasibility Report

Table 1: Sector-wise Installed Capacity of Power Utilities as on 31st May, 2018

(Figures in MW)

Sector Hydro Thermal

Nuclear R.E.S Total Coal Gas Diesel Total

State 29,858.00 64456.50 7078.95 363.93 71899.38 0 2003.37 103760.75

Private 3,394.00 75546.00 10580.60 473.70 86600.30 0 65516.72 155511.02

Central 12151.42 56955.00 7237.91 0 64192.91 6780.00 1502.30 84626.63

Total 45403.42 196957.50 24897.46 837.63 222692.59 6780.00 69022.39 343898.39

Source: CEA Website

Table 2: Region-wise Installed Capacity of Power Utilities as on 31st May, 2018

(Figures in MW)

Sector Hydro

Thermal

Nuclear R.E.S Total

Coal Gas Diesel Total

Northern 19653.77 52845.20 5781.26 0.00 58626.46 1,620.00 12873.22 92773.45

Western 7547.50 70608.62 10806.49 0.00 81415.11 1,840.00 20446.38 111248.99

Southern 11808.03 45782.02 6473.66 761.58 53017.26 3,320.00 34369.28 102514.57

Eastern 4942.12 27201.64 100.00 0.00 27301.64 0.00 1038.40 33282.16

N Eastern 1452.00 520.02 1736.05 36.00 2292.07 0.00 282.56 4026.63

Islands 0.00 0.00 0.00 40.05 40.05 0.00 12.56 52.61

All India 45403.42 196957.50 24897.46 837.63 222692.59 6780.00 69022.39 343898.39

Source: CEA website

Re-assessment Studies of hydroelectric potential of the country, completed by Central Electricity

Authority in 1987, have assessed the economically exploitable hydro power potential in terms of

installed capacity as 148,701 MW, of which 145,320 MW is from schemes having capacity above 25

MW.

3.2 Power Demand and Supply Scenario in the Country

The country has been facing growing shortages of power over the past five years. During the 11th

Plan (2007 - 2012), the average energy shortage in the country was about 400 Billion kWh (10%).

During the 12th Plan, the peak deficit was about 12,000 MW (9%) and the average energy shortage in

the country was about 50 Billion kWh (8.6%).

Page 16: KAMALA HYDRO ELECTRIC POWER COMPANY LTD. (KHEPCL) · Hydro Electric Power Company Ltd.), a joint venture between Jindal Power Ltd and Hydro Power Development Corporation of Arunachal

Kamala Hydroelectric Project Pre-Feasibility Report

Details of peak and energy shortages in the country from 2009 onwards are given in Table 3 below:

Table 3: Actual Power Supply Position of India

Peak

Demand

Peak

availability Surplus/Deficit

Energy

Requirement

Energy

Availability Surplus/ Deficit

(MW) (MW) (MW) (%) (MU) (MU) (MU) (%)

2009-10 1,19,166 1,04,009 -15,157 -12.7 8,30,594 7,46,644 -83,950 -10.1

2010-11 1,22,287 1,10,256 -12,031 -9.8 8,61,591 7,88,355 -73,236 -8.5

2011-12 1,30,006 1,16,191 -13,815 -10.6 9,37,199 8,57,886 -79,313 -8.5

2012-13 1,35,453 1,23,294 -12,159 -9.0 9,95,557 9,08,652 -86,905 -8.7

2013-14 1,35,918 1,29,815 -6,103 -4.5 10,02,257 9,59,829 -42,428 -4.2

2014-15 1,48,166 1,41,160 -7,006 -4.7 10,68,923 10,30,785 -38,138 -3.6

2015-16 1,53,366 1,48,463 -4,903 -3.2 11,14,408 10,90,850 -23,558 -2.1

2016-17 1,59,542 1,56,934 -2,608 -1.6 11,42,929 11,35,334 -7,595 -0.7

2017-18 1,64,066 1,60,752 -3,314 -2.0 12,12,134 12,03,567 -8,567 -0.7

2018-19* 1,73,226 1,70,765 -2,461 -1.4 2,16,292 2,14,971 -1,321 -0.6

Source: CEA Website

As per the report of the 19th Electric Power Survey, demand projections for the year 2021-22 &

2026-27 are as follows:

Table 4: Demand adopted for generation planning studies

Energy Requirement (GWh) Peak Load (MW)

2021-22 1566000 226000

2026-27 2047000 299000

Source: CEA Website

Rigorous advance planning/action is clearly required to achieve these formidable targets.

3.3 Hydro Power Potential of the North-East

The North-Eastern Region (NER) of the country comprises seven states: Arunachal Pradesh, Assam,

Manipur, Meghalaya, Mizoram, Nagaland, and Tripura. The area is endowed with bountiful water

resources with Brahmaputra flowing in the northern part and the Barak (Meghna) flowing through

Page 17: KAMALA HYDRO ELECTRIC POWER COMPANY LTD. (KHEPCL) · Hydro Electric Power Company Ltd.), a joint venture between Jindal Power Ltd and Hydro Power Development Corporation of Arunachal

Kamala Hydroelectric Project Pre-Feasibility Report

the southern margins. These two rivers, along with their numerous tributaries, have created a very

dynamic and powerful hydrologic regime in the region.

The state-wise estimated hydroelectric potential of the north-eastern region and its status of

development, as on 31st March, 2017, is given below:

Table 5: State-wise estimated hydroelectric potential of North-Eastern Region

State

Identified Potential as

per Re-assessment Study

(MW)

Capacity Developed

(schemes above 25 MW

capacity) (MW)

Capacity Under

Construction (schemes

above 25 MW capacity)

(MW)

Arunachal Pradesh 50328 405 2854

Assam 680 375 0

Manipur 1784 105 0

Meghalaya 2394 282 40

Mizoram 2196 0 60

Nagaland 1574 75 0

Tripura 15 0 0

Total 58971 1242 2954

Source: CEA Website

3.4 Hydropower Potential of Arunachal Pradesh

The topography of the state provides very ideal conditions for developing hydroelectric projects.

There are five major river basins in the state, namely Kameng, Subansiri, Siang, Dibang and Lohit.

There are also many smaller river systems in the state which offer very attractive sites for

hydroelectric projects. Almost all the major river systems flow in the north-south direction and

ultimately drain into the Brahmaputra. Apart from the major rivers, the state has many small

perennial rivulets providing ideal conditions for developing micro/mini and small hydroelectric

projects. As per the preliminary ranking study done by the Central Electricity Authority (CEA), the

total power potential from hydro projects in the north-eastern region is estimated to be about

58,971 MW, of which 50328 MW is in Arunachal Pradesh

Page 18: KAMALA HYDRO ELECTRIC POWER COMPANY LTD. (KHEPCL) · Hydro Electric Power Company Ltd.), a joint venture between Jindal Power Ltd and Hydro Power Development Corporation of Arunachal

Kamala Hydroelectric Project Pre-Feasibility Report

3.5 Necessity and Justification for Implementing the Project

The state plans to harness its enormous natural resource of hydro power and exploit its mineral

wealth to usher in an era of economic development and raise the per capita electricity consumption.

Comparing the projected growth of peak power demand, energy requirement anticipated and

increase in the generating capacity on the basis of new projects proposed and/or under

construction/consideration during 12th Five Year Plan, it is evident that there is a dire need to

provide additional power to the National Grid. New schemes have to be taken up immediately and

implemented to derive timely benefits. The most important source of power development in the

north-eastern region is Arunachal Pradesh and other sister states.

