Key capex projectsat the LOTOS Group
G R U P A L O T O S S . A .
Marcin PiankowskiChief Investment Officer
Piotr StatkiewiczCEO of LOTOS Exploration&Production Norge AS
Mateusz SiepielskiPresident of the Management Board of LOTOS Upstream
Grzegorz StrzelczykPresident of the Management Board of LOTOS Petrobaltic
DIGITAL
2
REFINING & MARKETING● Hydrocracked Base Oils
● Hydrogen Recovery Unit
● Intermodal transport services
● Construction of CCGT unit
● Modernisation of terminal in Piotrków Trybunalski
● Construction of fourth railway loading facility
● LOTOS Green H2
● Marine cargo handling terminal on Martwa Wisła river
● Partial shutdown programme● Grupa LOTOS S.A.’s financial interest in the Polimery
Police project
CAPEX PROJECTS
GRUPA LOTOS S.A.
3
HYDROCRACKED BASE OILS – HBOPlanning phase
Key capex projects at the LOTOS Group
REFINING & MARKETING
4
Start
DG (Decision Gate) 0
DG0 (Decision Gate 0)DG1
Process to select contractor for project execution
DG2
Obtaining the environmental decision for the HBO project
DG3
Development of structure and arrangement of financing for the project
Construction permit documentation
Delivery of long-lead equipment
Startup of IDW IHF
End of execution
Initiation Planning Execution
1378Forecast total expenditure206Forecast expenditure in 2021
HYDROCRACKED BASE OILS – HBOPlanning phase
Key capex projects at the LOTOS Group
Key activities under the project
Project timeline
● Work is under way to arrange financing for the project. The possibility of financing thefirst stage of the project has been confirmed (LNTP – Limited Notice to Proceed).
● It is expected that it will be possible to fully proceed with the project and that theEngineering Procurement Construction – Lump Sum Turnkey contract will be signed inthe third quarter of 2021.
Capex plan for 2021 [PLNm] Capex plan for the entire project execution time [PLNm]
Objectives of the project● To improve the economics of crude oil processing by generating higher margins as
a result of production and sale of new high-margin products (Group 2 and Group 3base oils).
● To increase Grupa LOTOS’ overall competitiveness in production and sale of base oilsand optimise the margin throughout the value chain.
REFINING & MARKETING
5
HYDROGEN RECOVERY UNIT (HRU)Closing phase
Key capex projects at the LOTOS Group
REFINING & MARKETING
6
3Forecast expenditure in 2021 176Forecast total expenditure
HYDROGEN RECOVERY UNIT (HRU)Closing phase
Key capex projects at the LOTOS Group
REFINING & MARKETING
● Performance test has been completed and the unit has been placed in service.● Repairs of minor defects are continued in accordance with the availability of the
production unit.
To improve the efficiency of crude oil processing and taking the opportunity to process allproduct streams (70 thousand tonnes of LPG, 43 thousand tonnes of naphtha, 39 thousandtonnes of light gasoline, and almost 9 thousand tonnes of hydrogen per year).
Start DG (Decision Gate) 0 DG2
Launch of HRU construction Execution of Annex 2 to the contract with
AMCS Corp.
HRU construction resumed
Completion of installation work on HRU (MC)
Ready for start up
Commissioning
Initiation Planning Execution
Key activities under the project
Project timeline
Objectives of the project
Capex plan for 2021 [PLNm] Capex plan for the entire project execution time [PLNm]
7 Key capex projects at the LOTOS Group
REFINING & MARKETING
PURCHASE OF MODERN INTERMODAL ROLLING STOCK BY LOTOS KOLEJ Execution phase
8
Start
DG (Decision Gate) 0
DG1
DG2
Start of Sggrss rail car delivery (216 pcs)
DG3
Start of Sgmmnss rail car delivery (36 pcs)
End of Sgmmnss rail car delivery (36 pcs)
Delivery of one single-system locomotive
Delivery of one multi-system locomotive
End of Sggrss rail car delivery (216 pcs)
Start of Sggrss rail car delivery (72 pcs)
End of Sggrss rail car delivery (72 pcs)
The end
Initiation Planning Execution
Key capex projects at the LOTOS Group
REFINING & MARKETING
PURCHASE OF MODERN INTERMODAL ROLLING STOCK BY LOTOS KOLEJ Execution phase
Key activities under the project
Project timeline
Objectives of the project
● Annexes have been signed to the flat car delivery contracts – accelerated delivery schedule
● Acceptance test has been conducted and the seventh batch of Sggrss cars has been placed in service.
