Upload
buithuan
View
217
Download
0
Embed Size (px)
Citation preview
FINAL
ENVIRONMENTAL LAND USE CONTROL IMPLEMENTATION PLAN
FOR
DEFENSE SUPPLY CENTER RICHMOND
RICHMOND, VIRGINIA
Prepared For
Defense Logistics Agency
And
Defense Supply Center Richmond
November 2008
Revision 3
FINAL
ENVIRONMENTAL
LAND USE CONTROL IMPLEMENTATION PLAN
FOR
DEFENSE SUPPLY CENTER RICHMOND RICHMOND, VIRGINIA
Prepared for:
Air Force Center for Engineering and the Environment
And
Defense Supply Center Richmond
And
Defense Logistics Agency
Updated by:
Earth Tech AECOM
November 2008 Revision 3
Final Environmental Land Use Control Implementation Plan November 2008 Defense Supply Center Richmond Rev 3
TABLE OF CONTENTS
Page
EXECUTIVE SUMMARY ..................................................................................................................ES-1
1.0 INTRODUCTION ......................................................................................................................1-1 2.0 LAND USE CONTROL PERFORMANCE OBJECTIVES ..................................................2-1 3.0 LAND USE RESTRICTIONS ...................................................................................................3-1 4.0 LAND USE CONTROLS...........................................................................................................4-1
4.1 ACCESS RESTRICTIONS .............................................................................................4-1 4.2 LEASE RESTRICTIONS................................................................................................4-1 4.3 PROPERTY TRANSFER RESTRICTIONS ..................................................................4-1 4.4 NOTICE OF LAND USE RESTRICTIONS...................................................................4-2 4.5 ZONING RESTRICTIONS.............................................................................................4-2 4.6 PRECONSTRUCTION ASSESSMENTS.......................................................................4-3 4.7 MAINTENANCE AND MONITORING........................................................................4-3 4.8 GROUNDWATER MONITORING ...............................................................................4-3 4.9 GROUNDWATER WELL RESTRICTIONS.................................................................4-3 4.10 ENGINEERING CONTROLS FOR INDOOR AIR QUALITY ....................................4-4
5.0 MONITORING...........................................................................................................................5-1 5.1 ANNUAL SITE INSPECTION.......................................................................................5-1 5.2 FIVE-YEAR LAND USE CONTROL VERIFICATION ...............................................5-1
6.0 MODIFICATION OF LAND USE CONTROLS ....................................................................6-1 7.0 ENFORCEMENT OF LAND USE CONTROLS ....................................................................7-1 8.0 COMPREHENSIVE ENVIRONMENTAL RESPONSE, COMPENSATION, AND
LIABILITY ACT FIVE-YEAR REVIEW ...............................................................................8-1 9.0 TERMINATION.........................................................................................................................9-1
i
Final Environmental Land Use Control Implementation Plan November 2008 Defense Supply Center Richmond Rev 3
LIST OF FIGURES
Figure
1 Operable Units at DSCR
2 DSCR Land Use Classifications
3 Defense Supply Center Richmond (DSCR) Annual Site Inspection Form
LIST OF APPENDICES
Appendix
A Land Use Controls for Operable Unit 1: Open Storage Area
B Land Use Controls for Operable Unit 3: National Guard Area Soils
C Land Use Controls for Operable Unit 12: Former Pesticides Building 112
D Land Use Controls for Operable Unit 8: Acid Neutralization Pits Groundwater
E Land Use Controls for Operable Unit 10: Building 68
F Land Use Controls for Operable Unit 11: Transitory Shelter 202
G Land Use Controls for Operable Unit 2: Area 50 Landfill
H Land Use Controls for PX Gas Station
ii
Final Environmental Land Use Control Implementation Plan November 2008 Defense Supply Center Richmond Rev 3
LIST OF ACRONYMS
CERCLA Comprehensive Environmental Response, Compensation, and Liability Act
DES DLA Enterprise Support
DLA Defense Logistics Agency
DSCR Defense Supply Center Richmond
DSCR-SDE Environment, Safety and Health Office operated under DLA Enterprise Support Richmond
DoD Department of Defense
ERP Environmental Restoration Program
ESD Explanation of Significant Difference
FFA Federal Facility Agreement
LUC Land Use Control
LUCIP Land Use Control Implementation Plan
MCL Maximum Contaminant Level
NPL National Priorities List
OSA Open Storage Area
OU Operable Unit
PESA Preliminary Environmental Site Assessment
POL Petroleum, Oils and Lubricants
PX Post Exchange
RAO Remedial Action Objective
ROD Record of Decision
USEPA U.S. Environmental Protection Agency
VDEQ Virginia Department of Environmental Quality
iii
Final Environmental Land Use Control Implementation Plan November 2008 Defense Supply Center Richmond Rev 3
EXECUTIVE SUMMARY
This Environmental Land Use Control Implementation Plan (LUCIP) was developed to describe land use
controls (LUCs) at Defense Supply Center Richmond (DSCR) operable units (OUs) for which a Record
of Decision (ROD) has been issued. The LUCIP is part of the remedial design phase. LUCs have been
specified at OUs where residual concentrations could be unsafe for unrestricted use or unrestricted
exposure.
Land use restrictions to meet performance objectives at DSCR OUs include the following:
• No residential land use or childcare facilities at specified OUs remediated to industrial risk-based levels.
• Access restrictions and preconstruction assessments at specified OUs.
• Restrict potable use of groundwater at the installation.
• No drilling groundwater wells at OUs or off the installation property where groundwater exceeds maximum contaminant levels (MCLs), Virginia Department of Environmental Quality (VDEQ) drinking water standards, or risk based-levels (where standards do not exist).
• Conduct indoor air monitoring at OUs with volatile organic compounds in groundwater. Implement vapor controls (e.g. air exchange, venting, barriers), if necessary.
Specific LUCs include access restrictions; lease restrictions, if property is leased to a non-military third
party; deed restrictions and land use notices, if the property is transferred out of federal ownership; zoning
restrictions, if the property is leased or transferred out of federal ownership; preconstruction assessments;
maintenance and monitoring; and groundwater well installation/use restrictions.
The LUCIP is an installation management tool that specifies LUCs, how they will be documented, and
how they will be maintained and managed. Procedures to modify the LUCIP if conditions change are
outlined. Annual site inspections and provisions for five-year reviews in accordance with the
Comprehensive Environmental Response, Compensation and Liability Act (CERCLA) are provided. The
responsibilities of the DSCR management office, along with review and approvals by the U.S.
Environmental Protection Agency and VDEQ are also provided.
ES-1
Final Environmental Land Use Control Implementation Plan November 2008 Defense Supply Center Richmond Rev 3 Specific LUCs by OU are provided in individual appendices. To date, OUs 1, 2, 3, 8, 10, 11 and 12 have
RODs that include LUCs, and these are included in this LUCIP. OUs 4, 5, and 9 do not have LUCs as
part of the remedy, and therefore are not included in this LUCIP. Appendices for other OUs will be
added if the final RODs specify LUCs. The LUCIP will be incorporated as an appendix to the DSCR
Master Plan to facilitate land use and planning.
In addition, this LUCIP includes the land use controls for the Post Exchange (PX) Gas Station site. Even
though this site is not under CERCLA, the land use controls for the site are included in this document to
ensure that they are implemented and continue to be protective.
ES-2
Final Environmental Land Use Control Implementation Plan November 2008 Defense Supply Center Richmond Rev 3
1.0 INTRODUCTION
This document presents the Land Use Control Implementation Plan (LUCIP) for the Defense Supply
Center Richmond (DSCR) installation, located approximately 8 miles south of Richmond, Virginia. The
installation is an active facility that occupies more than 600 acres. DSCR is the lead aviation center
within the Defense Logistics Agency (DLA), and it serves as a Department of Defense (DoD) operating
center for supply items. The installation was placed on the National Priorities List (NPL) in 1987. A
Federal Facility Agreement (FFA) between DSCR, the U.S. Environmental Protection Agency (USEPA),
and the Virginia Department of Environmental Quality (VDEQ) was signed in 1990. Thirteen operable
units (OUs) were designated for investigation and possible remediation under the Comprehensive
Environmental Response, Compensation and Liability Act (CERCLA) as amended. This LUCIP
describes the land use controls (LUCs), if any, at OUs for which a Record of Decision (ROD) has been
issued. The LUCIP is part of the remedial design phase, and the document will be updated as additional
RODs become available.
LUCs are physical, legal, or administrative restrictions to limit access where constituents remain in place
above permissible levels (namely, where residual concentrations are unsafe for unrestricted use or
unrestricted exposure). LUCs may be implemented in conjunction with other remedial measures and are
intended to protect human health and the environment after risk-based cleanup.
Physical LUCs are engineered remedies that include fences and signs. Administrative LUCs include
zoning and permitting. Legal LUCs, also referred to as “institutional controls,” include deed notices.
Federal mandates allow deed restrictions only for property transferred out of federal ownership.