The power from hydro projects in the north-eastern region would be in excess of the demand in the

region and would have to be exported for utilization in other regions of the country. Presently there

is no problem in the availability of transmission systems beyond the north-eastern power region for

distribution of power as the five power regions of the country are in the process of greater

integration within a national grid.

Considering the growth of peak demand and anticipated addition of generating capacity in the state,

the region and the country, and also from the current status of development of hydro power

potential of Arunachal Pradesh, it is pragmatic that earnest efforts are made for developing the

hydro power sector of the state. Implementation of Kamala Hydroelectric Project of 1800 MW

capacity would contribute significantly towards meeting this objective.

3.6 Employment Generation

The peak manpower strength likely to be employed during project construction stage is estimated

about 3000 Nos. Based on experience of similar projects, the increase in the population as a result of

migration may be of the order of 12000.

During the operation phase only a small number of staff, about 220 persons will be residing in the

project colony proposed to be developed.

Page 19: KAMALA HYDRO ELECTRIC POWER COMPANY LTD. (KHEPCL) · Hydro Electric Power Company Ltd.), a joint venture between Jindal Power Ltd and Hydro Power Development Corporation of Arunachal

Kamala Hydroelectric Project Pre-Feasibility Report

4 GEOGRAPHICAL FEATURES AND TOPOGRAPHY

The Subansiri River, in the basin of which the Project is located, is a prominent right bank tributary of

Brahmaputra. It originates in Tethys Himalaya in Tibet as Tsari Chu and cutting through Higher

Himalaya, it drains about 30,000 sq.km area in Lesser and Sub-Himalayan parts of Miri and western

parts of Abor Hills. It debouches into Brahmaputra Plains near Dulangmukh in Assam (El. 152m

above msl). The river in Himalayan sector has a length of about 208km and riverbed falls from an

altitude of 4206m to 152m in this reach. The Subansiri river and its tributaries in the plains flow

along a straight braided to highly meandering course.

The Kamla river, on which the proposed project is envisaged, is a main right bank tributary of

Subansiri river. It rises at an altitude of 6488m in Higher Himalaya and flows in southeasterly

direction almost parallel to the course of Subansiri River. It drains approximately 7000 sq.km. area in

Miri Hills and joins the main Subansiri river at Leling. Kurung river is a major right bank tributary of

Kamla that flows in NW direction and joins it east of Bala village at about 280m above msl.

In broad geomorphic classification, the area around the Kamala Hydroelectric Project lies in Lesser

Himalayan physiographic unit wherein mountain ranges are characterized by moderately dissected,

fine drainage textured, sharp crested ridges and is defined as S1e geomorphic unit of structural

origin. The trunk river Kamla in the project area flows along a meandering course towards SE

through a moderately wide valley with moderately steep valley slopes. The river, downstream of the

project area, near Tamen, turns towards east and follows WE course beyond that. The relief in the

area is moderate and valley slopes are generally covered with slopewash deposits that support

dense vegetation. The terrain is moderately dissected by various streams. The drainage pattern is

sub-dendritic to dendritic and drainage density moderate.

At the proposed dam site river Kamla flows towards SE through a symmetrical V-shaped valley. The

river width at various stretches in the area varies between 60m and 100m. Both the abutments rise

above riverbed at about 40° slopes except in short stretches where steeper or gentle slopes have

been observed locally. However, the valley attains a slightly asymmetric shape as one moves

upstream of the dam axis, where left abutment is comparatively steep as compared to right

abutment.

The project area exposes the gneissic rocks belonging to Daparijo/Ziro Gneiss. The granite gneiss

extends monotonously from Ziro-Hapoli region in the south to ENE towards Daparijo. This sequence

constitutes a part of Bomdilla Group and has been variously called as Daparijo/Ziro/Palin/Chakoo

Gneiss.

Page 20: KAMALA HYDRO ELECTRIC POWER COMPANY LTD. (KHEPCL) · Hydro Electric Power Company Ltd.), a joint venture between Jindal Power Ltd and Hydro Power Development Corporation of Arunachal

Kamala Hydroelectric Project Pre-Feasibility Report

The rock of Ziro Group consists of mainly biotite gneiss, augen gneiss, garnetiferous sillimanite

hornblende gneiss, mica schist, leucogranite and amphibolite. They are bounded by Sippi thrust in

the north-west, which has brought the low grade metasedimentaries of Niumi Formation in

juxtaposition with high grade gneiss. The south-east boundary is defined by unconformable contact

with the low grade metasedimentary rocks of Khetabari Group.

The gneisses exposed in the project area are foliated and traversed by three prominent sets of joints

in addition to those oriented along the foliation. These are folded in isoclinal and overturned folds.

As per the seismic zoning map of India (IS 1893: Part-I (2002)), the area around the proposed project

is located in Zone-V. The seismic Zone-V is broadly associated with seismic intensity IX and above on

MMI scale.

Land requirement

The total land to be acquired for the project is 3279 ha. The permanent and temporary land

acquisition is 3163 ha and 116 ha respectively. The land to be acquired for the project shall include

private, government and forest land as well. Based on the ownership status of land to be acquired

for the project, appropriate compensatory measures shall be implemented.

Page 21: KAMALA HYDRO ELECTRIC POWER COMPANY LTD. (KHEPCL) · Hydro Electric Power Company Ltd.), a joint venture between Jindal Power Ltd and Hydro Power Development Corporation of Arunachal

Kamala Hydroelectric Project Pre-Feasibility Report

5 ENVIRONMENTAL AND ECOLOGICAL ASPECTS

Introduction

Like any other developmental activity, the proposed hydroelectric project, while providing

planned benefit i.e. hydropower generation could also lead to a variety of adverse

environmental impacts as well. However, by proper planning at the inception and design

stages and by adopting appropriate mitigation measures in the planning, design,

construction and operation phases, the adverse impacts can be minimized to a large extent,

whereas the beneficial impacts could be maximized.

The present Chapter attempts a preliminary assessment of impacts likely to accrue during

project construction and operation phases of the proposed project. The Chapter also outlines

the framework of Environmental Management Plan (EMP) for mitigation of adverse impacts.

An Environmental Monitoring Programme too been delineated in the present chapter for

implementation during project construction and operation phases.

5.1.1 Meteorology

The Subansiri basin has four distinct seasons. The winter season lasts from December to

February, followed by the pre-monsoon season from March to May. The monsoon season

begins in June and continues upto middle of October. The period from second half of the

October to November is the post-monsoon season.

The months of January & February are the coolest months. The temperature varies from

place to place depending on the elevation. At higher elevations, the temperature in the

winter months goes even below the freezing point. The temperature rises gradually after

February. Except in the foothill region, the summer season is not distinctly palpable in the

area. The south-west monsoon season is slightly warmer than the period from March to

May.

The Subansiri basin extends from tropical to temperate zones and therefore, the area

exhibits a great diversity in rainfall characteristics. The annual normal rainfall in Subansiri

basin varies from 630mm at Raga to 4740mm at Gerukamukh. A major portion of the rainfall

is received in the south-west monsoon season. During the period from November to March,

western disturbances pass across or near the region from west to east. In association with

these disturbances, precipitation is received at lower elevations and snow fall at higher

elevations. The intensity of rainfall is extremely high in the project area, with a tendency to

decrease towards the north-east.

Page 22: KAMALA HYDRO ELECTRIC POWER COMPANY LTD. (KHEPCL) · Hydro Electric Power Company Ltd.), a joint venture between Jindal Power Ltd and Hydro Power Development Corporation of Arunachal

Kamala Hydroelectric Project Pre-Feasibility Report

The climate is highly humid throughout the year. The relative humidity varies from a

maximum of 94% to a minimum of 62%.

