46
1 LAO PDR: Implementation Support for the Rural Electrification Program (REP) REP I: IDA Grant Number H2180-LA (P075531) and GEF Grant Number TF056700-LA (P080054) REP I AusAID Additional Financing: Grant Number TF96084 (P119715) *** REP II: IDA Grant Number H5380-LA (P110978) REP II GEF Additional Financing: GEF Grant Number TF098662-LA (P117177) May 23-31, 2011 AIDE MEMOIRE 1. A joint World Bank/IFC/AusAID/Norad team 1 carried out an implementation support mission in Vientiane and Champasak province, Lao PDR from May 23-31, 2011 to assess the overall progress of REP I and II and the implementation performance of various activities under both the EdL and MEM components towards achievement of the development objectives and outcome targets set out in the respective results frameworks. 2. The team met with key government agencies including the Department of Electricity (DOE) under Ministry of Energy and Mines (MEM), and Electricité du Laos (EDL). (See Annex 1 for a list of persons met). The team wishes to record its appreciation to the management and staff of these agencies for the cooperation and hospitality extended to its members, and in particular, to the Provincial Department of Energy and Mines (PDEM) and EdL Branch in Champasak for a well organized and informative field visit to on- and off-grid villages in Champasak province. This Aide Memoire summarizes the findings of the mission and is subject to confirmation by the Bank management. 3. As part of the Bank’s new Access to Information policy, the team discussed with the Client whether the Aide Memoire would be publicly disclosed. It was agreed that this Aide Memoire would be disclosed. 4. The team proposes that the next implementation support mission take place in November/ December 2011 to coordinate with the submission of the quarterly progress reports. In this regard, the team reminded EdL and DOE of the importance of submitting timely quarterly progress reports by EdL and DOE as per the Financing Agreements. The Bank looks forward to receiving the next progress reports for April to June 2011 by August 15, 2011. 11 The Bank team was co-led by Ms. Julia Fraser (Sr. Financial Analyst, incoming TTL) and Mr. Jie Tang (Sr. Energy Specialist, outgoing TTL) and comprised: Mr. Sombath Southivong (Senior Infrastructure Operations Officer), Ms. Oithip Mongkolsawat (Sr. Procurement Specialist), Ms. Kannathee Danaisawat (Financial Management Specialist), Ms. Helene Carlsson Rex (Senior Gender Specialist), Mr. Satoshi Ishihara (Senior Social Development Specialist), Mr. Bunlong Leng (Environmental Specialist), Mr. Panos Vlahakis (Power Engineer, Consultant), and Ms. Patricia Ramos (Junior Infrastructure Specialist). The AusAID team included Mr. Alex Marks (AusAID Program Manager), Mr. Mone Sysavath (Program Manager), and Mr. James Muir (AusAID Consultant). The IFC team included Mr. Val Bagatsing (Senior Country Officer) and Mr. Phongsavanh Phomkong (Investment Officer) for the EdL on grid component, and Mr. James Morley (Investment Officer), Ms. Xuan-Dung Thi Duong (Operations Officer), Mr. Sol Castro (IFC consultant) and Mr. Sivath Sengdouangchanch (IFC Legal consultant) on the DOE off-grid component on PPP micro hydro. The Norad Representative was Ms. Elisabeth Clemens (Senior Advisor). Logistical support was provided by Ms. Souksavanh Sisoulidavanh. Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

LAO PDR: Implementation Support for the Rural ... · 5.01 (c) of the IFC-EdL Loan agreement. 11. Norad Co-financing. Norad grant agreement which provides parallel financing to REP

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: LAO PDR: Implementation Support for the Rural ... · 5.01 (c) of the IFC-EdL Loan agreement. 11. Norad Co-financing. Norad grant agreement which provides parallel financing to REP

1

LAO PDR: Implementation Support for the Rural Electrification Program (REP)

REP I: IDA Grant Number H2180-LA (P075531) and GEF Grant Number TF056700-LA (P080054)

REP I AusAID Additional Financing: Grant Number TF96084 (P119715)

***

REP II: IDA Grant Number H5380-LA (P110978)

REP II GEF Additional Financing: GEF Grant Number TF098662-LA (P117177)

May 23-31, 2011

AIDE MEMOIRE

1. A joint World Bank/IFC/AusAID/Norad team1 carried out an implementation support mission in

Vientiane and Champasak province, Lao PDR from May 23-31, 2011 to assess the overall progress of

REP I and II and the implementation performance of various activities under both the EdL and MEM

components towards achievement of the development objectives and outcome targets set out in the

respective results frameworks.

2. The team met with key government agencies including the Department of Electricity (DOE)

under Ministry of Energy and Mines (MEM), and Electricité du Laos (EDL). (See Annex 1 for a list of

persons met). The team wishes to record its appreciation to the management and staff of these agencies

for the cooperation and hospitality extended to its members, and in particular, to the Provincial

Department of Energy and Mines (PDEM) and EdL Branch in Champasak for a well organized and

informative field visit to on- and off-grid villages in Champasak province. This Aide Memoire

summarizes the findings of the mission and is subject to confirmation by the Bank management.

3. As part of the Bank’s new Access to Information policy, the team discussed with the Client

whether the Aide Memoire would be publicly disclosed. It was agreed that this Aide Memoire would be

disclosed.

4. The team proposes that the next implementation support mission take place in November/

December 2011 to coordinate with the submission of the quarterly progress reports. In this regard, the

team reminded EdL and DOE of the importance of submitting timely quarterly progress reports by EdL

and DOE as per the Financing Agreements. The Bank looks forward to receiving the next progress

reports for April to June 2011 by August 15, 2011.

11

The Bank team was co-led by Ms. Julia Fraser (Sr. Financial Analyst, incoming TTL) and Mr. Jie Tang (Sr.

Energy Specialist, outgoing TTL) and comprised: Mr. Sombath Southivong (Senior Infrastructure Operations

Officer), Ms. Oithip Mongkolsawat (Sr. Procurement Specialist), Ms. Kannathee Danaisawat (Financial

Management Specialist), Ms. Helene Carlsson Rex (Senior Gender Specialist), Mr. Satoshi Ishihara (Senior Social

Development Specialist), Mr. Bunlong Leng (Environmental Specialist), Mr. Panos Vlahakis (Power Engineer,

Consultant), and Ms. Patricia Ramos (Junior Infrastructure Specialist). The AusAID team included Mr. Alex Marks

(AusAID Program Manager), Mr. Mone Sysavath (Program Manager), and Mr. James Muir (AusAID Consultant).

The IFC team included Mr. Val Bagatsing (Senior Country Officer) and Mr. Phongsavanh Phomkong (Investment

Officer) for the EdL on grid component, and Mr. James Morley (Investment Officer), Ms. Xuan-Dung Thi Duong

(Operations Officer), Mr. Sol Castro (IFC consultant) and Mr. Sivath Sengdouangchanch (IFC Legal consultant) on

the DOE off-grid component on PPP micro hydro. The Norad Representative was Ms. Elisabeth Clemens (Senior

Advisor). Logistical support was provided by Ms. Souksavanh Sisoulidavanh.

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Page 2: LAO PDR: Implementation Support for the Rural ... · 5.01 (c) of the IFC-EdL Loan agreement. 11. Norad Co-financing. Norad grant agreement which provides parallel financing to REP

2

*********************

Part A: Implementation Support of Rural Electrification Project Phase I

and AusAID Additional Financing (REP I)

Overview of Project Status

Original Project Cost

Estimate:

US$36.27 million Board Approval Date: April 27, 2006

Revised Project Cost

Estimate:

US$50.88 million IDA Effectiveness Date:

August 30, 2006

Original Credit Amount: IDA Grant H218

US$10 million AusAID Signing/

Effectiveness Date:

October 1, 2010 /

October 14, 2010

Original GEF Amount: GEF TF56700,

US$3.75 million Original Closing Date: March 31, 2010

AusAID Additional

Financing Amount:

TF096084

US$9.42 million Formally Revised

Closing Date:

March 31, 2012

Environmental Category: B Number of Closing Date

Extensions:

1

IDA Disbursement %

(as of 5/29/2011)

92.8% of credit amount

in USD Project Develop.

Objective Rating:

Satisfactory (PDO);

Satisfactory (GEO)

GEF Disbursement %

(as of 5/29/2011)

100% of grant amount in

USD Implementation

Progress Rating:

Satisfactory

AusAID Disbursement %

(as of 5/29/2011)

62.2% of the grant

amount in USD

1. Project Development Objectives (PDOs). The REP I is the first phase of the Rural Electrification

Adaptable Program Loan (APL) Program. The PDOs of REP I are to (i) increase access to electricity of

rural households in villages of targeted provinces; and (ii) improve financial performance of the power

sector. Global Environment Objectives (GEOs) of REP I are (i) substantial adoption of off-grid

renewable energy in Government’s rural electrification program; and (ii) increased efficiency of energy

supply by EdL and consumption by customers, resulting in greenhouse gas emission reductions as

increased hydropower exports substitute for thermal power production in Thailand.

2. Additional financing of US$9.42 million by the Australian Government through the Bank-

administered Mekong AusAID Energy Fund was signed on October 1, 2010. This additional financing

will fill a financing gap to achieve the targeted number of household connections to the grid, and finance

activities to scale up the project impact.

3. Risks to PDO/GEO achievement. The progress towards achieving the PDO and GEO is rated

satisfactory as well as the overall implementation progress. However, the team raised its concern

regarding the risk to fully implementing the AusAID-financed activities within the closing date, and in

particular the DSM/EE component with EdL and the MEM components. Further details are provided in

Annex 2 for the IDA and GEF- financed components and Annex 3 for the AusAID-financed components.

The team urged EdL and DOE management to closely monitor the agreed actions and timetables to

prevent further slippages.

4. Key Results Indicators. The majority of the key result indicators have successfully met the target.

The indicators which have not met the target, such as number of households connected through grid

extension and village hydro, were due to financing gap and shortages of fund experienced during project

Page 3: LAO PDR: Implementation Support for the Rural ... · 5.01 (c) of the IFC-EdL Loan agreement. 11. Norad Co-financing. Norad grant agreement which provides parallel financing to REP

3

implementation. Nevertheless, it is expected that the key outcome indicator on number of households

connected will be surpassed due to AusAID additional financing and the highly satisfactory progress of

the P2P scale up program. See the full summary of Result Indicators in Annex 5.

5. Overall Implementation Progress of EdL Component. Implementation of the original activities

funded by IDA, GEF and NORAD under the EdL Component are virtually completed. The

implementation progress for each component is summarized in more details in Annex 2. However, close

follow-up on the AusAID additional financing activities under EdL is required to ensure that they can be

fully implemented by the March 31, 2012 closing date (see Annex 3).

6. Overall Implementation Progress of MEM component. Similar to the EdL component, virtually

all of the original activities under REP I have been completed (see Annex 2), but there is a risk that the

activities financed under AusAID will not be completed by the closing date. The teams stressed the

importance of adhering to the agreed procurement timetables as only 10 months remained before the REP

I closing date.

7. Key issues in the implementation of MEM component identified during the previous mission

remain. This included: (i) guidelines for processing withdrawals of SHS by some of the customers are

not implemented yet; (ii) verification of inventories at PESCOs’ warehouse in provinces against DOE’s

records at Vientiane, which should be conducted on a regular basis, has not been conducted; and (iii)

some SHS customers complained that dis-functioning of the SHS or its parts reported to the PESCOs

were not addressed by the PESCOs in a long time. In addition, the team discussed the poor performance

of certain PESCOs in terms of remitting funds back to the REF. DOE agreed to initiate the termination

for the Khammoune PESCO (which has never deposited funds into the REF account). Because of the

poor performance of some PESCOs, the Bank requested DOE to revise the allocation by province for

solar home systems to take into account PESCO performance as well as reconcile the provincial plans

against the Renewable Energy Master Plan.

*********************

Part B: Implementation Support of Joint IDA-IFC Rural Electrification Project Phase II

and GEF Additional Financing (REP II)

Overview of Project Status

Original Project Cost

Estimate:

US$ 35.80 million Board Approval Date: January 12, 2010

Original Credit

Amount:

IDA Grant H538

US$20 million Effectiveness Date: August 9, 2010

IFC Loan Amount: US$15.0 million GEF Signing/

Effectiveness Date:

May 5, 2011 / TBD

Norad Loan Amount: US$4 million Original Closing Date: June 30, 2014

GEF Additional Grant

Amount:

TF098662

US$1.818 million Formally Revised

Closing Date:

n/a

Environmental

Category:

B Number of Closing Date

Extensions:

0

IDA Disbursement %

(as of 5/29/2011)

0% Project Develop.

Objective Rating:

Satisfactory

GEF Disbursement % 0% Implementation

Progress Rating:

Marginally satisfactory

Page 4: LAO PDR: Implementation Support for the Rural ... · 5.01 (c) of the IFC-EdL Loan agreement. 11. Norad Co-financing. Norad grant agreement which provides parallel financing to REP

4

8. Project Development Objectives. The PDOs of REP II are to: (a) increase access to electricity of

rural households in villages of project provinces; and (b) further improve the financial performance of

EdL. The global environmental objectives (GEO) of the GEF additional financing are to: (i) increase

efficiency of energy supply by EdL and consumption by consumers; and (ii) adopt substantial renewable

energy in the government’s rural electrification program.