179Forecast total expenditure78Forecast expenditure in 2021
● The project will enable achieving the strategic objectives for intermodal transport of 0.8to 0.9 billion tkm in 2022.
● The project’s objective will be achieved by providing transport services based onacquired 2 engines and 324 flat cars.
Capex plan for 2021 [PLNm] Capex plan for the entire project execution time [PLNm]
9
CONSTRUCTION OF CCGT UNIT Planning phase
Key capex projects at the LOTOS Group
REFINING & MARKETING
10
Start
DG0'
DG0
Technical and economic analysis
DG1
Preparation of terms of reference
Obtaining environmental decisions and building permits
Completion of EPC & LTSA tenderDG2
DG3 (Final Investment Decision)
Signing the contract with General Contractor
Unit construction start
CCGT tests and start-ups
End of project execution
Initiation Planning Execution
2.5
Key capex projects at the LOTOS Group
REFINING & MARKETING
Key activities under the project
Project timeline
Capex plan for 2021 [PLNm]
Objectives of the project
● Following initial review, the CCGT project qualified for the National ReconstructionPlan. This creates a chance of winning grants or a preferential loan for 25-50% of theproject’s value.
● A scenario analysis, as part of which key project parameters (capacity, location,LOTOS’ equity interest in the ORLEN/Energa joint venture, etc.) will be approved, iscurrently underway.
0,6Forecast expenditure in 2021
The project budget will be defined in detail with the project partners during the planning phase before obtaining FID
● To reduce energy costs – internal electricity demand will be fully satisfied.● To make efficient use of assets – use of heat for heating purposes and integration of the
CHP plant with the refinery.
Capex plan for the entire project execution time [PLNm]
CONSTRUCTION OF CCGT UNIT Planning phase
11
MODERNISATION OF FUEL TERMINAL IN PIOTRKÓW TRYBUNALSKI Execution phase
Key capex projects at the LOTOS Group
REFINING & MARKETING
12
Start
DG0 DG2DG3
Signing of task financing and execution contracts
Submission of Project Information Sheet (PIS)
Submission of environmental impact report
Obtaining final decision on environmental impact of the project
Construction site handover with a handover report
Submission of application for building permit
Obtaining final building permit
Start of commissioning, supply of fuel to the construction site
Use permit, final acceptance
DG4
The end
Initiation Planning Execution
Key capex projects at the LOTOS Group
Key activities under the project
Project timeline
Capex plan for 2021 [PLNm] Capex plan for the entire project execution time [PLNm]
Objectives of the project
REFINING & MARKETING
● In April 2021, the Regional Director of Environmental Protection in Łódź issued a decision setting out the terms and conditions of project execution .
● Upon receipt of the environmental decision, an application for consent to tree and shrub removal is to be filed.
● Opinion on the technical working documentation is yet to be issued.
94Forecast total expenditure11Forecast expenditure in 2021
● The project’s purpose is to upgrade and expand the existing infrastructure of the Fuel Terminal in Piotrków Trybunalski, with the main objective to expand the range of fuels stored and handled at the terminal and to increase storage and handling capacities.
● Its strategic objective is to successfully compete on the fuel storage and distribution markets.
MODERNISATION OF FUEL TERMINAL IN PIOTRKÓW TRYBUNALSKI Execution phase
13
CONSTRUCTION OF THE FOURTH RAILWAY LOADING FACILITYExecution phase
Key capex projects at the LOTOS Group
REFINING & MARKETING
14
Project initiation
Contractor selectionConcept
DG0 IC resolution
Management Board resolution execution phase
DG2
Management Board resolution contract execution
Signing of the contract with Scherzer
Obtaining the building permit
Ready for start up
IC resolution – change of date
Commissioning of the railway loading facility
End of execution phase
Key capex projects at the LOTOS Group
Key activities under the project
Project timeline
Capex plan for 2021 [PLNm] Capex plan for the entire project execution time [PLNm]
Objectives of the project
REFINING & MARKETING
● The integrated environmental decision for the project was obtained in the first week of May.
● The loading facility has been placed in service, minor ancillary work is underway.
