34
Working towards better Urban living Karnataka Urban Infrastructure Development and Finance Corporation Karnataka Municipal Reforms Project Social & Environmental Assessment of Proposed KMRP Sub-projects in Chitradurga Town

Karnataka Urban Infrastructure Development and …...accordance with 74th Constitutional Amendment with a greater sustainability and accountability. 2. Strengthen institutional and

  • Upload
    others

  • View
    10

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Karnataka Urban Infrastructure Development and …...accordance with 74th Constitutional Amendment with a greater sustainability and accountability. 2. Strengthen institutional and

Working towards better Urban living

Karnataka Urban Infrastructure Development and Finance Corporation

Karnataka Municipal Reforms Project

Social & Environmental Assessment of Proposed KMRP Sub-projects in

Chitradurga Town

Page 2: Karnataka Urban Infrastructure Development and …...accordance with 74th Constitutional Amendment with a greater sustainability and accountability. 2. Strengthen institutional and
Page 3: Karnataka Urban Infrastructure Development and …...accordance with 74th Constitutional Amendment with a greater sustainability and accountability. 2. Strengthen institutional and

Contents

i

CONTENTS

1.1 BACKGROUND ........................................................................................................... 1

1.1.1 PROJECT OBJECTIVES ........................................................................................ 1

1.1.2 OBJECTIVES....................................................................................................... 1

1.1.3 METHODOLOGY ................................................................................................. 2

1.1.4 REVIEW OF INSTITUTIONAL MECHANISMS FOR ENVIRONMENTAL MANAGEMENT 2

1.2 SOCIAL AND ENVIRONMENTAL PROFILE AND BASELINE SITUATION ........................... 3

1.2.1 Town Description................................................................................................ 3

1.2.2 Socio-Economic Environment............................................................................... 3

1.2.2.1 Health ............................................................................................................ 3

1.2.2.2 Cultural and Historical Monuments ................................................................... 4

1.2.2.3 Other Features of the town.............................................................................. 4

1.2.3 Environmental Profile .......................................................................................... 4

1.2.3.1 Physical Environment ...................................................................................... 4

1.2.3.2 History ........................................................................................................... 5

1.2.3.3 Demographics................................................................................................. 5

1.2.3.4 Climate and Rainfall ........................................................................................ 5

1.2.3.5 Soil and Geology............................................................................................. 6

1.2.3.6 Economic Base ............................................................................................... 6

1.2.3.7 Topography .................................................................................................... 6

1.2.3.8 Surface Water Sources .................................................................................... 6

1.2.3.9 Ground Water ................................................................................................. 6

1.2.3.10 Ecological Environment................................................................................ 6

1.2.4 Baseline sample survey ....................................................................................... 6

1.3 IDENTIFICATION OF SOCIAL AND ENVIRONMENTAL IMPACTS .................................... 7

1.3.1 Public Consultation ............................................................................................. 7

1.3.2 Construction and Operation Phase ....................................................................... 7

1.4 ENVIRONMENTAL MANAGEMENT PLAN ....................................................................... 7

1.4.1 Benefits from the Project .................................................................................... 8

1.5 SOCIAL / RESETTLEMENT ACTION PLAN..................................................................... 8

1.6 RWH ......................................................................................................................... 8

1.6.1 Existing System .................................................................................................. 8

1.6.2 Proposed Development ....................................................................................... 8

1.6.3 Cost of RWH .....................................................................................................10

1.6.4 EMP for RWH ....................................................................................................10

Page 4: Karnataka Urban Infrastructure Development and …...accordance with 74th Constitutional Amendment with a greater sustainability and accountability. 2. Strengthen institutional and

Chitradurga

ii

1.7 ROADS.....................................................................................................................10

1.7.1 Existing System.................................................................................................10

1.7.2 Rehabilitation/Improvement of Roads .................................................................11

1.7.3 Cost of Roads....................................................................................................11

1.7.4 EMP for Rehabilitation/Improvement of Roads ....................................................12

1.8 STORMWATER DRAINS.............................................................................................16

1.8.1 Existing System.................................................................................................16

1.8.2 Proposed Development ......................................................................................16

1.8.3 Cost of SWD .....................................................................................................17

1.8.4 EMP for SWD ....................................................................................................17

1.9 SLUM INFRASTRUCTURE ..........................................................................................20

1.9.1 Existing Infrastructure .......................................................................................20

1.9.2 Upgradation of Physical Infrastructure in slums ...................................................21

1.9.3 Cost of Development .........................................................................................21

1.9.4 EMP for Slum Development................................................................................21

1.10 WATER TREATMENT PLANT ......................................................................................25

1.10.1 Existing System.................................................................................................25

1.10.2 Water Supply Augmentation...............................................................................27

1.10.3 Cost of Water Supply Augmentation ...................................................................27

1.10.4 EMP for Water Supply Augmentation ..................................................................28

1.11 SUMMARY ENVIRONMENTAL MANAGEMENT PLAN AND CONCLUSIONS.......................30

Tables and Figures

Table 1: Salient Features of Chitradurga Town............................................................................3Table 2: EMP for Rehabilitation/Improvement of Roads .............................................................12Table 3: Monitoring Requirement & Specifications for Roads ......................................................15Table 4: Details of drains to be constructed as part of the project ..............................................17Table 5: EMP for Storm Water Drains .......................................................................................17Table 6: Monitoring Requirement and Specification for SWD ......................................................19Table 7: EMP for Slum Development.........................................................................................21Table 8: Monitoring Requirement and Specification for Slum Development..................................25Table 9: EMP for Water Supply Augmentation ...........................................................................28

Page 5: Karnataka Urban Infrastructure Development and …...accordance with 74th Constitutional Amendment with a greater sustainability and accountability. 2. Strengthen institutional and

Brief EA

1

1.1 BACKGROUND

The Karnataka Municipal Reforms Project (KMRP) is a US$ 310 million (Rs.1364 crore) IBRD financed project that is fully consistent with the World Bank’s Country Assistance Strategy and focuses on working on governance issues and sectoral projects. The KMRP comprises of four major components, which include (i) Institutional Development; (ii) Bangalore Development; (iii) Municipal Investment Support; and (iv) Project Management. Broadly, KMRP would assist institutional development activities statewide and infrastructure development in 32 Urban Local Bodies (ULBs) as per GO No. UDD 56 PRJ 2005 dtd 13.09.2005.

1.1.1 PROJECT OBJECTIVES

1. Enhancing the capacity of Urban Local Bodies to discharge their functions in accordance with 74th Constitutional Amendment with a greater sustainability and accountability.

2. Strengthen institutional and financial frame work in urban service delivery at ULBs level and State level.

3. Improve the quality of urban infrastructure in 32 (ULBs) and

4. Improve the road system in Bangalore and the sanitary conditions in the 8 erstwhile ULBs surrounding Bangalore city, while ensuring financial viability and sustainability.

The Municipal Investment Support Component is to be managed by KUIDFC, working in close coordination with DMA’s office, the DUDCs and the ULBs. 32 ULBs are divided into 4 packages. Package-1 with 9 ULBs, 2 with 5, 3 with 10 and 4 with 8 ULBs respectively.

While the project is expected to improve the environmental conditions in selected urban areas of Karnataka by improving the quality of service, development ofinfrastructure including water & sanitation and substantial health benefits. Adverse social and environmental impacts are anticipated if the investments are not properly planned, sited, designed, constructed, operated and maintained.

Considering these aspects, GoK plans to integrate social and environmental issuesin the project at policy and sectoral levels. This will be achieved throughPreparation of Social Assessment and Resettlement Action Plan and Environmental Assessment (EA), Environmental Management Plan (EMP) at project level as required and appropriate.

1.1.2 OBJECTIVES

The objective of the present assignment is to prepare Social/Resettlement and Environmental Management Plans for the works proposed under KMRP andintegrate the concerns in the design. The scope includes the following:

providing social and environmental inputs into action plan

Page 6: Karnataka Urban Infrastructure Development and …...accordance with 74th Constitutional Amendment with a greater sustainability and accountability. 2. Strengthen institutional and

Chitradurga

2

planning for social and environmental activities to be carried out duringproject preparation and implementation

providing guidance / quality assurance for integration of environmental and social aspects in the work

preparing RAP and EMP as required as per SEMF

integrating finalised EMP into the contract for implementation and operation

1.1.3 METHODOLOGY

Identification and review of all the relevant policies and regulations that influencethe project environment is very important to assess the impacts on projectplanning and implementation. In view of this, review of all applicable operationalpolicies / directives of The World Bank and environmental laws / regulations inIndia, is carried out in the Social and Environmental Management Framework. This included review of the operational policies of The World Bank.

A Capital Investment Plan (CIP) was prepared in 2005 based on the ULB borrowing capacity. Based on CIP and SEMF including the policy, regulatory and institutional mechanism, a detailed review of the project and the proposed sub-projects in the ULBs was carried out and Detailed Project Reports (DPRs) wereprepared. This involved discussions with the project ULBs to understand thepresent basic infrastructure status.