However, deed restrictions are not applicable at this time because DSCR is an active installation under
DoD ownership. Deed restriction procedures are referenced herein for completeness in the event that
property transfer occurs in the future. In addition, no DSCR property is leased to third parties.
The LUCIP is an installation management tool that specifies LUCs, how they will be documented, and
how they will be maintained and managed. This LUCIP explains restrictions, outlines procedures to
modify the LUCIP if conditions change, and specifies the frequency and requirements for inspections.
Provisions for five-year reviews in accordance with CERCLA are included. The responsibility of the
management office within DSCR is described, along with review and approvals by USEPA and VDEQ.
1-1
Final Environmental Land Use Control Implementation Plan November 2008 Defense Supply Center Richmond Rev 3 The LUCIP will be incorporated as an appendix to the DSCR Master Plan to facilitate land use and
planning decisions.
Remediation at DSCR is organized into 13 OUs, as shown in Figure 1. Specific LUCs by OU are
provided in individual appendices, along with an associated map, LUC monitoring frequency, and
anticipated LUC duration. To date, OUs 1, 2, 3, 8, 10, 11 and 12 have RODs that include LUCs, and
these are summarized in Appendices A to F. OUs 4, 5, and 9 do not have LUCs as part of the remedy.
Appendices for the other OUs will be added if the final RODs specify LUCs.
In addition, this LUCIP includes the land use controls for the Post Exchange (PX) Gas Station site (see
Figure 1). Even though this site is not under CERCLA, the land use controls for the site are included in
this document to ensure that they are implemented and continue to be protective. No review and
approvals by USEPA and VDEQ are required for this site.
1-2
Final Environmental Land Use Control Implementation Plan November 2008 Defense Supply Center Richmond Rev 3
2.0 LAND USE CONTROL PERFORMANCE OBJECTIVES
The performance objectives of the LUCs are as follows:
1. Prevent dermal contact with, incidental ingestion of, and inhalation of volatiles/fugitive dust from surface soils above risk-based concentrations protective of an industrial or site worker.
2. Prevent dermal contact with, incidental ingestion of, and inhalation of volatiles from surface soil, subsurface soil, and shallow groundwater as well as inhalation of fugitive dust above risk-based concentrations protective of a construction worker.
3. Prevent ingestion of groundwater with concentrations above maximum contaminant levels (MCLs), VDEQ drinking water standards, or risk-based levels (where standards do not exist) from potential future wells drawing water from an OU-impacted aquifer.
4. Prevent ingestion of groundwater with concentrations above MCLs, VDEQ drinking water standards, or risk-based levels (where standards do not exist) from existing or potential future wells off the installation property.
5. Limit exposure to indoor air vapor intrusion from groundwater to current and potential future industrial workers at the OUs.
2-1
Final Environmental Land Use Control Implementation Plan November 2008 Defense Supply Center Richmond Rev 3
3.0 LAND USE RESTRICTIONS
The specific LUCs required by a remedy at DSCR are stated at Section 2.12.2 of the ROD for each OU,
and a summary of the LUCs required by those RODs are included as appendices to this LUCIP.
The following land use restrictions are required to meet the LUC performance objectives:
1. No residential land use or childcare facilities at the specified OUs remediated to industrial risk-based levels.
2. Access restrictions and preconstruction assessments at the specified OUs.
3. Restrict potable use of groundwater at the installation.
4. No drilling groundwater wells at OUs or off-the-installation property where groundwater exceeds MCLs, VDEQ drinking water standards, or risk-based levels (where standards do not exist).
5. Conduct periodic indoor air monitoring at OUs with volatile organic compounds in groundwater. Implement vapor controls (e.g., air exchange, venting, barriers), if necessary.
3-1
Final Environmental Land Use Control Implementation Plan November 2008 Defense Supply Center Richmond Rev 3
4.0 LAND USE CONTROLS
The LUCs include access restrictions, lease restrictions, property transfer restrictions, notice of land use
restrictions, zoning restrictions, preconstruction assessments, maintenance and monitoring, groundwater
monitoring, and groundwater well restrictions. A summary of the LUCs to be protective and meet
remedial action objectives (RAOs) is provided below.
4.1 ACCESS RESTRICTIONS
Access restrictions by fencing, warning signs, and guards are already in place. DSCR is a secure DoD
facility, and general access is restricted along the property boundary. A second layer of security exits in
some areas, as outlined for the individual OUs. Consequently, a dual security system is in effect in some
areas, including those areas with required restricted access pursuant to a ROD.
4.2 LEASE RESTRICTIONS
DSCR does not lease any property to third parties. In the event of future lease agreements, the lessee
would not be able to conduct subsurface excavation, digging, drilling, or other surface disturbance
without written approval from the DSCR-SDE (Environment, Safety and Health Office operated under
DLA Enterprise Support Richmond [DES]).
4.3 PROPERTY TRANSFER RESTRICTIONS
Property transfer out of federal ownership is not currently anticipated. However, if property transfer were
to occur in the future, it would be conducted in accordance with CERCLA Section 120(h), 42 U.S.C.
§ 9620(h) and any pursuant regulations. Any property transfer from the U.S. Army will include a
CERCLA Section 120(h)(3) covenant that will have descriptions of the residual contamination on the
property and the environmental use restrictions, expressly prohibiting activities inconsistent with the
performance measure goals and objectives.
The environmental restrictions are included in a section of the CERCLA 120(h) (3) covenant that the U.S.
Army is required to include in the deed for any property that has had hazardous substances stored for one
year or more, known to have been released, or disposed of on the property. Each deed will also contain a
reservation of property access for DLA, USEPA, and VDEQ, and their respective officials, agents,
4-1
Final Environmental Land Use Control Implementation Plan November 2008 Defense Supply Center Richmond Rev 3 employees, contractors, and subcontractors for purposes consistent with the DSCR Environmental
Restoration Program (ERP) or the FFA. The deed will contain appropriate provisions to ensure that the
restrictions continue to run with the land and are enforceable by DSCR. USEPA and VDEQ would
receive a draft copy of deed language for review and comment, and a copy of the final executed deed
would be mailed to both agencies. Deed restrictions would be filed with the Chesterfield County Circuit
Court, Deed Recording Department.
Notice to Transferee: Concurrent with the transfer of any deed from DSCR to transferee, information
regarding the environmental use restrictions and controls will be communicated in writing to the property
owners.
Notice to USEPA and VDEQ: DSCR will provide notice to USEPA and VDEQ at least six months prior
to any transfer or sale of OUs, including federal-to-federal transfers so that they can be involved in land
transfer notice, conveyance documents, and discussions. If a six-month notification is not possible, then
the agencies will be notified of property transfer as soon as possible, but not later than 60 days prior to
transfer.
4.4 NOTICE OF LAND USE RESTRICTIONS
In the event of property transfer, a notice would be filed with the deed. The notice would include a legal
description of the restricted area; the location and dimensions of areas of potential environmental concern
with respect to surveyed, permanent benchmarks; the general type, location, and quantity of regulated
hazardous constituents known to exist; and the specific restrictions on the current or future site use. The
Chesterfield County Circuit Court, Deed Recording Department, would file the notice and index it under
the property owner’s name. Copies of the notice would also be provided to the Chesterfield County
Planning Department and Zoning Enforcement Office.
4.5 ZONING RESTRICTIONS
As shown in the land use classification map (Figure 2), the most acreage-intensive DSCR activity is
storage (including warehousing). Residential development will not be allowed at the OUs remediated to
industrial risk-based levels. The Chesterfield County Planning Department/Zoning Enforcement Office is
responsible for zoning regulations. Currently, DSCR is zoned agricultural by the county. Local land use
ordinances would become applicable in the event that property was subleased to a non-military third
4-2
Final Environmental Land Use Control Implementation Plan November 2008 Defense Supply Center Richmond Rev 3 party. The county zoning regulations are referenced for informational purposes. DoD retains authority
for land use.
4.6 PRECONSTRUCTION ASSESSMENTS
Preconstruction assessments will be conducted before work begins. DSCR-SDE must be consulted
regarding utilities, buildings and grounds maintenance, construction, excavation, and permitting. The
DSCR-SDE must also be consulted regarding requirements for soil and groundwater assessments and
permitting.
4.7 MAINTENANCE AND MONITORING
Existing pavement, soil/vegetative covers and fencing will be maintained where outlined in the specific
OUs.
Monitoring in creeks will be conducted as specified for individual OUs. Other OU-specific monitoring
prior to construction may include groundwater and/or soil-gas sampling and analysis. Ambient air testing
and personnel monitoring will be conducted during construction where noted.
4.8 GROUNDWATER MONITORING
Groundwater monitoring will be conducted at specified OUs and adjacent areas. Constituents to be
analyzed and the anticipated timeframe vary by OU. DSCR-SDE should be consulted regarding
monitoring requirements.