81Forecast total expenditure12Forecast expenditure in 2021
● To increase railcar loading capacity (mainly diesel oil and gasoline).● To increase flexibility of domestic sales.
ExecutionPlanningInitiation
CONSTRUCTION OF THE FOURTH RAILWAY LOADING FACILITYExecution phase
15
LOTOS Green H2 ProgrammePlanning phase
Key capex projects at the LOTOS Group
REFINING & MARKETING
16
Start
Approval of initiative sheet (DG0)Submission of application with Innovation
Fund (phase 1)
Submission of application with Innovation Fund (phase 2)
Approval of scenario analysis (DG1)
Approval of the programme plan (DG2)
Proceeding to execution phase (DG3)
Commissioning of the unit
Project settlement
The end
Initiation Planning Execution
Key capex projects at the LOTOS Group
Key activities under the project
Project timeline
Capex plan for 2021 [PLNm] Capex plan for the entire project execution time [PLNm]
Objectives of the project
REFINING & MARKETING
● The key activity in the near future is to prepare the best application documentationfor the second round of calls in the Innovation Fund competition (by June 23rd 2021).
● Talks with electrolyzer vendors and potential strategic partners for the project werecontinued.
● To begin hydrogen production at the first large-scale green hydrogen generation plant (by water electrolysis) and integrate the plant into the national electricity market
● To reach a dominant position on the future market of green hydrogen.
The project budget will be defined in detail during the planning phase before obtaining FID2,5Forecast expenditure in 2021
LOTOS Green H2 ProgrammePlanning phase
17 Key capex projects at the LOTOS Group
REFINING & MARKETING
MARINE CARGO HANDLING TERMINAL ON THE MARTWA WISŁA RIVERPlanning phase
18
Start
DG 0
Obtaining design office’s analysis concerning the validity of building permit designs
and extent of required changes
Obtaining Regional Directorate for Environmental Protection’s decision
regarding habitat destruction
Scenario analysis development
DG 1
CSC’s recommendation of EPC turnkey
contractor
Preparation of project plan
DG 2
Preparing the project financing analysis
DG3
Conclusion of EPC contract
DG4 The end
Initiation Planning Execution
Key capex projects at the LOTOS Group
Key activities under the project
Project timeline
Capex plan for 2021 [PLNm] Capex plan for the entire project execution time [PLNm]
Objectives of the project
REFINING & MARKETING
● Navigation analysis must be carried out as this will help confirm the maximum size ofvessels to be served in the future by the terminal (draught, width, length).
● The Contractor Selection Committee (CSC) is working to select the general contractor(EPC contract).
1Prognozowane nakłady w 2021 roku The project budget will be defined in detail during the planning phase before obtaining FID
● To build a transshipment wharf for seagoing vessels of up to 5,000 DWTand necessary infrastructure linking the terminal with the refinery in Gdańsk.
● The strategic objective is to improve the security of goods dispatching from the refinery by providing an alternative way of shipment.
MARINE CARGO HANDLING TERMINAL ON THE MARTWA WISŁA RIVERPlanning phase
19 Key capex projects at the LOTOS Group
REFINING & MARKETING
ADAPTATION OF THE GDAŃSK REFINERY TO PARTIAL MAINTENANCE SHUTDOWNS
20 Key capex projects at the LOTOS Group
Key activities under the project
Capex plan for 2021 [PLNm] Capex plan over the entire project execution time [PLNm]
REFINING & MARKETING
12Forecast expenditure in 2021 The project budget will be defined in detail during the planning phase before obtaining FID
● P209 Upgrade of flare system and discharge point network − after obtaining theConceptual Design, the deadline for submission of a bid to prepare documentation forwelded connections which are contingent on the 2022 maintenance shutdown timing wasagreed with the contractor. Site visits with the contractor have been made since May 11th.
● P142 Plankton – a strategy has been developed to prepare output data for a request forproposal concerning a conceptual design (study).
● P224 Upgrade of flue gas discharge system – the contractor has delivered a conceptualdesign for the upgrade and a technical design of stacks. The Contractor Selection Process(CSP) for integration of the stacks with the existing infrastructure (designand execution) has been launched.
● P214 Upgrade of CHP Plant and PZE facilities – process to select a contractor to prepare aworking design is underway. At the request of the bidders, the deadline for submission oftenders has been extended until May 17th 2021.
● The environmental decision for all the projects is planned to be obtained in October 2021.
