22
Page | 1 KENYA COORDINATING MECHANISM CONSTITUENCY FEEDBACK MEETING REPORT NGO CONSTITUENCY CONSULTATIVE MEETING 6 TH TO 8 TH MARCH 2019

KENYA COORDINATING MECHANISM CONSTITUENCY … · 2019. 6. 25. · Procurement and supply chain processes and systems in ensuring availability of ... (2017) suspended due to lack of

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: KENYA COORDINATING MECHANISM CONSTITUENCY … · 2019. 6. 25. · Procurement and supply chain processes and systems in ensuring availability of ... (2017) suspended due to lack of

Page | 1

KENYA COORDINATING MECHANISM

CONSTITUENCY FEEDBACK MEETING REPORT

NGO CONSTITUENCY CONSULTATIVE MEETING

6TH TO 8TH MARCH 2019

Page 2: KENYA COORDINATING MECHANISM CONSTITUENCY … · 2019. 6. 25. · Procurement and supply chain processes and systems in ensuring availability of ... (2017) suspended due to lack of

Page | 2

1.1 Executive Summary

This report provides feedback on the NGO constituency meeting and the plans made for 2019.

The meeting was held to provide feedback to the NGO constituency as well as highlights from

KCM members, secretariat, SRs and PRs on the Global Fund implementation, OIG report and

other highlights.

The NGO constituency interacted with the reports and raised concerns which were discussed and

informed the recommendations in the report of importance was the need for KCM to look at

ways of building the capacity of smaller/ grass root organizations, the need for improved CSO

audit of Global Fund implementation in Kenya. The need for scheduled feedback sessions were

key on the meeting agenda with members agreeing on cost effective ways of consultations and

feedback.

Page 3: KENYA COORDINATING MECHANISM CONSTITUENCY … · 2019. 6. 25. · Procurement and supply chain processes and systems in ensuring availability of ... (2017) suspended due to lack of

Page | 3

Table of contents

2.1 List of Tables

3.1 Table 1: Constituency work Plan report 2018/2019

4.1 Acronyms

AIDS Acquired Immune Deficiency Syndrome

CCM Country Coordinating Mechanism

CHV Community Health Volunteer

CHEWs Community Health Extension Workers

GFATM Global Fund

HIV Human Immuno -deficiency Virus

KCM Kenya Coordinating Mechanism

ICC(s) Inter – Agency Coordinating Committee (s)

LFA Local Fund Agent

M&E Monitoring and Evaluation

NFM New Funding Model

OC Oversight Committee

PR(s) Principal Recipient(s)

SOP Standard Operating Procedure

SR(s) Sub Recipient(s)

Page 4: KENYA COORDINATING MECHANISM CONSTITUENCY … · 2019. 6. 25. · Procurement and supply chain processes and systems in ensuring availability of ... (2017) suspended due to lack of

Page | 4

SSR(S) Sub-sub-Recipient(s)

TB Tuberculosis

ToR Terms of Reference

TS Technical Support

Page 5: KENYA COORDINATING MECHANISM CONSTITUENCY … · 2019. 6. 25. · Procurement and supply chain processes and systems in ensuring availability of ... (2017) suspended due to lack of

Page | 5

Day One

5.1 Introduction

The meeting was opened with a word of prayer by Daniel followed by introductions of the

members. This was followed by introduction of the meeting including the purpose and

objectives. The objectives were discussed and adapted for the meeting. This was followed by

discussion on the expectations and feedback on a few with the rest being handled later during

The expectations for the meeting by the stakeholders were as follows:

Understand how PRs select SRs

To know how to fight TB and HIV

To get more know what Global Fund does and the processes

How Kenya can self fund

How smaller / grass root organizations can benefit from Global Fund grants

Know which organizations are getting GF and if they ar considering SSRs

Understand the funds breakdown and allocation of all 3 diseases

Understand the deliverables for the NGO representatives at KCM

How youth can get funds directly

How can we ask GOK to increase funding

Understand the feedback mechanism between NGO representative to the KCM and the

constituency.

