Upload
surendra-elayathamby
View
26
Download
5
Tags:
Embed Size (px)
Citation preview
SRI LANKA
THE PROJECT FOR REHABILITATION OF
23-May-13
THE GOVERNMENT OF DEMOCRATIC SOCIALIST REPUBLIC OF SRILANKA
MINISTRY OF WATER SUPPLY AND DRAINAGE
KDG GLOBAL ENGINEERING (PVT) LTD
KILLINOCHCHI WATER SUPPLY SCHEME
NATIONAL WATER SUPPLY AND DRAINAGE BOARD
DAIHO CORPORATION
JAPAN
AND
TENDER PRICE SCHEDULE
Tender Price Schedule
Grand Summary
Main Contractor: DAIHO Corportion
Sub Contractor: KDG Global Engineering
ITEM NO ITEM DESCRIPTION UNIT QTY AMOUNT
(RS) AMOUNT (JPY)
CONSTRUCTION WORK
CW(1) Water Intake and Water Treatment Plant L.Sum 1.00 148,991,256 112,023,497
CW(2) Central College Water Tower L.Sum 1.00 83,088,969 62,472,910
CW(3) Paranthan Water Tower L.Sum 1.00 51,950,334 39,060,405
CW(4) Transmission Pipe L.Sum 1.00 40,187,869 30,216,444
CW(5) Distribution Pipe along A9 Road L.Sum 1.00 150,183,976 112,920,285
CW(6) Distribution Pipe in Killinochchi Town L.Sum 1.00 56,802,215 42,708,432
CW(7) Distribution Pipe in Paranthan Area L.Sum 1.00 12,963,303 9,746,848
CW(8) Machinery and Electrical Work L.Sum 1.00 37,913,471 28,506,361
Sub Total 01 582,081,393 437,655,182
PROCUREMENT WORKS OF THE EQUIPMENT
PWE(a) House Connection Equipment L.Sum 1.00 8,422,800 6,332,932
PWE(b) Labouratory Instruments L.Sum 1.00 1,778,400 1,337,141
PWE(c) Operation and Maintenance Equipment L.Sum 1.00 322,400 242,406
Sub Total 02 10,523,600 7,912,479
Grand Total (Sun Total 01 + 02) 592,604,993 445,567,661
THE PROJECT FOR REHABILITATION OF KILLINOCHCHI WATER TREATMENT SCHEME
TENDER PRICE SCHEDULE
GRAND SUMMARY
1Yen=1.33 SL Rs
Cost and Management Consultant 2 Narayananan Associates
Tender Price Schedule
Summary
Main Contractor: DAIHO Corportion
Sub Contractor: KDG Global Engineering
1.33
ITEM NO ITEM DESCRIPTION UNIT QTY AMOUNT
(RS) AMOUNT (JPY)
CONSTRUCTION WORK
CW(1) Water Intake and Water Treatment Plant L.Sum 1.00 130,751,338 98,309,273
CW(2) Central College Water Tower L.Sum 1.00 72,916,990 54,824,805
CW(3) Paranthan Water Tower L.Sum 1.00 45,590,432 34,278,523
CW(4) Transmission Pipe L.Sum 1.00 35,267,960 26,517,264
CW(5) Distribution Pipe along A9 Road L.Sum 1.00 131,798,042 99,096,274
CW(6) Distribution Pipe in Killinochchi Town L.Sum 1.00 49,848,332 37,479,949
CW(7) Distribution Pipe in Paranthan Area L.Sum 1.00 11,376,300 8,553,612
CW(8) Machinery and Electrical Work L.Sum 1.00 33,272,000 25,016,534
Sub Total 01 510,821,394 384,076,234
PROCUREMENT WORKS OF THE EQUIPMENT
PWE(a) House Connection Equipment L.Sum 1.00 8,422,800 6,332,932
PWE(b) Labouratory Instruments L.Sum 1.00 1,778,400 1,337,141
PWE(c) Operation and Maintenance Equipment L.Sum 1.00 322,400 242,406
Sub Total 02 10,523,600 7,912,479
INDIRECT COST
IC(a) Common Temporary Work L.Sum 1.00 27,750,000 20,864,662
IC(b) Onsite Expences L.Sum 1.00 43,510,000 32,714,286
Sub Total 03 71,260,000 53,578,948
Grand Total (Sun Total 01 + 02 + 03) 592,604,994 445,567,661
THE PROJECT FOR REHABILITATION OF KILLINOCHCHI WATER TREATMENT SCHEME
TENDER PRICE SCHEDULE
SUMMARY
1Yen=1.33 SL Rs
Cost and Management Consultant 3 Narayananan Associates
Tender Price Schedule
CW(1)- Water Intake and Water Treatment Plant
Main Contractor: DAIHO Corportion
Sub Contractor: KDG Global Engineering
Item No Description Unit Qty Amount (Rs) Amount (JPY) Remarks
WATER INTAKE
WI 01 NEW INTAKE PIT L.Sum 1.00 4,443,120 3,340,692
WI 02 INTAKE SUMP L.Sum 1.00 1,210,040 909,802
WI 03 INTAKE PUMP HOUSE L.Sum 1.00 646,000 485,713
WI 04 DIRECT TEMPORARY WORK L.Sum 1.00 1,050,000 789,474
RAW WATER TRANSMISSION
RW 01 RAW WATER TRANSMISSION PIPE L.Sum 1.00 656,240 493,413
WATER TREATMENT PLANT
WTP 01 ROUGHING FILTER L.Sum 1.00 39,925,312 30,019,032
WTP 02 AERATOR / RECEIVING WELL L.Sum 1.00 1,320,080 992,541
WTP 03 SLOW SAND FILTER L.Sum 1.00 41,148,642 30,938,831
WTP 04 WASHED SAND STORAGE YARD L.Sum 1.00 4,591,652 3,452,371
WTP 05 STORAGE POND L.Sum 1.00 3,366,154 2,530,942
WTP 06 ADMINISTRATION BUILDING L.Sum 1.00 877,440 659,728
WTP 07 GENERATOR HOUSE L.Sum 1.00 5,741,501 4,316,917
WTP 08 GUARD HOUSE L.Sum 1.00 891,054 669,965
WTP 09 YARD PIPING L.Sum 1.00 8,550,260 6,428,767
WTP 10 LANDSCAPING L.Sum 1.00 14,983,843 11,266,047
WTP 11 DIRECT TEMPORARY WORK L.Sum 1.00 1,350,000 1,015,038
130,751,338 98,309,273
THE PROJECT FOR REHABILITATION OF KILLINOCHCHI WATER TREATMENT SCHEME
TENDER PRICE SCHEDULE
BILL NO: CW(1) - WATER INTAKE AND WATER TREATMENT PLANT
Total for CW(1) carried to Summary
Cost and Management Consultant CW(1) 4 Narayananan Associates
Tender Price Schedule
CW(1)- Water Intake and Water Treatment Plant
Main Contractor: DAIHO Corportion
Sub Contractor: KDG Global Engineering
Item No Description Unit Qty Rate
(Rs) Amount (Rs) Amount (JPY)
WI-01 NEW INTAKE PIT
WI-01-01 Site Clearance L.sum 1.00 160,000 160,000 120,301
WI-01-02 Care of water & dewatering L.sum 1.00 400,000 400,000 300,752
WI-01-03 Excavation in any material other than rock m3 21.00 960 20,160 15,158
WI-01-04 Extra over excavation in rock m3 1.00 8,000 8,000 6,015
WI-01-05 Permanent disposal of excavated materials m3 21.00 640 13,440 10,105
WI-01-06 Back filling item 1.00 40,000 40,000 30,075
WI-01-07Rubble packing (filling stone) 500mm thick
inside the intake pit for preventing muddiness m3 1.00 5,600 5,600 4,211
WI-01-08Rubble retaining wall (dry type) with 250-500
mm thick layersm3 25.00 5,760 144,000 108,271
WI-01-09 1000x500x2000mm sized - Kago Mat nr 51.00 14,000 714,000 536,842
WI-01-10 1000x1000x500mm sized - Gabion box nr 2.00 8,800 17,600 13,233
STEEL INTAKE PIT
Flange and plain ended, steel pipe
WI-01-11
Supplying/Fabricating and fixing 1350mm dia
12mm thick 4700mm deep steel pit as specified
in the drg No KWSP/INT/IP/C-02, Bottom plate
with 30mm dia hole @ 100mm c/c, top flanged
welded with following specials, fittings & cover.
(Specials, fittings and cover measured
separately.
nr 1.00 1,760,000 1,760,000 1,323,308
Inlet & outlet
Steel pipe flanged and plain ended
WI-01-12 250mm dia 600mm long nr 1.00 7,520 7,520 5,654
WI-01-13 250mm dia 650mm long nr 1.00 7,520 7,520 5,654
WI-01-14 250mm dia 400mm long nr 1.00 4,880 4,880 3,669
Air Release Pipe
Bend
WI-01-15100mm dia steel flange and plain ended 90
bendnr 1.00 6,720 6,720 5,053
L- shape fitting
WI-01-16100mm dia steel flange & Plain ended 'L' shape
pipenr 1.00 4,640 4,640 3,489
Cost and Management Consultant CW(1) 5 Narayananan Associates
Tender Price Schedule
CW(1)- Water Intake and Water Treatment Plant
Main Contractor: DAIHO Corportion
Sub Contractor: KDG Global Engineering
Item No Description Unit Qty Rate
(Rs) Amount (Rs) Amount (JPY)
Pipe Fittings
Supply and fixing all DCI fittings including
rubber rings, lubricant, gaskets, bolts & nuts
and all other associated material required for
complete installation.