Projects implemented as part of the programme
Name Project phase
Project P142 – Plankton Initiation
Project P209 – Upgrade of flare system and discharge point network Planning
Project P214 – Upgrade of CHP plant and PZE facilities Planning
Project P224 – Upgrade of flue gas discharge system Execution
ADAPTATION OF THE GDAŃSK REFINERY TO PARTIAL MAINTENANCE SHUTDOWNS
21
Start
Determination of project scope
Determination of work to be performed by contractors
Definition of contracting strategy
DG0 Planning phase DG2 Execution Phase
RFSU
DG4 Project completion
The end
Initiation Planning Execution
Key capex projects at the LOTOS Group
REFINING & MARKETING
ADAPTATION OF THE GDAŃSK REFINERY TO PARTIAL MAINTENANCE SHUTDOWNSTimeline for Project P142 – Plankton
Timeline for Project P209 – Upgrade of flare system and discharge point network
Start
Submission sheet Planning Phase Start
Conceptual design
Determination of welded connections scope
Welded connections documentation
Performance of welded connections
Front-end engineering design
Execution Phase start Execution Phase end
The end
Initiation Planning Execution
22
Submission sheet
Initiation Sheet Planning Phase Start
Approval of concept documentation
Process to select contractor to prepare multi-disciplinary working design
Selection of contractor to prepare multi-disciplinary working design
Design of repair welded connections completed
Execution Phase start
Purchases of materials for 2022 maintenance shutdown
Completed welded connections
End of execution phase
End of Completion Phase
The end
Initiation Planning Execution
Start
Planning Phase Start
Process to select contractor for stacks start
Start of Execution Phase
Stack contract
Process to select contractor for integration start
Conceptual design and working design stacks
Process to select contractor for integration end
Welded connections documentation
Building permit
Foundations ready
Installation of stacks
Installation of integration
Flue gas monitoring equipment installation
End of Execution Phase
Defect removal, final documentation
End of Completion Phase
The end
Initiation Planning Execution
Key capex projects at the LOTOS Group
REFINING & MARKETING
ADAPTATION OF THE GDAŃSK REFINERY TO PARTIAL MAINTENANCE SHUTDOWNSTimeline for Project P214 – Upgrade of CHP plant and PZE facilities
Timeline for Project P224 – Upgrade of Flue Gas Discharge System
23
GRUPA LOTOS S.A.’S FINANCIAL INTEREST IN THE POLIMERY POLICE PROJECT Execution phase
Key projects at the LOTOS Group
EQUITY
24
507Forecast total expenditure2,6Forecast expenditure in 2021
GRUPA LOTOS S.A.’S FINANCIAL INTEREST IN THE POLIMERY POLICE PROJECT Execution phase
Key projects at the LOTOS Group
Key activities under the project
Project timeline
● Grupa LOTOS has contributed equity and granted a loan in the total amount of PLN500m for the Polimery Police project;
● A contract has been concluded between GL S.A. and Fluor S.A. (to act, on asubcontractor basis, as a Joint Sponsor Monitor under the Polimery Police Project) andFluor S.A. has been engaged to monitor the project on behalf of the Company.
Capex plan for 2021 [PLNm] Capex plan for the entire project execution time [PLNm]
Objectives of the project● Business diversification towards petrochemical products;● To obtain financial benefits from the Polimery Police project.
EQUITY
execution ofLOI
Report of Grupa LOTOS S.A.’s Market Adviser
execution ofTerm Sheet
planning phase (DG0)
execution of Investment agreements
construction site handover
consent of Grupa LOTOS General Meeting to acquire
GAPoly shares
Plot Plan
financingof GL S.A.’s interest
execution phase (DG3)
completionof installations
Integrity test
Initiation Planning Execution
DIGITAL
25
EXPLORATION & PRODUCTION● YME – new development
● Development of the NOAKA area
● Development of fields B4/B6
● Development of field B8
● POLISH OFFSHORE WIND SERVICE
CAPEX PROJECTS
GRUPA LOTOS S.A.