The participants also shared what they know about GF. Some of the responses included: GF

funds TB; puts together funds; fund and supports low income countries; Funds 3 diseases; assists

youth, supports health and others did not know about GF.

Ground Rules were also set: phones on silent, active participation; mingling; show of hand

before talking

Page 6: KENYA COORDINATING MECHANISM CONSTITUENCY … · 2019. 6. 25. · Procurement and supply chain processes and systems in ensuring availability of ... (2017) suspended due to lack of

Page | 6

6.1 Purpose and Objectives of the Constituency feedback workshop

Purpose

Engage with Constituent members and share Global Fund information with a view to

strengthen and sustain Global Fund Programming in Kenya.

Specific Objectives

1. Update constituency members on GF/KCM operations ,OIG report, SR Selection

Process and GF replenishment.

2. Share overall experiences and achievements in relation to GF grants.

3. Review 2018/2019 Constituency Work plan implementation progress.

4. Develop Constituency Annual Plan for 2019/2020

5. Discuss strategies to strengthen and sustain GF Programming in Kenya.

Ms. Faith Ndungu gave updates on KCM, Global Fund strategic objectives 2017- 2022, Global

Fund key principles, and partnerships. This was followed by an update on KCM functions,

mandates and membership which stands at 23 constituencies. The roles of KCM, PRs and LFAs

was discussed.

Participants were taken through the new Global Fund Grant to Kenya and the allocation per

disease. 15th

December, 2017 Kenya signed new grant amounting to USD 380 Million for the

period Jan 2018 to June 2021.

HIV= 25 billion, TNT, 17.9 billion, KRCS=KShs 7.1 billion

Malaria 6.7 Billion, TNT 5.4 billion, Amref Health Africa, KShs 1.3 billion.

Tuberculosis =KShs 6.3 billion ,TNT KShs 3.0 billion, Amref Health Africa, KShs

3.3 billion

7.1 Status of planned activities- as per 2017.2018 work plan reporting template-annex

Page 7: KENYA COORDINATING MECHANISM CONSTITUENCY … · 2019. 6. 25. · Procurement and supply chain processes and systems in ensuring availability of ... (2017) suspended due to lack of

Page | 7

8.1 Highlights of sessions covered during the meeting

Day Two

Ms. Pamela Kibunja started the session by conducting a recap session and well as lead

participants on the expectations and program for Day 2 of the program.

Ms. Faith Ndungu, lead members through the OIG report by sharing key highlighted good

practices, areas of risks and concerns.

Background

• The Global Fund OIG Team conducted audit in June, 2018

• 21 health facilities, ten bed net distribution points, five KEMSA warehouses, five key

population groups in ten counties and KCM Secretariat visited during the Audit Period.

Specifically the audit assessed the efficiency and effectiveness of the:

1. Design and implementation of the programs to deliver quality services to intended

beneficiaries.

2. Procurement and supply chain processes and systems in ensuring availability of

quality assured medicines and health products to patients.

3. Grant implementation arrangements in the context of devolution including

governance, oversight and coordination to ensure sustainability.

4. Adequacy and effectiveness of frameworks in place to measure grant

performance.

Key Achievements and Good Practices

• Significant progress made in the fight against the three diseases:

• Increased government financial commitment to the three diseases:

• Functional in-country procurement and supply chain systems and processes, with

KEMSA, able to procure quality assured medicines at cheaper rates than

international reference prices.

Page 8: KENYA COORDINATING MECHANISM CONSTITUENCY … · 2019. 6. 25. · Procurement and supply chain processes and systems in ensuring availability of ... (2017) suspended due to lack of

Page | 8

Key issues and risks

Improvement required in quality of services: A number of quality of service issues to be

addressed

case notification targets for TB not met for the last three consecutive years.