4.9 GROUNDWATER WELL RESTRICTIONS
DSCR is a federal NPL site with groundwater above MCLs on-site and off-installation. In accordance
with the Chesterfield County Health Department, drinking water wells are not allowed within 100 feet of
new construction, septic/drain fields, or underground storage tanks. Potable groundwater wells must be
permitted with the Health Department before installation. VDEQ maintains a beneficial groundwater use
policy. Until off-installation areas meet MCLs, VDEQ drinking water standards, or risk-based levels
where standards do not exist, installation of new wells or consumptive use from existing wells within the
plume area would be prohibited. For groundwater-impacted OUs, a map of the plume where drinking
4-3
Final Environmental Land Use Control Implementation Plan November 2008 Defense Supply Center Richmond Rev 3 water wells should not be installed or used off the installation property should be forwarded to the
Chesterfield County Health Department when a ROD is finalized.
Groundwater will not be used for potable purposes on the installation. New groundwater wells will not
be drilled at OUs for productive use where MCLs, VDEQ drinking water standards, or risk-based levels
(where standards do not exist) are exceeded. Backup productive use of groundwater will continue (such
as for fire extinguishing) on an as needed and unrestricted basis. Groundwater plume maps are provided
with the specific OUs that address groundwater response actions.
4.10 ENGINEERING CONTROLS FOR INDOOR AIR QUALITY
Engineering controls may be used to limit exposure to indoor vapor intrusion from groundwater for
current and future industrial workers at specific OUs. Engineering controls that may be implemented
include, but are not limited to: a barrier, which may be either impervious or vented in such a way as to
prevent vapor intrusion; or the use of other appropriate measures such as negative/positive
exchange/ventilation systems. Indoor air monitoring may be performed to assure that the indoor air
quality meets applicable standards.
4-4
Final Environmental Land Use Control Implementation Plan November 2008 Defense Supply Center Richmond Rev 3
5.0 MONITORING
The U.S. Army owns the DSCR property, and there are no plans to transfer ownership. DSCR will
continue to operate the installation and will be responsible for LUC monitoring. The U.S. Army retains
the ultimate responsibility for the remedy integrity. The timing and nature of LUC monitoring are
specified below.
5.1 ANNUAL SITE INSPECTION
Until determined otherwise, DSCR-SDE will conduct annual site inspections (during the first quarter of
the year) to ensure that LUCs are effective and land use restrictions are being achieved. DSCR must sign
and certify that an inspection was performed at each OU that has LUCs, and the report of the inspection
will be sent to USEPA and VDEQ within 30 days of the inspection. An annual inspection checklist is
provided as Figure 3. These procedures will ensure that remedies at individual OUs will remain
protective. Annual Inspections will also be conducted at the PX Gas Station site.
5.2 FIVE-YEAR LAND USE CONTROL VERIFICATION
In accordance with CERCLA, Section 121(c), a five-year review will be conducted to assure that human
health and the environment are being protected by the remedy, including maintenance of the LUCs. The
annual site inspection forms will be used in preparation of the five-year review to evaluate the
effectiveness of the remedy.
Five-year reviews are not required for the PX Gas Station site.
5-1
Final Environmental Land Use Control Implementation Plan November 2008 Defense Supply Center Richmond Rev 3
6.0 MODIFICATION OF LAND USE CONTROLS
The LUCs outlined by specific OUs in the appendices are expected to remain in place until the
constituents in soil or groundwater are reduced to levels that allow for unlimited exposure and
unrestricted use. If conditions at the installation improve, land use objectives change, or remedial goals
are met, the parties agree to evaluate whether to modify or discontinue a particular LUC. For example, if
groundwater standards are met, groundwater use restrictions may no longer be necessary. Also, land use
restrictions may no longer be necessary for certain OUs if construction eliminates exposure and risk is
reduced.
DSCR will decide whether to modify or discontinue a LUC, with approval from USEPA and VDEQ.
Based on the FFA, USEPA and VDEQ have review and approval authority over primary documents. The
decision to modify or discontinue a LUC will be documented in a memorandum that will be placed in the
Administrative Record file. If the changes to a LUC are deemed significant and affect the remedy’s
scope, then DSCR may pursue an Explanation of Significant Difference (ESD) or an amendment to the
ROD. An ESD or ROD amendment would require review and concurrence by USEPA and VDEQ. A
public notice would be issued for proposed changes.
6-1
Final Environmental Land Use Control Implementation Plan November 2008 Defense Supply Center Richmond Rev 3
7.0 ENFORCEMENT OF LAND USE CONTROLS
Any activity that is inconsistent with the IC objectives or use restrictions, or any other action that may
interfere with the effectiveness of the ICs, will be addressed by DSCR as soon as practicable, but in no
case will the process be initiated later than 30 days after DSCR becomes aware of the breach. DSCR will
notify EPA and VDEQ as soon as practicable but no longer than 30 days after discovery of any activity
that is inconsistent with the IC objectives or use restrictions, or any other action that may interfere with
the effectiveness of the ICs. DSCR will notify EPA and VDEQ regarding how DSCR has addressed or
will address the breach within 30 days of sending EPA and VDEQ notification of the breach.
DSCR will notify EPA and VDEQ 45 days in advance of any proposed land use changes that may be
inconsistent with the LUC objectives or the selected remedy.
No notification to EPA and VDEQ is required for the PX Gas Station site.
7-1
Final Environmental Land Use Control Implementation Plan November 2008 Defense Supply Center Richmond Rev 3
8.0 COMPREHENSIVE ENVIRONMENTAL RESPONSE, COMPENSATION, AND LIABILITY ACT FIVE-YEAR REVIEW
As part of the CERCLA, Section 121(c), five-year remedy review, DSCR will prepare a report certifying
the continued effectiveness of the remedy, including LUCs. The report will include information
contained in the Annual Site Inspection Form, as well as an evaluation of the need to modify LUCs.
For the first five-year review, changes in site conditions due to constituent migration, construction,
natural attenuation, and/or remediation effectiveness will be evaluated. The evaluation will likely require
soil and/or groundwater sampling and analysis to provide new data. If conditions have changed and
LUCs are no longer needed, annual site inspections could occur less frequently, such as every five years.
Five-year reviews are not required for the PX Gas Station site.
8-1
Final Environmental Land Use Control Implementation Plan November 2008 Defense Supply Center Richmond Rev 3
9.0 TERMINATION
This LUCIP is part of the post-ROD remedial design documents for all OUs with final remedies including
land use controls and the Administrative Record file. The post-ROD remedial design is a primary
document under the FFA, and amendment of a primary document requires the concurrence of USEPA and
VDEQ. If conditions at the installation improve, land use objectives change, or RAOs are met such that
the LUCs become unnecessary, then continued implementation of the LUCIP will be evaluated.
Discontinuing implementation of any LUCs would be a significant change in the remedy. DSCR will not
modify or terminate LUCs or implementation actions without the concurrence of USEPA and VDEQ.
Any such decision would be documented in a closeout document, ESD, or ROD amendment and would
be added to the Administrative Record file.
9-1
Final Environmental Land Use Control Implementation Plan November 2008 Defense Supply Center Richmond Rev 3
FIGURES
APPROXIMATE EXTENTOF OU 6 PLUME
OU 1
APPROXIMATE EXTENTOF OU 7 PLUME
OU 3
OU 13
APPROXIMATE EXTENTOF OU 8 PLUME
OU 2
OU 4
OU 11
OU 12
OU 10
OU 5
OU 9
PX GASSTATION
P:g
is\p
roje
cts\
dscr
\rev
ised
_CS
M\m
xds\
site
_map
_zon
es.m
xd
PROJECT NO:
CHECKED BY:
PREPARED BY:
LAND USE CONTROL IMPLEMENTATION PLAN
OPERABLE UNITS AT DSCR
FIGURENUMBER:
DEFENSE SUPPLY CENTER RICHMONDRICHMOND, VIRGINIA
AIR FORCE CENTER FOR ENVIRONMENTAL EXCELLENCE
1
THP
6301-05-0016
JLK
0 1,000 2,000 3,000 4,000500
Scale in Feet
FALL
ING C
REE
K T
RIBUTA
RY
KINGSLAND CREEK
FALLING CREEK
LegendOPERABLE UNITS
INSTALLATION BOUNDARY
POND / RIVER
STREAMS
BUILDING
APPROXIMATE PLUME EXTENT
N O NAME CREEK
JAM
ES
RIV
ER
P:g
is\p
roje
cts\
dscr
\land
_use
_con
trol
\land
use.
mxd
PROJECT NO:
CHECKED BY:
PREPARED BY:
LAND USE CONTROL IMPLEMENTATION PLAN
DSCR LAND USE CLASSIFICATIONS
FIGURENUMBER:
DEFENSE SUPPLY CENTER RICHMONDRICHMOND, VIRGINIA
AIR FORCE CENTER FOR ENVIRONMENTAL EXCELLENCE
2
THP
6301-05-0016
JLK
0 1,000 2,000 3,000 4,000500
Scale in Feet
FALL
ING CR
EE
K T
RIB
UTAR
Y
KING SLAND CREEK
NO NAME CREEK
FALLING CREEK
LegendINSTALLATION BOUNDARY
POND / RIVER
STREAMS
LAND USE TYPEADMINISTRATIVE
COVERED STORAGE
FORMER RAIL YARD
GRASSY
HELI-PAD
MILITARY HOUSING
OPEN STORAGE
PARKING
WOODED
JAM
ES R
IVER
SOURCE:DSCR MASTER PLANJUNE 2005
Final Environmental Land Use Control Implementation Plan November 2008 Defense Supply Center Richmond Rev 3
FIGURE 3
DEFENSE SUPPLY CENTER RICHMOND (DSCR) ANNUAL SITE INSPECTION FORM
In accordance with the Environmental Land Use Control Implementation Plan (LUCIP) dated ____________ for DSCR, an inspection of Operable Unit (OU) ______ was conducted by ________________________________on ___________________(date). Refer to the OU-specific appendix of the Environmental LUCIP. Land use restrictions include the following:
• Access restrictions and preconstruction assessments at the OU. • No residential land use or child-occupied facilities including daycare at the OU. • No potable use of groundwater on the installation. • No installation of groundwater wells at the OU if concentrations exceed drinking water
standards or risk-based levels if standards do not exist. • Indoor air monitoring if volatile organic compounds are present in groundwater at the OU.