9. Risks to PDO/GEO achievement. The implementation progress is rated as marginally satisfactory

given the approximate one year delay in procurement vis-à-vis the dates in the project appraisal

document. As a result, no significant disbursements have taken place against a target disbursement of

$10.5 million (29%) by end FY11. Revised procurement timetables were agreed, and the team urged EdL

and DOE to undertake its best efforts to maintain the schedules to allow achievement of the project

objectives within the closing date. In addition, the team raised some concern about new government

arrears accumulating due to insufficient budget allocation by MOF and the rising arrears from irrigation.

These issues should be addressed in the Joint Committee set up by MOF.

10. IFC Co-financing. The IFC financing agreement was signed in July 2010, and EdL is taking the

steps to complete the Conditions of Disbursements as discussed below. IFC will follow overall IDA’s

policy and procedure in terms of procurement and social and environmental safeguards, however, being a

corporate loan, the (use) disbursement of IFC loan is flexible as long as it is earmarked for REP II.

Disbursement will be (made) available, upon completion of relative Conditions of Disbursement (CODs),

proportionally with IDA’s component subject to the amounts and timeline as agreed among involved

parties. There are some CODs that remain to be completed by EDL before the first disbursement can be

made including: (i) proposed name of bank where DSRA will be established; (ii) submission of all

evidences for payment made for related IFC fees and legal fees; (iii) proposed timetable for

disbursements; and (iv) a certificate of compliance issued by EdL's auditors in accordance with section

5.01 (c) of the IFC-EdL Loan agreement.

11. Norad Co-financing. Norad grant agreement which provides parallel financing to REP II was

signed by the Norwegian Government and the MOF on August 3, 2010. The implementation of the

Norad-financed activities will be managed as an integral part of the implementation of the REP II. The

team reminded EdL and DOE that Norad is to be used for technical assistance and capacity building and

consultants’ services must be selected using the Bank’s guidelines. The Bank has agreed to review the

TORs, RfPs and draft negotiated contracts on behalf of Norad, but the agencies will need to seek final

approval from Norad as per Article VIII of the Norad legal agreement. (See Annex 6 for further details on

NORAD-financed activities.)

12. GEF Additional Financing. GEF provided US1.818 million of additional financing in order to

scale up the impact of REP II and to achieve global environmental benefits. The activities under GEF

support include: improving energy efficiency in both the electricity supply and consumption, promoting

adoption of renewable energy in the government’s rural electrification program, and supporting project

implementation. (See Annex 6 for more details.) The GEF Grant Agreement was signed on May 5, 2011.

The team requested EdL and MOF to amend the Subsidiary Financing Agreement to include the EdL

portion (US$999,000) of the GEF Grant in order to meet the condition of effectiveness no later than July

1, 2011.

Page 5: LAO PDR: Implementation Support for the Rural ... · 5.01 (c) of the IFC-EdL Loan agreement. 11. Norad Co-financing. Norad grant agreement which provides parallel financing to REP

5

13. Overall implementation progress. There has been no significant progress to report on REP II

activities due to procurement delays. The team has been working closely with EdL and DOE to

accelerate the procurement of the large value contracts, and several bid documents (for grid extension and

solar home systems) are expected to be issued next month in June.

*********************

Part C: Next Steps

14. The list of agreed next steps by project is provided below.

No. Actions Component Agreed Date

REP I

REP I- EdL

1. EdL to submit next progress report in a timely fashion N/A August 15, 2011

2. EdL to submit audit report for 2010 to the Bank N/A June 30, 2011

3. EdL to issue bid document for measuring equipment for

loss reduction based on the Bank’s NOL dated May 24,

2011 (re-bid for Lots 1 and 3)

A.2. Loss reduction June 6, 2011

(completed June 6)

4. EdL and Joint-Committee to finalize recommendation on

irrigation arrears

A.4. Financial

sustainability

May 31, 2011

(overdue)

5 EdL to incorporate Bank’s comments to the safeguard

progress report and submit the revised report to the Bank

Environment and

social

June 10, 2011

REP I- DOE

6. DOE to submit next progress report in a timely fashion N/A August 15, 2011

REP I- MOF

7. - MOF to allocate adequate budget for electricity

consumption by Government agencies for FY10/11

onwards

- MoF to settle the accumulated government arrear up to

end of FY 2009 amounting to LAK 38 billion

- Technical committee for irrigation arrear will update the

finding report including more analysis on the causes of

arrears and prepare policy recommendations to the

government on how to settle the arrears and preventing the

future arrear.

A.4. Financial

sustainability

September 2011

September 2011

REP I- WB 8. Send to EdL the comments to safeguards operational

manual

Environment and

social

June 10, 2011

(completed June 21)

REP I Aus AID Additional Financing

REP I Aus AID AF- EdL

9. EdL to request WB for amendment to Financing

Agreements for AusAID AF and REP II to allow

disbursements for P2P program on a reimbursable basis

A.1. P2P July 25, 2011

10. EdL to send updated P2P Operations Manual regarding the

governance structure for the use of the revolving fund to

the Bank (this would be a condition of disbursement for

P2P)

A.1. P2P August 15, 2011

Page 6: LAO PDR: Implementation Support for the Rural ... · 5.01 (c) of the IFC-EdL Loan agreement. 11. Norad Co-financing. Norad grant agreement which provides parallel financing to REP

6

11. EdL to contact IECC to finalize the draft contract and

agree on a start date for the DSM-EE follow up to Phase

1B and Phase 2 and submit such contract to the Bank

A.6. DSM and EE June 15, 2011

(completed)

12. EdL to contract ten energy coordinators A.6. DSM and EE July 30, 2011

REP I Aus AID AF- DOE

13. DOE to open a designated account for AusAID

Additional Financing

N/A July 30, 2011

14. DOE to issue bid documents for SHS B.1. Off-grid

investment -SHS

June 20, 2011

(completed June 22)

15. DOE to issue guidelines for withdrawn SHS before the

installation of next batch of solar home systems to be

funded by AusAID and REP II

B.1 Off-grid

Investment -SHS

16. DOE to replace the Khammoune PESCO for non

performance, attempt to collect outstanding payments and

initiate recruitment for new PESCO

B.1 Off-grid

Investment - SHS

June 30, 2011

17. DOE to re-evaluate the allocation of SHSs by province in

order to reconcile the provincial requests with both the RE

Master Plan and the performance of PESCOs

B.1 Off-grid

Investment -SHS

Sept 15, 2011

18. DOE to send revised drafts of Bidding Memorandum,

License Terms and Conditions, and License Certificates to

WB for NOL

B.3. Alternative RE

Delivery Models: PPP

Micro Hydropower

Schemes

June 15, 2011

(overdue)

19. DOE to submit a draft TOR, cost estimate and justification

for the sole source selection of Chiang Mai University on

providing detailed feasibility study up to 4 pig farms no

later than

B.3. Alternative RE

Delivery Models:

Biogas Pilot Site

June 30, 2011

REP I Aus AID AF- WB

20. WB to provide for comments the TOR for Non-Technical

Loss Study to EdL and AusAID

A.2. System Loss

Reduction

July 15, 2011

21. WB to initiate procurement for Non-Technical Loss Study A.2. System Loss

Reduction

July 31, 2011

22. WB to provide NOL to MEM on the SHS bidding

documents

B.1. Off-grid

investment -SHS

June 16, 2011

(completed)

23. WB to provide for comments the TOR for SHS livelihood

assessment to EdL and AusAID

B.1 Off-grid

Investment -SHS

July 25, 2011

24. WB to initiate procurement for SHS livelihood assessment B.1 Off-grid

Investment -SHS

September 30, 2011

25. Bank to provide NOL to Bidding Memorandum, License

Terms and Conditions, and License Certificates sent by

IFC and DOE

B.3. Alternative RE

Delivery Models: PPP

Micro Hydropower

Schemes

June 24, 2011

(not yet received

from DOE)

REP I Aus AID AF- IFC

26. IFC to send revised drafts of Bidding Memorandum,

License Terms and Conditions, and License Certificates to

WB for NOL

B.3. Alternative RE

Delivery Models: PPP

Micro Hydropower

Schemes

June 15, 2011

(overdue)

Page 7: LAO PDR: Implementation Support for the Rural ... · 5.01 (c) of the IFC-EdL Loan agreement. 11. Norad Co-financing. Norad grant agreement which provides parallel financing to REP

7

REP II

REP II- EdL 27. EdL and MOF to amend the Subsidiary Financing

Agreement to include the EdL portion (US$999,000) of

the GEF Grant to meet the condition of effectiveness

N/A July 1, 2011

28. - EDL to send a letter to IFC about its decision regarding

the proposed bank where DSRA will be established.

- EDL to make payment, and submit respective

evidences, for all pending IFC fees and legal fees.

- EDL to request E & Y to issue certificate of Compliance

under section 5.01 (c) of the IFC-EdL Loan agreement.

A.1 Grid extension June 15, 2011

June 15, 2011

Within 60 days

before the date of

first disbursement

29. EDL, WB and IFC to work together and come up with a

schedule for IFC loan and IDA grant to be disbursed over

time for REP II.

A.1 Grid extension June 18, 2011

30. See item (9) above A.1. P2P June 30, 2011

31. EdL to draft bid document for the supply and installation

of VPN and 17 servers using standard bid document for

goods and request amendment to Financing Agreement to

include this component under IDA financing

A.3. IT System and

System and Financial

Management

June 30, 2011

(completed)

32. EdL to send WB scope of works and cost estimate for

technical assistance for the training on EdL staff provincial

offices on the AFMS system

A.3. IT System and

System and Financial

Management

June 20, 2011

REP II- DOE

33. DOE to submit the draft RfP and short list of VOPS will

be provided by MEM to the Bank

B.2. Institutional

Strengthening

July 15, 2011

34. DOE to submit a plan for the use of Norad funds for

technical assistance under this component

B.3. Alternative Rural

Electrification

Delivery Model

July 31, 2011

35. DOE will submit a request for sole source selection for the

local firm along with the draft terms of reference to update

the RE Master Plan and update the database

B.4. RE Master Plan

and Database

July 15, 2011

36. DOE to submit a proposal – including cost estimates,

procurement timetable and brief description – for the use

of the Norad technical assistance funds

B.5. Organization

Strengthening of

MEM

July 31, 2011.

List of Annexes

1. List of People Met

2. REP I Implementation Progress by Component

3. REP I AusAID Additional Financing Progress by Component

4. REP I Implementation of the Action Plan for Financial Sustainability of the Power Sector

5. REP I Key Results Indicators

6. REP II Implementation Progress by Component

7. REP II Checklist of the IFC Loan Conditions for FIRST Disbursement

8. REP II Key Results Indicators

9. REP I and I: Environmental and Social

10. Notes from Field Visit to Champasak Province

Page 8: LAO PDR: Implementation Support for the Rural ... · 5.01 (c) of the IFC-EdL Loan agreement. 11. Norad Co-financing. Norad grant agreement which provides parallel financing to REP

8

Annex 1: List of Persons Met

Name Company Position

Mr. Khammany Inthirath EdL Managing Director

Mr. Bounma Manivong EdL Director, Business Financial Department

Mr. Bounkeua Xayasone EdL Deputy Manager Southern Region Projects,

Transmission and Substation Dept.

Mr. Gnanhkham Douangsavanh EdL Project Manager

Mr. Khampaseuth Theppangna EdL Manager, Southern Region

Ms. Khamphiou Phounsavath EdL Deputy Director, Business Financial Division

Ms. Mithuna Soudthavong EdL Assistant, Business-Financial Division

Mr. Somsanith Sadettan EdL Engineering Office Manager

Ms. Thongxay Souryavong EdL Accounting, Department Manager

Mr. Ouna Sikhotchounnamaly EdL IT Office

Mr. Phonesavanh Oudomvilay EdL P2P coordinator and Site M.G

Mrs. Khamphiou Phounsavath EdL Business-Financial Division

Mr. Vongvilay Sisoulath EdL Deputy Manager, Environmental Office

Mr. Sonchanh Lovangaphay EdL Technical staff, Environmental Office

Ms Vanh Volasane EdL Technical staff, Environmental Office

Ms. Phommany Lattamalangny EdL Deputy Manager, Loss Reduction and DMS Office

Mr. Bounnong Panemalaythog EdL Loss Reduction and DSM Office

Mr. Saysanith Phounsavath EdL Deputy Director, T.L and Substations Department

Mr. Anousak Phongeavath DOE REP I & II Project Manager

Mr. Phayvanh Vongsaly DOE Financial Management Officer

Mr. Deb Majumdar MEM International Procurement Specialist Advisor

FIELD VISIT TO CHAMPASAK PROVINCE

Mr. Khampaseuth Theppangna EdL Southern Region Director, Champasak Branch

Manager

Mr. Oudom K. EdL Director Manager, Champasak Region

Mr. Sisay EdL Official Head, Southern Region

Mr. Phouthasack EdL Billing Department, Champasak Branch

Mr. L. Phouthong EdL Planning, Champasak Branch

Mr. Phethsamone Vantha EdL Technical Department, Champasak Branch

Mr. Khanthara Sisamouth DOE Deputy Head of Renewable Energy Division

Ms. Saly Eangmany DOE Power to the Poor, Engineer

Mr. Phim Phone DOE Power to the Poor, Engineer

Mr. Paseuth DDEM Champasak Branch

Mr. Chansamone Yokkhanthone PESCO Manager, Champasak and Attapeu province

Page 9: LAO PDR: Implementation Support for the Rural ... · 5.01 (c) of the IFC-EdL Loan agreement. 11. Norad Co-financing. Norad grant agreement which provides parallel financing to REP

9

Annex 2: REP I - Implementation Progress by Component

EdL Component

Component A.1 Grid Extension. The progress of EdL’s grid extension activity is shown in the table

below. The total number of households connected under REP I (including AusAID additional financing

and P2P) is 49,3972 which is 117% over the outcome indicator target of 42,000 households. A total of

570 villages have been connected over the target of 540 – a 106% increase.