TB treatment coverage remains low (45%).

Challenges in programming and implementation of interventions for key populations:

• Outdated bio-behavioural data informing current KP programs.

• New national survey (2017) suspended due to lack of consensus on use of

biometrics.

• The “in and out of school” AGYW behavioral interventions for 10-17 year olds,

piloted in Turkana, have not been effectively implemented.

- Delayed engagement of service providers by PR since January 2018, with no

commencement of AGYW interventions

Members participated acknowledged that the report as a true reflection of what was happening.

Key suggestions were given on ways of mitigating the risks and challenges including:

There is need for review of the TB targets especially on case notifications

There is need for improved TB diagnosis in order to identify more people and link them

to treatment

There is need to embrace new strategy in TB programs by embracing innovative ways

The need to invest more in community support systems especially the family when it

comes to the TB clients

Page 9: KENYA COORDINATING MECHANISM CONSTITUENCY … · 2019. 6. 25. · Procurement and supply chain processes and systems in ensuring availability of ... (2017) suspended due to lack of

Page | 9

Continuous medical education (CME), refresher trainings and On job trainings were

identified as ways of mitigating the capacity gaps in healthcare workers performing HIV

testing and Counselling

WOFAK and EMAC gave an update on the Global Fund implementation from SR point of

view. The presenters highlighted the programs they were performing as well as successes

and challenges faced.

Success in the implementation

Established community advisory board that is a crucial link with the community

Engaged National Police Service for security during the activities at no cost

Trained beneficiaries on self-reliance through entrepreneurial skills such as poultry

farming. The banks approached are willing to provide loans to the beneficiaries at low

interest rates.

Mobile wellness van clinic

Challenges

Constrained resources

Vast areas of coverage

Lateness in disbursement of funds

Poorly motivated CHVs sometimes they don’t get the money

Ms. Margaret Ndubi National Treasury (PR1) In her presentation she stated that 80% of the

new grant funds were allocated to procurement of commodities, an update of the activities which

were to be held in the new grant were presented. This lead to plenary session where participants

raised a number of questions including:

Why TB funding targeted commodities while the biggest gap was in finding the missing

TB cases: Response: TB case finding was funded through the catalytic funding

Page 10: KENYA COORDINATING MECHANISM CONSTITUENCY … · 2019. 6. 25. · Procurement and supply chain processes and systems in ensuring availability of ... (2017) suspended due to lack of

Page | 10

Why was there a general reduction of funding and no fund allocation towards nutritional

commodities

Lube stock outs

The National Treasury clarifications

The proposal from Kenya is spearheaded by KCM with an input from other stakeholders

and experts such as WHO, in this regard the fund allocation is not done by National

treasury. It is important for members to engage in the proposal writing process for key

areas for focus to be raised there eg TB funds allocation,

The research about the side effects of TLD is ongoing in Botswana results expected soon

In regards to late start of implementation, the TNT has an acceleration plan to ensure that

the program is on track

Mr.Ishmael Maina Kenya Redcross (PR2 implementing the HIV grant). An highlight of the

Sub Receiptient selection was given as well as the achievements in the grant implementation.

The PR also gave feedback on the OIG report and areas for KRCS which included the adolescent

girls and Young women Turkana Pilot project

Page 11: KENYA COORDINATING MECHANISM CONSTITUENCY … · 2019. 6. 25. · Procurement and supply chain processes and systems in ensuring availability of ... (2017) suspended due to lack of

Page | 11

Program status updates

Implementation started with 25 counties and has continued to grow. Now stands at 33

counties remainder 4 counties;

o All contracted SRs have started implementation of the grant activities

o Counties were involved in implementation sites mapping, prioritization and

selection

o The county needs are more than the GF grant can support hence need for stronger

partnerships and leverage with the county and other donors.