Stub backing flange including built fushion
weld
WI-01-17 250-280mm dia nr 1.00 8,080 8,080 6,075
Bend
WI-01-18 250mm dia DCIP double flange 90 short bend nr 2.00 37,440 74,880 56,301
Bell Mouth
WI-01-19 250mm dia DCIP flange bell mouth nr 2.00 16,400 32,800 24,662
NEW INTAKE PIT - INTAKE SUM PIPE WORK
Supply and laying all HDPE pipes and fittings &
specials including all other associated material
required for complete installation.
WI-01-20 280mm dia HDPE pipe (approx) m 15.00 5,440 81,600 61,353
WATERPROOFING
WI-01-21
Waterproofing - surface preparation with SSPC-
SR10, first, second & finish coat with 125
microns thick Epoxy Resin
m2 14.00 720 10,080 7,579
MISCELLANIOUS WORK
Bracket
WI-01-22 Steel pipe brackets including water proofing nr 3.00 3,200 9,600 7,218
Silt curtain
WI-01-23Silt curtain 1m height including frame work as
depicted in drg No KWSP/INT/IP/C-01m 27.00 32,000 864,000 649,624
Anchoring
WI-01-24Anchoring silt curtain structure with 12mm dia
wire 15-20m long to concrete anchor blocknr 4.00 12,000 48,000 36,090
4,443,120 3,340,692 Total WI 01 - New Intake Pit carried to CW(1) Bill Summary
Cost and Management Consultant CW(1) 6 Narayananan Associates
Tender Price Schedule
CW(1)- Water Intake and Water Treatment Plant
Main Contractor: DAIHO Corportion
Sub Contractor: KDG Global Engineering
Item No Description Unit Qty Rate
(Rs) Amount (Rs) Amount (JPY)
WI-02 INTAKE SUMP
INSITU CONCRETE
Rate shall include supplying and placing
concrete (with temperature control) and
curing as specified. Reinforcement &
formwork measured separately.
Reinforced concrete Grade 35 A
WI-02-01 In 250mm thick sump top slab m3 4.00 23,600 94,400 70,977
WI-02-02500x500x250mm sized concrete base to place
submersible pumpnr 2.00 1,600 3,200 2,406
CONCRETE ANCILLARIES
Reinforcement
Rate shall include supplying and delivering to
the yard, storing, cutting and bending,
transport to the site, cleaning as specified and
placing in position tied with GI binding wire fix
with cover blocks complete as depicted in
drawings.
WI-02-03 10mm dia Tor steel t 0.30 210,000 63,000 47,368
Chemical anchoring
WI-02-04Chemical anchoring 125mm long using Hiliti Re
500 or equivalent nr 172.00 320 55,040 41,383
Formwork
All formwork shall be plywood sheet. Rate
includes formwork support system
WI-02-05 Fair finish to bottom m2 17.00 2,560 43,520 32,722
WI-02-06 Fair finish to sides m2 6.00 2,560 15,360 11,549
MANHOLE COVER
WI-02-07Class A 150 Manhole cover 600mm dia clear
opening with circular basenr 1.00 24,000 24,000 18,045
PIPEWORK - PIPES
Supply and laying all DI pipes and fittings,
valves & specials including rubber rings,
lubricant, gaskets, bolts & nuts and all other
associated material required for complete
installation.
Suction Pipe
Rate included under mechanical works Rate included in mechanical works
Cost and Management Consultant CW(1) 7 Narayananan Associates
Tender Price Schedule
CW(1)- Water Intake and Water Treatment Plant
Main Contractor: DAIHO Corportion
Sub Contractor: KDG Global Engineering
Item No Description Unit Qty Rate
(Rs) Amount (Rs) Amount (JPY)
MISCELLANEOUS WORK
WI-02-18
25mm dia stainless steel steps fixed to concrete
wall with chemical anchoring rate include for
necessary drilling etc complete as depicted in
drawing no KWSP/STD/ST-02
nr 14.00 1,760 24,640 18,526
WI-02-19
Hand rails 32mm dia G.I pipes two horizontal
pipes in 550mm c/c and vertical pipes in
1500mm(max) c/c including G.I joints and fixing
to concrete slab
m 18.00 4,800 86,400 64,962
WI-02-20Pipe support in concrete (400x200x100mm
sized approx)nr 2.00 240 480 361
WI-02-21Allow for removal of existing slab and making
good as directedL.sum 1.00 40,000 40,000 30,075
WI-02-22Allow for supplying and fixing checqued plate as
per drg No KWSP/INT/IP/C-03L.sum 1.00 64,000 64,000 48,120
WI-02-23Allow for supplying and fixing screen inside the
sump completeL.sum 1.00 160,000 160,000 120,301
WI-02-24
Supplying & fixing pumps lifting device
including pulley, chain and etc as depicted in
the drg No WTP-PM-02 and as specified.
L.sum 1.00 480,000 480,000 360,902
WI-02-25
Provision for making holes for fixing HDPE pipe
280mm dia in existing sump wall and making
good
L.Sum 1.00 8,000 8,000 6,015
WI-02-26Provision for concrete pipe support including
brackets and clips etc completeL.Sum 1.00 48,000 48,000 36,090
1,210,040 909,802 Total WI 02 - Intake Sump carried to CW(1) Bill Summary
Cost and Management Consultant CW(1) 8 Narayananan Associates
Tender Price Schedule
CW(1)- Water Intake and Water Treatment Plant
Main Contractor: DAIHO Corportion
Sub Contractor: KDG Global Engineering
Item No Description Unit Qty Rate
(Rs) Amount (Rs) Amount (JPY)
WI-03 INTAKE PUMP HOUSE
PIPEWORK - PIPES
Supply and laying all DI pipes and fittings,
valves & specials including rubber rings,
lubricant, gaskets, bolts & nuts and all other
associated material required for complete
installation.
Delivery pipe (upto existing pipe)
DI Double flange pipe
WI-03-01 150mm dia 1320mm long (approx) nr 4.00 23,600 94,400 70,977
WI-03-02 150mm dia 330mm long (approx) nr 2.00 17,120 34,240 25,744
WI-03-03 150mm dia 1220mm long (approx) nr 2.00 22,880 45,760 34,406
WI-03-04 150mm dia 770mm long (approx) nr 2.00 19,920 39,840 29,955
WI-03-05 150mm dia 440mm long (approx) nr 6.00 17,760 106,560 80,120
WI-03-06 150mm dia 950mm long (approx) nr 2.00 21,120 42,240 31,759
PIPEWORK - FITTINGS AND VALVES
Radial Tee
WI-03-07 150mm dia DI flanged radial Tee nr 4.00 47,600 190,400 143,158
Blank flange
WI-03-08 150mm dia DI nr 2.00 3,440 6,880 5,173
Bend
WI-03-09 150mm dia DI double flanged 90 Bend nr 6.00 14,160 84,960 63,880
Gate valve
WI-03-10 150mm dia DI double flanged nr 4.00 Rate included in mechanical works
Flange Adaptor
WI-03-11 150mm dia DI nr 4.00 Rate included in mechanical works
Flexible pipe (coupling)
WI-03-12 150mm dia DI nr 1.00 Rate included in mechanical works
Reducer
WI-03-13 200-150mm dia DI double flanged nr 2.00 Rate included in mechanical works
MISCELLANEOUS WORK
WI-03-14Pipe support in concrete (400x200x100mm
sized approx)nr 3.00 240 720 541
646,000 485,713 Total WI 03 - Intake Pump House carried to CW(1) Bill Summary
Cost and Management Consultant CW(1) 9 Narayananan Associates
Tender Price Schedule
CW(1)- Water Intake and Water Treatment Plant
Main Contractor: DAIHO Corportion
Sub Contractor: KDG Global Engineering
Item No Description Unit Qty Rate
(Rs) Amount (Rs) Amount (JPY)
WI-04 DIRECT TEMPORARY WORK
WI-04-01Reinstatement of Roads damaged during
constructionL.sum 1.00 100,000 N/A N/A
WI-04-02Investigation including trial excavation and
borehole exploratory excavationL.sum 1.00 500,000 N/A N/A
WI-04-03Temporary Project Information Boards-As per
Vol II, General Requirement 19Nr 1.00 50,000 50,000 37,594
WI-04-04
Temporary Name plates for Grant Aid &
Equipment-As per Vol II, General Requirement
32
Nr 6.00 50,000 300,000 225,564
WI-04-05 Commemorative Plaque Nr 1.00 100,000 100,000 75,188
WI-04-06Temporary shoring with steel sheet pile- 6m
long 400mm wide m 34.00 Nill - -
WI-04-07 Coffer dam L.sum 1.00 Nill - -
WI-04-08 Permanent approach road L.sum 1.00 4,700,000 N/A N/A
WI-04-09Safety measures -Vol I, Instruction to
Tenderers 6.1L.sum 1.00 500,000 500,000 375,940
WI-04-10 Security Control system L.sum 1.00 100,000 N/A N/A
WI-04-11Provision for pressure & leakage test of pipe
lineL.sum 1.00 100,000 100,000 75,188
1,050,000 789,474 Total WI 04 - Direct Temporary Work carried to CW(1) Bill Summary
Cost and Management Consultant CW(1) 10 Narayananan Associates
Tender Price Schedule
CW(1)- Water Intake and Water Treatment Plant
Main Contractor: DAIHO Corportion
Sub Contractor: KDG Global Engineering
Item No Description Unit Qty Rate
(Rs) Amount (Rs) Amount (JPY)
RW 01 RAW WATER TRANSMISSION PIPE
PIPEWORK - EXISTING PIPES AND FITTINGS
Rate to include cleaning & repairing of existing
pipes.
RW-01-01 Clearing & repairing of existing pipe works L.Sum 1.00 400,000 400,000 300,752
Intake to aerator PVC Pipe
PIPEWORK - PIPES
Rate to include excavation, supply & installing
pipes, shoring & dewatering, backfilling or
filling with selected material (where
necessary), compaction & disposal of excess &
unsuitable material and installation of warning
tapes as required.