The project profile primarily focused on identifying the various activities that are envisaged for providing the basic infrastructure and the details of priority investments that are planned for each of the project ULB.

In addition to the above, the key environmental regulations / policies in India that may affect /influence the project environment both during preparation andimplementation stage are also reviewed.

1.1.4 REVIEW OF INSTITUTIONAL MECHANISMS FOR ENVIRONMENTALMANAGEMENT

A detailed analysis of various stake holder agencies who will be involved inplanning, designing, operating and maintaining the infrastructure that are beingdeveloped by the project and other improvement measures are important to assess the capacity, willingness and resource requirement of the institutions for effective integration of environmental concerns. More specifically, the environmental impacts will be influenced by the manner in which the project components are designed.

In view of this, a review of institutional and organisational set up of theinstitutions and beneficiary agencies are carried out.

The review primarily focuses on the role of each of the above agencies in various stages of project development. An assessment of technical and managerial

Page 7: Karnataka Urban Infrastructure Development and …...accordance with 74th Constitutional Amendment with a greater sustainability and accountability. 2. Strengthen institutional and

Brief EA

3

capabilities of these agencies with specific reference to the environmentalmanagement of various project activities is also carried out.

1.2 SOCIAL AND ENVIRONMENTAL PROFILE AND BASELINE SITUATION

1.2.1 TOWN DESCRIPTION

The profile of the Chitradurga City Municipal Council (CMC) and the proposed sub project under KMRP are discussed in this section. The information was collected from the CMC and other agencies, discussions with the respective officials of the city and the analysis of the information collected from various documents relevant to the study, including the Capital Investment Plan (CIP) report and Detailed Project Report (DPR) prepared by Project consultants.

Table 1: Salient Features of Chitradurga Town

Item Details

1. Population, 2001 125170

2. Area, km2 21.57 sq km

3. No. of House Holds, 2001 26138

4. No. of Wards 35

5. Population Growth Rate – Decadal 21%

6. Population Density, persons / km2 5800

7. Literacy Rate 64.5%

8. Slum Population 26,446

9. Industry and Economy Oil mills, cotton mills,

10. Administrative Status City Municipal Council

In terms of growth trends, the city has grown rapidly at an average decadal growth rate of 21% and comprises 26 slums with 20% of town population. Of late there is focus on trade and commerce, hence the city is expected to have higher growth rate and floating population. The salient features are presented in Table 1. The location of Chitradurga town in Chitradurga District is presented in Figure 1.

1.2.2 SOCIO-ECONOMIC ENVIRONMENT

1.2.2.1 Health

There are 21 major hospitals and nursing homes in the town. Apart from these the town is equipped with number of small clinics which cater to the needs of the town. There is one government hospital with 500 beds along with OPD facilities. Apart from these facilities the town has Sir Manjunathaswara Ayurvedic hospital

Page 8: Karnataka Urban Infrastructure Development and …...accordance with 74th Constitutional Amendment with a greater sustainability and accountability. 2. Strengthen institutional and

Chitradurga

4

located along B M road with 138 beds capacity is very famous in the surrounding areas. The ayurvedic hospital is a privately run hospital.

Figure 1: Location of Chitradurga City in Chitradurga District

1.2.2.2 Cultural and Historical Monuments

There are many places of worship in Chitradurga. Significant archeological sites in Chitradurga CMC area are Chitradurga Fort, Obavvana Kindi etc. The present SWM project related construction activities do not affect any of the religious structures.

1.2.2.3 Other Features of the town

The project area profile of the town depicts a predominant middle income neighbourhood with a mix of developed and extension areas.

1.2.3 ENVIRONMENTAL PROFILE

A description of the base line environmental conditions of Chitradurga CMC is discussed in this section. The profile is based on the secondary informationcollected from the various secondary sources such as ULB, KSPCB, MeteorologicalDepartment and various other government agencies.

1.2.3.1 Physical Environment

Chitradurga is situated in the heart of Deccan Plateau, northeast of Bangalore. It is located at 140 15’ North latitude and 760 25’ East longitudes, at an altitude of

Page 9: Karnataka Urban Infrastructure Development and …...accordance with 74th Constitutional Amendment with a greater sustainability and accountability. 2. Strengthen institutional and

Brief EA

5

735 metres above mean sea level. Chitradurga is a district headquarters situated in central Karnataka, at a point where two National Highways–Bangalore-Poona (NH - 4) and Chitradurga-Sollapur (NH-13) meet. It is at a distance of about 200 km from Bangalore. Pavagoda–Bhadravathi SH 48 also passes through the town. It is also connected to Davengere, Challakere, Holalkere by major district roads. Chitradurga is well connected by railways from Chikkajajur located along Miraj-Bangalore main line. Chitradurga has some important tourist spots like Chitradurga Fort, Obavvana Kindi Vaani Vilas Sagara, Murugha Rajendra Bruhanmatha & Chadravalli Garden.

1.2.3.2 History

Chitradurga features bold rock hills and picturesque valleys, huge towering boulders in unimaginable shapes. It is known as the "stone fortress" (Kallina Kote). The landscape looks much like a mischievous giant's playground, with boulders thrown around, forming silhouettes against the sky. According to a story in the Epic Mahabharatha, a man-eating giant named Hidimbasura lived on the Chitradurga hill and was a source of terror to everyone around. When the Pandava came with their mother Kunti in the course of their exile, Bhima had a duel with Hidimba. Hidimba was slain by Bhima and peace returned to the area. Legend has it the boulders were part of the arsenal used during that duel. In fact, the boulders on which major part of the city rests belong to the oldest rock formation in the country. Timmana Nayaka a chieften under the Vijayanagar empire rose to the rank of governor of Chitradurga as a reward for his excellence in military achievements, from the Vijayanagara ruler. This was the beginning of the rule of the Nayakas of Chitradurga.

1.2.3.3 Demographics

As per 2001 India census, Chitradurga had a population of 122,594. Males constitute 51% of the population and females 49%. Chitradurga has an average literacy rate of 76%, higher than the national average of 59.5%; with male literacy of 80% and female literacy of 72%. 11% of the population is under 6 years of age.

1.2.3.4 Climate and Rainfall

Climate is characterised by moderate summers & winters. Meteorologically, the year can be divided into three distinct seasons. Winter season sets in from the month of October and continues up to February, followed by summer season from March to mid-May. Rainy season commencing from mid-June lasts through July, August, September & October. Humidity is at peak during months of July & August and is minimum during winter months of January & February. Temperature rises after March and April is hottest month of the year with mean daily maximum temperature going up to 35.7oC. With the withdrawal of monsoons, by the end of October, there is a sharp decrease in temperature. December and January are the

Page 10: Karnataka Urban Infrastructure Development and …...accordance with 74th Constitutional Amendment with a greater sustainability and accountability. 2. Strengthen institutional and

Chitradurga

6

coolest months of the year, with mean daily minimum temperature at about 17oC. Total annual rainfall is about 642 mm. Maximum rainfall is received in the months from May to October.

1.2.3.5 Soil and Geology

There are two types of soil predominantly present in Chitradurga town area, black cotton soil and red soil. The soil is Red gravelly earth on Western and North Western parts on the eastern and northern part of the town is of black cotton type. Geology of Chitradurga, Black clay on Eastern & Northern part with impervious granite strata at 10 to 15m depths.

1.2.3.6 Economic Base

Chitradurga is a multi functional town. The economic base of the town depends on agriculture, trade and commerce, industries and tourism sector. Sheep rearing activity is predominantly found in the town along with small scale industries like Oil mills, lathes, welding units, cotton mills, etc. Dry agriculture is main occupation in hinterland of the town. Chitradurga is lagging behind industrially but of late trade and commerce is gaining an upper hand. Davanagere and Harihar have retained their industrial characters, which are surrounding towns of Chitradurga.

1.2.3.7 Topography

The town slopes from south & west to north and east. It is hilly in the south region of the town.

1.2.3.8 Surface Water Sources

There are no significant surface water sources in Chitradurga except for the Vedanthi river which runs about 40 km from the city and dry for most part of the year.

1.2.3.9 Ground Water

The ground water is very deep around Chitradurga and depth usually is more than 70m.

1.2.3.10 Ecological Environment

Being predominantly an urban area, the ecological environment of Chitradurga is not very diverse. Mostly dry mixed deciduous and open scrubs are found in this region.

1.2.4 BASELINE SAMPLE SURVEY

Quality of water and soil characteristics is very critical in assessing the impacts. In order to establish the water & soil quality and assess the possible impacts, 2 samples each was collected in the all the directions of the town.

Page 11: Karnataka Urban Infrastructure Development and …...accordance with 74th Constitutional Amendment with a greater sustainability and accountability. 2. Strengthen institutional and

Brief EA

7

It can be summarised from the environmental-social profile in the preceding sections that the Chitradurga town do not present any sensitive environmental features that could be affected by the proposed implementation.