Generally, there were noted delays in grant implementation and each SR developed an

acceleration plan that was shared with KCM for discussion and approval

PLHIV networks, Youth Organizations and 5 additional SRs are in the process of

contracting to enable them start implementation. This is started in October 2018 to enable

the county engagement and identification of HF and CHVs be done before end of

December 2018.

OIG Mamangement Action status

KRCS has signed an MOU with National Quality Control Laboratory in 2018 where as

part of the tendering process potential suppliers had to submit their needles & syringe

samples to them for evaluation and testing. Also upon award and delivery of the

commodities analysis & testing was done by NQCL and certificate of analysis showing

compliance issued upon which the commodities were then accepted by KRCS and

distributed to the beneficiaries.

AGY Turkana pilot project

New concept note developed and shared which:

Review of the beneficiaries – done for all

Biometric registration done for 4981 girls

2,411 were successfully reached with cash and dignity kits.

Vulnerability assessment done for an additional 5,447 girls

EBIs like SHUGA My Health My Choice, Healthy choices for a better future, sister to

sister k, were also offered.

The cash transfer conditioning is based on HTS and STI screening and treatment as part

of the health service provision at enrolment and every subsequent year. So far 93 percent

of the adolescent girls and young women had accessed STI screening, while 98 percent

received HIV Testing Services (HTS).

AGYW receive cash together with Dignity Kit (bathing towel (1), washing soaps (3,

hand towel (1), comb(1), toothbrush (1), toothpaste (1),slippers(1), bathing soaps (3),

Vaseline jelly(1), panties (2), sanitary towels (8)).

Page 12: KENYA COORDINATING MECHANISM CONSTITUENCY … · 2019. 6. 25. · Procurement and supply chain processes and systems in ensuring availability of ... (2017) suspended due to lack of

Page | 12

Each AGYW receives KES. 2000 per month: payment is done once every 2 months: last

done 1-3 March, 2019

AGYW must be present in person for biometric validation: those below 18 years are

accompanied by their caregivers/parents

Out of 3502 girls approved 2975 (85%) received cash and dignity kits

Concerns

Participants were worried in the lack of TWGs are supported at County level/ at national

level. County TWGs to also be supported.

Response

The PR informed members that they support National TWGs and the County

commodities TWG.

Mr. Edward AMREF Health PR2 who are implementing TB and Malaria grant. The

presentation focused on the new SR selection, new grant plans and focus areas were handled.

Updates

• Orientation of 11 SRs on grant making processes and Global Fund procedures

Page 13: KENYA COORDINATING MECHANISM CONSTITUENCY … · 2019. 6. 25. · Procurement and supply chain processes and systems in ensuring availability of ... (2017) suspended due to lack of

Page | 13

• Training of 1,470 CHEWS on CCMM

• Training of 7,350 CHVs on CCMM

• Established and support 735 CUs

• Trained 48 county and 243 sub county ToTs on school health program

• Trained 2,953 teachers under the school health program

• Trained 22,636 school pupils who reached 113,180 households with malaria

prevention and control messages

• CHVs have diagnosed and treated 496,752 uncomplicated malaria cases at

household level

• 3 more Counties; Busia (53 CUs), Kisumu (71 Cus) and Vihiga (69 CUs) have taken over

payment of stipend to CHVs

• All GF supported CUs are now reporting monthly on DHIS2 facilitated by the Ksh1000

worth of data bundles given to SCHRIOs monthly

Page 14: KENYA COORDINATING MECHANISM CONSTITUENCY … · 2019. 6. 25. · Procurement and supply chain processes and systems in ensuring availability of ... (2017) suspended due to lack of

Page | 14

Ms. Ann Ithibu AIDSPan Global Fund Accountability. The facilitator introduced AIDSPan

by stating that it is an Independent observer of the Global Fund which was founded in 2002 and

headquartered in Kenya,. The organisation offers information, targeted critical analyses,

sharing best practices/lessons learned and independent commentary.