5.1.2 Soils

Soil is the product of geological, chemical and biological interactions. The soils in a region

vary according to altitude and climate. The soils in the project and the study areas, like any

other region of Himalayas are young. The vegetal cover is one of the most important

influencing factors characterizing the soil types in a region. Soil on the slopes above 30o,

due to erosion and mass wasting processes, are generally shallow and usually have very

thin surface horizons. The texture of such soils is medium to coarse. Residual soils are well

developed on level summits of lesser Himalayas, sub-soils are deep and heavily textured.

High contents of organic matter are found in its `A’ horizon and are acidic in nature.

Valley soils are developed from coalluvium and alluvium brought down from the upper

slopes and thus is deposited in the valleys and low-lying tracts or river terraces as a process

of aggradation. In general north facing slopes support deep, moist and fertile soils. The

south facing slopes on the other hand, are too precipitous and well exposed to denudation.

The pH of the soil is in neutral range. The low EC values indicate low salt content. The levels

of nutrients indicate that the soil has low to moderate productivity. The continuous washout

of nutrients along with runoff as a result of high precipitation and steep slopes can be

attributed for this phenomenon.

5.1.3 Water Quality

The proposed project is located in an area with low population density with no major sources

of pollution. There are no industries in the area. The area under agriculture is quite less,

which coupled with negligible use of agro-chemicals, means that apart from domestic

sources, pollution loading from other sources is virtually negligible.

The total hardness in water samples ranges from 44 to 51mg/l in winter and 38 to 45mg/l in

summer seasons respectively. The low hardness level can be attributed to low calcium and

magnesium levels, which are responsible for soft nature of water. The low EC and

TDS values indicate the lower concentration of cations and anions. The concentration of

TDS level ranges from 74 to 80mg/l in winter and 70 to 78 mg/l in summer season, which is

much lower than the permissible limit of 500mg/l specified for domestic use. This is also

reflected by the fact that the concentration of most of the cations and anions are well within

the permissible limit.

Page 23: KAMALA HYDRO ELECTRIC POWER COMPANY LTD. (KHEPCL) · Hydro Electric Power Company Ltd.), a joint venture between Jindal Power Ltd and Hydro Power Development Corporation of Arunachal

Kamala Hydroelectric Project Pre-Feasibility Report

The BOD values are well within the permissible limits, which indicate the absence of organic

pollution loading. This is mainly due to the low population density and absence of industries

in the area. The low COD values also indicate the absence of chemical pollution loading in

the area. The marginal quantity of pollution load, which enters river Kamla, gets diluted.

In fact, even for the minimum flow, there is more than adequate water available for dilution.

The heavy metal concentration in the study area is below the permissible limit used for

drinking purposes. Total Coliform count is nil in the study area. It can be concluded that

water quality was observed to be quite good, as various parameters are well below the

permissible limit specified for meeting domestic requirements.

5.1.4 Ambient Air Quality

In a water resource project, impacts on air quality are marginal and limited only during

construction phase. The population density in the area is low. The number of vehicles plying

in the area is insignificantly low to cause any air pollution. This coupled with the fact that

there are no industries in the area, means that there are no major sources of air pollution.

5.1.5 Vegetation

Based on elevation and species composition, the forests in the study area of Kamala Hydro

Electric Project may be categorized into the following broad forest types:

Tropical Evergreen Forests: This type of forest was found in the catchment area of

the project.

Tropical Semi-Evergreen Forests: This type of forest was found in patches along

with tropical evergreen forests, particularly at the Dam site where deciduous

components dominated.

Tropical deciduous forests: This type of forest was found at Dam site and nearby

Power House site.

Riverine forests: This type of forest was present along banks of the river and along

the stream banks at the Dam site and Catchment area.

5.1.6 Fauna

Arunachal Pradesh has a rich diversity of fauna which has gathered the attention of

researchers and naturalists for the past many years. The systematic survey, collection and

inventorisation of the faunal diversity were started in the year 1916 with the establishment of

the Zoological Survey of India (ZSI). The present study has been carried out with the

following objectives: (1) inventorisation of the faunal diversity, and (2) to list the rare,

Page 24: KAMALA HYDRO ELECTRIC POWER COMPANY LTD. (KHEPCL) · Hydro Electric Power Company Ltd.), a joint venture between Jindal Power Ltd and Hydro Power Development Corporation of Arunachal

Kamala Hydroelectric Project Pre-Feasibility Report

endangered and threatened category of species in the study area i.e. Kamala Hydro Electric

Project in the Lower Subansiri District of Arunachal Pradesh.

5.1.7 Fisheries

Species of fishes found in the area are snowtrout, Chagunio/Balitora, Putitor mahseer, Tor

mahseer, Gotyla & Garra. None of the fish species fall under any threat category of IUCN.

Prediction of Impacts

Prediction is essentially a process to forecast the future environmental conditions of the

project area that might be expected to occur because of the implementation of the project.

Based on the project details and the baseline environmental status, potential impacts as a

result of the construction and operation of the proposed project have been identified.

5.1.8 Impacts on Water Environment

a) Construction phase

i) Sewage from labour camps

The peak manpower strength likely to be employed during project construction phase is

about 3000 nos. The employment opportunities in the area are limited. Thus, during the

project construction phase, some of the locals may get employment.

The construction phase also leads to mushrooming of various allied activities to meet the

demands of the immigrant labour population in the project area. Based on experience of

similar projects and above referred assumptions, the increase in the population as a result of

migration of labour population during construction phase is expected to be of the order of

12000.

The domestic water requirement has been estimated as 70 lpcd. Thus, total water

requirements work out to 0.70mld. It is assumed that about 80% of the water supplied will be

generated as sewage. Thus, total quantum of sewage generated is expected to be of the

order of 0.67mld. The BOD load contributed by domestic sources will be about 450kg/day.

No major impact is anticipated on river water quality, as a result of disposal of sewage from

labour camps. Even though no impact is envisaged on water quality of river Kamla, as a

result of disposal of untreated sewage, it is recommended to commission units for treatment

of sewage generated from labour camps. In the proposed project, sewage is proposed to be

treated, prior to disposal.

Page 25: KAMALA HYDRO ELECTRIC POWER COMPANY LTD. (KHEPCL) · Hydro Electric Power Company Ltd.), a joint venture between Jindal Power Ltd and Hydro Power Development Corporation of Arunachal

Kamala Hydroelectric Project Pre-Feasibility Report

ii) Effluent from crushers

During construction phase, four crushers will be commissioned at the site by the contractor

involved in construction activities. It is proposed only crushed material would be brought at

construction site. The total capacities of the crushers are likely to be of the order of 2000 tph.

Water is required to wash the boulders and to lower the temperature of the crushing edge.

About 0.1m3 of water is required per ton of material crushed. The effluent from the crusher

would contain high-suspended solids. About 190m3/hr of wastewater is expected to be

generated from each crusher. The effluent, if disposed without treatment can lead to

marginal increase in the turbidity levels in the receiving water bodies. It is proposed to treat

the effluent from crushers in settling tank before disposal so as to ameliorate even the

marginal impacts likely to accrue on this account.

b) Operation phase

The major sources of water pollution during project operation phase include:

Effluent from project colony.

Impacts on reservoir water quality.

i) Effluent from project colony

During project operation phase, due to absence of any large-scale construction activity,

the cause and source of water pollution will be much different. Since, only a small number of

O&M staff will reside in the area in a well-designed colony with sewage treatment plant and

other infrastructure facilities, the problems of water pollution due to disposal of sewage are

not anticipated.