1.3 IDENTIFICATION OF SOCIAL AND ENVIRONMENTAL IMPACTS

For the purpose of assessing the impacts, a summary of the same and various activities involved in execution of the Infrastructure components.

1.3.1 PUBLIC CONSULTATION

The willingness of the public and their expectations on the service levels is very critical in accomplishing the objective of improving the level of service in the project towns. For this purpose, Public Consultations were conducted.

The objective of these public consultations was to elicit public view on the present status of infrastructure, problems and issues associated with the same and their expectation on the proposed project. The economic, social and environmentalissues associated with the same were also identified during these public consultations. The results of the public consultations provide an input to identify the impacts of the project proposals and subsequent formulation of EMPs.

1.3.2 CONSTRUCTION AND OPERATION PHASE

The impacts on physical resources such as topography, climate will be insignificant or no impact. Whereas impacts on the environmental resources (Surface water quality, groundwater quality, air, noise); ecological resources and human use values (Soil, Archaeological / Cultural Properties, Social Impacts) will be very minor and temporary, however the measures presented subcomponent-wise will mitigate the possible impacts during construction and operation phases.

1.4 ENVIRONMENTAL MANAGEMENT PLAN

No major environmental impacts are anticipated due to the proposed development. The critical issues will be to ensure adequate safety and precautionary measures to minimise impacts during construction and during operation. Any specific impacts arising during execution has to be analyzed and appropriate mitigation measures taken accordingly.

While the impacts are not very severe and permanent, care has to be taken to ensure that the ambient environmental conditions do not deteriorate. The recommended mitigative measures to the impacts on key environmentalparameters are detailed out subcomponent-wise in the following sections.

Regular maintenance of infrastructure components will be carried out by the ULB. Equipments will be procured for operation and maintenance of the implemented infrastructure. Regular monitoring of implementation of the proposed infrastructure shall be carried out.

Page 12: Karnataka Urban Infrastructure Development and …...accordance with 74th Constitutional Amendment with a greater sustainability and accountability. 2. Strengthen institutional and

Chitradurga

8

1.4.1 BENEFITS FROM THE PROJECT

The proposed infrastructure components would increase the effectiveness of the water supply, stormwater disposal, RWH, traffic & transport and slums in the town by providing better infrastructure facilities. The proposed work will provide better health benefits for the public, preventing water borne diseases arising from the improper stormwater disposal system. Also, the proposed work will prevent the contamination of due to improper disposal of stormwater. The ground water contamination will also be arrested by allowing the sewage to flow in the pipeline. The beneficiaries will comprise households of the town.

1.5 SOCIAL / RESETTLEMENT ACTION PLAN

All the rainwater harvesting structures are proposed over existing buildings and no additional land will be required for the project. Also, the road network an stormwater drainage proposed to be developed as a part of the project shall be aligned over government land and no private land is proposed to be acquired. Further water augmentation and slum upgradation will be on existing land. Hence, issues related to resettlement and rehabilitation are not envisaged in the proposed project.

But in order to shift the electric poles and telephone poles the involvement of concerned authorities are necessary for road improvement works.

No major social impacts are anticipated due to the implementation of proposed infrastructure. The critical issues will be to ensure adequate safety and precautionary measures to minimise impacts during construction and operation phases to the standards prescribed by KSPCB during operation.

1.6 RWH

1.6.1 EXISTING SYSTEM

There have been some attempts to harvest rainwater in the town. Following is the list of some of the buildings where it has been carried out.

CMC Building

D C Office

PWD Ex. Office (Highways)

Inspection Bungalow

Survey and Land Records

Taluk Office

1.6.2 PROPOSED DEVELOPMENT

In order to tap rainwater from rooftop as well as falling on the open ground, following buildings have been selected for roof top rainwater harvesting:

Page 13: Karnataka Urban Infrastructure Development and …...accordance with 74th Constitutional Amendment with a greater sustainability and accountability. 2. Strengthen institutional and

Brief EA

9

General Hospital (B&C Wings)

Lokayukta Office

Krishna Rajendra Library

General Hospital one of the important land mark of the town and is situated close to CMC building on the Bangalore – Poona National Highway. It is a partly stone building and has approximately 3682 m2 area with wards in the first floor. There is a sump in the frontside of the General Hospital. It is proposed to harvest the roof top rain water and lead in to the sump for storage and use. The building has ample open space within and it is being used for maintaining gardens. The building has drain pipes both of PVC and AC inside as well as outside but most of it (110 mm dia) are broken or damaged. Hence, only the pipes which are in good condition are being used for vertical and horizontal collection. A total of 463m drain pipes are being dismantled out which pipes which are in good condition are being retained for vertical collection. The water that is likely to the harvested will be around 11,69,000 liters and the total estimated cost Rs. 5,98,000/-.

Lokayukta office is situated on the main road that is on NH4 and on the way to the KSRTC bus stand. The office is located in a building which is situated inside the compound and front portion of the compound converted to shops. The building has a built up area of 468 m2 and the top is partly of tiled roof. It has a sump and there is a hydro met station and an observational bore well in the backyard which is being used to record water level changes periodically. It is proposed to harvest rain water from the roof top and store it is the sump and the excess flows lead to the bore well to recharge ground water. The building has 90mm dia drain pipes which are partly good and partly damaged condition. A total length of 34m of pipes have been dismantled and the pipes in good condition have been utilized for vertical collection. The total estimated cost is likely to be Rs. 1,35,200/-. The water that is likely to be harvested will be 2,41,860 litres.

The Krishna Rajendra Library is situated in the heart of the town is on the NH4 and is above a half Km from the CMC building. It has an old British architecture type building (like the public library of Bangalore) and has two annex newly builtRCC buildings. There is a bore in the premises. For roof top harvesting purposes only the main building and one of the annex building is considered and the total roof area is 379 m2. The harvested roof water will be lead in to the bore well for recharging ground water. The main building which is an old building has only pipe projections to drain out rainwater where as the annexe building has drain pipes. A total of 22.3m pipes are being dismantled and the pipes which are in good condition are being retained for vertical collection. The total water that is likely to be harvested will be 1,95,860 liters and the estimated cost for the harvesting will be Rs. 1,33,400.

Page 14: Karnataka Urban Infrastructure Development and …...accordance with 74th Constitutional Amendment with a greater sustainability and accountability. 2. Strengthen institutional and

Chitradurga

10

S. No. Proposed Building

Roof Area considered

(m2)

Quantity of Rain Water likely to be harvested (liters)

1 General Hospital(B&C Wings) 2262 11,69,0002 Lokayukta Office 468 2,41,8603 Krishna Rajendra Library 379 1,95,860

Total 3109 16,06,720

1.6.3 COST OF RWH

The total cost to be incurred for rainwater harvesting structures will be Rs.10lakhs.

S. No.

Proposed BuildingRoof Area

considered (Sqm)Estimated cost

(Rs.)1 General Hospital (B&C Wings) 2262 5,98,000.003 Lokayukta Office 468 1,35,200.004 Krishna Rajendra Library 379 1,33,400.00

Total 3109 866600.00Add 10% Tender Premium 86660.00For contingencies 43330.00Miscellaneous 3410.00GRAND TOTAL 1000000.00

1.6.4 EMP FOR RWH

There is no EMP envisaged for the RWH subcomponent. However, the contractor shall take all reasonable steps to protect the environment on and off the Site and to avoid damage or nuisance to persons or to property of the public or others resulting from pollution, noise or other causes arising as a consequence of his methods of operation.

During continuance of the contract, the contractor and his sub-contractors shall abide at all times by all existing enactments on environmental protection and rules made there under, regulations, notifications and bye-laws of the State or Central Government, or local authorities and any other law, bye-law, regulations that may be passed or notification that may be issued in this respect in future by the State or Central Government or the local authority.

1.7 ROADS

1.7.1 EXISTING SYSTEM

The total local network comprises of lanes & streets roads for a length about 107.5 Km. Of these about 91 Nos of roads for a length of about 32.67 Km is taken up under this sub component. These roads cater the needs of main traffic insidethe city and are provided with bituminous and rigid riding surface with carriageway ranging from 3.0 to 7.00 m.

Page 15: Karnataka Urban Infrastructure Development and …...accordance with 74th Constitutional Amendment with a greater sustainability and accountability. 2. Strengthen institutional and

Brief EA

11

Most of the roads are in worn out condition with lot of pot holes and patches. Except for a few roads there are no pucca drains to carry the storm water. The interior roads are mostly having gravel and metal riding surface without proper drainage arrangement. In some of the new extension areas there are only earthen roads. Due to paucity of funds resulting in poor maintenance, the riding surface is in dilapidated condition. The traffic experiences difficulty in passing over the roads besides the problem of dust pollution.

1.7.2 REHABILITATION/IMPROVEMENT OF ROADS

The revised list provided for rehabilitation of 91 roads for about a length of 32.67 Km for various widths of carriage ways for providing bituminous and CC riding surface over different types of existing surfaces like earthen, metalled and bituminous surfaces. It also envisaged rehabilitation of 94 numbers of culverts and road drains for stretches where no pucca drains.

