Kick off meetingKick off meeting

1Innovation Energie Développement

CAP REDEO

February 07

CAP REDEO

GIS TOOL FOR RURAL ELECTRIFICATION PLANNING

VIENTIANE APRIL 2007

Kick off workshopKick off workshop

2Innovation Energie Développement

CAP REDEO

February 07

Project supported by the European Commission

Project title : – Capacity and Institutional strengthening for – Rural Electrification and Development, – Decentralized Energy Options

Aims at :– Developing a rural electrification plan – for one

Province in each country• grid extension and renewable energy

– Develop a National level electrification and development database with GIS interface

– Training project counterparts to use the GEOSIM model

Kick off workshopKick off workshop

3Innovation Energie Développement

CAP REDEO

February 07

Project supported by the European Commission

• Supported by the European Commission COOPENER program, under Intelligent Energy Europe

• Co-funded by the French Ministry of Foreign Affairs

• Target to complete the project by December 2008, where the results will be presented at an international workshop

Kick off workshopKick off workshop

4Innovation Energie Développement

CAP REDEO

February 07

Subcontractors

Laos

E.U. partners IED(CO)

ETC(CB)

European Commission

Cambodia

SubcontractorsKy Chanthan

SubcontractorsYoy ThipasoneProf Sengprasong

ProjectCounterparts

Ministry of Industry,Mines and Energy(MIME)

Electricity duCambodge (EdC)

Electricity Authorityof Cambodia (EAC)

Ministry of Energyand Mines (MoEM)

Electricité du Laos(EDL)

Kick off workshopKick off workshop

5Innovation Energie Développement

CAP REDEO

February 07

AREA OF ACTIVITY : Small power systems, RE, Decentralized RE, Energy efficiency & DSM

SERVICE : Cover the whole range of the project cycle

Power sector23%

Rural El.23%

RE17%

Other14%

Energy Eff.23%

2. Innovation Energie Développement (IED)

Kick off workshopKick off workshop

6Innovation Energie Développement

CAP REDEO

February 07

Kick off workshopKick off workshop

7Innovation Energie Développement

CAP REDEO

February 07

Kick off workshopKick off workshop

8Innovation Energie Développement

CAP REDEO

February 07

Relevance for Laos and Cambodia

• Current rate of population access is under 30% in Cambodia

• Laos has the objective of 90% household access by 2020

• Grid extension is underway and all cannot be achieved through public sector investments

• Identify areas of relevance for the various options– grid extension– Renewable energy options (micro & mini hydro, biomass)– Diesel– Off grid (stand alone systems – PV and Pico hydro)– with maximum development impact

Kick off workshopKick off workshop

9Innovation Energie Développement

CAP REDEO

February 07

Map of Laos

Kick off workshopKick off workshop

10Innovation Energie Développement

CAP REDEO

February 07

Map of Laos

Kick off workshopKick off workshop

11Innovation Energie Développement

CAP REDEO

February 07

Main Activities, Outputs & Expected Outcomes

At the National level, establish a Multisector Stakeholder Group, Chaired by the Energy Ministries – Collect existing data to establish a multi sector data base with a GIS interface– Engage the group in a discussion on multisector coordination and planning criteria to increase the

development impact of rural electrification – How energy inputs fit the Millenium Development Goals for the two countries and Poverty Reduction

Strategies

Education

Local econmy

HealthSocial

welfare

Data base with GIS available in August 2007

Kick off workshopKick off workshop

12Innovation Energie Développement

CAP REDEO

February 07

Energy’s contribution to achieving the Milleneum Development Goals - MDGs

1. Extreme Poverty and Hunger: to halve by 2015 the world’s population living with less than one dollar per day

2. Universal primary education by 20153. Gender equality: equal access of boys and girls to

education4. Child mortality reduction by 2/3 by 20155. Maternal mortality reduction by ¾ by 20156. HIV / AIDS, Malaria and other major deseases7. Environmental sustainability : halve people who do

not have access to safe drinking water; stop environmental exploitation of natural resources

Kick off workshopKick off workshop

13Innovation Energie Développement

CAP REDEO

February 07

Kick off workshopKick off workshop

14Innovation Energie Développement

CAP REDEO

February 07

Provincial level implementation of GEOSIM (1)

• In one pilot Province in each country : Khamouane and Kampong Cham or Kampong Speu

• Approach– Identify Development Centers in the Provinces based on

multisector criteria to assess development potential– Load forecasting - scenarios– Assessment of various production options – grid and off grid

(hydro and biomass)– Development of scenarios which will highlight the potential

projects for implementation

• Formulate the planning objective:– Population or village coverage? Time horizon?– Least cost? Priority on renewables?

Kick off workshopKick off workshop

15Innovation Energie Développement

CAP REDEO

February 07

Provincial level implementation of GEOSIM(2)

• Establish a Provincial level working group by August 07, – including potential private operators and financial

intermediaries

• Data collection / surveys and analysis:– Socio economic and production potential– August to December 2007

• Run the various planning scenarios: January to August 2008

• April to September 2008 : work on the investment plans with local stakeholders

Kick off workshopKick off workshop

16Innovation Energie Développement

CAP REDEO

February 07

Training, Capacity Building and transfer

• Training sessions on planning, Data Base management and GIS, and the planning tool and approach

• Discussion Workshops : results and scenarios• Hands on and continuos training• Install Manifold GIS software : April to August

2007• The GEOSIM tool : January 2008 Objective for Project counterparts to run the tool by

September 2008 and capable of replicating to other Provinces

Kick off workshopKick off workshop

17Innovation Energie Développement

CAP REDEO

February 07

Communication and Milestones

• A project web site will be developed: http\\: www.Cap-Redeo.com

– Newsletter– Methodologies– Reports– Background documents

• Mid term meeting in April in Vientiane• Final regional workshop in Phnom Penh in

November / December 2008

Kick off workshopKick off workshop

18Innovation Energie Développement

CAP REDEO

February 07