Upload
philomena-brooks
View
215
Download
0
Embed Size (px)
Citation preview
LAGUNA meetingLAGUNA meetingSeptember 7 - 10, 2010
CAES – CNRS – Aussois - FRANCE
Prospective Proton Drivers for Prospective Proton Drivers for neutrino facilities at CERNneutrino facilities at CERN
8/09/2010
R. Garoby
R.G. 7/09/20102
OUTLINEOUTLINE IntroductionIntroduction Plan for the injectors of LHCPlan for the injectors of LHC Plan for the SPLPlan for the SPL Summary of optionsSummary of options
R.G. 7/09/20103
IntroductionIntroduction
R.G. 7/09/20104
Outcome of Chamonix 2010Outcome of Chamonix 2010• Until the end of 2009 the favored scenario for the LHC luminosity upgrade
included the construction of new injectors (LP-SPL and PS2) to replace the PSB and PS, plus the upgrade of the SPS.
• During the Chamonix 2010 workshop, an alternative scenario was sketched, based on extensive consolidation and upgrade of the existing accelerators. That was associated with: an updated planning of increase of performance of the LHC a lessening of the required beam characteristics the statement that the cost of constructing the new accelerators would not be
affordable.
• As a result, a revised Scientific Strategy was prepared and included in the Medium Term Plan (approved by the Finance Committee in its August version). It includes: the continuation of Linac4, the systematic consolidation and upgrade of the existing accelerators to make
them able to fulfil reliably the needs of the High Luminosity LHC until ~2030, the conclusion of the PS2 and LP-SPL studies at short term, with the publication
of a “light” CDR to allow for resurrecting the option if necessary at a later date, “generic” R & D for a high power SPL in view of neutrino applications.
R.G. 7/09/20105
Plan for the injectors of LHCPlan for the injectors of LHC
R.G. 7/09/20106
Linac4Linac4Li
nac4
Lina
c4
Goals
Although it is designed to be capable of becoming the low energy front end of the SPL, the present (and only approved) goals of Linac4 are:
- to replace Linac2 (50 MeV protons, operational since 1979)- to double the potential brightness achievable by the PS Booster.
R.G. 7/09/20107
Linac4: main characteristics Linac4: main characteristics
Structures and klystrons dimensioned for 50 Hz Power supplies and electronics dimensioned for 2 Hz, 1.2 ms pulse.
Re-use of LEP RF components: klystrons, waveguides, circulators.
Ion species H−
Output Energy 160 MeVBunch Frequency 352.2 MHzMax. Rep. Rate 2 HzMax. Beam Pulse Length 1.2 msMax. Beam Duty Cycle 0.24 %Chopper Beam-on Factor 65 %Chopping scheme:
222 transmitted /133 empty bucketsSource current 80 mARFQ output current 70 mALinac pulse current 40 mAN. particles per pulse 1.0 × 1014
Transverse emittance 0.4 mm mrad
Max. rep. rate for accelerating structures: 50 Hz
160/50 MeV factor 2 in 2) same tune shift with twice the intensity.
Chopping at low energy to reduce beam loss in PSB.
H- charge exchange injection and painting in PSB
Lina
c4Li
nac4
R.G. 7/09/20108
CCDTL PIMS
3MeV
50MeV 94MeV 160MeV
Drift TubeLinac
18.7 m3 tanks3 klystrons4.7 MW111 PMQs
Pi-Mode Structure
22 m12 tanks8 klystrons~12 MW12 EMQuads
Cell-Coupled Drift TubeLinac25 m21 tanks7 klystrons7 MW21 EMQuads
RF accelerating structures: 4 types (RFQ, DTL, CCDTL, PIMS)Frequency: 352.2 MHzDuty cycle: 0.1% phase 1 (Linac4), 3-4% phase 2 (SPL), (design: 10%)
Linac4: 80 m, 18 klystrons
Ion current:40 mA (avg.),65 mA (peak)
CHOPPERRFQ
Chopper & Bunchers3.6 m11 EMquad3 cavities
Radio FrequencyQuadrupole3 m1 Klystron550 kW
H-
3MeV45keV
RF volumesource(DESY)45 kVExtrac.
DTL
Linac4: Block diagramLinac4: Block diagramLi
nac4
Li
nac4
R.G. 7/09/20109
Linac4: layoutLinac4: layout
9
• Linac4 is a normal-conducting H− linac at 160 MeV energy, made of 4 types of 352 MHz accelerating structures, matched to the increasing beam energy. A beam chopper at low energy allows modulating the linac beam pulse to minimise losses in the ring. A beam dump at linac end allows setting-up of the beam, will be displaced when connecting to the SPL.
• The Linac4 project includes important modifications to the PSB injection region (higher injection energy, H- stripping).
