L1622Terminal A Improvements
Consultant BriefingMay 7, 2019
• Interior improvements in main terminal and satellite terminal– Nursing Room– Pet Relief– Refresh Bar
• Reconfiguration and improvements at the security checkpoint
• New elevator construction• Study of post-security connectivity potential between:
– Terminal A and Terminal B– Terminal A and Terminal E
L1622Terminal A Improvements
PROJECT SCOPE
L1622Terminal A Improvements
Evaluate Post-Security A-E Connection Opportunities
Evaluate Post-Security A-B Connection Opportunities
Various Terminal A Improvements
L1622Terminal A Improvements
Security Checkpoint Elevator Relocation
L1622Terminal A Improvements
Terminal A-B Connection Evaluation
L1622Terminal A Improvements
Terminal A Amenity Improvements
L1622Terminal A Improvements
Terminal A Amenity Improvements
L1622Terminal A Improvements
Design Team Selection Process
Note dates are subject to change.
Supplemental Package
Available:05-01-2019
Consultant Briefing:
05-07-2019
Deadline For Written
Questions:05-17-2019
Official Answers
Published:05-24-2019
RFQ Submissions
Due:06-13-2019
• Current level of experience and knowledge of the team for similar projects, particularly the Project Manager,
• Geographic location and availability of the Project Manager, resident inspectors and other key personnel to be assigned to the project,
• Experience and expertise of sub-consultants, • Development of a BIM Model and management of a BIMxP (BIM Execution Plan) in
support of Design and Construction.• Demonstrated experience in Lean Planning, Lean Construction and long-term
experience working collaboratively with CMs selected early in the design phase.• Demonstrated ability to perform work with minimal disruption to airport operations,• Familiarity with MGL, including filed sub-bid experience, • Cost management and scheduling capabilities, • M/WBE and affirmative action efforts, please indicate the proposed % of M/WBE
participation • Current level of work with the Authority, and past performance for the Authority, if
any, • Experience with sustainable design concepts and resiliency, and • Project understanding and technical approach to this project.
L1622Terminal A Improvements
Consultant Evaluation Criteria
• Cover letter with items below highlighted• Current Statement of Qualifications response to A/E and Related
Services questionnaires SF 330 with appropriate number of Part IIs• M/WBE Certification of the prime and sib-consultants shall be current
at the time of submittal w/ copy of the M/WBE certification letter from the Supplier Diversity Office
• Prime Consultant must satisfy requirements of Chapter 7C, Section 44 of MGL including Firm’s Board of Directors majority registered in MA.
• Consultant’s responsible for technical disciplines must be registered in MA.
• Separate sealed envelope of litigation and legal proceedings information. See www.massport.com for more detail on requirements.
• Insurance Requirements
L1622Terminal A Improvements
Submission Requirement Highlights From RFQ
• Consultants agree to accept the terms and conditions of Massport’s standard work order agreement, found on the Authority’s web page at www.massport.com
• One (1) Original and Fourteen (14) copies of a bound document
• One (1) PDF electronic copy on a disc• Due: 12:00 Noon on Thursday, June 13, 2019
L1622Terminal A Improvements
Submission Requirement Highlights From RFQ
Questions may be sent via email to:[email protected]
Questions due:Friday, May 17, 2019 - 12:00 Noon
Official answers will be published: Friday, May 24, 2019 (Estimated)
Solicitation: Close Date/Submission Deadline Thursday, June 13, 2019 - 12:00 noon
L1622Terminal A Improvements
Schedule Milestones RFQ
Questions?
L1622Terminal A Improvements