In the operation phase, about 100 families (total population of 300) will be residing in the

project colony. About 0.2 to 0.3 mld of sewage will be generated. It is proposed to provide

biological treatment facilities including secondary treatment units for sewage so generated

from the BOD load after treatment will reduce to 10 to 12kg/day. It shall be ensured that

sewage from the project colony be treated in a sewage treatment plant so as to meet the

disposal standards for effluent. Thus, with commissioning of facilities for sewage treatment,

no impact on receiving water body is anticipated. Thus, no impacts are anticipated as a

result of disposal of effluents from the project colony.

ii) Impacts on reservoir water quality

The flooding of previously forest and agricultural land in the submergence area will increase

the availability of nutrients resulting from decomposition of vegetative matter. Phytoplankton

Page 26: KAMALA HYDRO ELECTRIC POWER COMPANY LTD. (KHEPCL) · Hydro Electric Power Company Ltd.), a joint venture between Jindal Power Ltd and Hydro Power Development Corporation of Arunachal

Kamala Hydroelectric Project Pre-Feasibility Report

productivity can supersaturate the euphotic zone with oxygen before contributing to the

accommodation of organic matter in the sediments. Enrichment of impounded water with

organic and inorganic nutrients will be the main water quality problem immediately on

commencement of the operation. However, this phenomenon is likely to last for a short

duration of few years from the filling up of the reservoir. In the proposed project, most of the

land coming under reservoir submergence is barren, with few patches of trees. These trees

too are likely to be cleared before filling up of the reservoir. The proposed project is

conceived as a multipurpose project with the twin objective of power generation and flood

moderation, with significant diurnal variations in reservoir water level. In such a scenario,

significant re-aeration from natural atmosphere takes place, which maintains Dissolved

Oxygen in the water body. Thus, in the proposed project, no significant reduction in D.O.

level in reservoir water is anticipated.

5.1.9 Impacts on Air Environment

In a water resources project, air pollution occurs mainly during project construction phase.

The major sources of air pollution during construction phase are:

Pollution due to fuel combustion in various equipment

Emission from various crushers

Dust emission from muck disposal

Pollution due to fuel combustion in various equipment

The operation of various construction equipment requires combustion of fuel. Normally,

diesel is used in such equipment. The major pollutant which gets emitted as a result of

combustion of diesel is SO2. The SPM emissions are minimal due to low ash content in

diesel. The short-term increase in SO2, even assuming that all the equipment are operating

at a common point, is quite low, i.e. of the order of less than 1g/m3. Hence, no major impact

is anticipated on this account on ambient air quality.

Emissions from crushers

The operation of the crusher during the construction phase is likely to generate fugitive

emissions, which can move even up to 1km in predominant wind direction.

During construction phase, four crushers are likely to be commissioned near proposed dam

and power house site. During crushing operations, fugitive emissions comprising mainly the

suspended particulate will be generated. Since, there are no major settlements close to the

dam and power house, hence, no major adverse impacts on this account are anticipated.

However, during the layout design, care should be taken to ensure that the labour camps,

Page 27: KAMALA HYDRO ELECTRIC POWER COMPANY LTD. (KHEPCL) · Hydro Electric Power Company Ltd.), a joint venture between Jindal Power Ltd and Hydro Power Development Corporation of Arunachal

Kamala Hydroelectric Project Pre-Feasibility Report

colonies, etc. are located on the leeward side and outside the impact zone (say about 2km

on the wind direction) of the crushers.

Dust emission from muck disposal

The loading and unloading of muck is one of the source of dust generation. Since, muck will

be mainly in form of small rock pieces, stone, etc., with very little dust particles. Significant

amount of dust is not expected to be generated on this account. Thus, adverse impacts due

to dust generation during muck disposal are not expected.

5.1.10 Impacts on Noise Environment

a) Construction phase

In a water resource project, the impacts on ambient noise levels are expected only during

the project construction phase due to earth moving machinery, etc. Likewise, noise due to

quarrying, blasting, vehicular movement will have some adverse impacts on the ambient

noise levels in the area.

i) Impacts due to operation of construction equipment

The noise level due to operation of various construction equipment is given in Table 10510.

Table 105: Noise level due to operation of various construction equipment

Equipment Noise level dB(A)

Earth moving

Compactors 70-72

Loaders and Excavator 72-82

Dumper 72-92

Tractors 76-92

Scrappers, graders 82-92

Pavers 86-88

Truck 84-94

Material handling

Concrete mixers 75-85

Movable cranes 82-84

Stationary

Pumps 68-70

Generators 72-82

Compressors 75-85

Page 28: KAMALA HYDRO ELECTRIC POWER COMPANY LTD. (KHEPCL) · Hydro Electric Power Company Ltd.), a joint venture between Jindal Power Ltd and Hydro Power Development Corporation of Arunachal

Kamala Hydroelectric Project Pre-Feasibility Report

Under the worst-case scenario, considered for prediction of noise levels during construction

phase, it has been assumed that all these equipment generate noise from a common point.

The increase in noise levels due to operation of various construction equipment is given in

Table 1111.

Table 11: Increase in noise levels due to operation of various construction equipment

Distance (m)

Ambient noise levels dB(A)

Increase in noise level due to construction

activities dB(A)

Increased noise level due to construction

activities dB(A)

Increase in ambient noise level due to

construction activities dB(A)

100 36 45 45 34

200 36 39 39 29

500 36 31 31 25

1000 36 25 25 25

1500 36 21 21 24

2000 36 19 19 24

2500 36 17 17 24

3000 36 15 15 24

It would be worthwhile to mention here that in absence of the data on actual location of

various construction equipment, all the equipment have been assumed to operate at a

common point. This assumption leads to over-estimation of the increase in noise levels.

Also, it is a known fact that there is a reduction in noise level as the sound wave passes

through a barrier. The transmission loss values for common construction materials are given

in Table 5-1.

Table 5-1: Transmission loss for common construction materials

Material Thickness of construction

material (inches) Decrease in noise

level dB(A)

Light concrete 4 38

6 39

Dense concrete 4 40

Concrete block 4 32

6 36

Brick 4 33

Page 29: KAMALA HYDRO ELECTRIC POWER COMPANY LTD. (KHEPCL) · Hydro Electric Power Company Ltd.), a joint venture between Jindal Power Ltd and Hydro Power Development Corporation of Arunachal

Kamala Hydroelectric Project Pre-Feasibility Report

Material Thickness of construction

material (inches) Decrease in noise

level dB(A)

Granite 4 40

Thus, the walls of various houses will attenuate at least 30 dB(A) of noise. In addition there

are attenuation due to the following factors.

Air absorption

Rain

Atmospheric inhomogeneties.

Vegetal cover

Thus, no increase in noise levels is anticipated as a result of various activities, during the

project construction phase. The noise generated due to blasting is not likely to have any

effect on habitations. However, blasting can have adverse impact on wildlife, especially

along the alignment of the tunnel portion. It would be worthwhile to mention that no major

wildlife is observed in and around the project site. Hence, no significant impact is expected

on this account.

5.1.11 Impacts on Land Environment

a) Construction phase

The major impacts anticipated on land environment during construction are as follows:

Quarrying operations

Operation of construction equipment

Muck disposal

Acquisition of land

i) Quarrying operations

A project of this magnitude would require significant amount of construction material.