Verification that land use restrictions are being accomplished and LUCs remain effective:
• Verify that any boundary fence in the OU vicinity is intact.
• Verify that no residential housing, development, or child daycare activities are occurring at the OU.
• Verify that no groundwater wells have been installed at the OU (except for monitoring and injection wells that were installed as part of the remedy) and that no consumptive use of groundwater is occurring.
• Verify that applicable LUCs are intact, meet specifications, and/or are in good working order.
• Verify that vapor intrusion has not occurred in buildings.
• Inspect the vegetative covers at OU 10 and OU 11. Please note deficiencies/ corrective actions below:
Description of any intrusive activities that occurred in the past year:
[Provide a detailed summary of any intrusive activity that occurred in the past year and include the location where it was observed.]
Final Environmental Land Use Control Implementation Plan November 2008 Defense Supply Center Richmond Rev 3
FIGURE 3 (continued)
Description of any deficiency or violation of the land use restrictions:
[Provide a detailed summary of observations. If known, indicate a deficiency or violation. Include the location where a deficiency or violation was observed.]
Description of any proposed measures or corrective actions taken to remediate a deficiency or violation:
[Provide a detailed summary of any proposed measures that will be undertaken to mitigate or remediate the deficiency or violation. Indicate the timeframe for completing the necessary actions.]
Certification Statement:
I, the undersigned, document that the inspection was performed as indicated above, and that the above information is true and correct to the best of my knowledge and belief. I have reviewed the OU-specific appendix of the Environmental LUCIP to verify requirements and restrictions.
Name and Title_____________________________________________________
Signature:_________________________________Date:________________________
Final Environmental Land Use Control Implementation Plan November 2008 Defense Supply Center Richmond Rev 3 Within 30 days of the inspection, completed annual site inspection forms shall be sent to:
Defense Supply Center Richmond Attention: Mr. Mark Leeper 8000 Jefferson Davis Highway Richmond, Virginia 23297 Defense Logistics Agency Attention: Mr. Phil Dawson Environment and Safety (DES-E) 8725 John J. Kingman Road Suite 2639 Fort Belvoir, VA 22060-6221
U.S. Environmental Protection Agency, Region 3 Attention: Mr. Jack Potosnak 1650 Arch Street Philadelphia, PA 19103
Virginia Department of Environmental Quality Commonwealth of Virginia Attention: Mr. Jim Cutler Division of Waste Operations 629 East Main Street P.O. Box 10009 Richmond, VA 23240-0009
Final Environmental Land Use Control Implementation Plan November 2008 Defense Supply Center Richmond Rev 3
APPENDIX A
LAND USE CONTROLS FOR OPERABLE UNIT 1: OPEN STORAGE AREA
OPERABLE UNIT 1: OPEN STORAGE AREA
Operable Unit (OU) 1 is the Open Storage Area (OSA) occupying approximately 45 acres in the central
portion of the installation, as shown in Figure A-1. Institutional controls (IC) were specified as the most
appropriate option at this location in the April 1992 Record of Decision (ROD) and July 2007
Explanation of Significant Differences (ESD). IC objectives delineated in the ROD were to limit access
to impacted source area soils by establishing physical and institutional controls. The contaminants of
concern at OU 1 include PAHs and metals (Arsenic and Antimony). Risk-based soil action levels (1992
ROD) were exceeded for arsenic and antimony in one sample each and at depths greater than 5 feet.
Neither of these soil constituents exceeded maximum contaminant levels in groundwater. Exposure
would be anticipated only if excavation were undertaken.
The land use controls for OU 1 are:
Access Restrictions. The OSA will continue operation as a restricted area. Because Defense Supply
Center Richmond (DSCR) is a secured Department of Defense facility, access is already restricted. The
OSA is located within the tenant organization confines of the Defense Distribution Depot Richmond,
Virginia (DDRV), which has a separate fence along the western OU boundary. Additional
badging/clearance are required to enter the DDRV area. This additional security provides a layering of
controls and will continue to be maintained. Installation police conduct routine security checks of this
area. Access restrictions will be maintained as long as hazardous materials are stored in the OSA.
Preconstruction Assessment. Future industrial development, including excavation or site grading, is not
precluded. In the event of construction activities, applicable health and safety measures will be followed.
The DSCR-SDE (Environment, Safety and Health Office operated under DLA Enterprise Support
Richmond) must be consulted prior to excavation. DSCR-SDE will issue an environmental review
document, which will outline the contaminant data in the area of the construction activity.
For military construction projects within the OU 1 footprint, an environmental site assessment will be
conducted. The environmental assessment will be completed prior to project design and submitted to
DSCR-SDE for review. Monitoring will include soil (soil gas and groundwater, if applicable) sampling
prior to construction. DSCR-SDE may also issue an environmental review document, if necessary. Soil
analyses, ambient air testing, and personnel monitoring may be required during construction.
A-1
For non-military construction projects (i.e., routine maintenance or utility operations requiring excavation
or trenching) within the OU 1 footprint, an environmental review document will be issued by DSCR-SDE
as specified in DSCR Maintenance Regulation 4150.1.
Depending on the type of construction activity, a health and safety plan may be required by the DSCR-
SDE prior to work commencement. The plan may include air monitoring, personal protective equipment,
dust suppression and runoff control during construction, as necessary.
Monitoring. Soil and groundwater analysis, ambient air testing, and personnel monitoring may be
required during construction activities. This determination will be made based on the type and location of
the construction activity proposed and the results of the preconstruction sampling. Routine groundwater
monitoring will continue as part of OU 6 activities.
Property Transfer Restrictions. If the U.S. Army were to transfer the OU 1 area out of federal
ownership, deed restrictions would apply to monitor future development within the site’s physical
boundaries. An environmental review would be required before construction. Residential development
or school or childcare-related facility development would be prohibited, if the transfer occurs before
property conditions allow for unlimited use and unrestricted exposure.
Inspections and Five-Year Reviews. An annual site inspection will be conducted until OU 1 is deemed
acceptable for unrestricted use. The annual site inspection will be documented and certified with the form
provided as Figure 3 of the Final LUCIP. A five-year review will be conducted in accordance with the
Comprehensive Environmental Response, Compensation, and Liability Act until the termination
provisions are met. Five-year reviews were conducted in 1997, 2003 and 2008. The next five-year
review is planned for 2013.
A-2
DMW-17A
DMW-16CDMW-16B
DMW-16ADMW-15A AEHA-16C
AEHA-1
Warehouse 60 Warehouse 59
54
Warehouse 14Warehouse 11Warehouse 10Warehouse 7Warehouse 6
40
41
85
Warehouse 61Warehouse 62
CHKD
DRAWN
PROJ. NO.Mike Pierce
96310
Manish Joshi
0 200 400 600 800100Feet
DATE
12/08/06 FIGUREA-1
OPERABLE UNIT 1OPEN STORAGE AREA
DEFENSE SUPPLY CENTER RICHMONDRICHMOND, VIRGINIALEGEND
ZONE 2
OPERABLE UNIT 1 IC AREA
BUILDINGS
MONITORING WELL
RO
AD
B
RO
AD
A
RO
AD
C
NORTH 2ND STREET
APPENDIX B
LAND USE CONTROLS FOR OPERABLE UNIT 3: NATIONAL GUARD AREA SOILS
OPERABLE UNIT 3: NATIONAL GUARD AREA SOILS
Operable Unit (OU) 3 is the National Guard Area (NGA) soils, which occupy approximately 15 acres in
the east-central portion of the installation, as shown in Figure B-1. Institutional controls (IC) were
specified as part of the remedy for this location in the October 1995 Record of Decision (ROD). IC
objectives delineated in the ROD were to reduce/eliminate human contact by reliance on physical controls
and regulatory and administrative requirements. In this way, inappropriate future site use and potential
exposure to impacted soil would be prevented. Constituents of concern included volatile organic
compounds, semivolatile organic compounds, petroleum hydrocarbons, and metals. Most of the area is
covered by concrete, asphalt, and gravel.