26 Key capex projects at the LOTOS Group
EXPLORATION & PRODUCTION
YME NEW DEVELOPMENT PROJECTEXECUTION PHASE
27
Start
DG1
DG2
DG3
Caisson permanent support
Existing facility
End of shipyard work
Transportation of the rig to the field
Start of preparation of CR1 change application
Resolution of the company’s governing bodies for CR1
Connection – integration on the field (hook up)
Start of production (First Oil)
Initiation Planning Execution
Key capex projects at the LOTOS Group
YME NEW DEVELOPMENT PROJECTEXECUTION PHASE
Key activities under the project
Project timeline
Capex plan for 2021 [PLNm] Capex plan for the entire project execution time [PLNm]
Objectives of the project
EXPLORATION & PRODUCTION
● The MODPU left the shipyards in Egersund on December 22nd 2020 and is connected to the field’s tree system.
● The connection and start-up of production systems and wells is in progress, with a pace of work due to favourable weather conditions.
● The YME project is at final stage of implementation. Production launch is scheduled for the fourth quarter of 2021.
● License partners’ decision to repurchase MODPU from Maersk Drilling platform.● Expenditure is projected to increase on account of COVID-19.
780Total approved capex252Forecast expenditure in 2021
● To produce from new fields, including YME reserves, in accordance with the Grupa LOTOS Strategy for 2017−2022.
● To gradually replace production from depleting fields.● To diversify the revenue stream for the Exploration & Production segment of the LOTOS
Group.
28 Key capex projects at the LOTOS Group
EXPLORATION & PRODUCTION
NOAKA DEVELOPMENT PLANNING PHASE
29 Key capex projects at the LOTOS Group
Key activities under the project
Project timeline
Capex plan for 2021 [PLNm] Capex plan for the entire project execution time [PLNm]
Objectives of the project
EXPLORATION & PRODUCTION
PL442 PL873 PL026 NOAKA DEVELOPMENT PLANNING PHASE
● Work is under way on numerical mineral deposit models to make a best estimate oil and gas reserves.
● Work on field appraisal is performed relying on the experience of the project partners, including AkerBP. The technical documentation is being reviewed.
● Preparations for IPR (Independent Project Review), expected to take place on June 15th and 16th 2021, are underway.
103Forecast expenditure in 2021 The project budget will be defined in detail during the planning phase before obtaining FID
● To increase production and expand the portfolio of LEPN production assets on the Norwegian Continental Shelf.
● To achieve estimated production from NOAKA at 29 mboe and net production of up to approximately 16,000 boe/d in 2028.
Start
DG0'
DG0
Concept Select
DG1 FEED
DG2
DG3
NUI HUC
PDQ HUC
First Oil
DG4
End
Initiation Planning Execution
30 Key capex projects at the LOTOS Group
EXPLORATION & PRODUCTION
DEVELOPMENT OF GAS FIELDS B4 AND B6 PLANNING PHASE
31 Key capex projects at the LOTOS Group
Key activities under the project
Project timeline
Capex plan for 2021 [PLNm] Capex plan for the entire project execution time [PLNm]
Objectives of the project
EXPLORATION & PRODUCTION
DEVELOPMENT OF GAS FIELDS B4 AND B6 PLANNING PHASE
● The gas market and the market of materials and service providers is continually monitoredas part of the Project.
● The ownership status of the land on the gas pipeline route is being established.● The strategy to raise financing needs to be agreed.
10Forecast expenditure in 2021The project budget will be defined in detail during the planning phase before obtaining FID
To design, construct and commission the production, conversion and transmission facilities enabling production and sale of natural gas and light fractions from the B4 and B6 natural gas fields in the Baltic Sea.Project in figures:
o 4.8 bcm recoverable reserves o 400–500 mcm annual plateau production rate o +10–13% increase in domestic productiono 2022 possible investment decision
DG0'
DG0 DG1DG2
Development Plan
DG3FID
DG4First Gas
.
Initiation Planning Execution
32 Key capex projects at the LOTOS Group
EXPLORATION & PRODUCTION
DEVELOPMENT OF OIL FIELD B8 USING CONVERTED JACK_UP PETROBALTIC RIG AS A PRODUCTION HUB EXECUTION PHASE
33 Key capex projects at the LOTOS Group
Key activities under the project
Project timeline
Capex plan for 2021 [PLNm] Capex plan for the entire project execution time [PLNm]
Objectives of the project
EXPLORATION & PRODUCTION
DEVELOPMENT OF OIL FIELD B8 USING CONVERTED JACK_UP PETROBALTIC RIG AS A PRODUCTION HUB EXECUTION PHASE
● Work on reaching readiness for gas export has been completed.● Leak-tightness tests of the facilities were continued (preparation to start-up the gas
compression and export system), gas export to Energobaltic’s power plant has beenlaunch on a test basis.
