Presenting.. KUMKANGIndustrialised Building System FormworkKUMKANG ALU FORM
Its a lightweight hand-held aluminium shuttering systemIts a mass production technique It employs the latest CAD facilities in designingIt uses structural-grade aluminum alloyIts environmentally friendlyIts adaptable, flexible, accurate & fastIts cost effective for 50 plus repeats of a typical layoutKUMKANGALU FORM
ALLOWS BUILDINGS TO BE BUILT AT A RATE OF 5 DAYS per Floor(or SIX floors a month)KUMKANG ALU FORM
THE ANSWER IS CYCLING:DIVIDE THE TYPICAL FLOOR INTO 4 WORK ZONES;
DIVIDE THE WORK INTO 4 TASKS FOR 4 WORK TEAMS;
EACH TEAM WORKS IN A DIFFERENT ZONE & SIMPLY CARRIES OUT THE SAME TASK EVERY DAY;
SIZE THE TEAMS SO THAT ALL MEMBERS ARE FULLY OCCUPIED EVERY DAY;
EVERY 4 DAYS A WORK CYCLE IS COMPLETED AND A NEW FLOOR BUILT.
STRUCTURAL WORK ON SITE DIVIDES INTO FOUR MAIN TASKS: Erect & strike vertical forms (walls & column forms)Erect & strike horizontal forms (slabs)Install deck steel and M&E ductingPour the concrete
These tasks follow a logical sequence.Each task is performed by a separate team, which specializes in that task.
A SIMPLISTIC EXAMPLE ASSUME A RECTANGULAR BUILDING; DIVIDE FLOOR INTO FOUR WORK ZONES A, B, C and D:
DAY 1ERECT WALL FORMSZone AZone BZone CZone D
ERECT WALL FORMSERECT SLAB FORMSWALL FORMING TEAM moved to Zone BDAY 2Zone AZone CZone DZone B
BARBENDER + M&EWALL FORMING TEAM Moved to Zone CSLAB FORMING TEAM moves thusDAY 3Zone AZone CZone DZone BERECT WALL FORMSERECT SLAB FORMS
BARBENDER + M&EPOUR CONCRETEBARBENDER + M&E moves thusSLAB FORMING TEAM moves thusWALL FORMING TEAM moves thusDAY 4Zone AZone CZone DZone BERECT WALL FORMSERECT SLAB FORMS
STRIP &RE-ERECT WALL FORMSBARBENDER + M&EPOUR CONCRETENOW ALL TEAMS ARE ON CYCLE!Zone AZone BZone CZone DDAY 5 (TYPICAL)ERECT SLAB FORMS
EXAMPLEGROUND FLOOR(usually non-typical layout)CYCLE ON EACH FLOOR, THEN MOVE UP TO NEXT
START AT FIRST TYPICAL FLOOR FLOORS with TYPICAL LAYOUT
Kumkang ALU-FORM CONSISTS OF ALUMINUM PANELS & COMPONENTS
Kumkang ALU FORMALU Wall Form
Standard Design for ALU Wall FormStandard Modular Panel Form Design
Steel ties connectto opposite panels as well control the Wall Thickness
START OF WALL ERECTION SEQUENCE . . .
LOAD-BEARING / SHEAR WALL BUILDING DESIGN
Column, Beam & Slab Design ( R.C Frame)
ALU DECK Form
Slab Formwork before re-bar
BEAMSLAB
Column, Bean & Slab Design
Easy Dismantling of panels
Steel / Aluminium Gang Formwork For External
FORMING THE STAIRS
Stair Form
Preview of past projects using Kumkang Alu Form
4 Storey Apartment in Sabah
Project in Seoul, South Korea
Laya-Laya, Tuaran, Sabah, East MalaysiaSyarikat Perumahan Negara Berhads Affordable Housing Projects
Laya-Laya, Tuaran, Sabah, East MalaysiaSyarikat Perumahan Negara Berhads Affordable Housing Projects
Break down of Formwork System to be Delivered at TajuraSub-basement Footings = 6 setsTransfer Floor ( Columns, walls and slab) = 6 setsTypical Floor ( Walls and Slabs) = 13 sets
Cycle Time of Formwork systemSub-basement --- 7 days in one Building after move to next buildingTransfer floor --- 8 days in one Building and move to next BuildingTypical Floor (1F to Roof floor) --- 5 days per floor, total = 20 days per Building and move to next buildings