The land use controls for OU 3 are:
Access Restrictions. The NGA will continue operation as a restricted area. Because Defense Supply
Center Richmond (DSCR) is a secured Department of Defense facility, access is restricted. Separate
fencing exists at the NGA (Fencing follows the approximate OU boundary) and the area is locked at
night. This dual security system provides a layering of controls and will continue to be maintained.
Installation police conduct routine security checks of this area.
Preconstruction Assessment. Future industrial development, including excavation or site grading, is not
precluded. In the event of construction activities, health and safety measures will be followed. The
DSCR-SDE (Environment, Safety and Health Office operated under DLA Enterprise Support Richmond)
must be consulted prior to excavation. DSCR-SDE will issue an environmental review document, which
will outline the contaminant data in the area of the construction activity.
For military construction projects within the OU 3 footprint, an environmental site assessment will be
conducted. The environmental assessment will be completed prior to project design and submitted to
DSCR-SDE for review. Monitoring will include soil (soil gas and groundwater, if applicable) sampling
prior to construction. DSCR-SDE may also issue an environmental review document, if necessary. Soil
analyses, ambient air testing, and personnel monitoring may be required during construction.
For non-military construction projects (i.e., routine maintenance or utility operations requiring excavation
or trenching) within the OU 3 footprint, an environmental review document will be issued by DSCR-SDE
as specified in DSCR Maintenance Regulation 4150.1.
B-1
Depending on the type of construction activity, a health and safety plan may be required by the DSCR-
SDE prior to work commencement. The plan may include air monitoring, personal protective equipment,
dust suppression and runoff control during construction, as necessary.
Monitoring and Maintenance. Soil and groundwater analysis, ambient air testing, and personnel
monitoring may be required during construction activities. This determination will be made based on the
type and location of the construction activity proposed and the results of the preconstruction sampling.
Maintenance of existing pavement within the NGA is required. Contamination monitoring (volatile
organic compounds) for surface water in No Name Creek will continue until OU 6 remediation is
complete. Groundwater monitoring will continue as part of OU 6 activities.
Property Transfer Restrictions. If the U.S. Army were to transfer the OU 3 area out of federal
ownership, deed restrictions would apply to monitor future development within the site’s physical
boundaries. An environmental review would be required before construction. Residential development
or school or childcare-related facility development would be prohibited, if the transfer occurs before
property conditions allow for unlimited use and unrestricted exposure.
Inspections and Five-Year Reviews. An annual site inspection will be conducted until OU 3 is deemed
acceptable for unrestricted use. The annual site inspection will be documented and certified with the form
provided as Figure 3 of the Final LUCIP. A five-year review will be conducted in accordance with the
Comprehensive Environmental Response, Compensation, and Liability Act until the termination
provisions are met. Five-year reviews were conducted in 1997, 2003 and 2008. The next five-year
review is planned for 2013.
B-2
NO NAME CREEK
Warehouse 14 Warehouse 15
151
140
85
T-124
T-123 155154
T-125153
150
Shed149
CHKD
DRAWN
PROJ. NO.Mike Pierce
96310
Manish Joshi
0 200 400 600 800100Feet
DATE
12/08/06 FIGUREB-1
OPERABLE UNIT 3NATIONAL GUARD AREA
DEFENSE SUPPLY CENTER RICHMONDRICHMOND, VIRGINIA
LEGENDZONE 2
OPERABLE UNIT 3 IC AREA
DSCR BOUNDARY
APPROXIMATE EXTENT OF OU6 PLUME
BUILDINGS
EXTRACTION WELLMONITORING WELLPIEZOMETER
ALCOTT ROAD
1ST STREET
APPENDIX C
LAND USE CONTROLS FOR OPERABLE UNIT 12: FORMER PESTICIDES BUILDING 112
C-1
OPERABLE UNIT 12: FORMER PESTICIDES BUILDING 112
Operable Unit (OU) 12 is soils around the former pesticides Building 112, located approximately 900 feet
north of Kingsland Creek on 8th Street as shown in Figure C-1. Institutional controls were specified as
part of the remedy for this location in the November 2005 Record of Decision (ROD). The Remedial
Action Objectives delineated in the ROD were to limit human exposure to arsenic-impacted soils above
remediation levels; limit future migration of soil constituents to groundwater; and limit migration of soil
constituents to Kingsland Creek through the storm-sewer system. An asphalt cover with an approximate
area of 13,800 square feet will be installed to limit exposure to and migration of arsenic and pesticide
impacted soils.
The land use controls for OU 12 are:
Groundwater Restrictions. Groundwater beneath OU 12 shall not be used for potable, process, or
irrigation purposes. DSCR is currently modifying Maintenance Regulation 4150.1 to prohibit potable use
of groundwater throughout the installation.
Access Restrictions. The area of former Building 112 is currently enclosed by a chain-link fence along
the northern, western and southern OU boundaries. Because Defense Supply Center Richmond (DSCR)
is a secured Department of Defense facility, access to the overall installation is restricted. This dual
security system provides a layering of controls and will continue to be maintained. Installation police
conduct routine security checks of this area.
Intrusive Activity Restrictions and Signage. Future development, including excavation and site
grading of OU 12 surface soils are precluded. Construction or other intrusive activities that could disturb
the asphalt cover and monitoring wells are also precluded. Signs identifying the OU and prohibiting
intrusive activities have been posted along the eastern OU boundary. The use of the asphalt and backfill
area is limited to activities that will not damage the cover or clean backfill.
The one exception to precluding intrusive activities would be if maintenance of underlying utilities was
required. In this case, a health and safety plan would be required by the DSCR-SDE (Environment,
Safety and Health Office operated under DLA Enterprise Support Richmond) prior to work
commencement. The plan would include air monitoring, personal protective equipment, dust suppression
and runoff control during intrusive utility work, as necessary.
C-2
Maintenance and Monitoring. Maintenance of the asphalt cover is required. The integrity of the
asphalt cover will be inspected annually, and its integrity maintained for as long as constituents remain in
OU 12 soil at concentrations that preclude unrestricted use. The metric for cover integrity will be distress
of the asphalt slab, documented as low, medium or high. Documented distress types for the asphalt cover
will include alligator cracking, bleeding, block cracking, bumps and sags, depression edge cracking,
potholes, swell, and weathering and raveling. High distress will warrant repair of the asphalt cover.
Property Transfer Restrictions. If the U.S. Army were to transfer OU 12 out of federal ownership,
deed restrictions would apply in accordance with the Comprehensive Environmental Response,
Compensation, and Liability Act (CERCLA), Section 120(h). Deed restrictions would preclude intrusive
activities and groundwater use. An environmental review would be required before construction.
Residential development or school or childcare-related facility development would be prohibited, if the
transfer occurs before property conditions allow for unlimited use and unrestricted exposure.
Inspections and Five-Year Review. An annual site inspection will be conducted until OU 12 is deemed
acceptable for unrestricted use. The annual site inspection will be documented and certified with the form
provided as Figure 3. A five-year review will be conducted in accordance with the Comprehensive
Environmental Response, Compensation, and Liability Act until the termination provisions are met.
Five-year reviews were conducted in 1997, 2003 and 2008. The next five-year review is planned for
2013.
C-3
DEFENSE SUPPLY CENTER RICHMOND
OPERABLE UNIT 12 IC AREA
CHKD
DRAWN
PROJ. NO.Mike Pierce
96310
Manish JoshiDATE
12/08/06 FIGUREC-1
OPERABLE UNIT 12EXTENT OF ASPHALT COVER IN
THE SELECTED REMEDY
RICHMOND, VIRGINIA
APPENDIX D
LAND USE CONTROLS FOR OPERABLE UNIT 8: ACID NEUTRALIZATION PITS
GROUNDWATER
OPERABLE UNIT 8: ACID NEUTRALIZATION PITS GROUNDWATER
Operable Unit (OU) 8 consists of groundwater (in the upper water-bearing unit [WBU]) impacted by past
operations at the former ANPs (OU 5) and is located in the northern part of the installation, commonly
referred to as Zone 1. The ANPs were located approximately 25 feet northwest of Warehouse 65, as
shown in Figure D-1. The OU 8 impacted groundwater does not extend off the installation. Institutional
controls (IC) were specified as a component of the final remedy at this location in the February 2007
Record of Decision (ROD). IC objectives delineated in the ROD were to prevent unacceptable risk to
human health and the environment from exposure to constituents of concern (COCs) in groundwater by
physical controls and regulatory and administrative requirements. In this way, inappropriate future site
use and potential exposure to impacted groundwater would be prevented. COCs at OU 8 primarily include
volatile organic compounds. Exposure to COCs would be anticipated only if excavation was undertaken
or drinking water wells were installed.
The land use controls for OU 8 are:
Groundwater Use Restrictions: Potable groundwater use has been prohibited at OU 8. DSCR is
currently modifying Maintenance Regulation 4150.1 to prohibit potable use of groundwater throughout
the installation.