Progress of EDL Grid Extension Component as of May 2011

Item Description Target Progress Percentage

1 Detailed Field

Survey

22 kV (thousand km) 1,404.6 1,858.5 132%

12.7 kV (thousand km) 42.5 61.4 145%

0.4 kV (thousand km) 1,063.7 1,302.4 122%

Transformer (site) 627 737 118%

2 Stringing and

Erection

22 kV (thousand km) 1,404.6 1,471.4 105%

12.7 kV (thousand km) 42.5 49.2 116%

0.4 kV (thousand km) 1,063.67 .829.8 78%

Transformer (site) 627 651 104%

8 m pole (piece) 21,689 27,509 127%

10 m pole (piece) 1,475 123 8%

12 m pole (piece) 18,408 24,058 131%

14 m pole (piece) 533 144 27%

3 Electrification In-house wiring (HH) 42,295

32,168 117%

4 P2P HH connections 17,2292

Power to the Poor. Considerable progress has been made in the implementation and scale-up of the P2P

project following the initial pilot in Champasak province which connected 537 households using GEF and

EdL funds. Following the success of the pilot, it was agreed that AusAID additional financing would

contribute $600,000 under REP I and IDA would contribute another $600,000 under REP II. As of end

April 2011, a total of 16,692 households have been connected as part of P2P with 14,680 households

connected in the South and 1,952 households connected in the North. The total number of female headed

household supported is 1,042 and the total number of households with disabled is 535. P2P is active in

488 villages in 16 provinces both in the North and the South. The team discussed various recommended

changes to the P2P reporting format to clarify which connections would be eligible under REP I AusAID

additional financing and under REP II IDA financing and to reword some of the headings for clarity. This

would also prevent double counting of household connected under REP I vs REP II. In addition, the team

requested that the report include information on the financial status of the P2P revolving fund and agreed

to work with the P2P team to finalize the requested changes. The team informed EdL that the Financing

Agreement as well as the Disbursement letter for AusAID and REP II will have to be amended to allow

use of funds for replenishment of the P2P revolving fund. As a disbursement condition for P2P, the team

discussed the need to update the P2P Operations Manual to include guidelines to govern the operation and

use of the P2P revolving fund. It was agreed that a short term consultant be hired for this purpose.

Finally, the team would like to record its appreciation for the timely and regular reporting by the P2P unit.

2 It is noted that this figure also includes the connection for P2P households to be reimbursed under REP II;

however, EdL is verifying the exact figure.

Page 10: LAO PDR: Implementation Support for the Rural ... · 5.01 (c) of the IFC-EdL Loan agreement. 11. Norad Co-financing. Norad grant agreement which provides parallel financing to REP

10

Component A.2 Loss Reduction. The procurement of domestic and commercial revenue meters and

calibration and testing equipment, with an estimated amount of USD 491,000, had to be rebid (with the

exception of one lot for which EdL awarded a contract for $19,203 for the supply of measuring

equipment). To the extent that all of the goods cannot be delivered by the REP I closing date, the

contracts can be co-financed with REP II to allow more time. See Annex 6 for additional details on the

A.2 Loss Reduction component.

Timeline for Procurement Activities for System Loss Reduction - ReBid

Milestones Timeline Actual/Updated

Timeline

Finalize Bidding Documents and obtain NOL By January 31, 2010 May 24, 2011 (A)

Advertise By February 8, 2010 June 6, 2011

Bids opening By March 31, 2010 July 11, 2011

NOL for Bid Evaluation Report (BER) By April 30, 2010 August 31, 2011

Contract signed By May 15, 2010 September 20, 2011

Contract completion By December 31, 2010

Component A.3 IT System. There is not much progress in the roll out of the Accounting and Financial

Management System (AFMS):

Modification of the AFMS to cope with the new chart of account and correction of some errors

has been completed by the Chinese consulting firm, who first installed the AFMS.

Installation of all six modules of AFMS (G/L, A/R, A/P, Inventory, Fixed Asset and payroll)

together with the Billing System at 4 EDL branches (Bolikhamxay, Savannekhet, Salavanh and

Champasak).

Partial installation of two modules of AFMS (Inventory and Fixed Assets) together with the

Billing System at the other 13 EDL branches.

REP II will provide continued support to complete the roll out of the AFMS.

Suspense Account. The outstanding balance as of May 2011 is 858,372,200 Kip (compared to 1 billion

Kip as of August 2010). EDL has requested to offset this balance with the longest outstanding debts.

MOF, however, has requested EDL to first refund this amount to MOF, and MOF will then pay it back to

EDL. The team suggests EDL to negotiate with the MOF one more time whether the offset can be done,

otherwise, EDL should follow MOF instruction in order to clear the balance in the suspense account and

some long outstanding debts.

Component A.4 Tariff Reform. In line with the “Action Plan for Financial Sustainability of the Power

Sector” endorsed by the Prime Minister in 2005, the Prime Minister Office has approved annual average

increase for tariff adjustment. However, in order to implement the plan, there is a need for PMO approval

of the detailed implementation plan, which will include increase rate for different customer categories.

EDL had prepared the detail plan, which was endorsed by MEM and submitted to PMO, but the plan has

not yet been approved by PMO. The team urged EDL and MEM to closely follow up with the PMO on

the approval.

Component A.5 Safeguards Capacity Building. The Safeguards Capacity Building componenet had

been designed to enhance EdL’s (and MEM’s) capacity in environment and social assessment and impact

assessment through training, study tours and acquisition of necessary equipment. International consultants

Page 11: LAO PDR: Implementation Support for the Rural ... · 5.01 (c) of the IFC-EdL Loan agreement. 11. Norad Co-financing. Norad grant agreement which provides parallel financing to REP

11

(SD&SP Consultant Group and Consultant for Technology (COT)) were hired to conduct the training on

environment and social management for technical staffs and managers. A training program and a study

tour in Thailand was organized for managers in April 2010 and a training program and a study tour in

NT2 was organized for technical staffs in May, 2010. The activities under this component were fully

completed.

Positive outcomes of this Component were demonstrated by the excellent performance of the

Environmental and Social Office of EdL, as (i) the office have completed independently the field survey

and consultation and updated the EIA/EMP/RAP for a new Bank-funded 230 kV transmission and

substation line project, managed the local disclosure process satisfactory to the Bank safeguard review;

(ii) a satisfactory/highly satisfactory performance in safeguard management for a Bank-funded 115 kV

transmission line under construction, as concluded by the field visit of the Bank Safeguard Specialist

during this mission.

See Annex 9 on Environment and Social Issues for more details.

MEM Component

Component B.1 Off-grid Investment Program. Follow up from the last mission, for the 4 units of SHS

reported as lost in April 2008 while being transported by VOPS to PESCO, PESCO has refunded 50% of

the costs to DOE in September 2009 and the other 50% was offset with the bonus paid to the PESCO in

January 2010. In addition, DOE has not submitted the guidelines for withdrawn SHSs as agreed during

the last mission. The mission emphasized that the guidelines should be in place before the installation of

next batch of solar home systems to be funded by AusAID and REP II. It was agreed that the TOR for

local VOPS consultant to be hired under REP II will also include developing withdrawal guidelines and

verify the actual stock of withdrawn SHSs as reported by PESCO.

Component B.2. Institutional Strengthening – VOPS Management Contract. Execution of the

contract was fully completed. The consultant has completed (i) implementation support to DOE in

management of the SHS program, achieving 100% of the program targets on time; (ii) assessment of the

cost and efficiency of the implementation arrangement for SHS program and provided recommendations

on improvement, including recommendations on regulatory modifications of cost and charges for PESCO

services, and monthly charges for consumer payment, which were adopted by MEM; (iii) identification of

nine new PESCOs and training of new PESCOs, which have delivered the targeted SHS installation under

Component B.1 and are managing the operations of the installed SHS systems in their licensed provinces;

(iv) development of delivery models for micro hydropower technologies for off-grid electrification and

completed feasibility study for 13 micro hydropower projects side, for solicitation of private investment.

The VOPS has updated the Off-grid Operation Manual incorporating the regulatory changes and delivery

models for micro hydro and has fullfilled in full as a result of performance evaluation of the Quality

Insurance (QA) Surveyor, an international firm hired as an independent monitor for checking and

verifying the performance of the VOPS Contractor. Upon completion of the VOPS Contract, DOE has

conducted a full assessment of the performance of the VOPS Consultant with assistance of the Quality

Assurance Surveyor and paid bonus to the VOPS Contractor for excellent performance as specified in the

contract.

Page 12: LAO PDR: Implementation Support for the Rural ... · 5.01 (c) of the IFC-EdL Loan agreement. 11. Norad Co-financing. Norad grant agreement which provides parallel financing to REP

12

Off-grid Customer Database. The mission was informed that the VOPS Manager developed by the

VOPS Consultant is no longer used due to insufficient information provided in the system and difficult to

operate. The FM Consultant has developed the REF Management System. The functions currently

provided in the completed portion include:

Keep track of the monthly inflow and outflow in aggregated amounts;

PESCO’s performance indicators;

Monthly movement transactions in terms of units and amounts, such as new customers to be

installed to calculate the planning and installation fees, no. of customers and amounts collected to

calculate the net inflow, etc.

The portion to be developed will be the off-grid customer database to track the customer movement in

detail by customer and provide the outstanding debt per customer. In order to obtain the complete

customer database, a lot of data will need to be re-entered in the new system. As most of PESCO do not

have computer skill, the mission recommends that some staff be recruited to handle the data entering at

the central level.

Component B.2 Institutional Strengthening - Quality Assurance (QA) Surveyor. The final report of

the QA surveyor was submitted in June 2010. Activities have been completed and no further updates

required.

Component B.3 Alternative RE Delivery Models. The revised Rural Electrification Fund (REF)

Operation Manual was endorsed by the MEM in May 2010. However it has not been translated into Lao

language. DOE plans to further update the Operations Manual and translate to Lao language by the end of

2011, using remaining funds from GEF under REP1.

Component B.4 Rural Electrification Master Plan and Database. The consultant contract for Rural

Electrification Master Plan was completed by September 2010 as originally planned. The final workshop

was held in July 2010 and was attended by the Bank team.

Component B.5 Sector Financing Strategy. Activities completed and no further updates from the last

Aide Memoire.

Financial Management

Disbursements. As of May 29, 2011, the cumulative disbursements amounted to:

IDA Grant H2180 - SDR 6.283 million (US$ 9.509 million equivalent) out of the total

original IDA Grant of SDR 7 million (89.76%),

GEF Grant TF056700 - US$ 3.749 million out of total GEF Grant of US$ 3.75 million

(99.98%)

AusAID Grant TF096084 - US$5.862 million out of total AusAID Grant of US$9.42 million

(62.23%)

Due to overruns in some categories under IDA Grant H2180, the reallocation has been approved

by the Bank since February 2011. For some reasons, the revised allocations have not yet been reflected in

the Client Connection, the Bank concerned department has been noticed and the revision should be made

very soon. According to the current exchange rate, the Project has exchange gain of $650,000 from IDA

Page 13: LAO PDR: Implementation Support for the Rural ... · 5.01 (c) of the IFC-EdL Loan agreement. 11. Norad Co-financing. Norad grant agreement which provides parallel financing to REP

13

Grant H2180. The team recommends that the two IAs should monitor closely the movement of the

exchange rate and come up with the agreed plan to utilize the exchange gain within the closing date of

March 2012. The team noted that the disbursement grace period up to 4 months has not been provided for

both IDA Grant H2180 and GEF Grant TF056700, internal process will be arranged by the team with the

Bank concerned department soon.

Under AusAID Grant, the funds provided to EDL are to finance several large goods and

consultant contracts which can be paid via direct payments or special commitments, therefore, no

designated account (DA) will be opened by EDL. For DOE, a small amount of DA ($30,000) will be

opened to pay the consultants.