1.7.3 COST OF ROADS

The total cost for Road Rehabilitation and Improvement is Rs. 1885 lakhs.

Page 16: Karnataka Urban Infrastructure Development and …...accordance with 74th Constitutional Amendment with a greater sustainability and accountability. 2. Strengthen institutional and

Chitradurga

12

1.7.4 EMP FOR REHABILITATION/IMPROVEMENT OF ROADS

Table 2: EMP for Rehabilitation/Improvement of Roads

S. No.

Issues / Impacts

Mitigation Measures Project Phase Responsibility

1

Utility relocation

In case of utilities (water supply lines, electrical installations, telephone lines etc) and common property resources being impacted due to the project, they will be relocated with prior approval of the concerned agencies before construction starts. Relocation will be in accordance with the feasibility and choice of the community. Utility relocation shall be carried out in shortest possible time to reduce inconvenience to public.

Pre-construction

Contractor, PC, ULB

2 Site clearance Site clearance will be done only in the area required for the sub-project.

Pre-construction

Contractor, PC

3 Debris disposal site identification

Site for temporary storage and disposal of debris refuse to be identified. These disposal sites shall be finalized such that they are not located within designated forest or other eco-sensitive areas, does not impact natural drainage courses and no endangered / rare flora is impacted by such disposal.

Pre-Construction

Contractor, PC, ULB

4 Hot-mix plants & Batching Plants

Specifications hot mix plants and batching plants (existing or new) will comply with the requirements of the relevant national, state and local pollution control requirements. Hot-mix plants will be located at least 1000 m away from the nearest habitation, preferably in the downwind direction.

Construction Contractor, PC

5 Mitigating noise during construction

Noisy construction operations in residential andsensitive areas (hospitals and schools) should be restricted between 7.30 AM to 6.00 PM.Preventive maintenance of construction equipment and vehicles would be done to meet emission standards and to keep them with low noise.Sound barriers in inhabited areas shall be installed.Provision of ear plugs to operators of heavy machinery and workers in nearvicinityDuring night, material transport should be uniformly distributed to minimize noise impacts.

Construction Contractor, PC

6 Dust contamination at construction sites and along the

Unpaved haul roads near/passing through residential and commercial areas to be watered atleast once a day.Trucks carrying construction material to

Construction Contractor, PC, ULB

Page 17: Karnataka Urban Infrastructure Development and …...accordance with 74th Constitutional Amendment with a greater sustainability and accountability. 2. Strengthen institutional and

Brief EA

13

S. No.

Issues / Impacts

Mitigation Measures Project Phase Responsibility

roads be adequately covered.7 Earth work

excavationDispose surplus excavated earth at identified sites.Ensure minimum hindrance to normal local activities and business.Avoid damage to permanent structures.Immediate shifting of excavated earth.

Construction Contractor, PC, ULB

8 Disposal of construction debris

Daily inspection at haul roads and sites for construction debris for safe collection and disposal to identified site.Collection and disposal of refuse.Minimise construction debris by balancing cut and fill requirements, if relevant.

Construction Contractor, PC, ULB

9 Safety practices during construction

Contractor is required to comply with all the precautions as required for the safety of the workers as per the International Labour Organisation (ILO) Convention No. 62 as far as those are applicable to this contract. Contractor will supply all necessary safety appliances such as safety goggles, helmets, masks, etc., to the workers and staff. The contractor has to comply with all regulation regarding, working platforms, excavations, trenches and safe means of entry and egress.

Construction Contractor, PC, ULB

10 Social disruptions Minimise interruptions to utility services through proper planning and scheduling of activities and inter- departmental co-ordination.Construction of temporary road/access and diversion of traffic.Minimise interruptions to the commercial establishments observed in road nos. 9,10,12,15,16,17,42,57,58,59,61,64,66,67 & 91

Construction Contractor, PC, ULB

11 Aesthetic impairment

Aesthetic enhancement through proper house keeping of construction sites.Disposal of construction wastes at the approved disposal sites.Immediate closure of the trenches after completion of work.Complete construction activity by removing all temporary structures, restoring the project and surrounding areas as near as possible to the pre- construction condition.

Construction Contractor, PC, ULB

12 Material sourcing (sand, borrow material and stone material)

Procurement of construction material only frompermitted sites and licensed / authorized quarries.Farm land and forest belts shall not be

Construction Contractor

Page 18: Karnataka Urban Infrastructure Development and …...accordance with 74th Constitutional Amendment with a greater sustainability and accountability. 2. Strengthen institutional and

Chitradurga

14

S. No.

Issues / Impacts

Mitigation Measures Project Phase Responsibility

used for material sourcing or borrow sites.Arable land shall not be selected as borrow sits as much as possible. If excavation has to be done in arable land, top soil layer (30 cm) shall be saved and returned after construction work is completed, so as to minimize impacts.

13 Construction labour

Planning of labour camps, if required, needs to be done to ensure adequate water supply, sanitation and drainage etc., in conformity with the Indian Labour Laws.

Construction Contractor, PC

14 Risk of accidents In order to guarantee construction safety, efficientlighting and safety signs shall be installed on temporary roads during construction and adequate traffic regulations shall be adopted and implemented for temporary roads.

Construction Contractor, PC, ULB

15 Traffic and Transportation

Adequate actions to direct and regulate traffic shall be taken in consultation with municipality prevent jamming roads during construction period. While planning alternative routes, care to be taken to minimize congestion and negative impacts at sensitive receptors such as schools and hospitals.Traffic controls and diversions marked with signs, lights and other measures (flags) should be provided.Prior to creating diversions and detours the citizens should be consulted well in advance through citizen’s meetings. It should be an informed decision taken through public participation.Diversion works to be dismantled to restore the area to original condition aftercompletion of construction.

Construction Contractor, PC, ULB

15 Traffic and Transportation

Adequate actions to direct and regulate traffic shall be taken in consultation with municipality prevent jamming roads during construction period. While planning alternative routes, care to be taken to minimize congestion and negative impacts at sensitive receptors such as schools and hospitals.Traffic controls and diversions marked with signs, lights and other measures (flags) should be provided.Prior to creating diversions and detours the citizens should be consulted well in advance through citizen’s meetings. It should be an informed decision taken through public participation.Diversion works to be dismantled to

Construction Contractor, PC, ULB

Page 19: Karnataka Urban Infrastructure Development and …...accordance with 74th Constitutional Amendment with a greater sustainability and accountability. 2. Strengthen institutional and

Brief EA

15

S. No.

Issues / Impacts

Mitigation Measures Project Phase Responsibility

restore the area to original condition after completion of construction.

16 Protection of Religious Structures

All necessary and adequate care to be taken to minimize impact on religious structures found in road no.8,10,12,19,21,27,31,35,65,69,79 & 88

Construction Contractor, PC, ULB

17 First Aid Arrangement for a readily available first aid unit including an adequate supply of sterilized dressing materials and appliances shall be make available for full time.

Construction Contractor, PC, ULB

18 Cultural relics / finds

If fossils, coins, articles of value or antiquity, structures, and their remains of geologic or archaeological interest are found, local government shall be immediately informed of such discovery and excavation shall be stopped until identification of cultural relics by the authorised institution and clearance is given for proceeding with work.

Construction Contractor, PC, ULB

19 Clearing of construction camps andrestoring them.

To prepare camp restoration plans, if temporary camps were used. On completion of the works, all temporary structures will be cleared away, all rubbish properly disposed, excreta or other disposal pits or trenches filled in and effectively sealed off and the outline site left clean and tidy.

Construction Contractor, PC, ULB

Table 3: Monitoring Requirement & Specifications for Roads

No. Monitoring Requirement Specifications Responsible agency

1 Ambient air quality at fixed stations to understand the impact of change in traffic pattern due to the project.Moving station (1 No.) at the construction site (only during construction period) to understand the impact of construction operations.

SPM, RSPM, SO2, NOx, CO, HC. High volume air sampler to be located 50 m from the plant in the downwind direction.Use method specified by CPCB for analysis.Once before start of work & once every season of the year during construction period.

Contractor, PC, ULB

2 Noise levels at the construction sites (only during construction period)

Monitoring at all locations hourly basis for 24 hour period. Once every season of the year during construction period.

Contractor, PC, ULB

3 Disposal of construction debris Periodic inspection at haul roads and sites for construction debris for safe collection and disposal to identified land fill sites.

PC, ULB Once a week.

4 Traffic and Transportation Measures for divertingthe traffic during construction

across roads within the ULB

PC, ULB and Traffic Police, if relevant.Continuous.

5 Domestic sewage and refuse Check for adequacy of sanitation PC, ULB

Page 20: Karnataka Urban Infrastructure Development and …...accordance with 74th Constitutional Amendment with a greater sustainability and accountability. 2. Strengthen institutional and

Chitradurga

16

No. Monitoring Requirement Specifications Responsible agency

management at the labour camps and construction sites

arrangements at the labour camps Once a week.