Access Restrictions. OU 8 will continue operation as a restricted non-residential area. Because Defense
Supply Center Richmond (DSCR) is a secured Department of Defense facility, access is already
restricted. A portion of OU 8 is located within the tenant organization confines of the Defense
Distribution Depot Richmond, Virginia (DDRV), which has a separate fence. Additional
badging/clearance are required to enter the DDRV area. This additional security provides a layering of
controls and will continue to be maintained. Installation police conduct routine security checks of this
area.
Preconstruction Assessment. Future industrial development, including excavation or site grading, is not
precluded. In the event of construction activities, health and safety measures will be followed. The
DSCR-SDE (Environment, Safety and Health Office operated under DLA Enterprise Support Richmond)
must be consulted prior to excavation. DSCR-SDE will issue an environmental review document, which
will outline the contaminant data in the area of the construction activity.
D-1
For military construction projects within the OU 8 footprint, an environmental site assessment will be
conducted. The environmental assessment will be completed prior to project design and submitted to
DSCR-SDE for review. Monitoring may include soil, (soil gas and groundwater, if applicable) sampling
prior to construction. DSCR-SDE may also issue an environmental review document, if necessary. Soil
analyses, ambient air testing, and personnel monitoring may be conducted during construction.
For non-military construction projects (i.e., routine maintenance or utility operations requiring excavation
or trenching) within the OU 8 footprint, an environmental review document will be issued by DSCR-SDE
as specified in DSCR Maintenance Regulation 4150.1.
Depending on the type of construction activity, a health and safety plan may be required by the DSCR-
SDE prior to work commencement. The plan may include air monitoring, personal protective equipment,
dust suppression and runoff control during construction, as necessary.
Monitoring. Soil and groundwater analysis, ambient air testing, and personnel monitoring may be
required during construction activities. This determination will be made based on the type and location of
the construction activity proposed and the results of the preconstruction sampling. Groundwater
monitoring will continue as part of remedial action activities at OU 8.
Property Transfer Restrictions. If the U.S. Army were to transfer the OU 8 area out of federal
ownership, deed restrictions would apply to monitor future development within the site’s physical
boundaries. An environmental review would be required before construction. Potable groundwater use,
residential development or school or childcare-related facility development would be prohibited, if the
transfer occurs before property conditions allow for unlimited use and unrestricted exposure.
Inspections and Five-Year Reviews. An annual site inspection will be conducted until OU 8 is deemed
acceptable for unrestricted use. The annual site inspection will be documented and certified with the form
provided as Figure 3 of the Final LUCIP. A five-year review will be conducted in accordance with the
Comprehensive Environmental Response, Compensation, and Liability Act until the termination
provisions are met. Five-year reviews were conducted in 1997, 2003 and 2008. The next five-year
review is planned for 2013.
D-2
War
ehou
se 6
4
War
ehou
se 6
3
War
ehou
se 7
7
War
ehou
se 7
8
War
ehou
se 6
5
War
ehou
se 6
6
USGS-22
OS72-MW122MWANP-7
0
MWANP-397
MWANP-271.6
MWANP-261.8
MWANP-251.6
MWANP-242
MWANP-230
MWANP-220
MWANP-210
MWANP-201.2
MWANP-190
MWANP-183
MWANP-177.6
MWANP-160
MWANP-159.5MWANP-14
0
MWANP-130
MWANP-100
DP-961
DP-82.2
DP-76.6
DP-63.2
DP-50
DP-40
DP-30
DP-20
DP-129.8 DP-11
50
DP-108.3DP-1
0
DMW-31A140
DMW-30A40
DMW-24A14
DMW-23A0
CHKD
DRAWN
PROJ. NO.Mike Pierce
96310
Manish Joshi
0 200 400 600 800100Feet
DATE10/28/08
FIGURED-1
OPERABLE UNIT 8
DEFENSE SUPPLY CENTER RICHMONDRICHMOND, VIRGINIA
LEGENDMONITORING WELL
DUAL PHASE EXTRACTION WELL
ESTIMATED PLUME BOUNDARY (1ug/L)
ESTIMATED PLUME BOUNDARY (10ug/L)
PLUMES
OPERABLE UNIT 8 IC AREA
FORMER ACID NEUTRALIZATION PITS
APPENDIX E
LAND USE CONTROLS FOR OPERABLE UNIT 10: BUILDING 68
OPERABLE UNIT 10: BUILDING 68
Operable Unit (OU 10) consists of soils impacted by past operations at former Building 68 and is located
in the northern part of the installation, commonly referred to as Zone 1. OU 10 is located at the
intersection of Road A and North 5th Street within Defense Distribution Depot Richmond Virginia (a
restricted DSCR area enclosed by fencing and locked or guarded gates), as shown in Figure E-1.
Institutional controls (IC) were specified as part of the remedy for this location in the July 2007 Record of
Decision (ROD). IC objectives delineated in the ROD were to prevent future residential exposure to
impacted soils and prevent future on-installation use of groundwater as drinking water. In this way,
inappropriate future site use and potential exposure to impacted soil would be prevented. Constituents of
concern (COC) at OU 10 include metals (primarily arsenic), polycyclic aromatic hydrocarbons (PAHs)
and pesticides (dieldrin). The entire OU 10 surface area is covered by gravel with sparse vegetation
between the gravel. Exposure to COCs would be anticipated only if excavation was undertaken.
The land use controls for OU 10 are:
Groundwater Use Restrictions: Potable groundwater use has been prohibited at OU 10. DSCR is
currently modifying Maintenance Regulation 4150.1 to prohibit potable use of groundwater throughout
the installation.
Access Restrictions and Signage. OU 10 will continue operation as a restricted industrial area. Because
Defense Supply Center Richmond (DSCR) is a secured Department of Defense facility, access is already
restricted. OU 10 is located within the tenant organization confines of the Defense Distribution Depot
Richmond, Virginia (DDRV), which has a separate fence. Additional badging/clearance are required to
enter the DDRV area. This additional security provides a layering of controls and will continue to be
maintained. Installation police conduct routine security checks of this area. Access restrictions will be
maintained as long as DDRV occupies this area. Signs identifying the OU will be posted on the OU 10
fence.
Preconstruction Assessment. Future industrial development, including excavation or site grading, is not
precluded. In the event of construction activities, health and safety measures will be followed. The
DSCR-SDE (Environment, Safety and Health Office operated under DLA Enterprise Support Richmond)
must be consulted prior to excavation. DSCR-SDE will issue an environmental review document, which
will outline the contaminant data in the area of the construction activity.
E-1
For military construction projects at OU 10, an environmental site assessment will be conducted. The
environmental assessment will be completed prior to project design and submitted to DSCR-SDE for
review. Monitoring will include soil sampling prior to construction. DSCR-SDE may also issue an
environmental review document, if necessary. Soil analyses, ambient air testing, and personnel
monitoring may be required during construction.
For non-military construction projects (i.e., routine maintenance or utility operations requiring excavation
or trenching) within the OU 10 footprint, an environmental review document will be issued by DSCR-
SDE as specified in DSCR Maintenance Regulation 4150.1.
Depending on the type of construction activity, a health and safety plan may be required by the DSCR-
SDE prior to work commencement. The plan may include air monitoring, personal protective equipment,
dust suppression and runoff control during construction, as necessary. In the event that impacted soils are
removed in the future, they will be disposed of in a permitted facility and replaced with clean fill to
prevent exposure. In addition, if the impacted soils are disturbed in the future, erosion and sediment
controls will be required to prevent migration to the storm sewer.
Maintenance and Monitoring. Soil analysis, ambient air testing, and personnel monitoring may be
undertaken during construction activities, depending upon the type and location of the construction
activity and the results of the preconstruction sampling. A vegetative cover will be installed at the site as
part of the final remedy. The cover will be inspected on a monthly basis (for up to 6 months)
immediately after installation. Requirements for additional top soil, seeding or watering (during the
initial growing season) will be determined during these monthly inspections. Once the vegetative cover is
established, it will be inspected on an annual basis (during the annual site inspections). Maintenance
activities (if required) will be performed after the annual inspection site visits.
Property Transfer Restrictions. If the U.S. Army were to transfer OU 10 out of federal ownership,
deed restrictions would apply to monitor future development within the site’s physical boundaries. An
environmental review would be required before construction. Residential development or school or
childcare-related facility development would be prohibited, if the transfer occurs before property
conditions allow for unlimited use and unrestricted exposure.
Inspections and Five-Year Reviews. An annual site inspection will be conducted until OU 10 is deemed
acceptable for unrestricted use. The annual site inspection will be documented and certified with the form
provided as Figure 3 of the Final LUCIP. A five-year review will be conducted in accordance with the
E-2
Comprehensive Environmental Response, Compensation, and Liability Act until the termination
provisions are met. Five-year reviews were conducted in 1997, 2003 and 2008. The next five-year
review is planned for 2013.