The quarrying operations are semi-mechanized in nature. Normally, in a hilly terrain,

quarrying is normally done by cutting a face of the hill. A permanent scar is likely to be left,

once quarrying activities are over. With the passage of time, rock from the exposed face of

the quarry under the action of wind and other erosional forces, get slowly weathered and

after some time, they become a potential source of landslide. Thus, it is necessary to

Page 30: KAMALA HYDRO ELECTRIC POWER COMPANY LTD. (KHEPCL) · Hydro Electric Power Company Ltd.), a joint venture between Jindal Power Ltd and Hydro Power Development Corporation of Arunachal

Kamala Hydroelectric Project Pre-Feasibility Report

implement appropriate slope stabilization measures to prevent the possibility of soil erosion

and landslides in the quarry sites.

ii) Operation of construction equipment

During construction phase, various types of equipment will be brought to the site.

These include crushers, batching plant, drillers, earthmovers, rock bolters, etc. Positioning

this construction equipment would require significant amount of space. Similarly, space will

be required for storing of various other construction equipment. In addition, land will also be

temporarily acquired, i.e. for the duration of project construction for storage of quarried

material before crushing, crushed material, cement, rubble, etc. Efforts must be made for

proper positioning of these facilities.

Various criteria for selection of these sites would be:

Proximity to the site of use

Sensitivity of forests in the nearby areas

Proximity from habitations

Proximity to drinking water source

Efforts must be made to site the contractor’s working space in such a way that the adverse

impacts on environment are minimal, i.e. to locate the construction equipment, so that

impacts on human and faunal population are minimal.

iii) Muck disposal

Muck generation and disposal could lead to various adverse impacts. The muck needs to be

disposed at designated sites. This could lead to following impacts:

loss of land

problems regarding stability of spoil dumps

access to spoil dump areas

A part of the muck can be used for the following purposes:

use of suitable rock from the excavation as aggregate in the mixing of concrete.

use of muck for maintenance of roads.

use of muck in coffer dam.

use as backfill material in quarry and borrow pits.

Page 31: KAMALA HYDRO ELECTRIC POWER COMPANY LTD. (KHEPCL) · Hydro Electric Power Company Ltd.), a joint venture between Jindal Power Ltd and Hydro Power Development Corporation of Arunachal

Kamala Hydroelectric Project Pre-Feasibility Report

The balance muck shall be disposed at designated sites Muck, if not securely transported

and dumped at pre-designated sites, can have serious environmental impacts, such as:

Muck, if not disposed properly, can be washed away into the main river which can

cause negative impacts on the aquatic ecosystem of the river.

Muck disposal can lead to impacts on various aspects of environment. Normally,

the land is cleared before muck disposal. During clearing operations, trees are cut,

and undergrowth perishes as a result of muck disposal.

In many of the sites, muck is stacked without adequate stabilization measures.

In such a scenario, the muck moves along with runoff and creates landslide like

situations. Many a times, boulders/large stone pieces enter the river/water body,

affecting the benthic fauna, fisheries and other components of aquatic biota.

Normally muck disposal is done at low lying areas, which gets filled up due to

stacking of muck. This can sometimes affect the natural drainage pattern of the area

leading to accumulation of water or partial flooding of some area which can provide

ideal breeding habitat for mosquitoes.

5.1.12 Impacts on Biological Environment

Impacts on Terrestrial flora

a) Construction phase

i) Increased human interferences

The direct impact of construction activity of any water resource project in a Himalayan terrain

is generally limited in the vicinity of the construction sites only. As mentioned earlier, a large

population (12,000) including technical staff, workers and other group of people are likely to

congregate in the area during the project construction phase. It can be assumed that the

technical staff will be of higher economic status and will live in a more urbanized habitat, and

will not use wood as fuel, if adequate alternate sources of fuel are provided.

However, workers and other population groups residing in the area may use fuel wood, if no

alternate fuel is provided for whom alternate fuel could be provided. There will be an

increase in population by about 12000 of which about 8000 are likely to use fuel wood.

On an average, the fuel wood requirements will be of the order of 3,400m3. The wood

generated by cutting tree is about 2 to 3m3. Thus every year fuel wood equivalent to about

1100-1700 trees will be cut, which means every year on an average about 2-3 ha of forest

area will be cleared for meeting fuel wood requirements, if no alternate sources of fuel are

provided. Hence to minimize impacts, community kitchens have been recommended.

These community kitchens shall use LPG or diesel as fuel.

Page 32: KAMALA HYDRO ELECTRIC POWER COMPANY LTD. (KHEPCL) · Hydro Electric Power Company Ltd.), a joint venture between Jindal Power Ltd and Hydro Power Development Corporation of Arunachal

Kamala Hydroelectric Project Pre-Feasibility Report

ii) Impacts due to Vehicular movement and blasting

Dust is expected to be generated during blasting, vehicle movement for transportation of

construction material or construction waste. The dust particles shall settle on the foliage of

trees and plants, thereby reduction in amount of sunlight falling on tree foliage. This will

reduce the photosynthetic activity. Based on experience in similar settings, the impact is

expected to be localized upto a maximum of 50 to 100m from the source. In addition, the

area experiences rainfall for almost 8 to 9 months in a year. Thus, minimal deposition of dust

is expected on flora. Thus, no significant impact is expected on this account.

iii) Acquisition of forest land

During project construction phase, land will be required for location of construction

equipment, storage of construction material, muck disposal, widening of existing roads and

construction of new project roads. The total land requirement for the project is 3279 ha, a

part of which would be forest land. No rare and endangered species are observed in the

forest to be acquired for the project.

Impacts on Terrestrial fauna

a) Construction phase

i) Disturbance to wildlife

Based on the field studies and interaction with locals, it was confirmed that no major wildlife

is reported in the proposed submergence area. During construction phase, large number of

machinery and construction workers shall be mobilized, which may create disturbance to

wildlife population in the vicinity of project area. The operation of various equipments will

generate significant noise, especially during blasting which will have adverse impact on

fauna of the area. The noise may scare the fauna and force them to migrate to other areas.

Likewise siting of construction plants, workshops, stores, labour camps etc. could also lead

to adverse impact on fauna of the area. During the construction phase, accessibility to area

will lead to influx of workers and the people associated with the allied activities from outside

will also increase. Increase in human interference could have an impact on terrestrial

ecosystem. The other major impact could be the blasting to be carried out during

construction phase. This impact needs to be mitigated by adopting controlled blasting and

strict surveillance regime and the same is proposed to be used in the project. This will

reduce the noise level and vibrations due to blasting to a great extent.

Likewise, siting of construction equipment, godowns, stores, labour camps, etc. may

generally disturb the fauna in the area. However, no large-scale fauna is observed in the

area. Thus, impacts on this account are not expected to be significant. However, few stray

Page 33: KAMALA HYDRO ELECTRIC POWER COMPANY LTD. (KHEPCL) · Hydro Electric Power Company Ltd.), a joint venture between Jindal Power Ltd and Hydro Power Development Corporation of Arunachal

Kamala Hydroelectric Project Pre-Feasibility Report

animals sometimes venture in and around the project site. Thus, to minimize any harm due

to poaching activities from immigrant labour population, strict anti-poaching surveillance

measures need to be implemented, especially during project construction phase.

b) Operation phase

i) Increased accessibility

During the project operation phase, the accessibility to the area will improve due to

construction of roads, which in turn may increase human interferences leading to marginal

adverse impacts on the terrestrial ecosystem. The increased accessibility to the area can

lead to increased human interferences in the form of illegal logging, lopping of trees,

collection of non-timber forest produce, etc. Since significant wildlife population is not found

in the region, adverse impacts of such interferences are likely to be marginal.