• The NGO constituency has a role to play in the implementation of Global Fund in

kenya. Co-financing is an important requirement of Global Fund and Kenya has

adhered to this requirement. Below is Kenya’s performace on Co-financing

• Co-financing commitment for the 2018-2020 grant is $ 86 million

– A 10% increase from 2015-2017

– Mostly dedicated to health commodities

• Kenya met the co-financing requirements for 2015-2017 (100%) with a 78%

absorption rate.

– Spent US$ 84 million on the three programs

Page 15: KENYA COORDINATING MECHANISM CONSTITUENCY … · 2019. 6. 25. · Procurement and supply chain processes and systems in ensuring availability of ... (2017) suspended due to lack of

Page | 15

• Participants were taken through the importance of tracking funds absorption because

Global Fund is a performance based fund. The Global Fund requires grant recipients to

report results on a regular basis as part of the disbursement schedule through the

dashboard. Global Fund has a five-tier rating system: A1, A2, B1, B2 and C (description

of rating in the next slide).The rating influences disbursement decisions and future

funding decisions by the Global Fund.

• There after participants were given strategies of monitoring Global Fund grants as listed

below:

- Accurate and timely information. Potential sources (Global Fund website: strategies,

policies, grant performance reports, funding requests, OIG reports etc)

- Understand the GF strategies, policies and processes

- Pre-empt the implication of GF policies

Page 16: KENYA COORDINATING MECHANISM CONSTITUENCY … · 2019. 6. 25. · Procurement and supply chain processes and systems in ensuring availability of ... (2017) suspended due to lack of

Page | 16

- Understand and leverage the existing accountability framework (see diagram below)

- Push for increased transparency (Key documents to be published: budgets and

expenditures, proposed reprogramming requests)

- Strong and strategic partnerships

-

9.1 Constituency Work plan 2018/2019-as per 2018/2019 work plan template –annex

The workplan was developed by members by first reviewing the 2018 planned activities. The

members guided by previous years work plan made some additions. From the discussion it was

clear that the need for more feedback and engagement was necessary. This was proposed to be

done through constant communication and invitations to different fora.

The workplan 2018, will be reviewed in 2019 by the set means of verifications as follows:

Minutes

Meeting reports

Page 17: KENYA COORDINATING MECHANISM CONSTITUENCY … · 2019. 6. 25. · Procurement and supply chain processes and systems in ensuring availability of ... (2017) suspended due to lack of

Page | 17

Presence of list serve

List of participants

Meeting photos

10.1 Conclusion and recommendations

The meeting ended with remarks from the two KCM members, Faith Mwende and Pamela

Kibunja. They each thanked everyone for coming for the workshop.

It was recommended on KCM member and alternative working with the NGOs in getting more

forums for engagement as well as looking at ways of constant communication before the annual

consultative and feedback forum.

It was recommended that KCM needed to engage NGOs from across the country for increased

feedback, in the same regard it was proposed for more frequent feedback and consultative

meetings .

A small team of members was selected to work with the NGO constituency representative and

alternate in finalizing on the workplan and sharing the same to members for endorsement within

a week after the meeting:

The team members are:

Daniel Ndungire

Peter Kamau

Francis Apina

Diana Ondato

Page 18: KENYA COORDINATING MECHANISM CONSTITUENCY … · 2019. 6. 25. · Procurement and supply chain processes and systems in ensuring availability of ... (2017) suspended due to lack of

Page | 18

11.1 Annexes ( Program, work plan reports, Participants list and Photos)

KENYA COORDINATING MECHANISM

Constituency Workplan Report 2019/2020

S.No Planned Activity Achievements/Deliverable

s

Means of

Verification

Challenges

Noted

Suggestions for

Improvement/Remark

s

1

UPDATING NGO

DATA BASE&

NETWORKS

WORKING IN

KENYA WITH

INTEREST OR

WORKING IN HIV,

This activity was not

concluded .