Pipe work from A1 to A2 included in Yard
Piping.
Pipe work from New intake pit to EX. Raw
Water Main included in Intake Pit.
DI, Flanged and plain ended pipe
RW-01-02 200mm dia 1000mm long nr 2.00 24,000 48,000 36,090
DI, Plain ended pipe with puddle flange
RW-01-03200mm dia 1000mm long, puddle flange
400mm away from one end.nr 1.00 24,000 24,000 18,045
PIPEWORK - FITTINGS
Rate to include for providing fittings, thrust
blocks, anchor blocks etc.
Rate to include for additional excavation,
shoring, dewatering, construction of concrete
thrust block & all necessary items of work
required for complete installation of fittings.
DI, Coupling
RW-01-04 200mm dia nr 3.00 19,200 57,600 43,308
DI, Flange Tee
RW-01-05 200 x 200mm dia nr 1.00 46,560 46,560 35,008
DI, Flange Adaptor
RW-01-06 200mm dia nr 1.00 32,080 32,080 24,120
PIPEWORK - VALVES
Rate to include supply & fixing Valves and
providing supports, thrust blocks and
protection of joints (Chamber measured under
yard piping).
DI, Gate valve (Flanged Type)
RW-01-07 200mm dia nr 1.00 48,000 48,000 36,090
656,240 493,413 Total RW 01 - Raw Water Transmission Pipe carried to CW(1) Bill Summary
Cost and Management Consultant CW(1) 11 Narayananan Associates
Tender Price Schedule
CW(1)- Water Intake and Water Treatment Plant
Main Contractor: DAIHO Corportion
Sub Contractor: KDG Global Engineering
Item No Description Unit Qty Rate
(Rs) Amount (Rs) Amount (JPY)
WTP 01 RAUGHING FILTER
EARTH WORKS
WTP 01 - 01 Site Clearance L.Sum 1.00 80,000 80,000 60,150
WTP 01 - 02 Care of water and Dewatering L.Sum 1.00 160,000 160,000 120,301
WTP 01 - 03 Temporary steel shoring m Nill - - -
WTP 01 - 04 Excavation in any material other than rock m3 223.00 800 178,400 134,135
WTP 01 - 05 Extra over of rock excavation m 25.00 8,000 200,000 150,376
WTP 01 - 06 Compacting bottom of excavation m2 225.00 120 27,000 20,301
WTP 01 - 07 Disposal of excavated material m3 223.00 640 142,720 107,308
IN SITU CONCRETE
Rate to include supplying and placing concrete
(with temperature control) and curing as
specified (R/F & F/W measured separately).
Concrete in Grade 15
WTP 01 - 08 Mass concrete blinding, 75mm thick m3 169.00 18,400 3,109,600 2,338,045
Reinforced Concrete in Grade 35A
WTP 01 - 09 in base m3 115.00 23,600 2,714,000 2,040,602
WTP 01 - 10 in plinth, 300x300x500mm sized m3 5.00 23,600 118,000 88,722
WTP 01 - 11 in walls m3 208.00 23,600 4,908,800 3,690,827
WTP 01 - 12 in columns m3 0.50 23,600 11,800 8,872
WTP 01 - 13 in beams m3 3.40 23,600 80,240 60,331
WTP 01 - 14 in suspended slab, 300mm thick m3 14.00 23,600 330,400 248,421
CONCRETE ANCILLARIES
Reinforcement
Rate shall include supplying and delivering to
the yard, storing, cutting and bending,
transport to the site, cleaning as specified and
erection placing in position tied with GI
binding wire and concrete blocks complete as
depicted in drawings.
WTP 01 - 15 Tor steel (T10 - T20) t 51.30 210,000 10,773,000 8,100,000
WTP 01 - 16 Mild steel (R6 - R10) t 0.30 208,000 62,400 46,917
Cost and Management Consultant CW(1) 12 Narayananan Associates
Tender Price Schedule
CW(1)- Water Intake and Water Treatment Plant
Main Contractor: DAIHO Corportion
Sub Contractor: KDG Global Engineering
Item No Description Unit Qty Rate
(Rs) Amount (Rs) Amount (JPY)
Formwork
All formwork shall be plywood sheet. Rate
includes formwork support system.
WTP 01 - 17 Fair finish, plane horizontal m2 63.00 2,560 161,280 121,263
WTP 01 - 18 Fair finish, plane vertical m2 1,077.00 2,560 2,757,120 2,073,023
PRECAST CONCRETE
Rate to include supply and placing in position
PCC units.
WTP 01 - 19 1000x1000x200mm, PCC Slab with holes nr 110.00 30,400 3,344,000 2,514,286
WATERPROOFING
WTP 01 - 20 Two layer of Epoxy resin coating m2 803.00 720 578,160 434,707
PAINTING
WTP 01 - 21
Apply one under coat & two finishing coats of
approved weather proof emulsion paint on all
exposed surface of external walls.m2 347.00 560 194,320 146,105
Inlet, Washout, Outlet, Overflow & Drain Pipe
PIPEWORK - PIPES
Rate to include supply, delivery and laying all
pipes & specials including rubber rings,
lubricant, gaskets, bolts & nuts and all other
associated material required for complete
installation.
DI, Double flange pipe with puddle flange
WTP 01 - 22200mm dia 960mm long, puddle flange 450mm
away from one end.nr 2.00 43,840 87,680 65,925
DI, Double flange pipe
WTP 01 - 23 250mm dia 4480mm long nr 2.00 93,520 187,040 140,632
WTP 01 - 24 250mm dia 3000mm long nr 1.00 73,280 73,280 55,098
WTP 01 - 25 250mm dia 2100mm long nr 1.00 60,960 60,960 45,835
WTP 01 - 26 250mm dia 1500mm long nr 1.00 52,640 52,640 39,579
WTP 01 - 27 200mm dia 5000mm long nr 2.00 73,520 147,040 110,556
WTP 01 - 28 200mm dia 1300mm long nr 2.00 35,920 71,840 54,015
WTP 01 - 29 200mm dia 950mm long nr 2.00 32,320 64,640 48,602
WTP 01 - 30 150mm dia 600mm long nr 1.00 18,832 18,832 14,159
Cost and Management Consultant CW(1) 13 Narayananan Associates
Tender Price Schedule
CW(1)- Water Intake and Water Treatment Plant
Main Contractor: DAIHO Corportion
Sub Contractor: KDG Global Engineering
Item No Description Unit Qty Rate
(Rs) Amount (Rs) Amount (JPY)
DI, Flanged and plain ended pipe with puddle
flange
WTP 01 - 31250mm dia 1600mm long, puddle flange
500mm away from plain end.nr 1.00 54,480 54,480 40,962
WTP 01 - 32250mm dia 1000mm long, puddle flange
500mm away from plain end.nr 1.00 45,760 45,760 34,406
WTP 01 - 33250mm dia 750mm long, puddle flange 275mm
away from plain end.nr 2.00 42,400 84,800 63,759
WTP 01 - 34250mm dia 600mm long, puddle flange 430mm
away from flanged end.nr 1.00 40,400 40,400 30,376
WTP 01 - 35250mm dia 600mm long, puddle flange 200mm
away from plain end.nr 1.00 40,400 40,400 30,376
WTP 01 - 36250mm dia 600mm long, puddle flange 160mm
away from plain end.nr 2.00 40,400 80,800 60,752
WTP 01 - 37250mm dia 500mm long, puddle flange 150mm
away from plain end.nr 1.00 39,040 39,040 29,353
WTP 01 - 38150mm dia 725mm long, puddle flange 175mm
away from plain end.nr 1.00 20,000 20,000 15,038
WTP 01 - 39150mm dia 650mm long, puddle flange 185mm
away from plain end.nr 1.00 19,120 19,120 14,376
WTP 01 - 40100mm dia 1850mm long, puddle flange
160mm away from plain end.nr 1.00 20,640 20,640 15,519
WTP 01 - 41100mm dia 1450mm long, puddle flange
275mm away from plain end.nr 2.00 18,800 37,600 28,271
WTP 01 - 42100mm dia 1250mm long, puddle flange
160mm away from plain end.nr 1.00 17,760 17,760 13,353
DI, Flanged and plain ended pipe
WTP 01 - 43 250mm dia 3460mm long nr 1.00 63,520 63,520 47,759
WTP 01 - 44 250mm dia 1460mm long nr 1.00 36,160 36,160 27,188
WTP 01 - 45 200mm dia 1000mm long nr 1.00 21,520 21,520 16,180
WTP 01 - 46 200mm dia 900mm long nr 2.00 20,560 41,120 30,917
WTP 01 - 47 100mm dia 500mm long nr 2.00 8,400 16,800 12,632
DI, Plain ended pipe with puddle flange
WTP 01 - 48250mm dia 1500mm long, puddle flange
275mm away from one end.nr 2.00 36,800 73,600 55,338
Cost and Management Consultant CW(1) 14 Narayananan Associates
Tender Price Schedule
CW(1)- Water Intake and Water Treatment Plant
Main Contractor: DAIHO Corportion
Sub Contractor: KDG Global Engineering
Item No Description Unit Qty Rate
(Rs) Amount (Rs) Amount (JPY)
DI, Plain ended pipe
WTP 01 - 49 250mm dia 650mm long nr 2.00 9,040 18,080 13,594
PIPEWORK - FITTINGS
Rate to include supply, delivery and fixing all
fittings including all associated material
required for complete installation.