Management of REF Reflow Account for P2P. The amount pre-financed by EDL for payment

of coupons under P2P activity as of May 2011 amounting to approximately US$1.1 million, together with

US$60,000 under pilot project has not been reimbursed to the Project. The mission was informed that a

separate bank account has been set up to hold the repayment of 20,000 kip per month from the households

under P2P activity. The mission has consulted internally with the Bank concerned departments for the

amendment of the Grant Agreement to allow the reimbursement of the amount pre-finance by EDL under

sub-loan category, which is currently not available. Once it is done, the pre-financed amount can be

reimbursed by EDL using the SOE form, no supporting document is to be attached to the withdrawal

application.

Interim Financial Reports (IFRs). The quarterly IFRs have been submitted with delays by both

EDL and DOE. The mission would like to remind EDL that the financing agreement requires that

quarterly IFRs be submitted to the Bank within 45 days after the end of each quarter.

The Discussion of Progress Report prepared by DOE outlined several serious issues, some of

which have been outstanding for long and raised during the previous missions, but have not yet been

addressed. The mission strongly recommends that the appropriate measures should be developed to

address these issues:

Several advances by the Project Manager amounted to US$7,870 have been outstanding for

long time, some of them are outstanding since last year. In addition, the expenses to attend

the SD week in Washington D.C. in February 2010 by four project staff has not yet been

reimbursed to the project. The mission recommends that all advances should be cleared

within 10 days after the end of the activity, the longer the advance is outstanding, the more

possibility that the supporting document cannot be provided. For the claim of overseas

travel, all supporting document are required, except for per diem which is to be provided at

the rate not exceed the Bank provided to its own staff. Please refer to the previous aide

memoire for more detail.

The current collection scheme for small equipment, e.g. 20w SHS, does not support the

sustainability of the REF Reflow Account. The expenditures incurred from installation of the

small equipment scales are much less than the total inflow, hence, resulted in negative inflow.

The DOE should carefully review the collection scheme to ensure the sustainability of the

REF Reflow Account so that the customers can benefit the most from such system even after

the withdrawal of the donor support.

Since the departure of the VOPS contractor from January 2010, the inflows to the REF

Reflow Account (the amount collected and transferred by PESCOs) has been reduced

significantly ($7,000 per quarter compared to $9,000 per month). It is noted that some

PESCOs transferred only 1-2 times since January 2010, more than 50% of PESCOs did not

transfer any collection during the first quarter of 2011 (January to March 2011). The new

Page 14: LAO PDR: Implementation Support for the Rural ... · 5.01 (c) of the IFC-EdL Loan agreement. 11. Norad Co-financing. Norad grant agreement which provides parallel financing to REP

14

VOPS should be selected as soon as possible to resume the administrative and monitoring

tasks. During this period, DOE should monitor and follow up all issues closely, proper action

should be taken immediately to investigate and resolve the issues.

During the field visit to Champasak, the mission met with Champasak PESCO, and was

informed that he has not transferred the fund collected from the customers to the REF Reflow

Account since October 2010, as he is not happy that he has not received bonus, which should

have been paid since June 2010. According to DOE, one bonus has been paid by VOPS in

January 2010 to all PESCOs, which should be the bonus for the year 2009. The DOE is

currently working on the bonus to be paid for the year 2010. The mission recommends that

DOE communicate clearly with all PESCOs when bonus for the year 2010 will be paid and

all PESCOs should be requested to clear all debts.

Currently, there are several PESCOs with very poor performance which seldom or have never

transferred the funds collected from the customers to REF Reflow Account since the absent

of the VOPS – Khammouane, Borkeow, Savannakhet, Sekong, Xayabuli – Paklai and

Vientiane. The poor performance PESCOs should be evaluated and terminated. However,

the terminated PESCOs should be forced to clear all the outstanding debts, The mission

recommends that the DOE should consider whether any mechanisms should be added to the

existing PESCO selection criteria in order to prevent such problems occurring in the future,

such as DOE staff be assigned to responsible for following up closely with PESCO during the

selection period of the new VOPS, interest to be charged if funds are not transferred within

certain period, performance bond to be requested from PESCO, etc.

Significant increase in PESCO debts with total balance of 471 million Kip as of March 2011

(150 million Kip as of June 2010 and 358 million Kip as of December 2010). The DOE

should investigate the reason and a mutually agreed timeframe should be agreed for the

settlement of the outstanding debts. In addition, the PESCOs should be requested to confirm

the amount owed to the DOE quarterly, any discrepancy can then be investigated and

resolved promptly.

The cumulative withdrawn equipments as of March 2011 was reported as 2,728 units

(increased from 2,140 units in June 2010). Proper procedures have not yet been developed

for the administrative of the withdrawn equipments, such as confirmation of the withdrawn

equipment kept by PESCO, physical count by VOPS to check the existence and working

condition, etc.

Audit of FY2009. Two separate audit reports were submitted to the Bank for MEM and EDL

components on June 30, and July 6, 2010 respectively. The audit opinions are unqualified. The audit

report of EDL entity has just been submitted to the Bank on November 5, 2010 and the audit opinion is

unqualified. The management letter of EDL entity has just been submitted to the Bank during the mission

(on May 25, 2011), and outlined several weaknesses in internal control and operational procedures which

should be brought to the management attention as follows:

No aging report was prepared for accounts receivable, BS-2000 system is not able to generate

the complete aging report. Allowance for long outstanding debt was only providd at 3% of

total revenue excluding export sales.

No formal debt collection procedures in place. There are written policies and procedures on

debt collection. Different branches have different methods in collecting debts and there is no

follow by head office on the results of debt collection.

There is a difference of 817 million Kip between the balances of accounts receivable per

general ledger (G/L) and billing system (BS-2000) at VTE Municipality.

Page 15: LAO PDR: Implementation Support for the Rural ... · 5.01 (c) of the IFC-EdL Loan agreement. 11. Norad Co-financing. Norad grant agreement which provides parallel financing to REP

15

In July 2009, EDL made late payment for the personal income tax to the tax authorities. In

December 2009, incorrect amount was paid, and the different was settled in March 2010.

No segregation of duties between the staff who verifies the meter to the staff who records the

details before posting in the system at VTE Province. The preparer and the verifier were the

same person.

Fixed asset register is not updated.

The depreciation expense for the new fixed asset acquired during the month is calculated as if

the asset is acquired on the first of the month.

There was no specific vehicle log book maintained for all of the motor vehicles of the

Company.

No reconciliation was performed for Capital in Progress (CIP) transferred.

No insurance have been purchased for all the motorcycles kept in Nam Nguen 1.

Audit of FY2010. For EDL, E&Y has been appointed by EDL as its auditor for FY2010 and

FY2011. The audit field work has almost finished and the audit report is expected by the deadline of

June 30, 2011.

For MEM, the previous auditor has been subsequently evaluated as not acceptable to the Bank, therefore,

after the end of the audit contract, MEM is requested to select a new auditor. However, the selection

process has been carried out slowly until recently. The audit report is not expected by June 30, 2011.

Environment and Social

Please refer to Annex 9.

Page 16: LAO PDR: Implementation Support for the Rural ... · 5.01 (c) of the IFC-EdL Loan agreement. 11. Norad Co-financing. Norad grant agreement which provides parallel financing to REP

16

Annex 3: REP I AusAID Additional Financing - Implementation Progress and Agreed Actions

The Grant Agreement for the AusAID additional financing for REP I was signed on October 1, 2010 and

became effective on October 14, 2010. The AusAID financing of US$9.42 million was to fill in a

financing gap on grid extension in order achieve the project outcome of connecting 42,000 households

and to scale up the impact of several other components. The table below presents AusAID financed

activities, associated targets.

Table 1: Additional Financing Activities vs. Original Project Components

REP 1 Original Project

Components

Additional Financing

Activities Cost

(US$ m)

Remarks

A. EdL Component

A.1 Grid Extension 38 distribution subprojects 6.24 Fill in financing gap to

connect 11,500 HH

P2P * 0.60 Scale up impact to

connect 8,000 HH

A.6 DSM and EE hiring energy coordinators and TA 0.10 Scale up impact

B. MEM Component

B.1 Off-grid Investment procurement of SHS

2.00 Scale up impact to

connect 5,000 HH

B.3 Alternative RE

Delivery Model

micro hydro

TA to pilot biomass power plant

0.28

0.10

Scale up impact to

connect 250 HH

B.6 Organizational

Strengthening of DoE

hiring an international procurement

consultant;

training for DoE’s procurement capacity

building

0.10

Scale up impact

Total - 9.42 -

Component A.1 Grid Extension (US$6.24 million). EdL has signed seven contracts for goods and

materials for the AusAID-supported grid extension for a total value of $5,995,271. Construction of the

grid extension has commenced and completion is expected by end of September 2011. It is expected that

7475 out of the target of 11,500 household connections will be achieved by March 31, 2012, with the

remainder to be achieved under P2P. The number of household connections as of May 2011 is reported to

be 1,874. Progress of household connections for each of the target provinces is summarized in the table

below.

Progress of AusAID-supported Grid Extension

HHs Connected Target HH Connections

Province On-Grid P2P On-Grid P2P

Bolikhamxay 181 1032 809 1900

Khammouan 464 645 1,580 1000

Savannakhet 460 423 2,553 800

Saravan 163 856 1,416 1700

Page 17: LAO PDR: Implementation Support for the Rural ... · 5.01 (c) of the IFC-EdL Loan agreement. 11. Norad Co-financing. Norad grant agreement which provides parallel financing to REP

17

Sekong - 342 925 1000

Champasak 606 653 2,722 1200

Attapeu - 233 1,561 400

TOTAL 1874 4184 11566 8000

Power to the Poor (P2P) (US$0.6 million): In the past, EdL has been reporting that P2P connections in

the northern provinces would be covered under AusAID. To date, 1, 952 households have been

connected in the north. However, there is no reason that AusAID financing should be restricted to the

North and the team discussed with EdL to modify its reporting to allow all households connected from

October 1, 2010 (the signing date of Ausaid) through March 31, 2012 to be claimed as P2P connections

under REP I AusAID up to an amount of $600,000. It was agreed that EdL would submit the new

reporting tables by mid June with the revised figures. The team also expressed its satisfaction that the

P2P unit is including data on female headed HHs and HHs with people with disabilities in its reporting.

During the mission, it was discovered that the Financing Agreement and Disbursement Letter would need

to be amended in order to allow disbursement of P2P as a subloan as the current withdrawal schedule only

includes disbursement categories for goods and consultants’ services. It was agreed that EdL would

formally request an amendment to the Financing Agreements for both AusAID additional financing and

REP II by June 15, 2011. The team also discussed the need for the Operations Manual to be updated to

include provisions for the use of the P2P revolving fund which would be a condition for disbursement.

Once this is completed, EdL can request to be reimbursed for households connected on or after October 1,

2010 (the signing date of the Grant Agreement).

Component A.6 DSM and EE (US$0.1 million). Building on earlier activities, it was agreed that EdL

would appoint ten energy coordinators under the AusAID additional financing to continue implementing

energy efficiency initiatives in government buildings and in doing so, support the DSM/EE activities to

be supported under REP II. Following the Bank’s no objection to sole source IIEC provided on May 29,

2011, EdL agreed to immediately contact IIEC to finalize the draft contract and submit such contract

(using the sample contract for small assignments provided) to the Bank no later than June 15, 2011.

(IIEC was the original firm recruited to assist EdL in implementing the DSM/EE component under REP I.

The Bank agreed to a sole source selection for IIEC during an interim period of Phase 1B and Phase 2 to

prepare protocols, specifications and bidding documents of low-cost and medium-cost EE measures for

46 public sector buildings, to assist the DSM Cell to recruit new energy coordinators (ECs), and to scope

out and prepare Phase 2 implementation plan.) The team stressed the urgency of mobilizing IIEC as soon

as possible so that they can assist EdL in recruiting and managing the energy coordinators. AusAID

financing can be used to finance the EC contracts up to March 31, 2011 after which they can be financed

using Norad funds under REP II.

The timetable below was agreed with EdL for appointing IIEC and hiring the energy co-ordinators:

1. IIEC draft contract sent to Bank June 15, 2011

2. Mobilization of IIEC July 1, 2011

3. Contract ten energy coordinators July 31, 2011

4. Completion of recruitment and training September 30, 2011

program for energy coordinators

5. End of IIEC assignment December 31, 2011

Page 18: LAO PDR: Implementation Support for the Rural ... · 5.01 (c) of the IFC-EdL Loan agreement. 11. Norad Co-financing. Norad grant agreement which provides parallel financing to REP

18

Component B.1 Off-grid Investment for Solar Home Systems (US$2.0 million). It was agreed that

DOE would prepare a single bid document to procure about 15,000 SHSs in two lots for a total estimated

cost of $6 million ($2 million from AusAID financing under REP I and $4 million under REP II3).

Unfortunately, the bid document has experienced protracted delays. The Bank received the revised draft

bid document on April 18, 2011 and provided preliminary comments on the commercial terms on May

24, 2011 to allow DOE to respond with an alternative proposal on its desire to request the supplier to

submit a sample. It is expected that the no objection to the bid document will be issued by June 3, 2011.