6 Water Pollution Check for:Blockage of flowing water which may lead to stagnation of waterSoil erosion due to construction activities leading to contamination and siltation of water bodiesWater contamination due to use of fuel and lubricants at the construction sites.

PC, ULB Once in 15 days

7 Procurement of construction material Check that procurement of construction materials should be only from permitted sites and quarries.

PC, ULB Continuous.

Note: Location of Air monitoring shall be wherever the contractor decides to locate the hot mix plant and sensitive locationsalong the road stretch. Wherever air pollution parameters increase above specified standards, additional measures as decided by the engineer in charge shall be adopted.; Location of Noise monitoring shall be wherever the contractor decides to locate the equipment yard and at sensitive locations such as school, hospitals, dispensary etc. Incase of noise levels causing disturbance to the sensitive receptors, management measures as suggested in the EMP shall be carried out.

1.8 STORMWATER DRAINS

1.8.1 EXISTING SYSTEM

For drainage of storm water during rainy season and avoiding the flooding of low lying areas and water stagnation it is necessary to provide the drainage pathway for proper disposal of storm water from the developed area. The storm water drainage system in Chitradurga is predominantly open. The major storm water drainage network comprises of the primary drain from Kanaka Circle to Holalkere Road (NH4) which runs for 2.725 Km length in North ward direction inside the town. Road side drains from different parts of the town join this main drain.

Some portions of the drain needs desilting to facilitate smooth flow during rains. The main drain passes through the built up area of the city and is filled up with debris and encroached in some stretches. This results in water stagnation during rains leading to mosquito and contamination of under ground water sources which makes it more necessary to provide storm water drains from hygienic point of view.

1.8.2 PROPOSED DEVELOPMENT

At present storm water drains carry waste water from about 60%of the town because of non existence or non performance of underground drainage system in some of the areas of the town. Remaining 40% of the city area is not covered by storm water drains.

Three major open drains are discharging their waste in Baragere kere, which carries sullage and sewage from the households polluting the tank. In order to prevent the pollution of fresh water in the tank and also ground water, it is necessary provide suitable storm water drains to avoid the sewage entering into

Page 21: Karnataka Urban Infrastructure Development and …...accordance with 74th Constitutional Amendment with a greater sustainability and accountability. 2. Strengthen institutional and

Brief EA

17

the tank. The CMC has desired that following drains be constructed. The details are given in Table-4.1.

Table 4: Details of drains to be constructed as part of the project

S. No. Description

Length (m)

Width (m)

Depth(m)

1 From Karnataka Circle to NH-4 2725 2.0 to 5.0 1.0 to 3.0

2 Ravi Nursing home to Subbamma Galli 483 2.0 to 3.0 2.0 to 2.2

Total 3208

1.8.3 COST OF SWD

Sl. No.

DetailsLength(m)

Estimated Cost of Drain

Estimated Cost of Drop

Estimated Cost of Culvert/Bridge

Total

(Rs.) (Rs.) (Rs.) (Rs.)

1SWD from Kanaka circle to NH-4 bypass 2725 40675738 324745 2715657 43716140

2SWD from Ravi Nursing Home to Subbamma Galli

483 8571947 196276 - 8768223

Total 52484363Add 10% for Tender Premium 5248437Add 5% for contingencies 2398973Miscellaneous and Rounding off 227GRAND TOTAL 60132000

1.8.4 EMP FOR SWD

Table 5: EMP for Storm Water Drains

Sl.No.

Impacts Mitigation measures Project Phase

Responsibility

1 Utility relocation In case of utilities (water supply lines, electrical installations, telephone lines etc) and common property resources being impacted due to the project, they will be relocated with prior approval of the concerned agencies before construction starts. Therelocation will be in accordance with the feasibility and choice of the community. Utility relocation shall be carried out in shortest possible time to reduce inconvenience to public.

Pre-construction

Contractor, PC, ULB

2 Site clearance Site clearance will be done only in the area required for the sub-project.

Pre-construction

Contractor, PC

3 Debris disposal site identification

Site for temporary storage and disposal of debris refuse to be identified. These disposal sites shall be finalized such that they are not located within designated forest or other eco-sensitive areas, does not impact natural drainage courses and no endangered / rare flora is impacted by such disposal.

Pre-Construction

Contractor, PC, ULB

4 Mitigating noise during construction

Noisy construction operations in residential andsensitive areas (hospitals and schools) should be restricted between 7.30 a.m. to 6.00 p.m.

Construction Contractor, PC

Page 22: Karnataka Urban Infrastructure Development and …...accordance with 74th Constitutional Amendment with a greater sustainability and accountability. 2. Strengthen institutional and

Chitradurga

18

Sl.No.

Impacts Mitigation measures Project Phase

Responsibility

Preventive maintenance of construction equipment and vehicles would be done to meet emission standards and to keep them with low noise.Sound barriers in inhabited areas shall be installed.Provision of ear plugs to operators of heavy machinery and workers in near vicinityDuring night, material transport should be uniformly distributed to minimize noise impacts.

5 Dust contamination at construction sites and along the roads

Unpaved haul roads near/passing through residential and commercial areas to be watered at least once a day.Trucks carrying construction material to be adequately covered.

Construction Contractor, PC, ULB

6 Earth work excavation

Ensure unobstructed natural drainage through proper drainage channels/structures.Dispose surplus excavated earth at identified sites.Ensure minimum hindrance to normal local activities and business.Avoid damage to permanent structures.Immediate shifting of excavated earth.

Construction Contractor, PC, ULB

7 Disposal of construction debris

Daily inspection at haul roads and sites for construction debris for safe collection and disposal to identified site.Collection and disposal of refuse.Minimize construction debris by balancing cut and fill requirements, if relevant.

Construction Contractor, PC, ULB

8 Safety practices during construction

The Contractor is required to comply with all theprecautions as required for the safety of the workers as per the International Labour Organisation (ILO) Convention No. 62 as far as those are applicable to this contract. The contractor will supply all necessary safety appliances such as safety goggles, helmets, masks, etc., to the workers and staff. The contractor has to comply with all regulation regarding, working platforms, excavations, trenches and safe means of entry and egress.

Construction Contractor, PC

9 Social disruptions Minimise interruptions to utility services through proper planning and scheduling of activities and inter-departmental co-ordination.Construction of temporary road/access and diversion of traffic.

Construction Contractor, PC, ULB

10 Aesthetic impairment

Aesthetic enhancement through proper house keeping of construction sites.Disposal of construction wastes at the approved disposal sites.Immediate closure of the trenches after completion of work.Complete construction activity by removing all temporary structures, restoring the project and surrounding areas as near as possible to the pre-construction condition.

Construction Contractor, PC, ULB

11 Material sourcing (sand, borrow material and stone material)

Procurement of construction material only frompermitted sites and licensed / authorized quarries.Farm land and forest belts shall not be used for material sourcing or borrow sites.Arable land shall not be selected as borrow sits as

Construction Contractor

Page 23: Karnataka Urban Infrastructure Development and …...accordance with 74th Constitutional Amendment with a greater sustainability and accountability. 2. Strengthen institutional and

Brief EA

19

Sl.No.

Impacts Mitigation measures Project Phase

Responsibility

much as possible. If excavation has to be done in arable land, top soil layer (30 cm) shall be saved and returned after construction work is completed, so as to minimize impacts.

12 Construction labour

Planning of labour camps, if required, needs to be done to ensure adequate water supply, sanitation and drainage etc., in conformity with the Indian Labour laws.

Construction Contractor, PC

13 Traffic and Transportation

Adequate actions to direct and regulate traffic shall be taken in consultation with municipality prevent jamming roads during construction period. While planning alternative routes, care to be taken to minimize congestion and negative impacts at sensitive receptors such as schools and hospitals.Traffic controls and diversions marked with signs, lights and other measures (flags) should be provided.Prior to creating diversions and detours the citizens should be consulted well in advance through citizen’s meetings. It should be an informed decision taken through public participation.Diversion works to be dismantled to restore the area to original condition after completion of construction.

Construction Contractor, PC, ULB

14 First Aid Arrangement for a readily available first aid unit including an adequate supply of sterilized dressing materials and appliances shall be make available for full time.

Construction Contractor, PC, ULB

15 Cultural relics / finds

If fossils, coins, articles of value or antiquity, structures, and their remains of geologic or archaeological interest are found, local government shall be immediately informed of such discovery and excavation shall be stopped until identification of cultural relics by the authorised institution and clearance is given for proceeding with work.

Construction Contractor, PC, ULB

16 Clearing of construction camps andrestoring them.

To prepare camp restoration plans, if temporary camps were used. On completion of the works, all temporary structures will be cleared away, all rubbish properly disposed, excreta or other disposal pits or trenches filled in and effectively sealed off and the outline site left clean and tidy.

Construction Contractor, PC, ULB

Table 6: Monitoring Requirement and Specification for SWD

No. Monitoring Requirement Specifications Responsible agency

1 Ambient air quality at fixed stations to understand the impact of change in traffic pattern due to the project.Moving station (1 No.) at the construction site (only during construction period) to understand the impact of construction operations.