Aquatic Flora

a) Construction phase

During construction phase wastewater mostly from domestic source will be discharged

mostly from various camps of workers actively engaged in the project area. Sufficient water

for dilution will be available in Kamla to keep the DO of the river to significantly high levels.

b) Operation phase

The completion of Kamala Hydroelectric Project would bring about significant changes in the

riverine ecology, as the river transforms from a fast-flowing water system to a quiescent

lacustrine environment. Such an alteration of the habitat would bring changes in physical,

chemical and biotic life. Among the biotic communities, certain species can survive the

transitional phase and can adapt to the changed riverine habitat. There are other species

amongst the biotic communities, which, however, for varied reasons related to feeding and

reproductive characteristics cannot acclimatize to the changed environment, and may

disappear in the early years of impoundment of water. The micro-biotic organisms especially

diatoms, blue-green and green algae before the operation of project, have their habitats

beneath boulders, stones, fallen logs along the river, where depth is such that light

penetration can take place. But with the damming of river, these organisms may perish as a

result of increase in depth.

i) Impacts due to damming of river

The damming of river Kamla due to the proposed dam will result in creation of 2775 ha of

submergence area at FRL. The dam will change the fast flowing river to a quiescent

lacustrine environment. The creation of a pond will bring about a number of alterations in

Page 34: KAMALA HYDRO ELECTRIC POWER COMPANY LTD. (KHEPCL) · Hydro Electric Power Company Ltd.), a joint venture between Jindal Power Ltd and Hydro Power Development Corporation of Arunachal

Kamala Hydroelectric Project Pre-Feasibility Report

physical, abiotic and biotic parameters both in upstream and downstream directions of the

proposed barrage site. The micro and macro benthic biota is likely to be most severely

affected as a result of the proposed project.

The reduction in flow rate of river Kamla especially during lean period is likely to increase

turbidity levels downstream of the dam. Further reduction in rate of flow may even create

condition of semi-desiccation in certain stretches of the river. This would result in loss of fish

life by poaching. Hence, it is essential to maintain minimum flow required for well being of

fish life till the disposal point of the tail race discharge.

ii) Impacts on Migratory Fish Species

The obstruction created by the dam would hinder migration of species Schizothorax sp. and

Mahaseer. These fishes undertake annual migration for feeding and breeding. Therefore,

fish migration path may be obstructed due to high dam and fishes are expected to

congregate below the dam wall. Under this situation poaching activities may increase in the

area. It is also proposed that the artificial seed production in hatchery may be adopted which

can be stocked in the river stretches downstream and upstream of the proposed barrage.

5.1.13 Impacts on Socio-Economic Environment

A project of this magnitude is likely to entail both positive as well as negative impacts on the

socio-cultural fabric of the area. During construction and operation phases, a lot of allied

activities will mushroom in the project area.

Impacts due to influx of labour force

During the construction phase a large labour force, including skilled, semi-skilled and

un-skilled labour force of the order of about 2500 persons, is expected to immigrate into the

project area. It is felt that most of the labour force would come from other parts of the

country. However, some of the locals would also be employed to work in the project.

The labour force would stay near to the project construction sites.

The project will also lead to certain negative impacts. The most important negative impact

would be during the construction phase. The labour force that would work in the construction

site would settle around the site. They would temporarily reside there. This may lead to filth,

in terms of domestic wastewater, human waste, etc. Besides, other deleterious impacts are

likely to emerge due to inter-mixing of the local communities with the labour force.

Differences in social, cultural and economic conditions among the locals and labour force

could also lead to friction between the migrant labour population and the total population.

Page 35: KAMALA HYDRO ELECTRIC POWER COMPANY LTD. (KHEPCL) · Hydro Electric Power Company Ltd.), a joint venture between Jindal Power Ltd and Hydro Power Development Corporation of Arunachal

Kamala Hydroelectric Project Pre-Feasibility Report

Economic impacts of the project

Apart from direct employment, the opportunities for indirect employment will also be

generated which would provide great impetus to the economy of the local area.

Various types of business like shops, food-stall, tea stalls, etc. besides a variety of suppliers,

traders, transporters will concentrate here and benefit immensely as demand will increase

significantly for almost all types of goods and services. The business community as a whole

will be benefited. The locals will avail these opportunities arising from the project and

increase their income levels. With the increase in the income levels, there will be an

improvement in the infrastructure facilities in the area.

Impacts due to land acquisition

Another most important deleterious impact during construction phase will be that, pertaining

to land acquisition. About 3279 ha of land proposed to be acquired for the proposed

Kamala Hydroelectric Project, apart of which is private land. Based on the present level of

investigations, the ownership status of land to be acquired for the project is not known.

The number of families likely to lose land or homestead or both needs to be identified. Socio-

economic survey for the Project Affected Families (PAFs) shall be conducted. Based on the

findings of the survey an appropriate Resettlement and Rehabilitation Plan will be

formulated.

Environmental Management Plan

Based on the environmental baseline conditions and project inputs, the adverse impacts will

be identified and a set of measures will be suggested as a part of Environmental

Management Plan (EMP) for their amelioration. An outline of various measures suggested

as a part of Environmental Management Plan is briefly described in the following sections.

5.1.14 Environmental Measures during Construction Phase

Facilities in Labour Camps

It is recommended that project authorities can compulsorily ask the contractor to make semi-

permanent structures for their workers. These structures could be tin sheds. These sheds

can have internal compartments allotted to each worker family. The sheds will have

electricity and ventilation system, water supply and community latrines.

The water for meeting domestic requirements may be collected from the rivers or streams

flowing upstream of the labour camps.

Page 36: KAMALA HYDRO ELECTRIC POWER COMPANY LTD. (KHEPCL) · Hydro Electric Power Company Ltd.), a joint venture between Jindal Power Ltd and Hydro Power Development Corporation of Arunachal

Kamala Hydroelectric Project Pre-Feasibility Report

Sanitation facilities

One community toilet can be provided per 20 persons. The sewage from the community

latrines can be treated in a sewage treatment plant before disposal.

Solid waste management from labour camps

For solid waste collection, suitable number of masonry storage vats, each of 2m3 capacity

should be constructed at appropriate locations in various labour camps. These vats should

be emptied at regular intervals and should be disposed at identified landfill sites. Suitable

solid waste collection and disposal arrangement shall be provided. A suitable landfill site

should be identified and designed to contain municipal waste from various project township,

labour colonies, etc.

Provision of free fuel

During the construction period of the project, there would be around labour and technical

staff would be involved in the project construction work. Many families may prefer cooking on

their own instead of using community kitchen. In the absence of fuel for cooking, they would

resort to tree cutting and using wood as fuel. To avoid such a situation, the project authority

should make LPG and/ or kerosene available to these migrant workers. The supply of LPG

and kerosene can be ensured on regular basis. A local depot can be established through

LPG/ kerosene suppliers for supply of the same.

5.1.15 Muck Disposal

A part of the muck generated, if found suitable, is proposed to be utilized for construction

works after crushing it into the coarse and fine aggregates. The balance quantum of muck

would have to be disposed. The muck shall be disposed in designated muck disposal sites.

The sites shall then be stabilized by implementing bioengineering treatment measures.

In the hilly area, dumping is done after creating terraces thus usable terraces are developed.

The overall idea is to enhance/maintain aesthetic view in the surrounding area of the project

in post-construction period and avoid contamination of any land or water resource due to

muck disposal.