The team raised its serious concern that further slippages in the revised procurement timetable could

result in the goods not being delivered by the REP I closing date of March 31, 2011 and urged DOE to

undertake its best efforts to adhere to the agreed schedule below. In addition, it was agreed that the

delivery schedule for Lot 1 would be 90 days and the spare parts would be moved to Lot 2.

In addition, the team queried the proposed allocation of SHS by province in the bid document since about

25% of the SHS are expected to be installed in Khommoune, Savannakhet and Xayabir provinces for

which the PESCOs have been particularly poor performers and have failed to remit funds to DOE.

Therefore, DOE agreed to re-evaluate the allocation of SHSs by province in order to reconcile the

provincial requests with both the RE Master Plan and the performance of PESCOs by September 15,

2011 to allow sufficient time for the PESCOs to submit their cluster plans. In order not to delay the

issuance of the bid document, the team reserved the right to discuss and agree with DOE the final

breakdown by province before the final contract is signed.

Timeline for SHS Procurement

Milestones Timeline as of Sep 2010 Updated Timeline as of 29 May

2011

Draft Bidding Documents

submitted to the Bank for review

By February 28, 2010 June 1, 2011 (June 14, 2011-A)

NOL to Bidding Documents By April 30, 2010 June 3, 2011 (June 16, 2011-A)

Advertising By May 7, 2010 June 20, 2011 (June 22, 2011-A)

Receiving of Bids By June 30, 2010 August 1, 2011

BER Submitted for Bank NOL - September 5, 2011

NOL to BER By August 31, 2010 September 20, 2011

Signing of Contract / Effectiveness By September 15, 2010 December 31, 2011

Delivery of Goods – Lot 1 By December 31, 2010 March 31, 2012

Delivery of Goods – Lot 2 - Between June 30 and Sep 30, 2012

Complete installation of Lot 1 - May 31, 2013

Completion of all installations By June 30, 2011 December 31, 2013 including time

for wet season delays

Component B.3 Alternative RE Delivery Model - Micro Hydropower Schemes (US$0.28 million). In

December 2009, DOE appointed IFC as lead transaction advisor to assist in the implementation of a pilot

PPP (Public Private Partnership) transaction to electrify a number of villages using micro hydro systems.

3 During the mission, it was subsequently agreed that $300,000 under REP II should be reserved to support the PPP

microhydro pilot schemes in Houaphan province. In this regard, it is noted that bid document allows for variation of

+/- 33 percent.

Page 19: LAO PDR: Implementation Support for the Rural ... · 5.01 (c) of the IFC-EdL Loan agreement. 11. Norad Co-financing. Norad grant agreement which provides parallel financing to REP

19

While this procurement method is common for large infrastructure projects internationally, it will be the

first time this model is has been attempted for such small investments, or in Lao PDR at all. The IFC TA

is split into 2 phases – Phase 1 covers a technical review of potential sites, legal and regulatory review,

and transaction structuring; Phase 2 covers implementing a competitive tender to select a private investor.

IFC Phase 1 Transaction Structuring Report was submitted in December 2010. The report recommended

moving forward with two pilot public private partnership (PPP) microhydro schemes in Houaphan

province as follows:

1. Paonuea Village Micro Hydro Facility and Distribution System: 119 households, system capacity

21.4 kW (equivalent to 180 watts x no. of households)

2. Paotai Village Micro Hydro Facility and Distribution System: 102 households, system capacity

18.36 kW (equivalent to 180 watts x no. of households)

DOE would select a private partner to construct and operate these two micro hydro systems in Houaphan

province. The partner will be selected through a fully transparent competitive tender with a single bid

criterion: capital subsidy needed. The estimate for total REF funds needed is approximately $500,000.

This is split in two components:

A fixed "Availability Payment" of approximately $50,000 per year for the life of the project (5

years)

A "Capital Subsidy" payable at the beginning of the project. The amount will depend on the bids

received, but is expected to total about $275,000.

There is $280,000 available under REP I AusAID additional financing to finance the capital subsidy (as

long as the payments become due prior to the March 31, 2012 closing date) and another approximate

$300,000 under REP II IDA financing. The team pointed out to IFC and DOE that at least the last two

years of the availability payment will fall outside of the REP II closing date of June 30, 2014. Therefore,

these payments would need to be financed from the REF account. It was agreed that IFC would develop a

projection of estimated REF monthly payment obligations between now and the end of the concession to

inform how much AusAID, IDA and REF reflow funds would be utilized.

During the mission, IFC, DOE and the Bank discussed the draft Bidding Memorandum, License

Certificates and License Terms and Conditions. Based on these discussions, IFC will revise the

documents and advertise this week for potential bidders to comment on the draft transaction document.

The indicative transaction timetable

Indicative Transaction Timetable for Micro Hydro PPP Development

Milestones Timeline

proposed by IFC

Revised timetable

(to be vetted by

DOE)

Draft Transaction documents sent to

bidders

June 1, 2011 June 1, 2011

Bidder meetings to discuss transaction

documents

June 9-10, 2011 June 9-10, 2011

Draft transaction document sent for June 15, 2011

Page 20: LAO PDR: Implementation Support for the Rural ... · 5.01 (c) of the IFC-EdL Loan agreement. 11. Norad Co-financing. Norad grant agreement which provides parallel financing to REP

20

Bank NOL

Bank NOL June 24, 2011

Final transaction documents sent to

bidders

June 27, 2011 June 27, 2011

Bid submission date July 18, 2011 July 18, 2011

Opening financial bids and

announcement of successful bidder

July 22, 2011

Bid evaluation report submitted for

Bank NOL

Bank NOL

Announcement of successful bidder

Signing of license certificate July 29, 2011

Given the time needed to appoint the evaluation committee, it was agreed that DOE would initiate the

process to appoint the committee immediately and ensure that before confirming the members that they

would be available during the evaluation period.

Component B.3 Alternative RE Delivery Model - Pilot Biomass/Biogas Power Plant (US$0.1

million). DOE proposed to focus this activity on a pilot biogasification plant using pig manure and

proposed to extend Chiang Mai University’s current contract to cover the detailed design for and

construction supervision of such a plant. During the last mission, it was agreed that AusAID would fund

the detailed design, preparation of technical specifications of the plant for the pilot demonstration site

within the available budget. In the previous mission of September 2010, DOE had agreed to submit the

TOR/estimated budget for the detailed design and the preparation of the technical specifications for the

Bank review by September 30, 2010.

Given the delays in submitting the TOR, the team discussed a revised scope for the assignment that would

include the above mentioned activities in addition to the development of financial model to assess the

sustainability of the scheme and size of required subsidy, environment and social impact assessment,

calculation of environmental benefits in terms of GHG emission reductions (for GEF purposes), proposed

contractual arrangements, and the design of a monitoring report for farmers to regularly report to DOE on

key performance parameters. The first phase of the work would cover four pig farms in order to ensure

that at least one demonstration project was constructed under Phase 2. During the first phase of work, the

consultant would propose a methodology for selecting farms in a transparent and competitive manner

since a government subsidy would be involved if the biogasification programme was scaled up beyond

the initial demonstration project(s). Phase 2 of the work would include the supply and installation for at

least one pilot demonstration project. DOE agreed to submit a draft TOR, cost estimate and justification

for the sole source selection of Chiang Mai University no later than June 30, 2011. The procurement

schedule is as follows:

Timeline for Pilot Biogasification Plant

Milestones Timeline

DOE provides draft TOR, cost estimate and request for SSS June 30, 2011

Bank provides NOL Mid July 2011

Page 21: LAO PDR: Implementation Support for the Rural ... · 5.01 (c) of the IFC-EdL Loan agreement. 11. Norad Co-financing. Norad grant agreement which provides parallel financing to REP

21

Draft negotiated contract submitted to the Bank July 31, 2011

Contract award for Phase I End August 2011

Submission of Final Phase I report End February 2012

Component B.6 Organization Strengthening of DOE (US$0.1 million). The international procurement

consultant to support DOE under REP as well as to support another department of MEM under the Bank’s

Hydro Mining Technical Assistance Project (HMTA) was mobilized in January 2011. The contract is for

a total of 12 man months over an 18 month period. The team learned that DOE has been financing 50%

of the contract under REP II Norad financing instead of AusAID additional financing under REP I. The

team instructed DOE to finance 100% of the payments under AusAID additional financing from now

until the closing date (March 31, 2012) and from thereon, pay 100% under HMTA. The team also

requested DOE to provide an estimate of the payments due between now and March 31, 2012 to

determine how much excess funds from the $100,000 may be unused under the contract.

Page 22: LAO PDR: Implementation Support for the Rural ... · 5.01 (c) of the IFC-EdL Loan agreement. 11. Norad Co-financing. Norad grant agreement which provides parallel financing to REP

22

Annex 4: REP I Status of the Implementation of the Action Plan for Financial Sustainability of the

Power Sector (2005-2010)

Implementation of the Action Plan for Financial Sustainability of the Power Sector (2005-2010) is on

track. Status of agreed actions is summarized in the sections below.

1. Annual Tariff Adjustment. The tariff adjustment for 2010 according to the Tariff Adjustment

Plan (2005-2010) endorsed by MEM in 2005 is on track. Following the Bank’s comments during the last

supervision mission, EdL submitted the updated Tariff Adjustment Plan with an annual average increase

of 6% in the next five years (2011-2016) with reduced amount of capital investment by EdL to around

US$ 758 million for MEM’s approval in May 2010. The Plan has been submitted to the Prime Minister

Office by MEM, but not yet approved by PMO. The team urged EDL and MEM closely follow up the

PMO approval.

2. Settlement of Arrears. For settlement of the Government arrears up to September 2005, LAK 113

billion, payments from MOF to EdL over 2005 through 2009 were in line with the settlement plan agreed

between the two (see Table below). Due to insufficient budget allocated by MoF to settle the annual

consumption, the total arrears as per April 2011 remains LAK 84,821 billion. MoF has committed to

allocate another LAK 38 billion to settle the verified arrears before September 2011. The table below

shows the latest status of government arrear.

Status of Government Arrears and Settlement Plan as of April 2011

Unit: MILLION LAK

MOF Fiscal

Year (Oct-Sep) Total bill

Collected from

GoL Agencies Arrears

MOF

Settlement

Payment

Outstanding

Accumulated

Arrears

As of 9/2005 113,478.47

2005-2006 78,849.67 38,717.44 40,132.24 18,758.00 21,374.24 134,852.71

2006-2007 71,344.86 41,561.11 29,783.75 24,134.00 5,649.75 140,502.46

2007-2008 83,323,85 65,465.21 17,858.65 40,000.00 (22,141.35) 118,361.10

2008-2009 89,319.65 63,386.87 25,932.78 48,000.00 (22,067.22) 96,293.88

2009-2010 101,322.25 33,701.43 67,620.82 69,793.57 (2,172.75) 94,121.12

April 2011

9,300.12

84,821.01

3. Arrears from Irrigation continues to increase from the last mission. The accumulated arrears as

of June 2010 were LAK 70 billion. To reach an agreement on settlement of the arrears and solutions for

preventing new irrigation arrears from occurring, EdL held a workshop in June 2010 with concerned

government agencies to discuss the issues and possible solutions, including installation of pre-paid

meters. A committee led by MoF and comprising representatives from EdL HQ, EdL branch offices,

MOF, Ministry of Agriculture, and Prime Minister Office was set up to collect data and provide

recommendations. The draft report has been prepared and will be shared with the Bank. The main

findings are as follows:

(a) Water consumption rate has been set unreasonably, which could not cover the electricity

consumption for pumping water;

(b) Water use fee collected has been used for other purpose than electricity bill settlement; and

(c) Inefficiency of irrigation systems.

Page 23: LAO PDR: Implementation Support for the Rural ... · 5.01 (c) of the IFC-EdL Loan agreement. 11. Norad Co-financing. Norad grant agreement which provides parallel financing to REP

23

4. The committee will meet on June 1 to discuss on the findings and make recommendation to the

government. The Bank advises that the committee should look at three aspects:

(a) policy issue: will government provide subsidy to farmers covering electricity for

irrigation water, if so, government should allocate government budget to finance such

subsidy. Being a services provider, EDL should not cover the subsidy.

(b) collection system: find out if EDL can collect the electricity bill directly for the water

users;

(c) getting data on actual water consumption by individual household..

5. Demand Side Management and Energy Efficiency (DSM & EE). A DSM and EE Cell was

created within EdL and entered into full operation in the early stage of REP I implementation. All planned

training activities under REP I were completed. A DSM and EE Strategy was prepared and an action plan

including the first-stage no-cost and low-cost measures proposed for DSM/EE at major government

agency consumers was under implementation in four pilot buildings. Further implementation of the plan

will be done under REP II. Please see Part B on preparation of DSM/EE activities under REP II.

6. Operational Efficiency. The system loss reduction activity under the rural Electrification APL

Program aims to reduce the system loss from more than 20% in 2005 to 17% by the end of the REP I and

13% by the end of REP II. During January to July 2010, the distribution system loss was reduced to

11.44%, achieving the REP II target.