DI, Coupling
WTP 01 - 50 250mm dia nr 3.00 25,520 76,560 57,564
WTP 01 - 51 200mm dia nr 1.00 19,120 19,120 14,376
WTP 01 - 52 100mm dia nr 2.00 8,560 17,120 12,872
DI, Double Flanged 90 Bend
WTP 01 - 53 250mm dia nr 7.00 48,480 339,360 255,158
WTP 01 - 54 200mm dia nr 6.00 34,400 206,400 155,188
WTP 01 - 55 150mm dia nr 1.00 23,200 23,200 17,444
DI, Flange Tee
WTP 01 - 56 200 x 200mm dia nr 1.00 30,880 30,880 23,218
DI, Flange Adaptor
WTP 01 - 57 250mm dia nr 3.00 21,760 65,280 49,083
WTP 01 - 58 200mm dia nr 2.00 16,420 32,840 24,692
WTP 01 - 59 150mm dia nr 1.00 11,920 11,920 8,962
WTP 01 - 60 100mm dia nr 2.00 8,560 17,120 12,872
PIPEWORK - VALVES
Rate to include for providing supports, thrust
blocks and protection of joints (Chamber
measured under yard piping).
DI, Gate valve (Flanged Type)
WTP 01 - 61 250mm dia nr 2.00 68,560 137,120 103,098
WTP 01 - 62 200mm dia nr 2.00 43,600 87,200 65,564
WTP 01 - 63 150mm dia nr 1.00 25,600 25,600 19,248
WTP 01 - 64 100mm dia nr 2.00 14,400 28,800 21,654
Cost and Management Consultant CW(1) 15 Narayananan Associates
Tender Price Schedule
CW(1)- Water Intake and Water Treatment Plant
Main Contractor: DAIHO Corportion
Sub Contractor: KDG Global Engineering
Item No Description Unit Qty Rate
(Rs) Amount (Rs) Amount (JPY)
FILTRATION MEDIA
WTP 01 - 65 Filtration Gravel, 4-8mm dia pebbles m3 112.00 16,800 1,881,600 1,414,737
WTP 01 - 66 Filtration Gravel, 8-12mm dia pebbles m3 112.00 15,000 1,680,000 1,263,158
WTP 01 - 67 Filtration Gravel, 12-16mm dia pebbles m3 112.00 13,600 1,523,200 1,145,263
WTP 01 - 68 Filtration Gravel, 20mm dia pebbles m3 73.00 12,000 876,000 658,647
MISCELLANEOUS WORK
WTP 01 - 6920mm dia UPVC pipe fixed to PCC slab (300mm
long)m 825.00 224 184,800 138,947
WTP 01 - 70 Stainless steel ladder 450mm wide 4.55m long nr 4.00 88,000 352,000 264,662
WTP 01 - 71 GI handrail, 1100mm height m 92.00 7,200 662,400 498,045
WTP 01 - 72
Allow for providing concrete anchor blocks,
Thrust blocks for fittings as depicted in
drawing.
item 1.00 180,000 180,000 135,338
39,925,312 30,019,032 Total WTP 01 - Roughing Filter carried to CW(1) Bill Summary
Cost and Management Consultant CW(1) 16 Narayananan Associates
Tender Price Schedule
CW(1)- Water Intake and Water Treatment Plant
Main Contractor: DAIHO Corportion
Sub Contractor: KDG Global Engineering
Item No Description Unit Qty Rate
(Rs) Amount (Rs) Amount (JPY)
WTP 02 AERATOR / RECEIVING WELL
REPAIR WORK
WTP 02 - 1
Allow for necessary improvement and cleaning
concrete surface of damaged structures
completely.
L.Sum 1.00 640,000 640,000 481,203
PRECAST CONCRETE
Rate to include supply and placing as shown in
drawing PCC blocks.
WTP 02 - 2 450x75x75mm PCC block nr 16.00 80 1,280 962
WATERPROOFING
WTP 02 - 3Chipping or grinding internal concrete surface
and apply concrete repair mortar.m2 107.00 2,000 214,000 160,902
WTP 02 - 4 Two layer of Epoxy resin coating m2 107.00 720 77,040 57,925
PAINTING
WTP 02 - 5
Apply one under coat & two finishing coats of
approved weather proof emulsion paint on all
surface of external walls.m2 77.00 560 43,120 32,421
PIPEWORK - EXISTING PIPES AND FITTINGS
Rate to include cleaning & repairing of existing
pipes.
WTP 02 - 6 Existing inlet pipe work L.Sum 1.00 80,000 80,000 60,150
CI, 200mm dia 2100mm long Double flange
pipe.
CI, 200mm dia 375mm long Flanged and plain
ended pipe with puddle flange.
CI, 2 nr 200mm dia Flanged 90 Medium Bend.
200mm dia Flanged Stapered Core (225mm
Tapered core & Hang).
PIPEWORK - PIPES
Rate to include supply, delivery and laying all
pipes & specials including rubber rings,
lubricant, gaskets, bolts & nuts and all other
associated material required for complete
installation.
CI, Double flange pipe
WTP 02 - 7 100mm dia 850mm long nr 1.00 17,440 17,440 13,113
WTP 02 - 8 80mm dia 850mm long nr 1.00 13,760 13,760 10,346
Cost and Management Consultant CW(1) 17 Narayananan Associates
Tender Price Schedule
CW(1)- Water Intake and Water Treatment Plant
Main Contractor: DAIHO Corportion
Sub Contractor: KDG Global Engineering
Item No Description Unit Qty Rate
(Rs) Amount (Rs) Amount (JPY)
CI, Flanged and plain ended pipe with puddle
flange
WTP 02 - 9
100mm dia 2100mm long, puddle flange
140mm away from plain end, fixed with FI
brackets 50X10mm.
nr 1.00 24,160 24,160 18,165
WTP 02 - 10
80mm dia 2100mm long, puddle flange 140mm
away from plain end, fixed with FI brackets
50X10mm
nr 1.00 19,520 19,520 14,677
PIPEWORK - FITTINGS
Rate to include supply, delivery and fixing all
fittings including all associated material
required for complete installation.
CI, Flanged 90 Medium Bend
WTP 02 - 11 100mm dia nr 1.00 9,920 9,920 7,459
WTP 02 - 12 80mm dia nr 1.00 7,040 7,040 5,293
PIPEWORK - VALVES
Rate to include supply & fixing Valves and
providing supports, thrust blocks and
protection of joints (Chamber measured under
yard piping).
DI, Gate valve (Flanged Type)
WTP 02 - 13 100mm dia nr 1.00 14,400 14,400 10,827
WTP 02 - 14 80mm dia nr 1.00 12,000 12,000 9,023
MISCELLANEOUS WORK
WTP 02 - 15 Stainless steel ladder 450mm wide 4.75m long nr 1.00 80,000 80,000 60,150
WTP 02 - 16 MS Steps, 450mm wide in Receiving well L.Sum 1.00 16,000 16,000 12,030
WTP 02 - 17 V Notch nr 1.00 32,000 32,000 24,060
Chequer Plate
WTP 02 - 18 650x850x6mm Chequer Plate nr 1.00 10,400 10,400 7,820
WTP 02 - 19 650x650x6mm Chequer Plate, nr 1.00 8,000 8,000 6,015
1,320,080 992,541 Total WTP 02 - Aerator / Receiving Well carried to CW(1) Bill Summary
Cost and Management Consultant CW(1) 18 Narayananan Associates
Tender Price Schedule
CW(1)- Water Intake and Water Treatment Plant
Main Contractor: DAIHO Corportion
Sub Contractor: KDG Global Engineering
Item No Description Unit Qty Rate
(Rs) Amount (Rs) Amount (JPY)
WTP 03 SLOW SAND FILTER
EARTH WORKS
WTP 03 - 01 Site Clearance L.Sum 1.00 240,000 240,000 180,451
WTP 03 - 02
Allow for necessary improvement and cleaning
concrete surface of damaged structures
completely.
L.Sum 1.00 800,000 800,000 601,504
WTP 03 - 03 Excavation / Cutting of embankment m3 2,500.00 480 1,200,000 902,256
WTP 03 - 04 Allow of stock pile of excavated soil m3 2,500.00 160 400,000 300,752
WTP 03 - 05 Backfilling up to ground level (up to 20.10) m3 1,137.00 960 1,091,520 820,692
IN SITU CONCRETE
Rate to include supplying and placing concrete
(with temperature control) and curing as
specified (R/F & F/W measured separately).
Concrete in Grade 20 (F/W measured
seperately)
WTP 03 - 06 Mass concrete supports to lateral pipe m3 0.81 20,000 16,200 12,180
Reinforced Concrete in Grade 35A
WTP 03 - 07 in filter collecting channel. m3 14.00 23,600 330,400 248,421
WTP 03 - 08 in additional placing wall in inlet channel. m3 0.03 23,600 708 532
WTP 03 - 09 in splash plate - 2nd pond. m3 0.22 23,600 5,192 3,904
CONCRETE ANCILLARIES
Reinforcement
Rate shall include supplying and delivering to
the yard, storing, cutting and bending,
transport to the site, cleaning as specified and
erection placing in position tied with GI
binding wire and concrete blocks complete as
depicted in drawings.
WTP 03 - 10 Tor steel t 1.00 240,000 240,000 180,451
WTP 03 - 11Chemical anchoring, 125mm long in wall &
splash plate.nr 20.00 320 6,400 4,812
Formwork
All formwork shall be plywood sheet. Rate
includes formwork support system.
WTP 03 - 12 Fair finish, plane horizontal m2 2.00 2,560 5,120 3,850
WTP 03 - 13 Fair finish, plane vertical m2 160.00 2,560 409,600 307,970
Cost and Management Consultant CW(1) 19 Narayananan Associates
Tender Price Schedule
CW(1)- Water Intake and Water Treatment Plant
Main Contractor: DAIHO Corportion
Sub Contractor: KDG Global Engineering
Item No Description Unit Qty Rate
(Rs) Amount (Rs) Amount (JPY)
PRECAST CONCRETE
Rate to include supply and placing in position
PCC cover slab.