SPM, RSPM, SO2, NOx, CO, HC. High volume air sampler to be located 50 m from the plant in the downwind direction.Use method specified by CPCB for analysis.Once before start of work & once every season of the year during construction period.

Contractor, PC, ULB

2 Noise levels at the construction sites (only during construction period)

Monitoring at all locations hourly basis for 24 hour period. Once every season of the year during construction period.

Contractor, PC, ULB

Page 24: Karnataka Urban Infrastructure Development and …...accordance with 74th Constitutional Amendment with a greater sustainability and accountability. 2. Strengthen institutional and

Chitradurga

20

No. Monitoring Requirement Specifications Responsible agency

3 Disposal of construction debris Periodic inspection at haul roads and sites for construction debris for safe collection and disposal to identified land fill sites.

PC, ULB Once a week.

4 Traffic and Transportation Measures for diverting the traffic during construction across roads within the ULB

PC, ULB and Traffic Police, if relevant.Continuous.

5 Domestic sewage and refuse management at the labour camps and construction sites

Check for adequacy of sanitation arrangements at the labour camps

PC, ULB Once a week.

6 Water Pollution Check for:Blockage of flowing water which may lead to stagnation of waterSoil erosion due to construction activities leading to contamination and siltation of water bodiesWater contamination due to use of fuel and lubricants at the construction sites.

PC, ULB Once in 15 days

7 Procurement of construction material Check that procurement of construction materials should be only from permitted sites and quarries.

PC, ULB Continuous.

1.9 SLUM INFRASTRUCTURE

1.9.1 EXISTING INFRASTRUCTURE

The total local network comprises of lanes & streets roads for a length about 107.5 Km. Of these about 58 Nos of roads for a length of about 8.85 Km is taken up under this sub component. These roads cater the needs of main traffic inside the city and are provided with bituminous and rigid riding surface with carriageway ranging from 3.0 to 5.50 m.

Few roads there have no pucca drains to carry the storm water. The interior roads are mostly earthen or having gravel and metal riding surface without proper drainage arrangement. In some of the new extension areas there are only earthen roads. Due to paucity of funds resulting in poor maintenance, the riding surface is in dilapidated condition. The traffic experiences difficulty in passing over the roads besides the problem of dust pollution.

Santhe Maidhan is situated in northern part of the Chitardurga town, 800 m away from the KSRTC bus stand. There is burial ground and private bus stand closely situated near the area. The habitation living around the area belongs to low income group .i.e below the poverty line. The space in and around the area is presently occupied by the vehicle repairing garages. Every Monday there will be trading of vegetables .i.e. (Sandy day santhe). To boost up their standard of living conditions by providing good hygiene conditions, a market yard covering a area of 60 m x 30 m is proposed with 102 shops is proposed. By providing this market, there will be increase in revenue collection to the municipality.

Page 25: Karnataka Urban Infrastructure Development and …...accordance with 74th Constitutional Amendment with a greater sustainability and accountability. 2. Strengthen institutional and

Brief EA

21

1.9.2 UPGRADATION OF PHYSICAL INFRASTRUCTURE IN SLUMS

The revised list provided for rehabilitation of 58 roads for about a length of 8.85 Kms for various widths of carriage ways for providing bituminous & concrete riding surface over different types of existing surfaces like earthen, metalled and bituminous surfaces. It also envisaged rehabilitation of 75 numbers of culverts and road drains for stretches where no pucca drains.

The ULB has also proposed to take up the construction of Sante maidhan market, providing cover slabs on existing storm water drain in Budda nagar slum and providing basic facilities for the residents of Mandakki batti.

The market yard is designed as a pitched roof covering a plan area of 60 x 30 m comprising of steel angular trussess resting on concrete columns. The structural analysis of the structural was performed by Staad pro with various load combinations of live load, dead load and wind load (basic wind speed 33 m/s).The steel angular truss will be covered with 0.5 mm galvalume sheet which is more corrosive resultant than conventional sheets. The market yard will also be provided with civic amenities like roads, water supply and electrification.

1.9.3 COST OF DEVELOPMENT

S. No

Particulars Amount (Rs.)

1 Rehabilitation of roads 27851593.002 Rehabilitation / construction of road side drain 19666027.003 Construction of culverts 3945278.004 Construction of Sante Maidan Market yard 8630125.00

Total Cost 60093023.00Add 10% Tender Premium 6009303.00

Contingences 2974605.00

Misce and rounding off 23067.00

Grand Total 69100000.00

1.9.4 EMP FOR SLUM DEVELOPMENT

Table 7: EMP for Slum Development

Sl.No.

Impacts Mitigation Measures Project Phase

Responsibility

1 Utility relocation In case of utilities (water supply lines, electrical installations, telephone lines etc) and common property resources being impacted due to the project, they will be relocated with prior approval of the concerned agencies before construction starts. The relocation will be in accordance with the feasibility and choice of the community. Utility relocation shall be carried out in shortest possible time to reduce inconvenience to public.

Pre-construction

Contractor, PC, ULB

2 Site clearance Site clearance will be done only in the area required for the sub-project.

Pre-construction

Contractor, PC

3 Debris disposal site identification Site for temporary storage and disposal of Pre- Contractor,

Page 26: Karnataka Urban Infrastructure Development and …...accordance with 74th Constitutional Amendment with a greater sustainability and accountability. 2. Strengthen institutional and

Chitradurga

22

Sl.No.

Impacts Mitigation Measures Project Phase

Responsibility

debris refuse to be identified. These disposal sites shall be finalized such that they are not located within designated forest or other eco-sensitive areas, does not impact natural drainage courses and no endangered / rare flora is impacted by such disposal.

ConstructionPC, ULB

4 Hot-mix plants & Batching Plants Specifications hot mix plants and batching plants(existing or new) will comply with the requirements of the relevant national, state and local pollution control requirements. Such plants will be located at least 1000 m away from the nearest habitation, preferably in the downwind direction.

ConstructionContractor, PC

5 Mitigating noise during construction

Noisy construction operations in residential andsensitive areas (hospitals and schools) should be restricted between 7.30 a.m. to 6.00 p.m.Preventive maintenance of construction

equipment and vehicles would be done to meet emission standards and to keep them with low noise.Sound barriers in inhabited areas shall be installed.Provision of ear plugs to operators of heavy machinery and workers in near vicinityDuring night, material transport should be uniformly distributed to minimize noise impacts.

ConstructionContractor, PC

6 Dust contamination at construction sites and along the roads

Unpaved haul roads near/passing through residential and commercial areas to be watered atleast once a day.Trucks carrying construction material to be adequately covered.

ConstructionContractor, PC, ULB

7 Earth work excavation Ensure unobstructed natural drainage through proper drainage channels/structures.Dispose surplus excavated earth at identified sites.Ensure minimum hindrance to normal local activities and business.Avoid damage to permanent structures.Immediate shifting of excavated earth.

ConstructionContractor, PC, ULB

8 Disposal of construction debris Daily inspection at haul roads and sites for construction debris for safe collection and disposal to identified site.Collection and disposal of refuse.Minimise construction debris by balancing cut and fill requirements, if relevant.

ConstructionContractor, PC, ULB

Page 27: Karnataka Urban Infrastructure Development and …...accordance with 74th Constitutional Amendment with a greater sustainability and accountability. 2. Strengthen institutional and

Brief EA

23

Sl.No.

Impacts Mitigation Measures Project Phase

Responsibility

9 Safety practices during construction

The Contractor is required to comply with all theprecautions as required for the safety of the workers as per the International Labour Organisation (ILO) Convention No. 62 as far as those are applicable to this contract. The contractor will supply all necessary safety appliances such as safety goggles, helmets, masks, etc., to the workers and staff. The contractor has to comply with all regulation regarding, working platforms, excavations, trenches and safe means of entry and egress.

ConstructionContractor, PC

10 Social disruptions Minimise interruptions to utility services through proper planning and scheduling of activities and inter- departmental co-ordination.Construction of temporary road/access and diversion of traffic.

ConstructionContractor, PC, ULB

11 Aesthetic impairment Aesthetic enhancement through proper house keeping of construction sites.Disposal of construction wastes at the approved disposal sites.Immediate closure of the trenches after completion of work.Complete construction activity by removing all temporary structures, restoring the project and surrounding areas as near as possible to the pre- construction condition.

ConstructionContractor,PC, ULB

12 Material sourcing (sand, borrow material and stone material)

Procurement of construction material only frompermitted sites and licensed / authorized quarries.Farm land and forest belts shall not be used for material sourcing or borrow sites.Arable land shall not be selected as borrow sits as much as possible. If excavation has to be done in arable land, top soil layer (30 cm) shall be saved and returned after construction work is completed, so as to minimize impacts.

ConstructionContractor

13 Construction labour Planning of labour camps, if required, needs to be done to ensure adequate water supply, sanitation and drainage etc.,

ConstructionContractor, PC

Page 28: Karnataka Urban Infrastructure Development and …...accordance with 74th Constitutional Amendment with a greater sustainability and accountability. 2. Strengthen institutional and

Chitradurga

24

Sl.No.