Page 24: LAO PDR: Implementation Support for the Rural ... · 5.01 (c) of the IFC-EdL Loan agreement. 11. Norad Co-financing. Norad grant agreement which provides parallel financing to REP

24

Annex 5. REP I Status of Key Performance Indicators

Objectives and indicators Baseline 2006 End of Project Target

Values

Progress Remarks

Global Environmental Outcome

"Market share"of off-grid

renewable HHs under REP

I

8% of "Market share"

of off-grid renewable

HHs during SPRE

19% of newly

electrified households

have solar/VH

22% Target exceeded.

Final objective of

reducing CC gas

emissions was

achieved through

loss reduction of a

comparative 18.85%.

Measurable increase in

awareness and adoption of

energy efficiency

technologies and practices

by Government agencies

and other EdL customers

A complete lack of

awareness by EdL

customers

100% central

government agencies,

20% of domestic and

33% of commercial

customers aware of

energy efficiency

Survey to be

conducted at the later

stage of the REP I to

measure the

percentages.

Project development Objectives

Numbers of villages and

HHs electrified

About 428,000 by the

end of 2004

Increase villages and

HHs electrified by

about 250 and 42,000,

respectively

Increase of villages

electrified by 671

(441 by the grid and

230 by SHS) and

the number of HHs

electrified by 63478

Implementation status of

the Sustainability Action

Plan

Tariff adjustment

initiated in July 2005

Satisfactory

implementation of the

Sustainability Action

Plan

1) Tariff reform

2) Loss reduction

3) DSM & EE EDL

Cell established

4) Arrears

- Settlement of the

committee

- Enough budget

allocated

1) New average

tariff of 673

Kip/Kwh (USD

0.084) to be ratified

by the MEM and

start being applied

on the 1st of July.

2) 10.55% system

losses (18.85% in

2009)

3) Completed.

4) GoL agencies

Arrears: 18 months

- Operational

- Unsatisfactory

EdL-Grid electrification

Number of villages

electrified

Number of HHs electrified

2004 access levels-

about 428,000 HHs in

about 35% of villages

Add 42,000 HHs in

540 villages in the 7

central provinces

441 (82%) villages

electrified; 32,168

HHs in addition to

(17,229 disadvant-

aged rural families

connected to the

grid under the P2P.

AusAID Additional

Financing is to fill a

financial gap to reach

the original target –

11,500 HH connected

by EdL and an

additional 8,000 HH

under P2P.

EdL-Reform & Improved

Efficiency

Rate of return on revalued

assets; debt service

2004 financial

performance indicators

RRRA>4%

DSCR>1.5 times

SFR>30%

1%

DSCR 1.69 times

SFR 35%

See details in Annex

A2 below.

Page 25: LAO PDR: Implementation Support for the Rural ... · 5.01 (c) of the IFC-EdL Loan agreement. 11. Norad Co-financing. Norad grant agreement which provides parallel financing to REP

25

coverage ratio; self-

financing ratio; account

receivables

AR<2 months

AR= 2.4

Overall system losses About 22% in 2005 System losses below

17%

10.55%

Establishment of DSM cell

and implementation of pilot

DSM/energy efficiency &

awareness building

programs

Energy audit and other

pilot programs

implemented

Established and

operational. 50 GoL

central agencies

energy audited and

no-cost and low

cost efficiency

measures in 4 pilot

buildlings.

Further

implementation of

action plan to be

done under REP II

MEM-Off-Grid Electrification

Number of villages

electrified

200 villages, 17

provinces

230 villages, 17

provinces

AusAID Additional

Financing for an

additional 5,000 SHS

to scale-up impact.

However

procurement has not

yet begun and there is

a risk that the goods

would not be

delivered by the

closing date.

Number of HHs electrified Currently 6,000 HHs

in 7 provinces

10,000 new HHs 14,081(98%) by

SHS

Village hydro share in HHs

electrified through off-grid

Only 150 out of the

6,000 HHs not SHS

1,000 (10%) HHs

through VH

0

MEM-Reform & Improved

Efficiency

Development of alternative

delivery model

Only hire-purchase &

MEM delivery

Alternative delivery

models developed

Completed

Development of legal,

regulatory and institutional

arrangements for the REF

REF established with

issuance of Prime

Minister’s Degree in

August 2005

REF opened to other

participants

REF established and

operational

Fully satisfactory.

Development of a sector

financing strategy and pilot

projects

Recommendations

made by consultants

on sector financing

strategy

Sector financing

strategy developed and

legal documents for

concessioning small-

hydro projects to IPPs

prepared

Completed

Establishment of RE

Master Plan and Database

Initial version of RE

database developed

Initial RE Master Plan

and RE Database

developed

Initial RE Master

Plan and RE

Database developed

Fully satisfactory.

Implementation of Action

Plan for DoE organizational

strengthening

Development of

Action Plan under way

Completion of Action

Plan

Achieved

Page 26: LAO PDR: Implementation Support for the Rural ... · 5.01 (c) of the IFC-EdL Loan agreement. 11. Norad Co-financing. Norad grant agreement which provides parallel financing to REP

26

Annex 6: REP II Implementation Progress by Component

Under REP II, IDA is financing goods and incremental operating costs (no technical assistance) for EdL

and DOE; IFC is financing grid extension with EdL; Norad is financing technical assistance and capacity

building for EdL and DOE; and GEF is financing goods, services, training and incremental operating

costs for components A.2(a), A.5, B.3, and B.5.

The overall implementation progress is rated as marginally satisfactory given the approximate one year

delay in procurement vis-à-vis the dates in the project appraisal document. As a result, no significant

disbursements have taken place against a target disbursement of $10.5 million by end FY11. Detailed

progress by component is discussed below.

EdL Component

Component A.1 Grid Extension (IDA US$14.6 million4 + IFC US$15 million; Norad $0.5 million for

TA). (a) installation and commission of MV and LV transmission lines, transformers, and house wiring

to cover about 27,700 households in the project provinces; and (b) provision of technical advisory

services to EdL in project implementation and supervision, and capacity building for economic and

financial evaluation, project management, and procurement.

It was agreed that the procurement for grid extension under REP II would be divided into 5 packages of

goods (funded by IDA and IFC) and one package of installation (funded by EdL). All goods packages

would be procured using ICB. EdL’s detailed project cost estimate submitted during the mission is as

follows:

(in US$ millions)

Contract EdL IDA IFC Total

REP 1/1 Overhead conductors 3.55 6.45 10.00

REP 2/1 Distribution transformers 0.89 0.80 1.69

REP 2/2 Distribution transformer fitting material 0.51 0.50 1.01

REP 2/3 Distribution line materials 3.37 2.10 5.47

REP 3/1 Concrete poles 3.37 2.10 5.47

REP 3/2 Concrete cross arms 0.45 0.70 1.15

REP 4 Watt hour meters/meter boxes 0.33 0.40 0.73

REP 5 Office equipment 0.25 0.10 0.35

Sub-Total Goods 12.72 13.15 25.87

Works 1 Construction/installation 12.00 12.00

Works 2 Info for Outreach to Villages 0.10 0.10

Works 3 UXO Clearance 0.22 1.60 1.82

GRAND TOTAL 12.32 12.72 14.75 39.79

The team proposed to EdL that it might wish to consider dividing the contracts between IDA and IFC as

opposed to having IDA and IFC co-finance each contract as it might reduce the administration burden on

EdL. For instance, IDA could finance REP 1/1, 1/2 and 1/3 and IFC could finance the remaining

4 It was discussed that this amount could be reduced by $230,000 to pay for goods (VPN plus 17 servers) under

Component A.3 for Information Technology. However, as stated earlier, this would require an amendment to the

Financing Agreement as this component is currently not eligible under the IDA Financing Agreement.

Page 27: LAO PDR: Implementation Support for the Rural ... · 5.01 (c) of the IFC-EdL Loan agreement. 11. Norad Co-financing. Norad grant agreement which provides parallel financing to REP

27

contracts; however, it is realized that at least one contract would need to be financed from both sources.

Regardless, EdL would follow WB procurement guidelines for all goods packages.

The procurement under this component has been delayed for almost one year. The bid opening date as

stated in the project appraisal document was June 2010. The revised procurement schedule is provided in

the table below. It is noted that for meters, the timeline might take one month longer since changes to the

technical specifications are required.

Timeline for Goods Procurement under Grid Extension Component

Milestones Timeline/Milestone

Realistic Optimistic

Draft Bidding Documents submitted to the Bank for review Wed 15/6/11 Wed 15/6/11

NOL to Bidding Documents Assume two rounds Fri 15/7/11 Mon 27/6/11

Advertising Mon 20/6/11 Mon 20/6/11

Receiving of Bids Thu 4/8/11 Thu 4/8/11

Prepare BER and Submitfor Bank NOL – Assume two rounds Mon 19/9/11 Mon 5/9/11

NOL to BER Thu 29/9/11 Mon 12/9/11

Contract Negotiations and Signing of Contract Fri 14/10/11 Thu 22/9/11

Date of effectiveness Mon 5/12/11 Fri 11/11/11

Delivery of Goods Thu 3/5/12 Mon 9/4/12

Installation completed Tue 24/12/13 Fri 11/10/13

Project Closing date Mon 30/6/14 Mon 30/6/14

Power to the Poor. There is US$600,000 in IDA financing to scale up the impact of P2P under REP II.

During the mission, the team discovered that an amendment to the IDA Financing Agreement (as well as

to the AusAID Grant Agreement under REP I) is needed to allow the disbursements of “sub-loans” for

P2P credit schemes to poor households under the Project. In order to process this amendment, the team

requested the P2P team to submit by June 30, 2011 (i) the revised P2P operations manual which includes

an overview of the arrangements for the revolving fund and (ii) a list of households connected to date by

province and by month to determine the eligibility for reimbursement under REP I AusAID and REP II of

P2P credit schemes extended to date.

During the last mission, the P2P team raised questions about the availability of funds for the P2P scale-up

and proposed for the following activities and budget.

No Description Budget Proposed (US$)

1 Value of Credit Extended 495,500

2

Cost of EdL's training group, Workshop, social &

environmental group (Posters, Brochures, coupons,

Manuals..) 48,586

3 Miscellaneous Costs (Awareness Materials, Transport) 55,828

Total Budget 599,915

The team clarified that for items (2) and (3) above, IDA resources cannot be used to finance EdL staff

salaries working on P2P. To the extent that any of the items qualify under the definition of “incremental

Page 28: LAO PDR: Implementation Support for the Rural ... · 5.01 (c) of the IFC-EdL Loan agreement. 11. Norad Co-financing. Norad grant agreement which provides parallel financing to REP

28

operating costs5”, expenditures up to US$100,000 can be reimbursed under the Project. The team further

clarified that this US$100,000 for IOC is for EdL as a whole and not specifically for the P2P unit, so the

P2P unit would need to reach agreement within EdL. All other expenses (including pick-up trucks) will

need to be covered by EdL’s own resources.

As per the Project Appraisal Document, Norad will finance technical assistance to EdL in (i) project

implementation and supervision; (ii) capacity building for economic and financial evaluation, project

management and procurement. During the mission, the team discussed with EdL the concept of having

the implementation supervision consultant also assist EdL to establish standardized specifications and

equipment for the whole of EdL. This would help EdL improve future tendering processes, do eliminate

the need for consultants to produce technical specifications, improve spare management of EdL, reduce

implementation and operation cost, and rationalize some of the domestic electricity market. EdL agreed

to submit a draft TOR for this consultancy no later than September 30, 2011.

Component A.2. Loss Reduction (IDA US$1 million; Norad US$0.68 million; GEF US$0.2 million):

(a) enhancement of EdL’s loss reduction efforts through the provision of goods to support the

implementation of prioritize investment projects recommended by the Loss Reduction Master Plan; and

(b) provision of technical advisory services to EdL for nontechnical loss reduction activities.

EdL’s proposal for financing under the Loss Reduction component is as follows:

Project Activity Category Funding

Source

Procurement

Method

Budget

A2.1 Implementation for nontechnical loss Consultancy Norad QCBS 680,000

A2.2 Portable watt hour meter testers 3 phase (14

sets)

Goods IDA ICB 252,000

A2.3 Watt hours meter test bench (1 set) Goods IDA ICB 219,797

A2.4 LV Capacitor Bank Goods IDA ICB 180,000

A2.5 Watt-hour meter Goods IDA ICB 420,000

A2.6 Portable watt hour meter testers 3 phase (16

sets) and Megger Power Clamp 3 phase (35

sets)

Goods IDA ICB 400,000

Sub-total 2,151,797

The team indicated that $200,000 of GEF financing for technical assistance on technical loss reduction is

missing from the above table. It was also clarified that the Norad budget is for loss reduction in general,

and not only nontechnical loss. In addition, some of the project activities above have been financed under

REP I and therefore can be removed the list – EdL to revise proposal.

It was agreed earlier that AusAID would finance a Bank-executed study for nontechnical loss reduction.

The Bank indicated that it would share a draft terms of reference for EdL comment no later than June 30,

2011. Norad financing could be used for consultancy services to assist/train EdL in implementing the

recommendations under the Bank-executed study.

