Kick off meetingKick off meeting
1Innovation Energie Développement
CAP REDEO
February 07
CAP REDEO
GIS TOOL FOR RURAL ELECTRIFICATION PLANNING
VIENTIANE APRIL 2007
Kick off workshopKick off workshop
2Innovation Energie Développement
CAP REDEO
February 07
Project supported by the European Commission
Project title : – Capacity and Institutional strengthening for – Rural Electrification and Development, – Decentralized Energy Options
Aims at :– Developing a rural electrification plan – for one
Province in each country• grid extension and renewable energy
– Develop a National level electrification and development database with GIS interface
– Training project counterparts to use the GEOSIM model
Kick off workshopKick off workshop
3Innovation Energie Développement
CAP REDEO
February 07
Project supported by the European Commission
• Supported by the European Commission COOPENER program, under Intelligent Energy Europe
• Co-funded by the French Ministry of Foreign Affairs
• Target to complete the project by December 2008, where the results will be presented at an international workshop
Kick off workshopKick off workshop
4Innovation Energie Développement
CAP REDEO
February 07
Subcontractors
Laos
E.U. partners IED(CO)
ETC(CB)
European Commission
Cambodia
SubcontractorsKy Chanthan
SubcontractorsYoy ThipasoneProf Sengprasong
ProjectCounterparts
Ministry of Industry,Mines and Energy(MIME)
Electricity duCambodge (EdC)
Electricity Authorityof Cambodia (EAC)
Ministry of Energyand Mines (MoEM)
Electricité du Laos(EDL)
Kick off workshopKick off workshop
5Innovation Energie Développement
CAP REDEO
February 07
AREA OF ACTIVITY : Small power systems, RE, Decentralized RE, Energy efficiency & DSM
SERVICE : Cover the whole range of the project cycle
Power sector23%
Rural El.23%
RE17%
Other14%
Energy Eff.23%
2. Innovation Energie Développement (IED)
Kick off workshopKick off workshop
8Innovation Energie Développement
CAP REDEO
February 07
Relevance for Laos and Cambodia
• Current rate of population access is under 30% in Cambodia
• Laos has the objective of 90% household access by 2020
• Grid extension is underway and all cannot be achieved through public sector investments
• Identify areas of relevance for the various options– grid extension– Renewable energy options (micro & mini hydro, biomass)– Diesel– Off grid (stand alone systems – PV and Pico hydro)– with maximum development impact
Kick off workshopKick off workshop
9Innovation Energie Développement
CAP REDEO
February 07
Map of Laos
Kick off workshopKick off workshop
10Innovation Energie Développement
CAP REDEO
February 07
Map of Laos
Kick off workshopKick off workshop
11Innovation Energie Développement
CAP REDEO
February 07
Main Activities, Outputs & Expected Outcomes
At the National level, establish a Multisector Stakeholder Group, Chaired by the Energy Ministries – Collect existing data to establish a multi sector data base with a GIS interface– Engage the group in a discussion on multisector coordination and planning criteria to increase the
development impact of rural electrification – How energy inputs fit the Millenium Development Goals for the two countries and Poverty Reduction
Strategies
Education
Local econmy
HealthSocial
welfare
Data base with GIS available in August 2007
Kick off workshopKick off workshop
12Innovation Energie Développement
CAP REDEO
February 07
Energy’s contribution to achieving the Milleneum Development Goals - MDGs
1. Extreme Poverty and Hunger: to halve by 2015 the world’s population living with less than one dollar per day
2. Universal primary education by 20153. Gender equality: equal access of boys and girls to
education4. Child mortality reduction by 2/3 by 20155. Maternal mortality reduction by ¾ by 20156. HIV / AIDS, Malaria and other major deseases7. Environmental sustainability : halve people who do
not have access to safe drinking water; stop environmental exploitation of natural resources
Kick off workshopKick off workshop
14Innovation Energie Développement
CAP REDEO
February 07
Provincial level implementation of GEOSIM (1)
• In one pilot Province in each country : Khamouane and Kampong Cham or Kampong Speu
• Approach– Identify Development Centers in the Provinces based on
multisector criteria to assess development potential– Load forecasting - scenarios– Assessment of various production options – grid and off grid
(hydro and biomass)– Development of scenarios which will highlight the potential
projects for implementation
• Formulate the planning objective:– Population or village coverage? Time horizon?– Least cost? Priority on renewables?
Kick off workshopKick off workshop
15Innovation Energie Développement
CAP REDEO
February 07
Provincial level implementation of GEOSIM(2)
• Establish a Provincial level working group by August 07, – including potential private operators and financial
intermediaries
• Data collection / surveys and analysis:– Socio economic and production potential– August to December 2007
• Run the various planning scenarios: January to August 2008
• April to September 2008 : work on the investment plans with local stakeholders
Kick off workshopKick off workshop
16Innovation Energie Développement
CAP REDEO
February 07
Training, Capacity Building and transfer
• Training sessions on planning, Data Base management and GIS, and the planning tool and approach
• Discussion Workshops : results and scenarios• Hands on and continuos training• Install Manifold GIS software : April to August
2007• The GEOSIM tool : January 2008 Objective for Project counterparts to run the tool by
September 2008 and capable of replicating to other Provinces
Kick off workshopKick off workshop
17Innovation Energie Développement
CAP REDEO
February 07
Communication and Milestones
• A project web site will be developed: http\\: www.Cap-Redeo.com
– Newsletter– Methodologies– Reports– Background documents
• Mid term meeting in April in Vientiane• Final regional workshop in Phnom Penh in
November / December 2008