1
GEOTECHNICAL CONSULTING GROUP (ASIA) LTD J383 20/F Henan Building, 90 Jaffe Road, Wanchai, Hong Kong Tel: (852) 2591 1709 (852) 2591 1729 (852) 2591 1774 Fax: (852) 2591 1730 email: [email protected] Asia Description of Work The Kowloon Southern Link will connect the KCRC WestRail and EastRail operating railways and for the purposes of construction has been divided into three separate design and build Contracts. KDB 300 and 400 are the two contracts for the design and construction of approximately 1.8km of cut and cover tunnel from the WestRail terminus at Nam Cheung Station to the new ventilation building at Yau Ma Tei on the West Kowloon Reclamation. These two contracts have been awarded to China State Construction Engineering. GCG (Asia) have been employed by the contractor to provide expert advice on a wide range of geotechnical of issues relating to design and construction. They provide a value engineering review of the temporary and permanent works designs submitted to the contractor by various consultants. They have also set up a fully interactive geotechnical database for the ground conditions anticipated during tunnelling. GCG (Asia) also manage the interpretation and reporting associated with the ground and building instrumentation and monitoring programme and advise on the technical issues associated with commercial and contractual matters Kowloon Southern Link Contracts KDB300 & 400 Technical Support to Main Contractor Client: Chine State Construction Dates: 2006 - ongoing Estimated Project Cost: N/A

Kowloon Southern Link Asia Technical Support to Main ... KCRC Kowloon Southern Link KDB300... · and 400 are the two contracts for the design and construction of approximately 1.8km

Embed Size (px)

Citation preview

Page 1: Kowloon Southern Link Asia Technical Support to Main ... KCRC Kowloon Southern Link KDB300... · and 400 are the two contracts for the design and construction of approximately 1.8km

GEOTECHNICAL CONSULTING GROUP (ASIA) LTD J383 20/F Henan Building, 90 Jaffe Road, Wanchai, Hong Kong Tel: (852) 2591 1709 (852) 2591 1729 (852) 2591 1774 Fax: (852) 2591 1730 email: [email protected]

Asia

Description of Work

The Kowloon Southern Link will connect the KCRC WestRail and EastRail operating railways and for

the purposes of construction has been divided into three separate design and build Contracts. KDB 300

and 400 are the two contracts for the design and construction of approximately 1.8km of cut and cover

tunnel from the WestRail terminus at Nam Cheung Station to the new ventilation building at Yau Ma Tei

on the West Kowloon Reclamation. These two contracts have been awarded to China State Construction

Engineering. GCG (Asia) have been employed by the contractor to provide expert advice on a wide range

of geotechnical of issues relating to design and construction. They provide a value engineering review of

the temporary and permanent works designs submitted to the contractor by various consultants. They

have also set up a fully interactive geotechnical database for the ground conditions anticipated during

tunnelling. GCG (Asia) also manage the interpretation and reporting associated with the ground and

building instrumentation and monitoring programme and advise on the technical issues associated with

commercial and contractual matters

Kowloon Southern Link

Contracts KDB300 & 400

Technical Support to Main Contractor

Client: Chine State Construction

Dates: 2006 - ongoing

Estimated Project Cost: N/A