WTP 03 - 14600x480x50mm PCC cover slab with lifting
handle in collecting chamber. nr 18.00 800 14,400 10,827
WTP 03 - 15500x500x50mm PCC cover slab with lifting
handle in drain channel . nr 85.00 640 54,400 40,902
WTP 03 - 16500x500x50mm PCC cover slab in collecting
channel.nr 180.00 640 115,200 86,617
WATERPROOFING
WTP 03 - 17Chipping or grinding internal concrete surface
and apply concrete repair mortar.m2 2,027.00 2,000 4,054,000 3,048,120
WTP 03 - 18 Two layer of Epoxy resin coating m2 2,187.00 720 1,574,640 1,183,940
PAINTING
WTP 03 - 19Chipping or grinding external concrete surface
and apply concrete repair mortar.m2 942.00 2,000 1,884,000 1,416,541
WTP 03 - 20
Apply one under coat & two finishing coats of
approved weather proof emulsion paint on all
surface of external walls.m2 942.00 560 527,520 396,632
PIPEWORK - EXISTING PIPES AND FITTINGS
Rate to include cleaning & repairing of existing
pipes & removal of pipes.
WTP 03 - 21 Clearing, repairing and removal as shown L.Sum 1.00 160,000 160,000 120,301
Collecting, Overflow & Drain Pipe
PIPEWORK - PIPES
Rate to include supply, delivery and laying all
pipes & specials including rubber rings,
lubricant, gaskets, bolts & nuts and all other
associated material required for complete
installation.
CI, Double flange pipe
WTP 03 - 22 200mm dia 4100mm long nr 3.00 70,720 212,160 159,519
WTP 03 - 23 225mm dia 425mm long nr 3.00 29,920 89,760 67,489
WTP 03 - 24 150mm dia 4025mm long nr 1.00 46,400 46,400 34,887
WTP 03 - 25 150mm dia 3480mm long nr 1.00 42,320 42,320 31,820
CI, Flanged and plain ended pipe with puddle
flange
WTP 03 - 26 200mm dia 425mm long nr 3.00 29,920 89,760 67,489
Cost and Management Consultant CW(1) 20 Narayananan Associates
Tender Price Schedule
CW(1)- Water Intake and Water Treatment Plant
Main Contractor: DAIHO Corportion
Sub Contractor: KDG Global Engineering
Item No Description Unit Qty Rate
(Rs) Amount (Rs) Amount (JPY)
DI, Flanged and plain ended pipe with puddle
flange
WTP 03 - 27 150mm dia 2700mm long nr 1.00 33,120 33,120 24,902
WTP 03 - 28 150mm dia 2600mm long nr 2.00 32,560 65,120 48,962
PVC, Plain ended pipe
WTP 03 - 29 160mm dia PVC scour pipe m 2.11 4,560 9,622 7,235
WTP 03 - 3090mm dia PVC (perforated) pipes including
forming 10mm dia holes @ 150mm c/c m 490.00 1,520 744,800 560,000
PIPEWORK - VALVES
Rate to include Supply & fixing Valves and
providing supports, thrust blocks and
protection of joints (Chamber measured under
yard piping).
DI, Sluice valve (Flanged Type)
WTP 03 - 31200mm dia double flange with extended
spindle & hand wheelnr 3.00 46,960 140,880 105,925
WTP 03 - 32 150mm dia double flange nr 3.00 29,600 88,800 66,767
FILTRATION MEDIA
WTP 03 - 33 Filtration Sand, 0.32mm dia pebbles m3 1,113.00 17,400 19,366,200 14,561,053
WTP 03 - 34 Filtration Gravel, 5-9mm dia pebbles m3 86.00 16,800 1,444,800 1,086,316
WTP 03 - 35 Filtration Gravel, 5-16mm dia pebbles m3 86.00 15,200 1,307,200 982,857
WTP 03 - 36 Filtration Gravel, 9-62mm dia pebbles m3 248.00 14,400 3,571,200 2,685,113
MISCELLANEOUS WORK
WTP 03 - 37 Stainless steel ladder 450mm wide 3.96m long nr 2.00 72,000 144,000 108,271
WTP 03 - 38Timber stop log 50mm thick including fittings as
per drawing. nr 6.00 40,000 240,000 180,451
WTP 03 - 39 Triangular weir SUS 304, 6mm long nr 3.00 64,000 192,000 144,361
WTP 03 - 40 Steel Cradle, 1410x600mm nr 3.00 8,000 24,000 18,045
WTP 03 - 41 Allow provision for rubble steps L.Sum 1.00 16,000 16,000 12,030
WTP 03 - 42Allow for providing concrete anchor blocks,
Thrust blocks for fittings & valves.L.Sum 1.00 7,200 7,200 5,414
Galvanized Chequer Plate with lifting hook
WTP 03 - 43 1130x820x6mm Chequer Plate nr 3.00 24,000 72,000 54,135
WTP 03 - 44 1000x1000x6mm Chequer Plate nr 2.00 24,000 48,000 36,090
WTP 03 - 45 900x810x6mm Chequer Plate nr 1.00 24,000 24,000 18,045
41,148,642 30,938,831 Total WTP 03 - Slow Sand Filter carried to CW(1) Bill Summary
Cost and Management Consultant CW(1) 21 Narayananan Associates
Tender Price Schedule
CW(1)- Water Intake and Water Treatment Plant
Main Contractor: DAIHO Corportion
Sub Contractor: KDG Global Engineering
Item No Description Unit Qty Rate
(Rs) Amount (Rs) Amount (JPY)
WTP 04 WASHED SAND STORAGE YARD
EARTH WORKS
WTP 04 - 01 Site Clearance L.sum 1.00 80,000 80,000 60,150
WTP 04 - 02 Care of water & dewatering L.sum 1.00 40,000 40,000 30,075
WTP 04 - 03 Excavation in any material other than rock m3 73.00 960 70,080 52,692
WTP 04 - 04 Extra over excavation in rock m3 10.00 8,000 80,000 60,150
WTP 04 - 05 Permanent disposal of excavated materials m3 73.00 640 46,720 35,128
WTP 04 - 06 Compacting bottom of excavation m2 163.00 120 19,560 14,707
WTP 04 - 0720mm dia gravel filling in chamber suit as per
drg no KWSP/WTP/SY/ST-01m3 0.50 2,400 1,200 902
IN SITU CONCRETE
Rate to include supplying and placing concrete
(with temperature control) and curing as
specified (R/F & F/W measured separately).
Mass concrete in Grade 15
WTP 04 - 08 In blinding 50mm thick m3 8.00 18,400 147,200 110,677
Reinforced concrete in Grade 35 A
WTP 04 - 09 In base 300mm thick m3 53.00 23,600 1,250,800 940,451
WTP 04 - 10 In walls 200-250mm thick m3 38.00 23,600 896,800 674,286
CONCRETE ANCILLARIES
Reinforcement
Rate shall include supplying and delivering to
the yard, storing, cutting and bending,
transport to the site, cleaning as specified and
erection placing in position tied with GI
binding wire and concrete blocks complete as
depicted in drawings.
WTP 04 - 11 Tor steel (T10 - T12) t 7.30 210,000 1,533,000 1,152,632
Formwork
All formwork shall be plywood sheet. Rate
includes formwork support system.
WTP 04 - 12 Fair finish, plane vertical m2 149.00 2,560 381,440 286,797
Cost and Management Consultant CW(1) 22 Narayananan Associates
Tender Price Schedule
CW(1)- Water Intake and Water Treatment Plant
Main Contractor: DAIHO Corportion
Sub Contractor: KDG Global Engineering
Item No Description Unit Qty Rate
(Rs) Amount (Rs) Amount (JPY)
PIPEWORK - PIPES
Rate to include supply, delivery and laying all
pipes & specials including rubber rings,
lubricant, gaskets, bolts & nuts and all other
associated material required for complete
installation.
DI, Plain ended pipe
WTP 04 - 13DI, 100mm dia 750mm long with puddle flange
75mm away form one end.nr 1.00 15,840 15,840 11,910
PVC, Plain ended pipe
WTP 04 - 14 PVC, 110mm dia m 4.24 2,510 10,642 8,002
PIPEWORK - FITTINGS
Rate to include supply, delivery and fixing all
fittings including all associated material
required for complete installation.
DI, Coupling
WTP 04 - 15 100mm dia nr 1.00 8,560 8,560 6,436
PVC, 90 Bend
WTP 04 - 16 110mm dia nr 1.00 2,610 2,610 1,962
MISCELLANEOUS WORK
WTP 04 - 17
Allow for providing concrete anchor blocks,
Thrust blocks for fittings as depicted in
drawing.
L.Sum 1.00 7,200 7,200 5,414
4,591,652 3,452,371 Total WTP 04 - Wsah Sand Storage Yard carried to CW(1) Bill Summary
Cost and Management Consultant CW(1) 23 Narayananan Associates
Tender Price Schedule
CW(1)- Water Intake and Water Treatment Plant
Main Contractor: DAIHO Corportion
Sub Contractor: KDG Global Engineering
Item No Description Unit Qty Rate
(Rs) Amount (Rs) Amount (JPY)
WTP 05 STORAGE POND
EARTH WORKS
WTP 05 - 01 Site Clearance L.sum 1.00 80,000 80,000 60,150
WTP 05 - 02 Care of water & dewatering L.sum 1.00 40,000 40,000 30,075
WTP 05 - 03 Shoring L.sum Nill - - -
WTP 05 - 04 Excavation in any material other than rock m3 316.00 960 303,360 228,090
WTP 05 - 05 Extra over excavation in rock m3 30.00 8,000 240,000 180,451
WTP 05 - 06 Permanent disposal of excavated materials m3 316.00 640 202,240 152,060
WTP 05 - 07 Compacting bottom of excavation m2 77.00 120 9,240 6,947
WTP 05 - 08 Compacting in slope area m2 202.00 120 24,240 18,226
WTP 05 - 09 Slop protection work item 1.00 96,000 96,000 72,180
IN SITU CONCRETE
Rate to include supplying and placing concrete
(with temperature control) and curing as
specified (R/F & F/W measured separately).