Linac4 tunnel and surface equipment building
160 MeV
100 MeV
50 MeVLina
c4
Lina
c4
R.G. 7/09/201010
Milestones
• End CE works: December 2010
• Infrastructure:2011
• Installation:2011 - 2012
• Commissioning: 2013 - 2015
• Modifications PSB: shut-down 2015/16
• On-line for physics:
2016
ID Task Name
1 Linac4 project start
2 Linac systems
3 Source and LEBT construction, test
4 Drawings, material procurement
5 RFQ construction and commissioning
6 Accelerating structures construction
7 Klystron prototype production
8 Klystrons production
9 Transfer line construction and installation
10 Magnets construction
11 Power converters construction
12 Building and infrastructure
13 Building design and construction
14 Infrastructure installation
15 PS Booster systems
16 PSB injection elements construction
17 Installation and commissioning
18 Test stand operation
19 Cavities testing, conditioning
20 Cabling, waveguides installation
21 Accelerator installation
22 Klystrons, modulators installation
23 Hardware tests
24 Front-end commissioning
25 DTL1 commissioning
26 Linac accelerator commissioning
27 Transfer line commissioning
28 PSB modifications
29 PSB commissioning with Linac4
30 PSB beam ready for PS
01/01
01/04
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32008 2009 2010 2011 2012 2013 2014
Linac4: planningLinac4: planning
2013 -
20152016
?
Lina
c4
Lina
c4
R.G. 7/09/201011
PSB, PS and SPSPSB, PS and SPS
Objectives
• Until the implementation of HL-LHC in the LHC (~2020), guarantee the availability of beam with adequate characteristics at injection (possibly beyond nominal),
• As soon as HL-LHC is implemented and for as long as it will operate (~2030), guarantee that the beam delivered by the injectors will meet its needs
PS
B,
PS
and
SP
SP
SB
, P
S a
nd S
PS Extensive
&continuous
consolidation
Upgrade
R.G. 7/09/201012
PSB & PS upgradesPSB & PS upgradesIncrease of the PS brightness up to the level required by HL-LHC (including
margin for beam loss in the successive accelerators), by increasing the transfer energy from PSB to PS, and implementing all the necessary improvements in the PS
PS
B,
PS
and
SP
SP
SB
, P
S a
nd S
PS
• New power supplies (PSB dipoles and transfer line)• New magnets (transfer line)• Upgrade of RF power systems (beam loading etc.)• Additional beam instrumentation• Cures against collective effects• Cures/mitigation measures against e-clouds• More feedback loops…
R.G. 7/09/201013
SPS upgradesSPS upgrades
Increase of the SPS brightness and maximum intensity up to the level required by HL-LHC (including margin for beam loss in transfer line and LHC)
PS
B,
PS
and
SP
SP
SB
, P
S a
nd S
PS
• Treatment of vacuum chamber (reduction of SEY)• Upgrade of RF power systems (increased RF power etc.)• Impedance reduction (kickers, cavities, etc.)• Cures against collective effects (damping systems)• Upgrade of beam dump• Upgrade of beam instrumentation• Collimators (?)• ?
R.G. 7/09/201014
Plan for the SPLPlan for the SPL
R.G. 7/09/201015
•Prepare for future potential physics programmes (Neutrinos, RIB)
•Update CERN generic competences in superconducting RF
•Synergy with other applications outside of CERN
SP
L R
& D
SP
L R
& D
Motivation for the SPL R & DMotivation for the SPL R & D(1/2)(1/2)
R.G. 7/09/201016
• Preserve the possibility of new injectors at long term
PSB
SPS
Linac4
LP-SPL
PS
LHC / sLHC
160 MeV
1.4 GeV4 GeV
26 GeV50 GeV
450 GeV
7 TeV
Linac250 MeV
Proton flux / Beam power
PS2
1978
1975
1959
2008
LP-SPL: Low Power-Superconducting Proton Linac PS2: High Energy PS (~ 5 to 50 GeV – 0.3 Hz)sLHC: “Super-luminosity” LHC (up to 1035 cm-2s-1)
PS2
SPL
LINAC4
SPS
PS
Motivation for the SPL R & DMotivation for the SPL R & D(2/2)(2/2)
SP
L R
& D
SP
L R
& D
R.G. 7/09/201017
Option 1 Option 2
Energy (GeV) 2.5 or 5 2.5 and 5
Beam power (MW)2.25 MW (2.5 GeV)
or
4.5 MW (5 GeV)
5 MW (2.5 GeV)
and
4 MW (5 GeV)
Protons/pulse (x 1014) 1.1 2 (2.5 GeV) + 1 (5 GeV)
Av. Pulse current (mA) 20 40
Pulse duration (ms) 0.9 1 (2.5 GeV) + 0.4 (5 GeV)
2 beam current 2 nb. of klystrons etc .