Impacts Mitigation Measures Project Phase

Responsibility

in conformity with the Indian Labour laws.14 Risk of accidents In order to guarantee construction safety,

efficientlighting and safety signs shall be installed on temporary roads during construction and adequate traffic regulations shall be adopted and implemented for temporary roads.

ConstructionContractor, PC, ULB

15 Traffic and Transportation Adequate actions to direct and regulate traffic shall be taken in consultation with municipality prevent jamming roads during construction period. While planning alternative routes, care to be taken to minimize congestion and negative impacts at sensitive receptors such as schools and hospitals.Traffic controls and diversions marked with signs, lights and other measures (flags) should be provided.Prior to creating diversions and detours the citizens should be consulted well in advance through citizen’s meetings. It should be an informed decision taken through public participation.Diversion works to be dismantled to restore the area to original condition after completion of construction.

ConstructionContractor, PC, ULB

16 Protection of Religious Structures All necessary and adequate care to be taken to minimize impact on religious structures

ConstructionContractor, PC, ULB

17 First Aid Arrangement for a readily available first aid unit including an adequate supply of sterilized dressing materials and appliances shall be make available for full time.

ConstructionContractor, PC, ULB

18 Cultural relics / finds If fossils, coins, articles of value or antiquity, structures, and their remains of geologic or archaeological interest are found, local government shall be immediately informed of such discovery and excavation shall be stopped until identification of cultural relics by the authorised institution and clearance is given for proceeding with work.

ConstructionContractor, PC, ULB

19 Clearing of construction camps andrestoring them.

To prepare camp restoration plans, if temporary camps were used. On completion of the works, all temporary structures will be cleared away, all rubbish properly disposed, excreta or other disposal pits or trenches filled in and effectively sealed off and the outline site left clean and tidy.

ConstructionContractor, PC, ULB

Page 29: Karnataka Urban Infrastructure Development and …...accordance with 74th Constitutional Amendment with a greater sustainability and accountability. 2. Strengthen institutional and

Brief EA

25

Table 8: Monitoring Requirement and Specification for Slum Development

No. Monitoring Requirement Specifications Responsible agency

1 Ambient air quality at fixed stations to understand the impact of change in traffic pattern due to the project.Moving station (1 No.) at the construction site (only during construction period) to understand the impact of construction operations.

SPM, RSPM, SO2, NOx, CO, HC. High volume air sampler to be located 50 m from the plant in the downwind direction.Use method specified by CPCB for analysis.Once before start of work & once every season of the year during construction period.

Contractor, PC, ULB

2 Noise levels at the construction sites (only during construction period)

Monitoring at all locations hourly basis for 24 hour period. Once every season of the year during construction period.

Contractor, PC, ULB

3 Disposal of construction debris Periodic inspection at haul roads and sites for construction debris for safe collection and disposal to identified land fill sites.

PC, ULB Once a week.

4 Traffic and Transportation Measures for diverting the traffic during construction across roads within the ULB

PC, ULB and Traffic Police, if relevant.Continuous.

5 Domestic sewage and refuse management at the labour camps and construction sites

Check for adequacy of sanitation arrangements at the labour camps

PC, ULB Once a week.

6 Water Pollution Check for:Blockage of flowing water which may lead to stagnation of waterSoil erosion due to construction activities leading to contamination and siltation of water bodiesWater contamination due to use of fuel and lubricants at the construction sites.

PC, ULB Once in 15 days

7 Procurement of construction material Check that procurement of construction materials should be only from permitted sites and quarries.

PC, ULB Continuous.

1.10WATER TREATMENT PLANT

1.10.1 EXISTING SYSTEM

The present water Supply system for Chitradurga is V. V. Sagar dam across Vedavathi River near Hiriyur above 42 km away. A pick up weir is constructed across Vedavathi River and raw water is drawn into Jack Well of 6.20m dia with pump house above. Two vertical Turbine pumps (1W+1S) of 100 HP are provided to pump raw water though 400mm dia C. I. ‘B’ class rising main over a length of 2300m to water treatment plant of 9.08 MLD

Page 30: Karnataka Urban Infrastructure Development and …...accordance with 74th Constitutional Amendment with a greater sustainability and accountability. 2. Strengthen institutional and

Chitradurga

26

capacity. The WTP is located at outskirts of Hiriyur near NH-4. WTP comprises of aeration, flash mixers, chemical coagulation, clarifier, rapid sand filter and treated water sump. Filtered and chlorinated water is pumped using 320 HP centrifugal pumps, 2 Nos. (1W+1S) through 400mm dia C. I. ‘B’ class rising main over a length of 18 km and water discharged into a rectangular sump of 1.00 lac liters capacity at intermediate pumping station.

Non functional Water Treatment Plant at Hiriyur

The status of various units/equipments of water treatment plant is given in following table.S. No. Component Present status of the component1 Aerator : The aerator is in good working condition2 Raw Water channel : This requires reconditioning by repairing the plastering on removing

the old plastering & installing raw water meter.3 Flash Mixer : This requires to be improved by attending fresh plastering the side

walls, bottom & external sides. The agitator assembly including support frame, 3 HP motor (3 PH-415 volts). Reduction gears and coupling are out of order and the unit required to be replaced with new fixtures.

4 Clariflocculator : The electro-mechanical component is not in order, and found to be totally unserviceable and cannot be repaired. Hence supply of scraper bridge assembly including drive carriage viz., motor, gear box assembly, central bearing, slip ring apparatus, rubber squeegees and M.S. track are required to be replaced in order to recondition the systems.

5 Rapid sand gravity filters : The RPS filtration is not in order and the system is found to be not working. It is advisable to recondition the system by total revamping by providing of pipe gallery and out let valves of 400mm dia & back wash valve of 300mm dia. Also, providing fresh filer media as per technical specification, further filter apparatus including LOH & ROF meters & ROH controllers, are to be provided.

6 Chlorinators : The apparatus are in good working condition on improvements of the treatment plant as detailed above, this will ensure a potable, water supply of 9,08,000 Ltrs (2 MGD) for a population of 1,50,000 at 60 LPCD with proper chlorination, as the ion exchange chlorinators installed are under good working condition.

7. Electro-Mechanical fixtures & Filter Media

: Again, the present status of electro mechanical fixtures provided have been inspected, under the water treatment plant at Hiriyur on 29.08.2007. Due to lack of maintenance, Alum mixing tank apparatus, flash mixing devices and clariflocculator bridge in the treatment plant are required to be changed by new fixtures; Including wiring and controls needs to be replaced. Further, the filter media is formed to be totally worn out and un serviceable, hence required to be replaced conforming to quality standard prescribed by CPHEEO: to ensure supply of potable water to the public in particular with due chlorination. Also, the pipe gallery is found to be very old and not suitable to screen the water and this has to be replaced newly, along with control valves and control meters and equipping of required laboratory apparatus.

Water Supply arrangements from TP for supply to the Chitradurga City.

: The treated water from the filter plant is conveyed to 70,000 ltr. Capacity pure water sump in the treatment plant area. (50’ x 24’ x 10’) water from this sump is then pumped to IPS (25’ x14’ x 12’). 21,000 ltr capacity sump at Burujanakoppa through 400mm CI pure water rising main 23Km length. Originally there were 2 No. of 150 HP pumpset with 1 No. of additional pump set on stand by. As these pumps are out dated and involving frequent repairs, as such in 1984, 2 Nos. of 300 HP pumpset with 1 No. as stand by was installed. Again during 1997-98 under Deputy Commissioner scarcity relief fund 2 Nos. of 320 HP pumpset were installed and now presently, these pumps

Page 31: Karnataka Urban Infrastructure Development and …...accordance with 74th Constitutional Amendment with a greater sustainability and accountability. 2. Strengthen institutional and

Brief EA

27

S. No. Component Present status of the componentare in working condition and providing water supply in the city. Earlier, at IPS 2 Nos-140 HP pumpset and 1 No. as standby was provided. But, the pumpsets were out lived involving frequent repairs and also of low discharge capacity. As such during 1984, 2 Nos. of290 HP pumpset were installed, of which 1 No as standby. Again during 1997-98 under DC scarcity relief fund 2 Nos. of 300 HP pumpset were installed, of which 1 No. as standby and with this, water supply is made in the town. Further from this IPS, water is again pumped to sump of 5000 gallons (40’ x 20’ x 10’) capacity located near Kanave Maramma temple through 400mm dia CI rising main of 10.30 Km. From this reservoir water is then distributed through 400mm dia CI of gravity main of 5.40 Km length to existing GLSR and OHTs. Thus water obtained from Hiriyur TP is distributed to following reservoirs to distribution network pipes and also directly supplied to distribution pipes.

1.10.2 WATER SUPPLY AUGMENTATION

It is proposed to provide new electro mechanical fixtures to the flash mixer alum tank and clari-flocculator etc. Further, it is observed that the plastering provided for the above component works for interior and exterior are also required to be dismantled and good plastering in cement mortar of requisite proportion is to be attended in order to achieve proper water tightness of the component. Thus, necessary repairs for attending plastering to this works are proposed.