Mass concrete in Grade 15
WTP 05 - 10 In screed, 50mm thick m3 3.20 18,400 58,880 44,271
Mass concrete in Grade 25
WTP 05 - 11 In steps, 200mm thick m3 4.62 20,800 96,096 72,253
Reinforced concrete in Grade 25
WTP 05 - 12 In base, 300mm thick m3 12.11 20,800 251,888 189,389
WTP 05 - 13 In walls, 150-250mm thick m3 13.20 20,800 274,560 206,436
CONCRETE ANCILLARIES
Reinforcement
Rate shall include supplying and delivering to
the yard, storing, cutting and bending,
transport to the site, cleaning as specified and
erection placing in position tied with GI
binding wire and concrete blocks complete as
depicted in drawings.
WTP 05 - 14 Tor steel (T12) t 1.88 210,000 394,800 296,842
Cost and Management Consultant CW(1) 24 Narayananan Associates
Tender Price Schedule
CW(1)- Water Intake and Water Treatment Plant
Main Contractor: DAIHO Corportion
Sub Contractor: KDG Global Engineering
Item No Description Unit Qty Rate
(Rs) Amount (Rs) Amount (JPY)
Formwork
All formwork shall be plywood sheet. Rate
includes formwork support system.
WTP 05 - 15 Fair finish, plane vertical m2 173.00 2,560 442,880 332,992
MASONRY WORK
WTP 05 - 16
Rubble work 150-250mm sized including insitu
concrete 15MPa as per drawing no
KWSP/WTP/SP/C-01m3 24.00 13,600 326,400 245,414
PIPEWORK - PIPES
Rate to include supply, delivery and laying all
pipes & specials including rubber rings,
lubricant, gaskets, bolts & nuts and all other
associated material required for complete
installation.
DI, Flange and plain ended pipe with puddle
flange
WTP 05 - 17250mm dia 1000mm long, puddle flange
300mm away from plain end.nr 1.00 45,760 45,760 34,406
DI, Plain ended pipe
WTP 05 - 18 250mm dia 1000mm long nr 1.00 13,760 13,760 10,346
PVC, Plain ended pipe
WTP 05 - 19 280mm dia 3200mm long nr 1.00 43,120 43,120 32,421
WTP 05 - 20 280mm dia 500mm long nr 1.00 6,880 6,880 5,173
WTP 05 - 21 280mm dia 835mm long nr 1.00 11,280 11,280 8,481
WTP 05 - 22 280mm dia 360mm long nr 1.00 5,330 5,330 4,008
WTP 05 - 23 280mm dia 3525mm long nr 1.00 47,520 47,520 35,729
WTP 05 - 24 280mm dia 5250mm long nr 1.00 70,720 70,720 53,173
RC (Hume pipe), Plain ended pipe
WTP 05 - 25 300mm dia 1040mm long (approx) nr 1.00 6,640 6,640 4,992
PIPEWORK - FITTINGS
Rate to include supply, delivery and fixing all
fittings including all associated material
required for complete installation.
DI, Coupling
WTP 05 - 26 250mm dia nr 2.00 25,440 50,880 38,256
Cost and Management Consultant CW(1) 25 Narayananan Associates
Tender Price Schedule
CW(1)- Water Intake and Water Treatment Plant
Main Contractor: DAIHO Corportion
Sub Contractor: KDG Global Engineering
Item No Description Unit Qty Rate
(Rs) Amount (Rs) Amount (JPY)
DI, Flange Adaptor
WTP 05 - 27 250mm dia nr 1.00 21,760 21,760 16,361
PVC, Tee
WTP 05 - 28 280x280x280mm dia nr 1.00 96,180 96,180 72,316
PVC, 90 Bend
WTP 05 - 29 280mm dia nr 2.00 14,990 29,980 22,541
PIPEWORK - VALVES
Rate to include supply & fixing Valves and
providing supports, thrust blocks and
protection of joints (Chamber measured under
yard piping).
DI, Gate valve (Flanged Type)
WTP 05 - 30 250mm dia nr 1.00 68,560 68,560 51,549
MISCELLANEOUS WORK
WTP 05 - 31
Allow for providing concrete anchor blocks,
Thrust blocks for fittings as depicted in
drawing.
L.Sum 1.00 7,200 7,200 5,414
3,366,154 2,530,942 Total WTP 05 - Storage Pond carried to CW(1) Bill Summary
Cost and Management Consultant CW(1) 26 Narayananan Associates
Tender Price Schedule
CW(1)- Water Intake and Water Treatment Plant
Main Contractor: DAIHO Corportion
Sub Contractor: KDG Global Engineering
Item No Description Unit Qty Rate
(Rs) Amount (Rs) Amount (JPY)
WTP 06 ADMINISTRATION BUILDING
SUCTION PIPE
WTP 06 - 01150mm dia DI flange strainer including foot
valvenr 2.00 Rate included in Mechanical items
PIPEWORK - PIPES
Rate to include supply, delivery and laying all
pipes & specials including rubber rings,
lubricant, gaskets, bolts & nuts and all other
associated material required for complete
installation.
DI, Double flange pipe
WTP 06 - 02 150 mm dia , 3050 mm long (approx.) nr 2.00 Rate included in Mechanical items
WTP 06 - 03 150 mm dia , 400 mm long (approx.) nr 2.00 Rate included in Mechanical items
WTP 06 - 04 150 mm dia , 200 mm long (approx.) nr 2.00 Rate included in Mechanical items
PIPEWORK - FITTINGS
Rate to include supply, delivery and fixing all
fittings including all associated material
required for complete installation.
DI, Double Flanged 90 Medium Bend
WTP 06 - 05 150 mm dia nr 2.00 Rate included in Mechanical items
DI, Flexible Coupling
WTP 06 - 06150mm dia flexible joint including Stapered
Coupling.nr 2.00 Rate included in Mechanical items
PIPEWORK - VALVES
Rate to include for supply & fixing Valves and
providing supports, thrust blocks and
protection of joints (Chamber measured under
yard piping).
Sluice valve
WTP 06 - 07150 mm dia double flanged Sluice valve with
hand wheelnr 2.00 Rate included in Mechanical items
CIVIL WORK
WTP 06 - 08Reinforced Concrete pipe support 450x225mm
sized, 600mm long (approx.)nr 2.00 1,600 3,200 2,406
Cost and Management Consultant CW(1) 27 Narayananan Associates
Tender Price Schedule
CW(1)- Water Intake and Water Treatment Plant
Main Contractor: DAIHO Corportion
Sub Contractor: KDG Global Engineering
Item No Description Unit Qty Rate
(Rs) Amount (Rs) Amount (JPY)
DELIVERY PIPE
PIPEWORK - PIPES
Rate to include supply, delivery and laying all
pipes & specials including rubber rings,
lubricant, gaskets, bolts & nuts and all other
associated material required for complete
installation.
DI, Double flange pipe
WTP 06 - 09 300 mm dia , 900 mm long (approx.) nr 1.00 53,440 53,440 40,180
WTP 06 - 10 300 mm dia , 1300 mm long (approx.) nr 1.00 60,160 60,160 45,233
WTP 06 - 11 150 mm dia , 1500 mm long (approx.) nr 2.00 25,280 50,560 38,015
WTP 06 - 12 150 mm dia , 1300 mm long (approx.) nr 2.00 23,600 47,200 35,489
WTP 06 - 13 150 mm dia , 1000 mm long (approx.) nr 2.00 20,560 41,120 30,917
WTP 06 - 14 150 mm dia , 600 mm long (approx.) nr 1.00 18,880 18,880 14,195
WTP 06 - 15150 mm dia , Flexible pipe 600 mm long
(approx.)nr 1.00 18,800 18,800 14,135
PIPEWORK - FITTINGS
Rate to include supply, delivery and fixing all
fittings including all associated material
required for complete installation.
DI, Flexible Coupling
WTP 06 - 16150mm dia flexible joint including Stapered
Coupling.nr 2.00 11,120 22,240 16,722
DI, Double Flanged 90 Medium Bend
WTP 06 - 17 300 mm dia nr 2.00 45,760 91,520 68,812
WTP 06 - 18 1500 mm dia nr 3.00 14,400 43,200 32,481
DI, Flanged Radial Tee
WTP 06 - 19 150 mm dia nr 3.00 48,240 144,720 108,812
DI, Blank Flanges
WTP 06 - 20 150 mm nr 1.00 6,560 6,560 4,932
DI, Double Flanged Flow meter
WTP 06 - 21 150 mm dia nr 1.00 212,320 212,320 159,639
DI, Double Flanged Coupling
WTP 06 - 22 150 mm dia nr 1.00 13,120 13,120 9,865
Cost and Management Consultant CW(1) 28 Narayananan Associates
Tender Price Schedule
CW(1)- Water Intake and Water Treatment Plant
Main Contractor: DAIHO Corportion
Sub Contractor: KDG Global Engineering
Item No Description Unit Qty Rate
(Rs) Amount (Rs) Amount (JPY)
DI, Double Flanged Reducer
WTP 06 - 23 150 - 300 mm dia nr 1.00 37,600 37,600 28,271
PIPEWORK - VALVES
Rate to include for supply & fixing Valves and
providing supports, thrust blocks and
protection of joints (Chamber measured under
yard piping).