Email list / Email

content

informing

members on

upcoming

moments &

Global Fund

Time and

resources to

finalise the

database

KCM members will

work in collaboration

with KANCO to

develop the data base

Page 19: KENYA COORDINATING MECHANISM CONSTITUENCY … · 2019. 6. 25. · Procurement and supply chain processes and systems in ensuring availability of ... (2017) suspended due to lack of

Page | 19

TB ANDN

MALARIA

Opportunities

ADVOCACY AT

KCM MEETINGS

ON THE

INVOLVEMENT

OF COMMUNITY

BASED

ORGANIZATIONS

IN ACCESSING

GLOBAL FUND

Review was done on the

networks application by

advocating for a criteria

which was CBOs friendy

Meeting minutes

DEVELOPMENT

OF

COMMUNICATIO

N PLAN (Including

a mailing list serve)

This activity was not

done

A email list serve

with constant

communication

by KCM NGO

Member and

alternative

A email list serve will

be created after the data

base is finalised

QUARTERLY

FEEDBACK

FORUMS

Done through the

HENNET forums

(national and Nairobi

Chapter) and also at the

Meeting reports,

List of

participants,

Minutes

Page 20: KENYA COORDINATING MECHANISM CONSTITUENCY … · 2019. 6. 25. · Procurement and supply chain processes and systems in ensuring availability of ... (2017) suspended due to lack of

Page | 20

annual CSO forum held

in Dec 2018

Updates/Progress on Previous Recommendations

Workplan templates (landscape orientation) to be annexed in the Narrative Report

Proposed Organisation Position Name Contacts PA

X

Email Address

1. PAPWC Chair Pamela

Kibunja

0722802668 1 [email protected]

2. AHF KENYA Advocacy

Manager

Faith

Ndungu

0728246766 1 [email protected]

3. WOFAK Programs Samantha

Ariri

0722725967 1 [email protected]

4. KENEPOTE Member Angela 0720793761 1 [email protected]

Page 21: KENYA COORDINATING MECHANISM CONSTITUENCY … · 2019. 6. 25. · Procurement and supply chain processes and systems in ensuring availability of ... (2017) suspended due to lack of

Page | 21

Maitima

5. KANCO Deputy

Director

Peter

Kamau

1 [email protected] [email protected]

6. STOP TB

PARTNERSHIP

Daniel

Ndugire

0727008232 1 [email protected]

7. BARAKA UNITED Chair Joseph 0721703311 1 [email protected]

8. YOUTH VENTURES

INITIATIVES (YOVI)

CEO Jane

Munene

0722

847835

1 [email protected]

/ [email protected]

9. AVAC Fellow Consolata

Opiyo

0718651230 1 [email protected]

1

0.

EMAC Programs Nelson Sila

1

1.

SRHR Alliance Program

Manager

Mwikali

Kivuvani

0710630635 1 [email protected]

1

2.

ITPC EA Board

Chair

Francis

Apina

0703411077 1 [email protected]

1

3.

LEAN ON ME Cordinator Diana

Ondato

1 [email protected]

1

4.

Love and Hope Programs Minne

Muthoni

1 [email protected]

1 COPH ED CEO Gabriel 0729174477 1 [email protected]

Page 22: KENYA COORDINATING MECHANISM CONSTITUENCY … · 2019. 6. 25. · Procurement and supply chain processes and systems in ensuring availability of ... (2017) suspended due to lack of

Page | 22

5.

1

6.

KIJIJI CHA UPENDO Programs Moses

Omondi

0726296130 1 [email protected]

1

7.

GAPLINK Programs Dickson

Njogu

[email protected]

1

8.

YAPBECK Programs Keji

Stephen

0728013808 1 Keji.malika @gmail.com;

[email protected]

1

9.

AIDSPAN Programs Ann Ithibu 0726995872 1 [email protected]

2

0

KOSO Director Ruth

Nasiyo

0722890769 1 [email protected]