Suitable retaining walls shall be constructed to develop terraces so as to support the muck

on vertical slope and for optimum space utilization. Loose muck would be compacted layer

wise. The muck disposal area will be developed in a series of terraces of boulder crate wall

and masonry wall to protect the area/muck from flood water during monsoons. In-between

the terraces, catch water drain will be provided.

Page 37: KAMALA HYDRO ELECTRIC POWER COMPANY LTD. (KHEPCL) · Hydro Electric Power Company Ltd.), a joint venture between Jindal Power Ltd and Hydro Power Development Corporation of Arunachal

Kamala Hydroelectric Project Pre-Feasibility Report

The terraces of the muck disposal area will be ultimately covered with fertile soil and suitable

plants will be planted adopting suitable bio-technological measures.

Various activities proposed as a part of the management plan are given as below:

Land acquisition for muck dumping sites

Civil works (construction of retaining walls, boulder crate walls etc.)

Dumping of muck

Levelling of the area, terracing and implementation of various engineering control

measures e.g., boulder, crate wall, masonry wall, catch-water drain.

Spreading of soil

Application of fertilizers to facilitate vegetation growth over disposal sites.

For stabilization of muck dumping areas following measures of engineering and biological

measures have been proposed

Engineering Measures

Wire crate wall

Boulder crate wall

Retaining wall

Catch water Drain

Biological Measures

Plantation of suitable tree species and soil binding species

Plantation of ornamental plants

Barbed wire fencing

5.1.16 Restoration Plan for Quarry Sites

The following biological and engineering measures are suggested for the restoration of

quarry site:

Garland drains around quarry site to capture the runoff and divert the same to the

nearest natural drain.

Construction of concrete guards check the soil erosion of the area.

The pit formed after excavation be filled with small rocks, sand and farmyard manure.

Page 38: KAMALA HYDRO ELECTRIC POWER COMPANY LTD. (KHEPCL) · Hydro Electric Power Company Ltd.), a joint venture between Jindal Power Ltd and Hydro Power Development Corporation of Arunachal

Kamala Hydroelectric Project Pre-Feasibility Report

Grass slabs will be placed to stabilized and to check the surface runoff of water and

loose soil.

Bench terracing of quarry sites once extraction of construction material is completed.

5.1.17 Compensation for Acquisition of Forest Land

Based on the ownership status of land to be acquired, it is proposed to afforest twice the

forest area being acquired for the project. The species for afforestation shall be selected in

consultation with local forest department.

5.1.18 Wildlife Conservation

It is recommended to commission check posts along few sites, i.e. barrage site, power

house site, labour camps, construction material storage site etc. during project construction

phase. Each check post will have 4 guards. One Range Officer would be employed to

supervise the operation of these check-posts and ensure that poaching does not become a

common phenomenon in the area. These check posts also will also be provided with

appropriate communication facilities and other infrastructure as well.

5.1.19 Greenbelt Development

Although the forest loss due to reservoir submergence and other project appurtenances

have been compensated as a part of compensatory afforestation, it is proposed to develop

greenbelt around the periphery of various project appurtenances, selected stretches along

reservoir periphery.

The green belt on either side of the reservoir will reduce the sedimentation and ensure

protection of the reservoir area from any other human activity that could result in the

reservoir catchment damage. On moderately steep slopes tree species will be planted for

creation of green belt which are indigenous, economically important, soil binding in nature

and an thrive well under high humidity and flood conditions. In addition greenbelt is

recommended around permanent colony for the project.

5.1.20 Sustenance of Riverine Fisheries

a) Release of minimum flow

The construction of the project would lead to modification of hydrologic regime during

peaking power operation, especially in lean and non-monsoon and non-lean season. It is

therefore, recommended to maintain a minimum flow to ensure survival and propagation of

invertebrates and fish. In case of proposed hydroelectric project, a flow of 48.56 Cumec

Page 39: KAMALA HYDRO ELECTRIC POWER COMPANY LTD. (KHEPCL) · Hydro Electric Power Company Ltd.), a joint venture between Jindal Power Ltd and Hydro Power Development Corporation of Arunachal

Kamala Hydroelectric Project Pre-Feasibility Report

equivalent to 20% of the average lean period flows (December to March) of the 90%

Dependable Year has been considered as the Environmental Flows.

b) Sustenance of Endemic Fisheries

It is proposed to implement supplementary stocking programmes for the project area. It is

proposed to stock reservoir, river Kamla upstream and the downstream sides. The stocking

can be done annually by the Fisheries Department, State Government of Arunachal

Pradesh. To achieve this objective, facilities to produce seed of trout need to be developed

at suitable sites.

5.1.21 Public Health Delivery System

The suggested measures are given in following paragraphs:

The site selected for habitation of workers shall not be in the path of natural drainage.

Adequate drainage system to dispose storm water drainage from the labour colonies

shall be provided.

Adequate vaccination and immunization facilities shall be provided for workers at the

construction site.

The labour camps and resettlement sites shall be at least 2km away from a main

water body or quarry areas.

As a part of Health Delivery System, following measures shall be implemented:

Clearing of river basins, shoreline, mats and floating debris, etc. to reduce the

proliferation of mosquitoes.

Development of medical facilities in the project area and near labour camps

Implementation of mosquito control activities in the area.

Infrastructure

Dispensary: Considering the number of rooms, staff quarters and open space etc., it is

estimated that 10,000 sq.feet of plot will be required for dispensary, out of which about

8000 sq.feet will be the built-up land which includes staff quarters, etc.

First Aid Posts: Temporary first aid posts shall be provided at major construction sites.

These will be constructed with asbestos sheets, bamboo, etc.

Page 40: KAMALA HYDRO ELECTRIC POWER COMPANY LTD. (KHEPCL) · Hydro Electric Power Company Ltd.), a joint venture between Jindal Power Ltd and Hydro Power Development Corporation of Arunachal

Kamala Hydroelectric Project Pre-Feasibility Report

5.1.22 Maintenance of Water Quality

The sewage generated from the labour camps, as mentioned earlier, is proposed to be

treated in sewage treatment plant prior to disposal. In the project operation phase, a plant

colony with about 50 quarters is likely to be set up. The sewage so generated would be

treated through a sewage treatment plant, equipped with secondary treatment units.

5.1.23 Control of Noise

The suggested measures are given in following paragraphs:

contractors will be required to maintain properly functioning equipment and comply

with occupational safety and health standards.

construction equipment will be required to use available noise suppression devices

and properly maintained mufflers.

vehicles to be equipped with mufflers recommended by the vehicle manufacturer.

staging of construction equipment and unnecessary idling of equipment within noise

sensitive areas to be avoided whenever possible.

use of temporary sound fences or barriers to be evaluated.

monitoring of noise levels will be conducted during the construction phase of the

project. In case of exceeding of pre-determined acceptable noise levels by the

machinery will require the contractor(s) to stop work and remedy the situation prior to

continuing construction.

It is known that continuous exposures to high noise levels above 90 dB(A) affects the

hearing acuity of the workers/operators and hence, should be avoided. To prevent these

effects, it has been recommended by Occupational Safety and Health Administration

(OSHA) that the exposure period of affected persons be limited as per the maximum

exposure period specified in Table 5-2.