E-3
NORTH 5TH STREET
SURFACE DRAINAGE
RO
AD
A
FORMERBUILDING
68LOCATION
CHKD
DRAWN
PROJ. NO.Mike Pierce
96310
Manish Joshi
0 25 50 75 10012.5Feet
DATE
12/08/06 FIGUREE-1
OU 10 SITE MAP
DEFENSE SUPPLY CENTER RICHMONDRICHMOND, VIRGINIALEGEND
MANHOLE COVER
STORM SEWER INLET
2000 STORM SEWER
ZONE 2
OPERABLE UNIT 10 IC AREA
APPENDIX F
LAND USE CONTROLS FOR OPERABLE UNIT 11: TRANSITORY SHELTER 202
OPERABLE UNIT 11: TRANSITORY SHELTER 202
Operable Unit (OU) 11 consists of soils impacted by past operations at former Transitory Shelter
(TS) 202 and is located near the western boundary of the installation, approximately 170 feet east
of Road A between South 2nd and 3rd Streets. OU 11 is within Defense Distribution Depot
Richmond Virginia (a restricted DSCR area enclosed by fencing and locked or guarded gates), as
shown in Figure F-1. Institutional controls (IC) were specified as part of the remedy for this
location in the July 2007 Record of Decision (ROD). IC objectives delineated in the ROD were
to prevent future residential exposure to impacted soils and prevent future on-installation use of
groundwater as drinking water. In this way, inappropriate future site use and potential exposure
to impacted soil would be prevented. Constituents of concern (COC) at OU 11 include metals
(primarily arsenic) and pesticides. Approximately 97 percent of the OU-11 surface area is
covered with asphalt or riprap. The remaining area has a vegetative cover. Exposure to COCs
would be anticipated only if excavation was undertaken.
The land use controls for OU 11 are:
Groundwater Use Restrictions: Potable groundwater use has been prohibited at OU 11. DSCR
is currently modifying Maintenance Regulation 4150.1 to prohibit potable use of groundwater
throughout the installation.
Access Restrictions and Signage. OU 11 will continue operation as a restricted industrial area.
Because Defense Supply Center Richmond (DSCR) is a secured Department of Defense facility,
access is already restricted. OU 11 is located within the tenant organization confines of the
Defense Distribution Depot Richmond, Virginia (DDRV), which has a separate fence. Additional
badging/clearance are required to enter the DDRV area. This additional security provides a
layering of controls and will continue to be maintained. Installation police conduct routine
security checks of this area. Access restrictions will be maintained as long as DDRV occupies
this area. Signs identifying the OU will be posted at OU 11.
Preconstruction Assessment. Future industrial development, including excavation or site
grading, is not precluded. In the event of construction activities, health and safety measures will
be followed. The DSCR-SDE (Environment, Safety and Health Office operated under DLA
Enterprise Support Richmond) must be consulted prior to excavation. DSCR-SDE will issue an
F-1
environmental review document, which will outline the contaminant data in the area of the
construction activity.
For military construction projects at OU 11, an environmental site assessment will be conducted.
The environmental assessment will be completed prior to project design and submitted to DSCR-
SDE for review. Monitoring will include soil sampling prior to construction. DSCR-SDE may
also issue an environmental review document, if necessary. Soil analyses, ambient air testing,
and personnel monitoring may be conducted during construction. For non-military construction
projects (i.e., routine maintenance or utility operations requiring excavation or trenching) within
the OU 11 footprint, an environmental review document will be issued by DSCR-SDE as
specified in DSCR Maintenance Regulation 4150.1.
Depending on the type of construction activity, a health and safety plan may be required by the
DSCR-SDE prior to work commencement. The plan may include air monitoring, personal
protective equipment, dust suppression and runoff control during construction, as necessary. In
the event that impacted soils are removed in the future, they will be disposed of in a permitted
facility and replaced with clean fill to prevent exposure. In addition, if the impacted soils are
disturbed in the future, erosion and sediment controls will be required to prevent migration to the
storm sewer.
Maintenance and Monitoring. Soil analysis, ambient air testing, and personnel monitoring may
be undertaken during construction activities, depending upon the type and location of the
construction activity and results of the preconstruction sampling. A vegetative cover will be
installed at the site as part of the final remedy. The cover will be inspected on a monthly basis
(for up to 6 months) immediately after installation. Requirements for additional top soil, seeding
or watering (during the initial growing season) will be determined during these monthly
inspections. Once the vegetative cover is established, it will be inspected on an annual basis
(during the annual site inspections). Maintenance activities (if required) will be performed after
the annual inspection site visits.
Property Transfer Restrictions. If the U.S. Army were to transfer OU 11 out of federal
ownership, deed restrictions would apply to monitor future development within the site’s physical
boundaries. An environmental review would be required before construction. Residential
development or school or childcare-related facility development would be prohibited, if the
transfer occurs before property conditions allow for unlimited use and unrestricted exposure.
F-2
Inspections and Five-Year Reviews. An annual site inspection will be conducted until OU 11 is
deemed acceptable for unrestricted use. The annual site inspection will be documented and
certified with the form provided as Figure 3 of the Final LUCIP. A five-year review will be
conducted in accordance with the Comprehensive Environmental Response, Compensation, and
Liability Act until the termination provisions are met. Five-year reviews were conducted in 1997,
2003 and 2008. The next five-year review is planned for 2013.
F-3
War
ehou
se 9
CHKD
DRAWN
PROJ. NO.Mike Pierce
96310
Manish Joshi
0 125 250 375 50062.5Feet
DATE
12/08/06 FIGUREF-1
OPERABLE UNIT 11
DEFENSE SUPPLY CENTER RICHMONDRICHMOND, VIRGINIALEGEND
OU 11 LUCIP
FORMER BUILDING LOCATION
SOUTH 3RD STREET
RO
AD
A
BUILDING 50006
WA
RE
HO
USE
8
TRA
NSI
TOR
Y SH
ELTE
R 2
02
TRA
NSI
TOR
Y SH
ELTE
R 2
01
STO
RA
GE
AR
EA 5
RO
AD
C
SOUTH 2ND STREET
WAREHOUSE 6 WAREHOUSE 7
APPENDIX G
LAND USE CONTROLS FOR OPERABLE UNIT 2: AREA 50 LANDFILL
OPERABLE UNIT 2: AREA 50 LANDFILL
Operable Unit 2 (OU 2) consists of soils impacted by past operations at former Area 50 landfill
and is located in the central part of the installation, commonly referred to as Zone 2. Located in a
ravine, the Area 50 landfill was used for disposal of chemicals, construction debris and from the
late 1950s to the early 1970s. While the area was used as a landfill, material was placed in
various parts of the original ravine, and when full, areas of the ravine were sequentially regraded
and revegetated. By 1975, the entire area had been graded and seeded.
OU 2 is located in the central portion of the DSCR between the Open Storage Area (OSA) (OU 1)
and the National Guard Area (NGA) (OU 3, as shown in Figure G-1. These three units are
suspected to be contributing sources to contamination in the underlying groundwater, which has
been designated as OU 6. OU 2 is now generally level and covered with grass. A helipad and
parking area are now located near the northern boundary and southeastern corner, respectively.
Institutional controls (IC) were specified as part of the remedy for this location in the August
2008 Record of Decision (ROD). IC objectives delineated in the ROD were to prevent future
residential exposure to impacted soils, prevent exposure to buried OE and prevent future on-
installation use of groundwater as drinking water. In this way, inappropriate future site use and
potential exposure to impacted soil would be prevented. Constituents of concern (COC) at OU 2
include arsenic, polycyclic aromatic hydrocarbons (PAHs) and volatile organic compounds
(VOCs). After installation of the soil cover, exposure to COCs and OE would be anticipated only
if excavation was undertaken.
The land use controls for OU 2 are:
Groundwater Use Restrictions: Potable groundwater use has been prohibited at OU 2. DSCR is
currently modifying Maintenance Regulation 4150.1 to prohibit potable use of groundwater
throughout the installation.
Access Restrictions and Signage. OU 2 will continue operation as a restricted industrial area.
Because Defense Supply Center Richmond (DSCR) is a secured Department of Defense facility,
access is already restricted. In addition, the OU 2 area has a separate fence. This additional
security provides a layering of controls and will continue to be maintained. Installation police
G-1
conduct routine security checks of this area. Signs identifying the OU will be posted on the OU 2
fence.
Preconstruction Assessment. Future industrial development, such as site grading or well
installation, is not precluded. In the event of construction activities, health and safety measures
will be followed. The DSCR-SDE (Environment, Safety and Health Office operated under DLA
Enterprise Support Richmond) must be consulted prior to execution of these activities. DSCR-
SDE will issue an environmental review document, which will outline the contaminant data in the
area of the construction activity. Depending on the type of construction activity, a health and
safety plan may be required by the DSCR-SDE prior to work commencement. The plan may
include air monitoring, personal protective equipment, dust suppression and runoff control during
construction, as necessary. In the event that impacted soils are removed in the future, they will be
disposed of in a permitted facility and replaced with clean fill to prevent exposure. In addition, if
the impacted soils are disturbed in the future, erosion and sediment controls will be required to
prevent migration to the storm sewer.
