Page 1: L Management & Asset Optimization

1

** not what the Urban Dictionary defines LMAO

Lifecycle Management & Asset Optimization

Page 2: L Management & Asset Optimization

The 3 Things You Will Learn

Know What You Have

Don’t Wait Until It Breaks

What’s Your Story

2

Page 3: L Management & Asset Optimization

Do You Know What You Have?

• Utility Inventory• Age• Material• Diameter• Length

• Utility Assessment• Condition• Capacity• Work Order History

3

Page 4: L Management & Asset Optimization

GPS Field Inventory

• Survey-Quality GPS Data Collection

• X,Y, and Z (elevation data)

• Geometric Network Analysis

• QA/QC by Professional Surveyors

4

Page 5: L Management & Asset Optimization

Field Assessment

• Industry Standard Practices• Visual• Non-Destructive• Sensor Technologies• Leak Detection• NASSCO (Sewer)

• ArcGIS Collector

• LGIM Schema

5

Page 6: L Management & Asset Optimization

NASSCO

6

• NASSCO Assessment• PACP• MACP• LACP

• NASSCO Inspection• Manhole Rehab• CIPP

Page 7: L Management & Asset Optimization

Don't Wait Until It Breaks

• Predictive

• Proactive (not reactive)

• Anticipated Service Life

• Understanding Life Cycle

7

Page 8: L Management & Asset Optimization

< 107%

10-2019%

20-3066%

30-406%

40+2%Pipe Age

8

Age Range Miles< 10 15.8 10-20 42.720-30 150.430-40 13.840 + 5.5Total 228 miles

Service Life

Water Utility Pipe Age and ASL

Pipe Material MSL ASL % of PipeCast Iron 50-100 75 32%Ductile Iron 75-125 100 3%Galvanized Iron 40-60 50 1%Polyvinyl Chloride 50-150 100 55%Asbestos Cement 75-125 100 9%

Page 9: L Management & Asset Optimization

Asset Lifecycle

New 20Years

40Years

60Years

80Years

100Years

120Years

Medium

Significant

High

Extreme

Low

Likelihood of Failure

Page 10: L Management & Asset Optimization

Asset Lifecycle

Medium

Significant

High

Extreme

Low

New 20Years

40Years

60Years

80Years

100Years

120Years

AssetRehabilitation

Likelihood of Failure

Page 11: L Management & Asset Optimization

Risk Matrix Exercise

11

Page 12: L Management & Asset Optimization

• Likelihood of Failure• ???• ???• ???

• Consequence of Failure• ???• ???• ???

Risk Matrix Exercise

12

Page 13: L Management & Asset Optimization

• Age• Material• Velocity• Depth• Past Work Orders

What Do You Think?

Likelihood of Failure

13

Page 14: L Management & Asset Optimization

• Public Spaces• High Traffic Areas• Medical / School Facilities• Customers Impacted• Adjacent Infrastructure• Environmental Impact• High Visibility

What Do You Think?

Consequence of Failure

14

Page 15: L Management & Asset Optimization

• Likelihood of Failure - Age• <10 =0• 10-30 = 1• 30-50 = 2• 50-70 = 4• 70 > = 6

• Likelihood of Failure - Material• ACP = 1.5• CIP = 2• DIP = 1• PVC = 0.5

• Likelihood of Failure – Past Work Orders• 0-5 WO = 1• 5 - > = 2

Risk Matrix ExerciseMax Score of 10

15

Page 16: L Management & Asset Optimization

• Consequence of Failure - Customers Impacted• <10 = 0• 10-30 = 1• 30-100 = 2• 100-1,000 = 4• 1,000 > = 6

• Consequence of Failure – Environmental• Private Property = 0.5• Adjacent Stream = 1• Wetland = 1• Endangered Species = 1

• Consequence of Failure – Medical / School Facilities• Yes = 1• No = 0

Risk Matrix ExerciseMax Score of 10

16

Page 17: L Management & Asset Optimization

Criticality Matrix Exercise

17

Page 18: L Management & Asset Optimization

GIS Geoprocessing

• SQL Select• Attributes• Calculate Values

• Geoprocessing• Intersect• Spatial Select

• Database Summary• Calculate

18

Pipe #1034Customers = 6Stream = 1Critical = 1Species = 1

Total = 9

Total = 36

Pipe #1034Age = 2Material = 1WO = 1

Total = 4

Page 19: L Management & Asset Optimization

Risk MatrixTemplate

19

Pipe #1034 Criticality Score

36

Page 20: L Management & Asset Optimization

Risk MatrixTemplate(Non-weighted)

20

Criticality Composite Score

Score of 366*6 = Significant Risk9*4 = Significant Risk4*9 = Significant Risk

Page 21: L Management & Asset Optimization

Risk MatrixTemplate(Weighted for Consequence)

21

Criticality Composite Score

Score of 366*6 = Medium Risk

9*4 = Consequence Weighted4*9 = Likelihood Weighted

Page 22: L Management & Asset Optimization

22

386 Miles ofSewer Utility

Page 23: L Management & Asset Optimization

Criticality MatrixBy Length

23

Level of Service Composite ScoreBy Linear Foot

Score of 36 = 16,458 LFMedium = 10,222 LF

Significant = 6,236 LF

Page 24: L Management & Asset Optimization

Criticality ScoreMap by Color

24

36

Page 25: L Management & Asset Optimization

Depreciated Value vs. Replacement Cost

25

$87.9M$153.2M

Existing Sewer Depreciated Value

Complete Sewer Replacement Cost

Page 26: L Management & Asset Optimization

Required Rehab / Replacement Funding

2020 2040 2060 2080 2100 2120< 1M

20M

40M

60M

80M

0M

2M

4M

6M

8M

$1.9M / YRRehab Budget

$2.9M / YR20 YR Deferred Budget

@ 3.68% Inflation

Page 27: L Management & Asset Optimization

Deferred Maintenance Annual Escalation

27

$1.9M

$2.9M

Annual Rehab Budget Contribution

20 YR DeferredBudget Contribution

(3.68% avg. annual inflation)

+ $19M of Deferred Replacement

Page 28: L Management & Asset Optimization

What Did You Learn?

Know What You Have

Don’t Wait Until It Breaks

What’s Your Story

28

Page 29: L Management & Asset Optimization

Do You Know What You Have?

• Utility Inventory• Age• Material• Diameter• Length

• Utility Assessment• Condition• Capacity• Work Order History

29

Page 30: L Management & Asset Optimization

Don't Wait Until It Breaks

• Predictive

• Proactive (not reactive)

• Anticipated Service Life

• Understanding Life Cycle

30

Page 31: L Management & Asset Optimization

31

Page 32: L Management & Asset Optimization

32