DI, Sluice valve/ Gate valve (Flanged Type)
WTP 06 - 24 150 mm dia nr 4.00 Rate included in Mechanical items
DI, Non - Return Valve (Flanged Type)
WTP 06 - 25 150 mm dia nr 2.00 Rate included in Mechanical items
DI, Air vent Valve (Flanged Type)
WTP 06 - 26 150 mm dia nr 1.00 Rate included in Mechanical items
CIVIL WORKS
WTP 06 - 27Reinforced Concrete pipe support 450x225mm
sized, 2200mm long (approx.)nr 2.00 5,600 11,200 8,421
WTP 06 - 28Reinforced Concrete pipe support 450x225mm
sized, 600mm long (approx.)nr 1.00 1,600 1,600 1,203
877,440 659,728 Total WTP 06 - Administration Building carried to CW(1) Bill Summary
Cost and Management Consultant CW(1) 29 Narayananan Associates
Tender Price Schedule
CW(1)- Water Intake and Water Treatment Plant
Main Contractor: DAIHO Corportion
Sub Contractor: KDG Global Engineering
Item No Description Unit Qty Rate
(Rs) Amount (Rs) Amount (JPY)
WTP 07 GENERATOR HOUSE
EXCAVATION AND EARTH WORK
WTP 07 - 01 Site Clearance item 1.00 40,000 40,000 30,075
WTP 07 - 02 Excavating top soil for preservation item 1.00 40,000 40,000 30,075
WTP 07 - 03
Excavation in any material other than rock for
wall foundation, Column, Ramp foundation and
Genset Foundationm3 69.00 800 55,200 41,504
WTP 07 - 04 Extra over of rock excavation m3 14.00 8,000 112,000 84,211
WTP 07 - 05 Compacting bottom of excavation m2 62.00 120 7,440 5,594
WTP 07 - 06Back Filling with selected excavated materials
including well rammed and consolidated.m3 21.00 1,600 33,600 25,263
WTP 07 - 07Filling under GF with imported material
including well rammed and consolidated.m3 73.00 1,600 116,800 87,820
WTP 07 - 08Filling with ABC including well rammed and
consolidated in Genset Area.m3 12.00 4,000 48,000 36,090
WTP 07 - 09
Gravel paving 1200mm wide, 100mm thk
around the building and well rammed and
consolidated.m2 60.00 2,240 134,400 101,053
WTP 07 - 10 Permanent Disposal of Excavated material m3 92.00 160 14,720 11,068
IN SITU CONCRETE
Rate to include supplying and placing concrete
(with temperature control) and curing as
specified (R/F & F/W measured separately).
Concrete in Grade 15
WTP 07 - 11 Mass concrete blinding in Column, 50mm thk m3 0.50 18,400 9,200 6,917
WTP 07 - 12 Mass concrete in wall foundation, 150mm thk m3 6.90 18,400 126,960 95,459
Reinforced Concrete Grade 25
WTP 07 - 13 In ground floor slab 150mm thick m3 16.50 20,800 343,200 258,045
WTP 07 - 14 In column base & ramp m3 5.00 20,800 104,000 78,195
WTP 07 - 15 In Column stump & ramp wall m3 2.40 20,800 49,920 37,534
WTP 07 - 16 In Plinth beam m3 3.10 20,800 64,480 48,481
WTP 07 - 17 In Genset Foundation m3 9.60 20,800 199,680 150,135
Cost and Management Consultant CW(1) 30 Narayananan Associates
Tender Price Schedule
CW(1)- Water Intake and Water Treatment Plant
Main Contractor: DAIHO Corportion
Sub Contractor: KDG Global Engineering
Item No Description Unit Qty Rate
(Rs) Amount (Rs) Amount (JPY)
WTP 07 - 18 In column m3 3.00 20,800 62,400 46,917
WTP 07 - 19 In Beam m3 6.10 20,800 126,880 95,398
REINFORCEMENT
High yield steel (fy = 460N/mm2) in foundation
base, ground floor slab, column, ramp, beam
and plinth beams
WTP 07 - 20 Tor steel (T10 - T20) t 3.02 210,000 634,200 476,842
Mild steel (fy = 250N/mm2) As stirrups in
columns, ramp, plinth beam and Beam
WTP 07 - 21 6mm dia. t 0.12 208,000 24,960 18,767
FORMWORK
All formwork shall be plywood sheet. Rate
includes formwork support system.
WTP 07 - 22 For sides of Screed concrete m2 14.50 1,600 23,200 17,444
WTP 07 - 23 For sides of column and ramp base m2 15.00 1,600 24,000 18,045
WTP 07 - 24 For sides of column stump and ramp wall m2 32.50 2,560 83,200 62,556
WTP 07 - 25 For sides of Genset base m2 15.40 2,560 39,424 29,642
WTP 07 - 26 For sides of Plinth Beam m2 30.20 2,560 77,312 58,129
WTP 07 - 27 For sides of column m2 40.00 2,560 102,400 76,992
WTP 07 - 28 For sides and soffits of Beam m2 57.00 2,560 145,920 109,714
MASONRY WORK
Random rubble work
WTP 07 - 29150x225mm sized Random rubble masonry in
foundation in cement sand mortar 1:6m3 30.20 5,920 178,784 134,424
Block Work
WTP 07 - 3075mm thick block lining in both sides of plinth
beam in cement sand mortar 1:5m2 29.00 760 22,040 16,571
WTP 07 - 31Block wall masonry 200mm thick in cement
sand mortar 1:5m2 265.00 1,520 402,800 302,857
WATER PROOFING
WTP 07 - 32
Single layer of 1000 gauge polythene DPM laid
with 150mm end and side lap on sand fill to
receive concrete floorm2 132.20 120 15,864 11,928
WTP 07 - 33 Floor Acrylic polymer water proofing in Oil tank m2 6.30 800 5,040 3,789
WTP 07 - 34 Joint Filler m 57.60 80 4,608 3,465
Cost and Management Consultant CW(1) 31 Narayananan Associates
Tender Price Schedule
CW(1)- Water Intake and Water Treatment Plant
Main Contractor: DAIHO Corportion
Sub Contractor: KDG Global Engineering
Item No Description Unit Qty Rate
(Rs) Amount (Rs) Amount (JPY)
ROOF WORK AND CEILING
All timber sections and ceiling planks to be
treated with two coats of sealer and wood
preservatives as per specification.
WTP 07 - 35
Zn/Al metal sheet roof on Steel purlin "C"
channel including Hard wood ridge
plate150x50mm Sized, 100x50mm sized rafters
and 100x75mm sized wall plate Complete.
m2 158.00 1,280 202,240 152,060
WTP 07 - 36
300x25 mm sized valance and barge board in
class I timber fixed complete. Rate to include
for applying two coats of approved enamel
paint to all timber.
m 52.00 800 41,600 31,278
WTP 07 - 37Lunimidelle timber ceiling, nailed to the under
side of the raftersm2 158.00 1,280 202,240 152,060
ROOF PLUMBING
Rain water down pipe to be connected to the
rain water Drain
WTP 07 - 38
Gutter 150x150 mm sized in metal sheet fixed
on valance board with Galvanized mild steel
brackets 300mm c/c
m 32.70 1,384 45,257 34,028
WTP 07 - 39Square shape 100x50 mm sized metal down
pipes at fixed to columnm 40.00 1,960 78,400 58,947
WTP 07 - 40
200x200 mm sized surface drain in 100 mm thk
Gr 25 base and walls finished smooth with
cement rendering 1:3.
m 28.00 2,160 60,480 45,474
FLOOR, WALL AND CEILING FINISHES
WTP 07 - 4120mm thick smooth rendering to floor in
cement sand (1:4) in Electrical room. m2 52.00 560 29,120 21,895
WTP 07 - 4220mm thick power trowel finished in Genset
room and ramp. m2 65.00 720 46,800 35,188
WTP 07 - 4320mm thick Skirting 100mm high in cement
sand 1:3. m 58.00 80 4,640 3,489
WTP 07 - 44
20mm thick smooth plastering in cement, lime
and sand (1:1:5) to internal walls, beam,
columns m2 308.00 520 160,160 120,421
WTP 07 - 45
20mm thick plastering in cement, lime and
sand (1:1:5) and trowel semi-rough to external
walls, beam, columns. m2 228.00 480 109,440 82,286
Cost and Management Consultant CW(1) 32 Narayananan Associates
Tender Price Schedule
CW(1)- Water Intake and Water Treatment Plant
Main Contractor: DAIHO Corportion
Sub Contractor: KDG Global Engineering
Item No Description Unit Qty Rate
(Rs) Amount (Rs) Amount (JPY)
PAINTING
WTP 07 - 46
Prepare and apply one under coat and two
finishing coats of approved Emulsion paint on
all internal plastered surface. m2 308.00 520 160,160 120,421
WTP 07 - 47
Prepare and apply one coat of approved
primer and two coats of approved weather
shield paint to External plastered surface m2 228.00 480 109,440 82,286
WTP 07 - 48
Prepare and apply one coat of approved primer
and two coats of approved weather shield paint
to Ceiling.m2 154.00 560 86,240 64,842
DOORS AND WINDOWS
Use white colour powder coated Aluminium
section for all Aluminium windows.
