  • Presenting.. KUMKANGIndustrialised Building System FormworkKUMKANG ALU FORM

  • Its a lightweight hand-held aluminium shuttering systemIts a mass production technique It employs the latest CAD facilities in designingIt uses structural-grade aluminum alloyIts environmentally friendlyIts adaptable, flexible, accurate & fastIts cost effective for 50 plus repeats of a typical layoutKUMKANGALU FORM

  • ALLOWS BUILDINGS TO BE BUILT AT A RATE OF 5 DAYS per Floor(or SIX floors a month)KUMKANG ALU FORM

  • THE ANSWER IS CYCLING:DIVIDE THE TYPICAL FLOOR INTO 4 WORK ZONES;

    DIVIDE THE WORK INTO 4 TASKS FOR 4 WORK TEAMS;

    EACH TEAM WORKS IN A DIFFERENT ZONE & SIMPLY CARRIES OUT THE SAME TASK EVERY DAY;

    SIZE THE TEAMS SO THAT ALL MEMBERS ARE FULLY OCCUPIED EVERY DAY;

    EVERY 4 DAYS A WORK CYCLE IS COMPLETED AND A NEW FLOOR BUILT.

  • STRUCTURAL WORK ON SITE DIVIDES INTO FOUR MAIN TASKS: Erect & strike vertical forms (walls & column forms)Erect & strike horizontal forms (slabs)Install deck steel and M&E ductingPour the concrete

  • These tasks follow a logical sequence.Each task is performed by a separate team, which specializes in that task.

  • A SIMPLISTIC EXAMPLE ASSUME A RECTANGULAR BUILDING; DIVIDE FLOOR INTO FOUR WORK ZONES A, B, C and D:

  • DAY 1ERECT WALL FORMSZone AZone BZone CZone D

  • ERECT WALL FORMSERECT SLAB FORMSWALL FORMING TEAM moved to Zone BDAY 2Zone AZone CZone DZone B

  • BARBENDER + M&EWALL FORMING TEAM Moved to Zone CSLAB FORMING TEAM moves thusDAY 3Zone AZone CZone DZone BERECT WALL FORMSERECT SLAB FORMS

  • BARBENDER + M&EPOUR CONCRETEBARBENDER + M&E moves thusSLAB FORMING TEAM moves thusWALL FORMING TEAM moves thusDAY 4Zone AZone CZone DZone BERECT WALL FORMSERECT SLAB FORMS

  • STRIP &RE-ERECT WALL FORMSBARBENDER + M&EPOUR CONCRETENOW ALL TEAMS ARE ON CYCLE!Zone AZone BZone CZone DDAY 5 (TYPICAL)ERECT SLAB FORMS

  • EXAMPLEGROUND FLOOR(usually non-typical layout)CYCLE ON EACH FLOOR, THEN MOVE UP TO NEXT

    START AT FIRST TYPICAL FLOOR FLOORS with TYPICAL LAYOUT

  • Kumkang ALU-FORM CONSISTS OF ALUMINUM PANELS & COMPONENTS

  • Kumkang ALU FORMALU Wall Form

  • Standard Design for ALU Wall FormStandard Modular Panel Form Design

  • Steel ties connectto opposite panels as well control the Wall Thickness

  • START OF WALL ERECTION SEQUENCE . . .

  • LOAD-BEARING / SHEAR WALL BUILDING DESIGN

  • Column, Beam & Slab Design ( R.C Frame)

  • ALU DECK Form

  • Slab Formwork before re-bar

  • BEAMSLAB

  • Column, Bean & Slab Design

  • Easy Dismantling of panels

  • Steel / Aluminium Gang Formwork For External

  • FORMING THE STAIRS

  • Stair Form

  • Preview of past projects using Kumkang Alu Form

  • 4 Storey Apartment in Sabah

  • Project in Seoul, South Korea

  • Laya-Laya, Tuaran, Sabah, East MalaysiaSyarikat Perumahan Negara Berhads Affordable Housing Projects

  • Laya-Laya, Tuaran, Sabah, East MalaysiaSyarikat Perumahan Negara Berhads Affordable Housing Projects

  • Break down of Formwork System to be Delivered at TajuraSub-basement Footings = 6 setsTransfer Floor ( Columns, walls and slab) = 6 setsTypical Floor ( Walls and Slabs) = 13 sets

  • Cycle Time of Formwork systemSub-basement --- 7 days in one Building after move to next buildingTransfer floor --- 8 days in one Building and move to next BuildingTypical Floor (1F to Roof floor) --- 5 days per floor, total = 20 days per Building and move to next buildings

  • ---THE END---

    ************************************