SPL: main characteristicsSPL: main characteristics
Re-use of LEP RF components in Front-end (Linac4)
Ion species H−
Output Energy 5 GeVBunch Frequency 352.2 MHzRepetition Rate 50 HzHigh speed chopper < 2 ns(rise & fall times)
Required for muon production (Neutrino Factory)
Required for flexibility and low loss in accumulator
Required for low loss in accumulatorGeneral features
Options
SP
L R
& D
SP
L R
& D
R.G. 7/09/201018
SC-linac [160 MeV 5 GeV] with ejection at intermediate energy
Length: ~500 m
Medium cryomodule
High cryomodules
Ejec
tion
9 x 6=0.65 cavities
11 x 8=1 cavities
13 x 8=1 cavitiesto
EURI
SOL
Debunchers
To H
P-PS
2 an
d/or
Acc
umul
ator
High cryomodules
From
Lin
ac4
0 m0.16 GeV
110 m0.73 GeV
291 m2.5 GeV
500 m5 GeV
SPL: Block diagramSPL: Block diagramS
PL
R &
DS
PL
R &
D
R.G. 7/09/201019
Frequency/temperature:
704 MHz and 2 K,
Accelerating gradient (=1 cavity): 25 MV/m “on average” (= with a high yield) is very challenging and may be costly (in terms of reprocessing), 20 MV/m seems more achievable but will have an impact on linac length (or energy).
High-power RF cavity tests of fully equipped High-power RF cavity tests of fully equipped cryo-modules are mandatory for realistic SPL cryo-modules are mandatory for realistic SPL layout estimates!!layout estimates!!
Ref.: Assessment of the basic Parameters of the CERN SPL, CERN-AB-2008-067-BI-RF,http://cdsweb.cern.ch/record/1136901/files/CERN-AB-2008-067.pdf
Cavities parametersCavities parametersS
PL
R &
DS
PL
R &
D
R.G. 7/09/201020
Medium cryomodule
High cryomodule
Energy range: 160 MeV – 732 MeV5 cell cavitiesGeometrical : 0.65Maximum energy gain: 19.4 MeV/m54 cavities (9 cryomodules)Length of medium section: ~110.35 m
Energy range: 732 MeV – 5 GeV5 cell cavitiesGeometrical : 1Maximum energy gain: 25 MeV/m192 cavities (24 cryomodules)Length of high section: ~360 m
Energy gain (MeV/m)
1
5
1
0
1
5
Position (m)
100 200 300 400
CryomodulesCryomodulesS
PL
R &
DS
PL
R &
D
R.G. 7/09/201021
Prototype cryomodulePrototype cryomodule
P.Coelho Moreira de Azevedo
SP
L R
& D
SP
L R
& D
R.G. 7/09/201022
Coordinator External partners
RF hardware (low level & high power)
E. Ciapala Cockcroft Institute, ESS + (FNAL, SNS, JLAB, ANL)
Cavities (structures & auxiliary equipment)
W. Weingarten CEA-Saclay, CNRS-Orsay, TRIUMF, Stony Brook + (JLAB, SNS)
Cryomodule (cryostat & cryogenics) V. Parma CEA-Saclay, CNRS-Orsay, Stony Brook + (FNAL)
Beam dynamics (beam parameters) A. Lombardi CEA-Saclay, TRIUMF, Soltan Institute, ESS
Architecture (layout & geometry, extraction, transfer)
F. Gerigk
Surface treatment and vacuum S. Calatroni
Mechanical design and construction
O. Capatina
Working Groups
Study leader: R. Garoby
OrganizationOrganization
Structured storage for all SPL documentation in EDMS Structured filing of all SPL meetings and workshops in Indico Structured filing of all collaboration meetings in Indico
SPL Collaboration
SP
L R
& D
SP
L R
& D
R.G. 7/09/201023
R & D subjects until 2015R & D subjects until 2015
(in continuity with the work previously done for the LP-SPL)
•R & D towards a high duty cycle H- source (continuation after end of SLHC-PP ?)
•Study of the optimum high power RF architecture for a high power SPL
•Design, construction and test of superconducting RF cavities(704 MHz – 5 cells – =1)
•Development of high power RF coupler, HOM damper and adaptation of tuner
•Upgrade of the SM18 test place [2 K cooling + pulsed RF source at704 MHz (1 MW @ 50 Hz )]
•Pulsed high power RF tests of contiguous cavities in a single cryostat
•Design, construction and test a high power klystron modulator
•Design, construction and test of a prototype cryomodule equipped with 8 =1 cavities
Treated in sLHC-PP
Partly addressed in
sLHC-PP
Partly addressed in
“EuCARD”Partly
supported by French “in-kind”
contrib.Partly
supported by ESS
Org
aniz
atio
n an
d pl
anni
ngO
rgan
izat
ion
and
plan
ning
R.G. 7/09/201024
Planning for cavities and Planning for cavities and cryomodulecryomodule
2011 2012 2013 2014 2015
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4SM18 - 2K Cryogenics
Vcryo.
X
SM18modulator
1 2
SM18 - 704 MHz High Power RF X
High Power RF couplers
4 >4 >8
Superconductingcavities
>4 >8
Assembled string of 4 cavities
X
Horiz. short cryom. (4 cav.)
X
Equipped horiz. short cryom.
X
High power RF tests in short cryo.
X
Assembled string of 8 cavities X
8 cavities cryomodule
X
Equipped cryomodule
X
High power RF tests in full CM
X
From ESS CERN design
~ In-phase with ESS
design update
SP
L R
& D
SP
L R
& D