In case military construction projects are planned at OU 2, an environmental site assessment will
be conducted. The environmental assessment will be completed prior to project design and
submitted to DSCR-SDE for review. Monitoring will include soil and groundwater sampling
prior to construction. DSCR-SDE may also issue an environmental review document, if
necessary. Soil and groundwater analyses, ambient air testing, and personnel monitoring may be
required during construction. In addition, supervision by an OE expert (e.g., UXO technician)
may be required during subsurface intrusion activities.
For non-military construction projects (i.e., routine maintenance or utility operations requiring
excavation or trenching) within the OU 2 footprint, an environmental review document will be
issued by DSCR-SDE as specified in DSCR Maintenance Regulation 4150.1. Soil and
groundwater analyses, ambient air testing, and personnel monitoring may be required during
construction. In addition, supervision by a OE expert (e.g., UXO technician) may be required
during subsurface intrusion activities.
Maintenance and Monitoring. Soil and groundwater analysis, ambient air testing, and
personnel monitoring may be undertaken during construction activities, depending upon the type
and location of the construction activity and the results of the preconstruction sampling. A soil
cover will be installed at the site as part of the final remedy. The cover will be inspected on an
G-2
annual basis after installation. Requirements for additional top soil or seeding will be determined
during these annual inspections. Maintenance activities (if required) will be performed after the
annual inspection site visits.
Property Transfer Restrictions. If the U.S. Army were to transfer OU 2 out of federal
ownership, deed restrictions would apply to monitor future development within the site’s physical
boundaries. An environmental review would be required before construction. Residential
development or school or childcare-related facility development would be prohibited, if the
transfer occurs before property conditions allow for unlimited use and unrestricted exposure.
Inspections and Five-Year Reviews. An annual site inspection will be conducted until OU 2is
deemed acceptable for unrestricted use. The annual site inspection will be documented and
certified with the form provided as Figure 3 of the Final LUCIP. A five-year review will be
conducted in accordance with the Comprehensive Environmental Response, Compensation, and
Liability Act until the termination provisions are met. Five-year reviews were conducted in 1997,
2003 and 2008. The next five-year review is planned for 2013.
G-3
OU6MW35
OU6MW34
OU6MW33
OU6MW31OU6MW30
OU6MW29OU6INJ32
OU6INJ28
OU6EBF02DOU6EBF01S
OU6EBF04D
OU6EBF03S
AEHA-7
AEHA-6
AEHA-5
AEHA-4
AEHA-34B
AEHA-34A
AEHA-3
AEHA-26B
AEHA-26A
AEHA-24B
AEHA-24A
AEHA-23BAEHA-23A
AEHA-22B
AEHA-22A
AEHA-21B
AEHA-21A
AEHA-2
AEHA-19B
AEHA-19A
AEHA-16B
AEHA-16A
AEHA-15BAEHA-15A
AEHA-12BAEHA-12A
MWA50-38
MWA50-37
MWA50-36
MWA50-35
DMW-9B
DMW-9A
DMW-8E
DMW-8BDMW-8A
DMW-7B
DMW-7A
DMW-34B
DMW-28EDMW-28B
DMW-18A
DMW-14E
DMW-14ACSMMW-9C
CSMMW-9BCSMMW-9A
Operable Unit 2Area 50 Landfill
DEFENSE SUPPLY CENTER RICHMONDRICHMOND, VIRGINIA
AREA ENLARGED
INSET
ZONE 3
ZONE 2
ZONE 1
LEGENDMONITORING WELL
OU 2 IC
DATE
CHKD
DRAWN
PROJ. NO.
10/27/08
Mike Pierce
96310
Manish Joshi FIGUREG-1
0 200 400100Feet
APPENDIX H
LAND USE CONTROLS FOR PX GAS STATION
PX GAS STATION: POL CONTAMINATED SOILS AND GROUNDWATER
The PX Gas Station site consists of soil and groundwater impacted by past release of
approximately 4,000 gallons of unleaded gasoline. The release was discovered during
underground storage tank inventory tracking in 1987. The leaking UST is no longer in operation.
Contaminated soils around the UST and the UST and related infrastructure have been removed.
The site location is shown in Figure H-1. The impacted groundwater does not extend off the
installation. The regulatory agency for this site is the VDEQ Piedmont Regional office. The
VDEQ send DSCR a letter stating that the contaminant levels at this site do not warrant further
corrective actions. The constituents of concern at this site are Benzene, Toluene, Ethylbenzene,
Xylenes and Methyl Tertiary-Butyl Ether (MTBE). Since the contaminant levels are above
Federal MCLs, DSCR has decided to implement Institutional controls (IC) at this site. IC
objectives are to prevent unacceptable risk to human health and the environment from exposure to
constituents of concern (COCs) in soil and groundwater by physical controls and administrative
requirements. In this way, inappropriate future site use and potential exposure to impacted soil
groundwater would be prevented. Exposure to COCs would be anticipated only if excavation was
undertaken or drinking water wells were installed.
The land use controls for PX Gas Station are:
Groundwater Use Restrictions: Potable groundwater use has been prohibited at PX Gas Station.
DSCR is currently modifying Maintenance Regulation 4150.1 to prohibit potable use of
groundwater throughout the installation.
Access Restrictions. PX Gas Station will continue operation as a restricted non-residential area.
Because Defense Supply Center Richmond (DSCR) is a secured Department of Defense facility,
access is already restricted. Installation police conduct routine security checks of this area.
Preconstruction Assessment. Future industrial development, including excavation or site
grading, is not precluded. In the event of construction activities, health and safety measures will
be followed. The DSCR-SDE (Environment, Safety and Health Office operated under DLA
Enterprise Support Richmond) must be consulted prior to excavation. DSCR-SDE will issue an
environmental review document, which will outline the contaminant data in the area of the
construction activity.
H-1
For military construction projects within the PX Gas Station site footprint, an environmental site
assessment will be conducted. The environmental assessment will be completed prior to project
design and submitted to DSCR-SDE for review. Monitoring may include soil, (soil gas and
groundwater, if applicable) sampling prior to construction. DSCR-SDE may also issue an
environmental review document, if necessary. Soil analyses, ambient air testing, and personnel
monitoring may be conducted during construction.
For non-military construction projects (i.e., routine maintenance or utility operations requiring
excavation or trenching) within the site footprint, an environmental review document will be
issued by DSCR-SDE as specified in DSCR Maintenance Regulation 4150.1.
Depending on the type of construction activity, a health and safety plan may be required by the
DSCR-SDE prior to work commencement. The plan may include air monitoring, personal
protective equipment, dust suppression and runoff control during construction, as necessary.
Monitoring. Soil and groundwater analysis, ambient air testing, and personnel monitoring may
be required during construction activities. This determination will be made based on the type and
location of the construction activity proposed and the results of the preconstruction sampling.
Groundwater monitoring will continue as part of remedial action activities at the site.
Property Transfer Restrictions. If the U.S. Army were to transfer the PX area out of federal
ownership, deed restrictions would apply to monitor future development within the site’s physical
boundaries. An environmental review would be required before construction. Potable
groundwater use, residential development or school or childcare-related facility development
would be prohibited, if the transfer occurs before property conditions allow for unlimited use and
unrestricted exposure.
Inspections and Five-Year Reviews. An annual site inspection will be conducted until PX Gas
Station site is deemed acceptable for unrestricted use. The annual site inspection will be
documented and certified in the form provided as Figure 3 of the Final LUCIP. A five-year
review will not be required at this site.
H-2
Road JRoad J
Road IRoad I
USTSITE
USTSITE
Road HRoad H
Road KRoad K
Road LRoad L
USTSITE
5th Street
5th Street
4th Street
4th Street
PX-23 110.47
17
Warehouse 33
Warehouse 32
191
192
Warehouse 51
19
21
18
20
T-10392
Warehouse 31
Warehouse 30
126
MH9(Dry)
MH10(Dry)
MH1
MH11
MH2
MH7
MH15(Dry)MH6
MH5
MH8(Dry)MH3
MH4
MH14
MH13(Dry)
PXET-B03
PXET-B02
PXET-B01
PXET-B10
PXET-B07
PXET-B05
PXET-B04
PXET-B06
PXET-B08
PXET-B09
PXET-02
PXET-01
B32-MW2
B32-MW1
B19-MW2B19-MW1
MP126-MW5MP126-MW4
MP126-MW3
MP126-MW2
MP126-MW1
B30-MW1
B30-MW2
PX-9
PX-8 *
PX-7
PX-6
PX-5PX-4
PX-35
PX-34
PX-33
PX-32PX-31 *
PX-30
PX-29
PX-28PX-27
PX-26PX-25
PX-24
PX-23
PX-22
PX-21
PX-20
PX-2
PX-1D
PX-19
PX-18
PX-17 *PX-16
PX-15
PX-14PX-13
PX-12
PX-11
PX-10
PX-1
LegendInstitutional Control Area
Manhole sample locations
PX-GAS monitoring wells (not sampled)
PX-GAS monitoring wells (sampled in July 2007)
Decommissioned or inaccessible wells
Basemap
Storm sewer lines
0 200 400100Feet
DSCR PX Gas Station Site
DEFENSESUPPLYCENTER
RICHMOND
FigureH-1
DATE
CHKD
DRAWN
PROJ. NO.