WTP 07 - 49SD1, 2100x3000mm sized Steel framed metal
sheet Cladding door.nr 2.00 40,000 80,000 60,150
WTP 07 - 50D2, 900x2100mm sized Aluminium framed
Aluminium glazed doornr 1.00 53,500 53,500 40,226
WTP 07 - 51AW1, 1500x2500mm sized Aluminium Glazed
windownr 2.00 106,080 212,160 159,519
WTP 07 - 52ALU, 1500x2500mm sized Aluminium fixed
Louvered windownr 1.00 111,600 111,600 83,910
WTP 07 - 53 FG1, 1200x1200mm sized fixed Glass Blocks nr 2.00 20,000 40,000 30,075
MISCELLANEOUS WORK
WTP 07 - 54
Reinforced concrete Lintel, Gr C 25 concrete
including all necessary formwork and
reinforcement.
m 15.80 2,240 35,392 26,611
WTP 07 - 55
Supplying and Fixing Gantry Beam Steel I beam
300x150mm sized , 7500 mm long anchored to
the concrete beams.
nr 1.00 400,000 400,000 300,752
WTP 07 - 56
Allow Oil tank for Generator, 200x200x200 mm
sized Oil pit, 200x400 mm high side wall
finished as depicted in Drawing.
L.Sum 1.00 Nill - -
WTP 07 - 57
Allow for 2 nr of 900x1200x200mm sized Hand
hole and 500x300 mm sized (25m long approx),
400x300 mm sized (5m long approx) Reinforced
concrete trench including all necessary finishing
and forming holes.
L.Sum 1.00 Nill - -
5,741,501 4,316,917 Total WTP 07 - Generator House carried to CW(1) Bill Summary
Cost and Management Consultant CW(1) 33 Narayananan Associates
Tender Price Schedule
CW(1)- Water Intake and Water Treatment Plant
Main Contractor: DAIHO Corportion
Sub Contractor: KDG Global Engineering
Item No Description Unit Qty Rate
(Rs) Amount (Rs) Amount (JPY)
WTP 08 GUARD HOUSE
EXCAVATION AND EARTH WORK
WTP 08 - 01 Site Clearance L.sum 1.00 50,000 50,000 37,594
WTP 08 - 02 Excavating top soil for preservation L.sum 1.00 50,000 50,000 37,594
WTP 08 - 03
Excavation in any material other than rock for
wall foundation, Column, Ramp foundation and
Genset Foundationm3 2.71 1,000 2,710 2,038
WTP 08 - 04 Extra over of rock excavation m3 0.27 10,000 2,700 2,030
WTP 08 - 05 Compacting bottom of excavation m2 3.71 150 557 419
WTP 08 - 06Filling under GF with imported material
including well rammed and consolidated.m3 2.70 2,000 5,400 4,060
IN SITU CONCRETE
Rate to include supplying and placing concrete
(with temperature control) and curing as
specified (R/F & F/W measured separately).
Concrete in Grade 15
WTP 08 - 07Mass concrete blinding in wall foundation,
50mm thk m3 0.19 18,400 3,496 2,629
Reinforced Concrete Grade 25
WTP 08 - 08 In ground floor slab 150mm thick m3 2.17 20,800 45,136 33,937
WTP 08 - 09 In Beam m3 0.23 20,800 4,784 3,597
REINFORCEMENT
High yield steel (fy = 460N/mm2) in foundation
base, ground floor slab, column, ramp, beam
and plinth beams
WTP 08 - 10 Tor steel (T10 - T20) kg 0.80 210,000 168,000 126,316
Mild steel (fy = 250N/mm2) As stirrups in
columns, ramp, plinth beam and Beam
WTP 08 - 11 6mm dia. kg 0.01 208,000 2,080 1,564
FORMWORK
All formwork shall be plywood sheet. Rate
includes formwork support system.
WTP 08 - 12 For sides and soffits of Beam m2 2.76 3,200 8,832 6,641
MASONRY WORK
Random rubble work
WTP 08 - 13150x225mm sized Random rubble masonry in
foundation in cement sand motor 1:6m3 3.34 7,400 24,716 18,583
Cost and Management Consultant CW(1) 34 Narayananan Associates
Tender Price Schedule
CW(1)- Water Intake and Water Treatment Plant
Main Contractor: DAIHO Corportion
Sub Contractor: KDG Global Engineering
Item No Description Unit Qty Rate
(Rs) Amount (Rs) Amount (JPY)
Block Work
WTP 08 - 14Block wall masonry 150mm thick in cement
sand mortar 1:5m2 23.02 1,900 43,738 32,886
WATER PROOFING
WTP 08 - 15
Single layer of 1000 gauge polythene DPM laid
with 150mm end and side lap on sand fill to
receive concrete floorm2 22.00 150 3,300 2,481
WTP 08 - 16 Floor Acrylic polymer water proofing. m2 3.71 1,000 3,710 2,789
ROOF WORK AND CEILING
All timber sections and ceiling planks to be
treated with two coats of sealer and wood
preservatives as per specification.
WTP 08 - 17
Zn/Al metal sheet roof on Steel purlin "C"
channel including Hard wood ridge
plate150x50mm Sized, 100x50mm sized rafters
and 100x75mm sized wall plate Complete.
m2 27.03 1,600 43,248 32,517
WTP 08 - 18
300x25 mm sized valance and barge board in
class I timber fixed complete. Rate to include
for applying two coats of approved enamel
paint to all timber.
m 20.80 1,000 20,800 15,639
WTP 08 - 19Lunimidelle timber ceiling, nailed to the under
side of the raftersm2 27.03 1,600 43,248 32,517
ROOF PLUMBING
Rain water down pipe to be connected to the
rain water Drain
WTP 08 - 20
Gutter 150x150 mm sized metal sheet fixed on
valance board with Galvanized mild steel
brackets 300mm c/c
m 10.20 1,730 17,646 13,268
WTP 08 - 21Square shape 100x50 mm sized metal down
pipes at fixed to columnm 12.00 2,450 29,400 22,105
WTP 08 - 22
200x200 mm sized surface drain in 100 mm thk
Gr 25 base and walls finished smooth with
cement rendering 1:3.
m 18.92 2,700 51,084 38,409
FLOOR, WALL AND CEILING FINISHES
WTP 08 - 2320mm thick smooth rendering to floor in
cement sand (1:4) in Electrical room. m2 6.00 700 4,200 3,158
WTP 08 - 24
20mm thick smooth plastering in cement, lime
and sand (1:1:5) to internal walls, beam,
columns m2 21.76 650 14,144 10,635
Cost and Management Consultant CW(1) 35 Narayananan Associates
Tender Price Schedule
CW(1)- Water Intake and Water Treatment Plant
Main Contractor: DAIHO Corportion
Sub Contractor: KDG Global Engineering
Item No Description Unit Qty Rate
(Rs) Amount (Rs) Amount (JPY)
WTP 08 - 25
20mm thick plastering in cement, lime and
sand (1:1:5) and trowel semi-rough to external
walls, beam, columns. m2 25.10 600 15,060 11,323
PAINTING
WTP 08 - 26
Prepare and apply one under coat and two
finishing coats of approved Emulsion paint on
all internal plastered surface. m2 21.76 650 14,144 10,635
WTP 08 - 27
Prepare and apply one coat of approved
primer and two coats of approved weather
shield paint to External plastered surface m2 25.10 600 15,060 11,323
WTP 08 - 28
Prepare and apply one coat of approved primer
and two coats of approved weather shield paint
to Ceiling.m2 27.03 700 18,921 14,226
DOORS AND WINDOWS
Use white colour powder coated Aluminium
section for all Aluminium windows.
WTP 08 - 29SD1, 2100x3000mm sized Steel framed metal
sheet Cladding door.nr 1.00 50,000 50,000 37,594
WTP 08 - 30AW1, 1500x2500mm sized Aluminium Glazed
windownr 1.00 132,600 132,600 99,699
MISCELLANEOUS WORK
WTP 08 - 31
Reinforced concrete Lintel, Gr C 25 concrete
including all necessary formwork and
reinforcement.
m 0.90 2,600 2,340 1,759
891,054 669,965 Total WTP 08 - Guard House carried to CW(1) Bill Summary
Cost and Management Consultant CW(1) 36 Narayananan Associates
Tender Price Schedule
CW(1)- Water Intake and Water Treatment Plant
Main Contractor: DAIHO Corportion
Sub Contractor: KDG Global Engineering
Item No Description Unit Qty Rate
(Rs) Amount (Rs) Amount (JPY)
WTP 09 YARD PIPING
PIPEWORK - EXISTING PIPES AND FITTINGS
Rate to include cleaning & repairing of existing
pipes.
WTP 09 - 01 Clearing & repairing of existing pipe works L.Sum 1.00 200,000 200,000 150,376
Raw water main to Aireator & Slow sand filter
to Water Reservior.
YARD AND PROCESS DRAINAGE PIPE
PIPEWORK - PIPES
Rate to include excavation, supply & installing
pipes, shoring & dewatering, backfilling or
filling with selected material (where
necessary), compaction & disposal of excess &
unsuitable material and installation of warning
tapes as required.
DI, Double flange pipe
WTP 09 - 02 250mm dia 1000mm long nr 1.00 47,420 47,420 35,654
WTP 09 - 03 200mm dia 1000mm long nr 2.00 34,520 69,040 51,910
DI, Flanged and plain ended pipe
WTP 09 - 04 200mm dia 1000mm long nr 3.00 23,160 69,480 52,241
DI, Plain ended pipe with puddle flange
WTP 09 - 05250mm dia 1000mm long, puddle flange
400mm away from one end.nr 1.00 31,885 31,885 23,974
WTP 09 - 06200mm dia 1000mm long, puddle flange
400mm away from one end.nr 2.00 23,160 46,320 34,827
HDPE (PN 10), Plain ended pipe
WTP 09 - 07 300mm dia m 31.00 12,800 396,800 298,346
WTP 09 - 08 250mm dia m 14.00 11,710 163,940 123,263
RC (HUME PIPE) Plain ended pipe
WTP 09 - 09 300mm dia m 105.00 11,025 1,157,625 870,395
W