Table 5-2: Maximum Exposure Periods specified by OSHA

Maximum equivalent continuous Noise level dB(A)

Unprotected exposure period per day for 8 hrs/day and 5 days/week

90 8

95 4

100 2

105 1

110 ½

Page 41: KAMALA HYDRO ELECTRIC POWER COMPANY LTD. (KHEPCL) · Hydro Electric Power Company Ltd.), a joint venture between Jindal Power Ltd and Hydro Power Development Corporation of Arunachal

Kamala Hydroelectric Project Pre-Feasibility Report

115 ¼

120 No exposure permitted at or above this level

5.1.24 Control of Air Pollution

Minor air quality impacts will be caused by emissions from construction vehicles, equipment

and DG sets, and emissions from transportation traffic. Frequent truck trips will be required

during the construction period for removal of excavated material and delivery of select

concrete and other equipment and materials. The following measures are recommended to

control air pollution:

Contractor will be responsible for maintaining properly functioning construction

equipment to minimize exhaust.

Construction equipment and vehicles will be turned off when not used for extended

periods of time.

Unnecessary idling of construction vehicles to be prohibited.

Effective traffic management to be undertaken to avoid significant delays in and

around the project area.

Road damage caused by sub-project activities will be promptly attended to with

proper road repair and maintenance work. An amount of Rs. 2.0 million has been

earmarked for this purpose.

Dust Control

To minimize issues related to the generation of dust during the construction phase of the

project, the following measures have been identified:

Identification of construction limits (minimal area required for construction activities).

When practical, excavated spoils will be removed as the contractor proceeds along

the length of the activity.

When necessary, stockpiling of excavated material will be covered or staged offsite

location with muck being delivered as needed during the course of construction.

Excessive soil on paved areas will be sprayed (wet) and/or swept and unpaved areas

will be sprayed and/or mulched. The use of petroleum products or similar products

for such activities will be strictly prohibited.

Contractors will be required to cover stockpiled soils and trucks hauling soil, sand,

and other loose materials (or require trucks to maintain at least two feet of

freeboard).

Page 42: KAMALA HYDRO ELECTRIC POWER COMPANY LTD. (KHEPCL) · Hydro Electric Power Company Ltd.), a joint venture between Jindal Power Ltd and Hydro Power Development Corporation of Arunachal

Kamala Hydroelectric Project Pre-Feasibility Report

Contractor shall ensure that there is effective traffic management at site. The number

of trucks/vehicles to move at various construction sites to be fixed.

Dust sweeping - The construction area and vicinity (access roads, and working

areas) shall be swept with water sweepers on a daily basis or as necessary to ensure

there is no visible dust.

Page 43: KAMALA HYDRO ELECTRIC POWER COMPANY LTD. (KHEPCL) · Hydro Electric Power Company Ltd.), a joint venture between Jindal Power Ltd and Hydro Power Development Corporation of Arunachal

Kamala Hydroelectric Project Pre-Feasibility Report

6 RESETTLEMENT AND REHABILITATION PLAN

Based on the present level of investigations, the number of project affected families is not

available. The number of families likely to lose land will be finalized. In addition, information

of any family losing homestead or other private properties shall also be ascertained.

Socio-economic survey for the Project Affected Families (PAFs) will be conducted. Based on

the findings of the survey an appropriate Resettlement and Rehabilitation Plan will be

formulated as per the norms and guidelines of National Resettlement and Rehabilitation Plan

2007 (NRRP-2007). The key measures are listed as below:

Resettlement for houseless

Financial assistance to houseless families for construction of house

Shop construction grant

Rehabilitation cash grant

Subsistence allowance

Grants for cattle-shed and transportation

Compensation for land development cost

Compensation for loss of agricultural produce

One time financial assistance for “training for development of entrepreneurship”

Scholarship for students

Monitoring and evaluation set-up

Page 44: KAMALA HYDRO ELECTRIC POWER COMPANY LTD. (KHEPCL) · Hydro Electric Power Company Ltd.), a joint venture between Jindal Power Ltd and Hydro Power Development Corporation of Arunachal

Kamala Hydroelectric Project Pre-Feasibility Report

7 PROJECT SCHEDULE & COST ESTIMATES

7.1.1 Project Cost

The estimated cost of the project as worked out is

11343.21 Crores, which is the cost of the envisaged scheme (with surcharge storage).

7.1.2 Implementation Schedule

For determination of phasing, escalation & interest during construction the implementation

schedule of project is given as under:

Base date of Estimate: June 2016

Start date of main construction: October 2019

Total construction period including commissioning of all units: 90 months from

October 2019 to March 2028

Commission period of 8 units of main powerhouse and 2 units of auxiliary

powerhouse: 9 months from July 2027 to March 2028

Table 7X: Financial Analysis Results - Cost with Flood Moderation component

S.No. Description Unit Amount

1 Basic Cost at June-2016 Price Level with Flood

Moderation

Crores 11343.21

2 Escalation Crores 3705.34

3 IDC & FC Crores 5771.38

4 Total Completed Cost Crores 20819.93

5 Cost Apportionment to Flood Moderation

a) Cost due to additional height of dam & appurtenances

including effect of reduction in construction period

Crores 2333.40

b) Cost due to energy loss Crores 433.00

c) Total Cost apportionment to Flood Moderation (5a+5b)

Which needs to be compensated to developer

(2333.40 + 433.00 = 2766.40)

Crores 2766.40

6 Completed Cost chargeable to Power Component as per

CERC regulation (20819.93 – 2766.40 = 18053.53)

Crores 18053.53

Page 45: KAMALA HYDRO ELECTRIC POWER COMPANY LTD. (KHEPCL) · Hydro Electric Power Company Ltd.), a joint venture between Jindal Power Ltd and Hydro Power Development Corporation of Arunachal

Kamala Hydroelectric Project Pre-Feasibility Report

7 Levelized Tariff (with free power to state) after apportioning

cost to flood moderation

/ Unit 5.43

* As per updated information required by CEA vide their letter dated 24.03.2017.

* The Project Schedule & Cost shall be approved from CEA, as the DPR stands submitted for concurrence.

Compensation for Provision of Flood Moderation

As Kamala project seeks simultaneous achievement of twin objectives of power generation

and flood moderation, completed cost of the project has been apportioned between the two.

The cost of project to determine sale rate of power is 18053.53 Crores and the

corresponding levelled tariff is 5.43/Unit.

The cost apportioned to flood moderation of 2766.40 Crores is required to be

compensated by the government to the project developer, KHEPCL.

Page 46: KAMALA HYDRO ELECTRIC POWER COMPANY LTD. (KHEPCL) · Hydro Electric Power Company Ltd.), a joint venture between Jindal Power Ltd and Hydro Power Development Corporation of Arunachal

Kamala Hydroelectric Project Pre-Feasibility Report

8 ANALYSIS OF PROPOSAL

The Project affected families and in general the local people shall have immense benefits

due to the implementation of the project. There would be much improved healthcare

facilities, Infrastructure & Transport facilities due to the project implementation of the project.

Project affected families / local population shall have edge on being employed during

construction and operation phase subject to fulfilment of eligibility criteria. A provision

already exists in MoU with state Government on grant of employment to local population.

Schools in the vicinity shall be upgraded & if required, more shall be constructed after

discussion with District Administration. Provision shall be kept in R&R Plan for scholarship to

meritorious students. Health check-up programmes are already taken up and shall continue

in and around the vicinity of the project. Regular sanitation programme shall also be

undertaken as per the requirement. Project affected families shall get financial compensation

as per the provision of LARR-Act-2013 and SRRP-2008.

Under social welfare scheme, provision shall be kept under EMP for preservation of culture

& Tradition of local tribe. Provision shall be made for Skill Development Centre in the R&R

Plan. CSR activities shall be taken which shall ensure necessary development of the project

area & project people / local population.