5 “Incremental Operating Costs” means reasonable expenditures directly related to the Project incurred by the

Recipient (which expenditures would not have been incurred absent the Project), including expenditures for Project

staff travel and per diem, office supplies, communications services (including telephone and internet costs),

publication services, translation services, maintenance of office equipment, and maintenance of vehicles, but

excluding civil services salaries of officials of the Recipient’s civil service.

Page 29: LAO PDR: Implementation Support for the Rural ... · 5.01 (c) of the IFC-EdL Loan agreement. 11. Norad Co-financing. Norad grant agreement which provides parallel financing to REP

29

Component A.3 IT System and Financial Management (Norad US$0.3 million): Provision of

technical advisory services to EdL to: (a) integrate the operation of EdL headquarters and branch offices

in the project provinces by making the existing information technology system fully operational; and (b)

strengthen its financial management through the information technology system, which includes

computerized billing and accounting systems.

Since the last mission, EdL has proposed the following budget for IT system under REP II:

1. IT Roll Out. Due to the limited number of IT staff to support the users during the conversion period

and lack of powerful IT equipment to support the day-to-day activities, the EDL has proposed the

action plan to continue the roll out of the Accounting and Financial Management System (AFMS) as

follows:

Acquire the virtual private network (VPN), internet network, which will allow the IT staff to

access remotely to the user system, so that the problems can be investigated and solved timely.

The budget is estimated at $50,000.

Install new servers at all 17 branches which will provide more disk space as the existing server is

run on PC which has limited disk space and caused the system not workable. The budget is

estimated at $170,000.

Engage local IT consultants to assist in system roll out. Enough IT consultants will be engaged

and first trained by the EDL IT staff to get familiar with the EDL IT configurations and the

AFMS. They will then assist to support the users during the conversion period at the provincial

sites. The budget is estimated at $100,000.

2. Financial Model. Budget for updating the financial model according to the new Power Development

Plan including training for EdL Staff (US$35,000)

It was agreed in principle that EdL would prepare a single bid document for the supply and installation

of the VPN plus 17 servers using the bidding document for goods by June 20, 2011. However, the team

highlighted that this component is not eligible for financing by IDA under the Financing Agreement as it

was originally envisaged to only involve technical assistance – and all technical assistance was to be

financed by Norad. Therefore, unless EdL wishes to request an amendment to the Financing Agreement,

this equipment would need to be funded using EdL’s own resources. If an amendment is requested, EdL

FM Dept would need to discuss with the EdL Project Team for managing the Component A.1 to finalize

the IDA funding re-allocation of $320,000 to finance the goods under the IT System Component. For the

engagement of the IT consultants to be financed by Norad, the Bank recommends that the TOR should be

revised to incorporate in more detail the tasks to be performed, required mandate and expected timeframe

to complete the job at all provincial branches. EdL agreed to submit the TOR for the consulting services

for the Bank review by June 20, 2011. The team also advised EdL to initiate the procurement for the VPN

and 17 servers in parallel.

Component A.4. Safeguards Capacity Building (Norad US$0.25 million): Provide goods and training

to EdL and its provincial authority counterparts to strengthen their capacity in management of

environmental and social assessment and impacts associated with distribution and substation projects.

Page 30: LAO PDR: Implementation Support for the Rural ... · 5.01 (c) of the IFC-EdL Loan agreement. 11. Norad Co-financing. Norad grant agreement which provides parallel financing to REP

30

Component A5. Demand-Side Management and Energy Efficiency Program (IDA US$0.3 million;

Norad US$0.75 million, GEF US$0.88 million): Provision to EdL of: (a) goods to support the

implementation of the action plan under the DSM and EE Master Plan; and (b) technical assistance to

implement the action plan.

With the budget available, the priority activities (most of them are in the table below) under the REP II fo

DSM and EE, include:

(i) Hire a firm (like IIEC under REP I) for (a) continuous capacity building of EdL’s DSM and

EE Cell; (b) preparation of priority DSM/EE projects (hospitals, CFL, markets), including

detailed auditing and design for investment, and support and supervise the implementation of

these projects to be funded under REP II (with funding indicated above); (c) mentoring,

training and supporting the energy coordinators to be hired by the DSM/EE Cell under this

component;

(ii) Implementation of the projects (no cost and low cost) recommended by the Master Plan for

DSM and EE developed by the international consultant under REP I;

(iii) Hiring the 10 energy coordinator, and more if needed, to (a) expand walk-through energy

audit of more government office building in Vientiane and in provincial government as well;

(b) help these government agencies at both central and provincial level to implement no-cost

activities, and facilitate implementation of low-cost projects if budget is made available

(either under this component or from government’s own budget)

(iv) Implementation of the priority investment projects as prepared under item (i), according to

budget availability for investment; and

(v) Other activities as listed by the DSM and EE Cell.

It was agreed that the Low-cost investment program at the central government office building as

recommended by the international consultant under REP I should be implemented as a priority. These

activities are targeting to energy saving at the central government agencies, which are the major consumer

default on electricity bill payment, and the MOF is also expecting EE program in these agencies to save

energy consumption so as to save budget allocation and reduce electricity arrears.

EdL proposed the following for financing under the project –the team has provided its preliminary

comments on the proposal as shown in the table below:

Project Activity Category Funding

Source

Procurement

Method

Budget

A5.1 Master Plan and Implementation of the Loss

Reduction Master Plan

Consultancy Norad QBS QCBS 750,000

A5.2 CFL Pilot Project (Residential Customers) in

Vientiane Capital

Goods IDA Shopping 48,000

A5.3 Amplian Standard & Labeling Program Goods IDA Shopping 25,000

A5.4 Office Rental for 10 Coordinators (24 months) Goods IDA EdL Shopping 38,000

A5.5 Public Awareness Campaign Goods IDA Shopping 20,000

A5.6 Office Equipment Facilities for 10 EC Goods IDA Shopping 25,000

A5.7 CFL Pilot Project (Residential Customers) in

Vientiane Province

Goods IDA Shopping 48,000

A5.8 CFL Pilot Project (Residential Customers) in Goods IDA Shopping 48,000

Page 31: LAO PDR: Implementation Support for the Rural ... · 5.01 (c) of the IFC-EdL Loan agreement. 11. Norad Co-financing. Norad grant agreement which provides parallel financing to REP

31

Khammuane Province

A5.9 CFL Pilot Project (Residential Customers) in

Savannakhet Province

Goods IDA Shopping 48,000

A5.10 Hiring Energy Coordinators * Works

Consultancy GEF * IC 170,000

A5.11 EE Pilot Project (Medium Cost)** Goods GEF ICB 398,000

A5.12 EE Pilot Project (Low Cost)*** Goods GEF ICB 200,000

A5.13 EE Awareness Building Campaign Goods

Consultancy GEF IC 11,000

A5.14 EDL Project Manager Cost Cost GEF EdL 20,000

Sub-total 1,849,000

*There is also US$100,000 in AusAID additional financing under REP I for hiring energy coordinators which can

co-finance the contracts with GEF under REP II.

** Develop implementation plan for medium-cost EE measures for all 50 buildings (Medium-cost implementation

plan for 4 buildings have been prepared under REP I)

*** Implementation of no-cost/low-cost EE measures in the remaining 46 government buildings (No-cost/low-cost

implementation plan has been prepared for 50 government buildings and 4 buildings have been piloted under REP I)

The Bank provided its no objection on May 29, 2011 to sole source IIEC for an estimated contract value

of $65,000 to: (1) help EdL recruit energy coordinators; (2) implementation of low-cost EE measures in

the 46 public sector buildings for which plans were developed during Phase 1B in 2009 under REP I; (3)

preparation of medium-cost EE measures in 50 public sector buildings; (4) preparation of a CFL program

proposal for the residential sector; and (5) preparation of DSM/EE Phase 2 scope of works.

MEM Component

Component B.1 Off-grid Investment Program (IDA US$4 million): Application of off-grid renewable

energy technologies, including solar home systems (SHSs) and pico-hydro to provide electricity to about

10,000 households in the project provinces.

The procurement of the bulk purchase of solar home systems under REP II will be combined with the

procurement of solar home systems under AusAID Additional Financing to REP I. See Annex 3 under

Component B.1 for more details

The team reminded DOE that the total budget for off-grid investment is $4 million. Therefore, DOE

should retain some budget from this to cover the investment needs of the PPP microhydro (about

$300,000) and the biomass and biogass investment as needed. DOE should finalize the number of SHS

purchase based on the actual bid prices and budget needs for the items (b) and (c).

Component B.2. Institutional Strengthening (Norad US$0.5 million): Provision of technical advisory

services to MEM to support: (a) the implementation of its comprehensive program of management; and

(b) the monitoring of the performance of the outsourced management and the off-grid investment

program, including provincial electrification service companies (PESCOs) and village electricity

managers.

The Bank provided its no objection to the TOR for the VOPS management contract on May 12, 2011.

DOE has proposed a contract with two phases – each of 18 months duration for a total estimated cost of

$500,000 (to be financed by Norad using Bank procurement procedures). DOE has advertised the

Request for Expressions of Interest (REOI) with a deadline of June 30, 2011. It was agreed that DOE

Page 32: LAO PDR: Implementation Support for the Rural ... · 5.01 (c) of the IFC-EdL Loan agreement. 11. Norad Co-financing. Norad grant agreement which provides parallel financing to REP

32

would submit for Bank no objection a waiver in order to use CQS method and advertise locally with

appropriate justification no later than June 4, 2011. Given the delays in recruiting the new VOPS

consultant and the necessity of having the VOPS in place well before the delivery of the new solar home

systems, the team urged DOE to undertake its best efforts to mobilize the VOPS without delay. In this

regard, it was agreed that the draft RfP and short list would be provided to the Bank no later than July 15,

2011 with the aim of mobilizing the consultant no later than October 2011.

Component B.3. Alternative Rural Electrification Delivery Model (Norad US$0.2 million and GEF

US$0.799 million): Provision of technical advisory services to MEM to: (a) promote alternative

renewable energy development and develop associated delivery models and financing mechanisms; and

(b) support small and medium enterprises in income generation that is linked to the use of the renewable

energy use.

AusAID funds will be used to find technical assistance for detailed project design, etc. to pilot up to four

biogas sites using pig manure. GEF resources could be used for the supply and installation of these four

biogas sites in addition to biomass sites. The team requested DOE to submit a plan for the use of Norad

funds for technical assistance under this component by July 31, 2011.

Component B.4 Rural Electrification Master Plan and Database (Norad US$0.1 million): Provision

of technical advisory services to MEM to: (a) maintain the rural electrification database; and (b) update

the rural electrification master plan.

DOE indicated its preference to use the local JV partner who did the original RE Master Plan and

Database to do the maintenance and update given the continuity of work and that it would require

significantly more resources for a new firm to carry out this assignment as they would need substantial

time to understand the approach and details of the renewable energy master plan for Lao PDR and

understand how the database is structured. It was agreed that DOE would submit a request for sole

source selection along with the draft terms of reference no later than July 15, 2011.

Component B.5. Organization Strengthening of MEM (IDA US$0.1 million and GEF US$0.02

million for incremental operating costs; Norad US$0.72 million): Provision of technical advisory

services to MEM: (a) to support the project management unit in the implementation of Part B of the

project; and (b) to establish and support the initial operation of a REFS to enable REF in its mandate.

The $100,000 of IDA and $20,000 of GEF resources is for incremental operating costs. The team

requested DOE to submit a proposal – including cost estimates, procurement timetable and brief

description – for the use of the Norad technical assistance funds under this component by July 31, 2011.

REP II Disbursement. As of May 29, 2011, the cumulative disbursement amounted to SDR 32,142

(US$50,000 equivalent) out of the total IDA Grant H5380 of SDR 12.6 million (0.26%). Only the

Designated Account of US$50,000 has been set up by DOE in January 2011 after the effectiveness of the

project since August 2010. A small amount of DA (US$50,000) will also be opened by EDL for small

payments of incremental operating costs.

Environment and Social Issues. See Annex 9 for details.

Page 33: LAO PDR: Implementation Support for the Rural ... · 5.01 (c) of the IFC-EdL Loan agreement. 11. Norad Co-financing. Norad grant agreement which provides parallel financing to REP

33

Annex 7: UPDATE May 30, 2011: Checklist of the IFC Loan Conditions for FIRST Disbursement

Condition (detailed in Section 4.01, page 36, in

Loan Agreement)

Party

responsible

Status Remarks/Next Steps

(a) Transaction documents: (i) IFC and (ii) IDA EdL Completed Documents completed and filed.

EDL suggested a Designated Account for IFC

disbursements to be opened at BCEL.

(b) Certificate of Incumbency/Authority

EdL Completed Document filed

(c) Authorizations- as listed in Annex

EdL, IFC Completed Document filed

(d) Legal opinions as to Lao law

EdL, IFC,

DFDL

Completed Document filed (issued by MOJ)

(e) legal Opinion as to English law IFC, A&O To be completed To work with A&O before the first disbursement

(f) Auditor’s certificate of compliance to Section 5.01

(c) of IFC loan agreement

EdL, E&Y To be completed To work with E&Y before the first disbursement

(g) IFC fees paid (mandate fee, commitment fee, and

front-end fee)

EdL Partially

Completed EDL to make payment, and submit related

evidences, for IFC fees and legal fees pending at

this stage.

