1
Laboratory and Office Fit-Out £1.8m Wolverhampton 26 weeks We are employed by the client to undertake the fit-out of the client’s new two- storey building extension to house new food and water tesng laboratories. Working within a tradional contract with some design porons, we are compleng the project in six phases across 26 weeks. Each phase to be completed on me to accommodate the hygienic clean and decant within a defined mescale so producvity remains at full capacity throughout. We are working in a live environment, adjacent to live working laboratories. In addion to programme, key priories are quality of workmanship, health and safety standards and cleanliness to avoid contaminaon. Works included: Mechanical and electrical installaons Hygienic clad walls New ceilings and floors Cold room installaon Incubator installaons New laboratories New office installaon and layout £

Laboratory and Office Fit-Out - adi Groupadiltd.co.uk/wp-content/uploads/2017/05/adi-Case-Studies... · 2018-08-07 · Laboratory and Office Fit-Out £1.8m Wolverhampton 26 weeks

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Laboratory and Office Fit-Out - adi Groupadiltd.co.uk/wp-content/uploads/2017/05/adi-Case-Studies... · 2018-08-07 · Laboratory and Office Fit-Out £1.8m Wolverhampton 26 weeks

Laboratory and Office Fit-Out

£1.8m

Wolverhampton

26 weeks

We are employed by the client to undertake the fit-out of the client’s new two-storey building extension to house new food and water testing laboratories.

Working within a traditional contract with some design portions, we are completing the project in six phases across 26 weeks. Each phase to be completed on time to accommodate the hygienic clean and decant within a defined timescale so productivity remains at full capacity throughout.

We are working in a live environment, adjacent to live working laboratories. In addition to programme, key priorities are quality of workmanship, health and

safety standards and cleanliness to avoid contamination.

Works included:• Mechanical and electrical

installations

• Hygienic clad walls

• New ceilings and floors

• Cold room installation

• Incubator installations

• New laboratories

• New office installation and layout

£