● Hydrocarbons were produced from the Central Production Facility on the B8 field usingseven wells: B8-Z1 bis, B8-2, B8-3K, B8-4K bis, B8-5K, B8-6K, B8-7K. The average dailyoutput is approximately 3,500 barrels.
1043Forecast total expenditure15Prognozowane nakłady w 2021 roku
● To obtain stable and efficient production from the converted Petrobaltic rig. ● To achieve optimum production value, water injection into the field and ready for gas
transmission.
● The project ends once the central production facility is ready to extract and transmit gas.
34
EXPLORATION & PRODUCTION
INVESTMENT AND MAINTENANCE SERVICES UNDER THE WIND FARM CONSTRUCTION PROGRAMME
PHASE 1 PREPARATIONS
● Geotechnical surveys● Geophysical surveys● Hydrographic surveys
PHASE 3OPERATIONS
● Operations and Maintenance (O&M)● Maintenance, replacement and repair of
OWF components
POLISH OFFSHORE WIND SERVICE will offer a full range of services in each project phase
PHASE 4DECOMMISSIONING
● Dismantling of OWF components
● Upgrade/re-installation
Services planned to be provided in the future on the OWP marketServices currently provided
LOTOS Petrobaltic S.A. (LPB), which has been operating in the oil and gas production sector in the Baltic Sea for more than thirty years, is the company in Poland which has the best technical and operational resources and the potential to act as the operator and coordinator in the provision of maritime logistics services to OWF.
Source: Report entitled “Installation Fleet Operator. Potential of Polish Maritime Industry for the Needs of Offshore Wind Farms”, published in March 2021
12%
88%
Target revenue of the LOTOS Petrobaltic Group in Phase 1 and Phase 2 as a share of spending (PLN 140bn) on the OWP sector in Poland in 2025-2040
Przychody LPB na tle wydatków CAPEX
Pozostałe wydatki CAPEX
Source: In-house analysis, Controlling and Reporting Office, LOTOS Petrobaltic S.A.
PHASE 2CONSTRUCTION
● Laying of submarine cables● Installation of foundations● Installation of wind turbines ● Installation of transformer stations● Installation of other OWF components
„
Key capex projects at the LOTOS Group
35 Key capex projects at the LOTOS Group
EXPLORATION & PRODUCTION
INVESTMENT AND MAINTENANCE SERVICES UNDERTHE WIND FARM CONSTRUCTION PROGRAMME
Vessels to be secured as part of the project
OWP infrastructure maintenance and servicing vessels – CTV
Vessel for installation of foundations – WTFIV
ready in 2023
Vessel for turbine installation – WTIV
ready in 2024
Cable layer – CLV
ready in 2023
ready in 2025-2026 ready in 2025
OWPinfrastructure maintenance and maintenance vessels - SOV
DIGITAL
36
RETAIL● CODO 2020-2023 service station network development
programme
● Mała Holandia Motorway Service Area III property lease and construction of Motorway Service Area
stations
● Kierzno Południe Motorway Service Area III property lease and construction of Motorway Service Area
stations
● Kierzno Północ Motorway Service Area III property lease and construction of Motorway Service Area
stations
CAPEX PROJECTS
GRUPA LOTOS S.A.
37 Key capex projects at the LOTOS Group
RETAIL
CAPEX ON STATION NETWORK EXPANSION
Key activities under the projects
Capex plan for 2021 [PLNm] Capex plan for the entire project execution time [PLNm]
Objectives of the projects
● Adding two CODO service stations in 2021● Adding six CODO service stations in 2022● Adding seven CODO service stations in 2023● Construction of Mała Holandia Motorway Service Area with the work to be completed in 2021● Settlement of Kierzno Północ i Kierzno Południe Motorway Service Area projects.
● To increase the number of LOTOS service stations in line with the adoptedstrategy.
● To increase the economic efficiency of the service station network and boostthe return on capital employed.
● To strengthen the market position of the LOTOS service station network onPoland’s main transport routes (expressways and motorways).
190Forecast expenditure in 2021 Detailed capex specification for each project
DIGITAL
Thank you for your attention
38 GRUPA LOTOS S.A.