The rapid sand filter is found to be unserviceable and it requires total revamping of filter media and filter sand. Hence, it is proposed to provide filter media as per CPHEEO standards on removing the existing filter media and attending repairs to filter box viz., plastering the cement mortar both inside and outsides of the filter box and proposing cement mortar grouting to the bed to fill the cracks and crevices in order to recondition the filter box for water tightness. Anti-corrosive painting for the interior of the filter box is also proposed.

Electro-mechanical equipments required in case of alum tank and flow meters, gauges, valves, etc. for the filters for inlet and outlet connections as well as for wash water pipe have been proposed in place of worn out and unserviceable valves and fixtures in accordance with Dondeli model. The estimate has been prepared based on Dondeli treatment plant repairs model. For laboratory apparatus and safety equipment rates approved under Dondeli model for repairs to treatment plant has been estimated it amounts to Rs. 1,20,000/.

On improvement of the treatment plant by attending the above repairs and installations and proper chlorination. water shall be treated to the standards specified as per IS 11095. besides this necessary laboratory apparatus required for testing of water samples together with safety equipments have been proposed.

1.10.3 COST OF WATER SUPPLY AUGMENTATION

S. No.

Component Cost (Rs.)

1. Electro Mechanical works (As per Estimate) 9474172 Civil Works 15627393. Laboratory Apparatus and Safety Equipment 120000

TOTAL 2630156

Page 32: Karnataka Urban Infrastructure Development and …...accordance with 74th Constitutional Amendment with a greater sustainability and accountability. 2. Strengthen institutional and

Chitradurga

28

1.10.4 EMP FOR WATER SUPPLY AUGMENTATION

Table 9: EMP for Water Supply Augmentation

Sl.No.

Potential Negative Impacts

Mitigation Measures Project Phase

1. Storage of materials

The contractor shall identify the site for temporary use of land for construction sites /storage of construction materials including pipes, etc. These sites shall not cause any inconveniences to local population / traffic movement and shall not be located within 500 m from schools/hospitals. These locations shall be approved by the engineer and shall be operated only after the approval.

Pre-construction & construction phase

2. Disposal of construction debris and excavated materials.

Contractor will identify the sites for excess earth and debris disposal, prior to start of the earthworks; taking into account the following:(a) The dumping shall not impact natural drainage courses (b) no endangered / rare flora is impacted by such dumping (c) Settlement area located at least 500 km away from the site. (d) located at least 1000m from the designated forest land.(e) avoid disposal on productive land.(f)In case of community lands, should be located with the consensus of the local community , in consultation with the engineer

Pre-construction and Construction

3. Disposal of silt / sludge

A suitable site should be identified for safe disposal of silt / sludge generated from old sewers (preferably approved sludge disposal sites of STPs), excavations at the pumping / lifting station sites, which should be away from the water bodies, residential & sensitive areas, agricultural areas and etc., and got approved by the Engineer.

During construction and operation

4. Temporary water supply interruptions

i) Establish coordination with the concerned department to avoid or minimize the interruption of regular supply of drinking water to the residents. ii) Proper alternative arrangements to be planned when interruption of drinking water supply to the near by residents.iii) Prior intimation (at least 5 working days) shall be given in case of planned disruption of water supply. In the event of accidental disruptions, the supply lines shall be restored within 24 hours, and alternative water supply arrangement should be made...

Pre-construction and Construction

5. Dust Pollution near settlements

i) Construction material shall be covered or stored in such a manner so as to avoid being affected by wind direction.ii) Unpaved haul roads near / passing through residential and commercial areas to be watered thrice a day. The costs thereof will be borne by the contractor iii) Trucks carrying construction material to be adequately covered to avoid the dust pollution and to avoid the material spillage.

During construction

6. Protection of residential / sensitive receptors.

i) All the properties along the construction site shall be provided with clear access. Noisy construction operations in residential and sensitive areas should be carried out only between 7.30 am and 6.00 pm. ii) Preventive maintenance of construction equipment and vehicles to meet emission standards and to keep them with low noise, including PUC certification to check air pollution. iii) Low noise generators shall be used.

During construction

7. Noise from vehicles, plants and equipments

v) Maintenance of vehicles, equipment and machinery shall be regular and up to the satisfaction of the Engineer to keep noise levels at the minimum.

During construction

Page 33: Karnataka Urban Infrastructure Development and …...accordance with 74th Constitutional Amendment with a greater sustainability and accountability. 2. Strengthen institutional and

Brief EA

29

Sl.No.

Potential Negative Impacts

Mitigation Measures Project Phase

8. Pollution from Fuel and Lubricants

iii) Contractor shall arrange for collection, storing and disposal of oily wastes to the pre-identified disposal sites (list to be submitted to Engineer) and approved by the Engineer. All spills and collected petroleum products will be disposed off in accordance with MoEF and state PCB guidelines.iv) Engineer will certify that all arrangements comply with the guidelines of PCB/ MoEF or any other relevant laws.

construction and operation

9. Pollution from Construction Wastes

The Contractor shall take all precautionary measures to prevent the wastewater generated during construction from entering into streams, water bodies or the irrigation system. All waste arising from the project is to be disposed off in the manner that is acceptable by the Engineer. The engineer shall certify that all liquid wastes disposed off from the sites meet the discharge standard.

During Construction and post-construction

10. Safety Aspects i)Adequate precautions shall be taken to prevent the accidents and from the machineries. All machines used shall confirm to the relevant Indian standards Code and shall be regularly inspected by the Engineer.iv) Personal Protective Equipment such as footwear and protective goggles to all workers employed on mixing of materials like cement, concrete and involved in dismantling operation etc.vi) Earplugs shall be provided to workers exposed to loud noise, and workers working in crushing, compaction, or concrete mixing operation.vii) The contractor shall supply all necessary safety appliances such as safety goggles, helmets, safety belts, ear plugs, mask etc to workers and staffs.The contractor will comply with all the precautions as required for ensuring the safety of the workmen as per the International Labor Organization (ILO) Convention No. 62 as far as those are applicable to this contract.The contractor will make sure that during the construction work all relevant provisions of the Factories Act, 1948 and the Building and other Construction Workers (regulation of Employment and Conditions of Services) Act, 1996 are adhered to.The contractor shall not employ any person below the age of 14 years for any work and no woman will be employed on the work of painting with products containing lead in any form.

During construction

11. First Aid The contractor shall arrange for: i) A readily available first aid unit including an adequate supply of sterilized dressing materials and appliances as per the Factories Rules in every work zoneii) Availability of suitable transport at all times to take injured or sick person(s) to the nearest hospital.

During construction

12. Monitoring of environment parameters

The contractor shall undertake seasonal monitoring of air, water, noise and soil quality through an approved monitoring agency. The parameter to be monitored, frequency and duration of monitoring plan shall be prepared

Project area

13. Clearing of construction of camps and restoration

Contractor to prepare site restoration plans for approval by the engineer. The plan is to be implemented by the contractor prior to demobilization.On completion of the works, all temporary structures will be cleared away, all rubbish cleared, excreta or other disposal pits or trenches filled in and effectively sealed off and the site left clean

Corridor of Impact

Page 34: Karnataka Urban Infrastructure Development and …...accordance with 74th Constitutional Amendment with a greater sustainability and accountability. 2. Strengthen institutional and

Chitradurga

30

Sl.No.

Potential Negative Impacts

Mitigation Measures Project Phase

and tidy, at the contractor’s expenses, to the entire satisfaction of the engineer. The substantial completion certification will be issued only after clearing of all construction camp sites.

1.11SUMMARY ENVIRONMENTAL MANAGEMENT PLAN ANDCONCLUSIONS

An effective co-ordination of various institutions, committees and understanding of regulations is required for the development and execution of KMRP project. KUIDFC will be the project development agency, the execution of the project needs to be carried out by the respective urban local bodies.

While developing and executing the projects, KUIDFC / ULBs shall follow the stipulations of various environmental regulations which will be enforced by KSPCB and DoEF. This necessitates the capacity building measures for ULBs in the areas of engineering skill and environmental management.

The EMPs framed, with an objective to minimise negative environmental impacts of the proposed sub-projects. The table includes the environmental issues andnecessary mitigative measures for the same. It is envisaged that mitigativemeasures for the construction phase impacts will form part of tender documents inviting proposals for construction. The responsibility for their compliance thus would be binding for the prospective contractor as the contract condition. Theoverall responsibility for implementation of mitigative measures will, however, rest with the project implementing agency, which will supervise the construction ofimprovements.

The implementation of mitigation measures are the responsibilities of the Contractor/PC/ULB. However, the mitigation measures during construction phase will be the full responsibility of prospective Contractor. The PC/ULB would be responsible only for monitoring/supervision/guidance, etc. Liquidated damages are also recommended on account of non-compliance of EMP provisions.