(h) Legal fee and expenses reimbursement per Section

2.16 (b) (ii) and confirmation of payment up to $

US 50,000 cap.

EdL Partially

Completed EDL to make payment, and submit related

evidences, for IFC fees and legal fees pending at

this stage.

(i) Authorization of Auditors EdL, E&Y Completed Letter sent to E&Y and filed at IFC

(j) Certificate of Solvency (Schedule 4) EdL Document filed

(k) Appointment of agent (process server) EdL Completed Document filed

(l) Disbursement timetable EdL To be completed To work with EDL in coordination with IDA team

(m) DSRA per Section 5.01 (p) EdL To be completed EDL to send a letter to inform IFC about its

decision regarding the proposed bank where DSRA

will be established.

(n) Receipt by IFC of documents: i). List of existing

liens [3.01 (k)]; ii). List of EdL’s Subsidiaries/

affiliates [3.01 (s)]; iii). List of financial debt [3.01

(l)]

EdL Completed Documents filed

Page 34: LAO PDR: Implementation Support for the Rural ... · 5.01 (c) of the IFC-EdL Loan agreement. 11. Norad Co-financing. Norad grant agreement which provides parallel financing to REP

34

Annex 8: REP II Key Result Indicators

Objectives and indicators Baseline

2009

Target values Actual values

Year 1 Year 2 Year 3 Year 4 2010 2011 2012 2013

Development objectives

I. Number of households electrified 0 2,000 14,000 25,000 37,700 0 0

II. EdL Financial Performance

-Rate of return on revalued assets <1%

1%

2%

3%

4% 1%

-Debt service coverage ratio >1.3 times >1.3 times >1.3 times >1.3 times >1.3 times

1.69

-Self-financing ratio

>15% >15% >15% >15% >15% 35%

-Months of account receivables from

Government agencies

20 months

15 months 8months 5months <3months 11 m

o

*

10.31 as

of June 1,

2011

Result Indicator for each Component

A. EdL component

-Length of MV and LV lines

-No. of households connected**

-System loss

-Measurable increase in awareness and

adoption of EE technologies

0

200 Km 500 Km 800 Km 1,209 Km 0

0

0 9,000 17,000 27,700

>13%

13% <13% <13% <13% 10.92%

10.55%

10 GoL

agencies

under

REP I

10% of

central

GoL

agencies

20% of

central

GoL

agencies

50% of

central

GoL

agencies

80% of

central

GoL

agencies

10% of

central

GoL

agencies

B.MEM Component

-No. of households electrified

-No. of rural electrification projects with

financial support of REF

0

2,000 5,000 8,000 10,000 0 0

0 0 1 2 3 0 0

*2009/2010 accumulated gov’t arrears 94,121 divided by (total bill 101322/12) = 11.14 months

**Of the 27,700 target, about 19,700 households will be connected through grid extension subprojects and 8,000 through P2P

Page 35: LAO PDR: Implementation Support for the Rural ... · 5.01 (c) of the IFC-EdL Loan agreement. 11. Norad Co-financing. Norad grant agreement which provides parallel financing to REP

35

Objectives and indicators Baseline

2010

Target values Actual values

Year 1 Year 2 Year 3 Year 4 2010 2011 2012 2013

Global Environmental Objectives

I. a).Measurable increase in awareness

50 GoL

agencies

60% central

GoL

agencies; 50

large

industrial

and

commercial

consumers

in Vientiane

100% central

GoL agencies;

100 large

consumers in

Vientiane

I b).Adoption of EE technologies and

practices by consumers

No

customers

25 GoL

agencies; 2

largest

hospitals

50 GoL

agencies.; 4

hospitals; 4

large

commercial

consumers

0

II. Reduction of EdL’s distribution system

loss

13% 12% 11% 10.92

%

10.55%

III. Newly installed renewable energy

generation capacity

0MW 0.12 MW 0.30 MW 0

IV. Cumulative CO2 emission reduction 0 t CO2 e About

100,000 t

CO2 e

About 300,000

t CO2 e

0

Page 36: LAO PDR: Implementation Support for the Rural ... · 5.01 (c) of the IFC-EdL Loan agreement. 11. Norad Co-financing. Norad grant agreement which provides parallel financing to REP

36

Annex 9: REP I and II - Environmental and Social Review – May 2011

Part A. On Grid installation implemented by EDL

Environment

As a follow up to the actions plan in the AM dated September 2010, EDL submitted to the World Bank

progress report of the Safeguard Implementation under REP I. The safeguard report confirmed no

significant safeguard issues for the on-grid sub-projects which have been implemented in the seven

southern provinces and (ii) summarized lessons learned by EDL management and technical staff who

participated in the study tour at EGAT in Thailand and NT 2 in Lao PDR respectively in April and May

2010. However, the report did not identify how many on-grid sub-projects that required EMPs based on

Environmental Screening datasheet (in accordance with ESSF or current safeguard operational manual).

EDL agreed to submit to the World Bank a list of on-grid subprojects which use house-keeping measures

and prepared EMPs by June 30, 2011.

House-Keeping Measures and EMP for on-grid investments. EDL branch office monitored and worked

closely with the contractor and EMU to ensure no serious disturbance to the environment and villagers

occurred during civil work activities and the record of damages (trimmed or cut trees for installation

clearance). The installation of all the on-grid distribution was within the existing right of ways and had

no effects on any known environmentally sensitive areas. This was evident through the on-grid site visits

in Champrasac province. Minimal damage on villagers’ crops and trees during the civil work activities --

such as installing poles and stringing conductors-- were managed by the contractor with the agreed house-

keeping measures. The mission discussed with EDL’s Environmental office regarding the incorporation

of either house-keeping measures or EMP in bidding and contract documents for the current and future

on-grid sub-projects (e.g. under REP I and II). EDL is requested to share with a copy of any recent on-

grid contract to the World Bank for verification or inputs for appropriate clause related to house-keeping

measures or EMP.

Safeguard Capacity Building. Under REP I, the ESL consultants provided basic safeguard training on the

preparation, monitoring, and reporting of safeguard instruments (such as EMP and RAP) to EDL staff at

central and provincial branch offices) in April 2010. The training proceedings was shared with the World

Bank safeguard specialists during the mission The mission discussed with EDL’s Environmental Office

on how to improve the TORs for the Safeguards Capacity Building under REP II’s A.5 . Component

(financed by NORAD). EDL will use the fund to hire a team of national and international safeguard

consultants (i) to deliver safeguard training courses based recommended in the safeguard training needs

assessment in 2008 and (ii) to assist staff of EDL’s Environmental Office and branch offices in planning,

preparing, and monitoring the implementation of safeguard instruments. EDL expected to have the

Safeguard Consultants on board by September 2011. The World Bank safeguard specialists agreed to

send written comments to EDL within one week after the mission. EDL will submit the revision of the

TORs by June 30, 2011 for review and approval by the World Bank.

Page 37: LAO PDR: Implementation Support for the Rural ... · 5.01 (c) of the IFC-EdL Loan agreement. 11. Norad Co-financing. Norad grant agreement which provides parallel financing to REP

37

Safeguards Operational Manual. EDL submitted to the World Bank its draft Safeguards Operational

Manual before the mission. The World Bank safeguard specialists clarified the status of and discussed

with EDL on how finalize the Safeguards Operational Manual . The World Bank safeguard specialists

agreed to send to EDL the written comments within one week after the mission. EDL will then finalize and

send the final Safeguards Operational Manual for the World Bank record, likely before end of the 2011.

The mission encouraged EDL to apply the Safeguards Operational Manual for all REP’s sub-projects and

other Rural Electrifications financed by other sources.

Social

All civil works under REP I that may have negative effects on private assets or the livelihood of local

population have been completed. The mission was also informed no negative social impact occurred due

to the off-grid program. According to the Safeguard Progress Report submitted by the EdL environment

and social unit, 30,466 households in seven provinces were affected under 67 subprojects financed by the

REP I. In total, 4,585m2 of land had been affected, and more than 1 million trees had been reportedly cut

or damaged6. Under the REP I AusAid Additional Financing, it is expected that about 8,900 households

would be impacted, with the size of land affected estimated at 990m2 and the number of trees cut at about

9,000.

According to the progress report, all affected people were willing to voluntarily contribute their land or

trees, given the large benefit from being connected to the grid and the limited negative impacts. The

report also mentions that the project supported the rehabilitation of primary schools, hospitals, temples,

and so on, with the value of such in-kind contribution estimated at about 247 million LAK. Therefore no

affected households were compensated for the negative impact. The mission noted, however, that the

progress report is not clear if impacts are minor at the household level too – the report seems to lump

together both private and public land in the total size of affected land, and the data on the number of

affected trees may include forest land that belong to the public too. In order to verify that no household

was significantly and negatively impacted without due compensation under the project, the mission

agreed with EdL that the size of impact on private assets will be separated from impact on the

publicly owned assets in the revised final report and submit it to the Bank by June 10.

EdL developed a log book, according to the template developed in the Social Operational Manual, in

which the environment and social specialist of the provincial project implementation units, under the

support of the environment and social department of the EdL HQs, recorded the size of the land acquired,

the number and types of trees affected, and other impacts. Some extracts of impacts recorded in the log

bookare attached to the Aide Memoire. A summary of impact was also developed at the provincial level.

The mission was informed that formal agreements were also developed for signature by relevant

households which describe the detailed list of impacts. The mission considers this is a very good practice

which could be used by other ministries implementing projects entailing minor impacts. The mission

requested to share with the task team the sample of filled inventory of impacts as well as sample

signed agreements for record and sharing with other projects and ministries.

6 The mission considers and EdL agrees that this number is very high, which may either lump together privately

owned and publicly owned trees, or could simply be wrong. EdL agreed to check the record and get back to the task

team.

Page 38: LAO PDR: Implementation Support for the Rural ... · 5.01 (c) of the IFC-EdL Loan agreement. 11. Norad Co-financing. Norad grant agreement which provides parallel financing to REP

38

For REP II, the mission noted the current good practice employed by the EdL can be further expanded by

strengthening voluntary donation processes and the documentation of informed consent. As noted above,

it is not clear if negative impacts are minor for all households and voluntary donations are thus justifiable.

It is not clear either if all households agree to forfeit their entitlements and donate assets with full

knowledge of their entitlements. The mission agreed with EdL that a clear threshold and simple

checklists be developed to ensure that impacts are indeed minor for all cases of voluntary donation

and that informed consent by affected people is clearly established and documented. The mission

recommended EdL to refer to some of the good practices that EdC recently introduced under the Bank

supported projects, and agreed to provide detailed description of what should be addressed in the checklist

in the comment to the draft Safeguards Operational Manual before the mission.

The mission observed very positive social impacts due to improved access to electricity in rural areas. As

mentioned above, schools and other public facilities were rehabilitated under the Project. The mission

also noted some instances of business growth following project implementation. The mission strongly

recommends an impact evaluation of off-grid and on-grid electrification among project beneficiaries

which will help showcase the positive impact of the project.

Part B. Off-grid component by MEM/DOE

Potential environmental safeguard issues of off-grid investments under REP I and II are limited to mainly

issues related to used and out-of-order batteries for SHS and safety of Pico-hydro technology. The

environmental and safety issues could be addressed through good housekeeping system (e.g. disposal

arrangement of used batteries with the SHS supplier, VOPS and awareness campaign program activities.

The batteries’ recycling is arranged by VOPs and its sub-contractor, PESCOs, in particular to collect

used/out of order batteries from households and send to a specialized company for recycling purpose.

PESCOs developed a one-page trouble shooting principles –including the do and don’ts of used batteries-

-for educating to the villagers prior to installing SHS to each household. DOE will send a copy of the

one-page trouble shooting principles to the World Bank for record purpose.

It was not clear on the disposal arrangement of broken or unused SHS panels. DOE was requested to

report to the World Bank on its arrangement or agreement with the SHS supplier regarding used or

unusable SHS panels in the next support mission in late 2011.

Safeguard capacity Building. DOE staff benefited from the basic environmental safeguard training

organized by EDL’s Environmental Office under REP I’s Safeguard Capacity Building component. The

mission discussed with DOE to integrate environmental and safety mitigation measures (defined in the

feasibility study of Pico and Mini hydropower in its bidding and contract documents. More safeguard

capacity building will be provided through the REP II’s safeguard consultants in order to ensure that DOE

staff has necessary capacity and skills to prepare and oversee the planning and implementation of the off-

grid investments.

Safeguards Operational Manual. DOE has translated the final ESSF in Lao and disclosed it in the country

and the World Bank’s Infoshop in October 2010. DOE has not submitted to the World Bank for review

Page 39: LAO PDR: Implementation Support for the Rural ... · 5.01 (c) of the IFC-EdL Loan agreement. 11. Norad Co-financing. Norad grant agreement which provides parallel financing to REP

39

and inputs the Safeguards Operational Manual for off-grid component. DOE agreed to update the World

Bank on development of its Safeguards Operational Manual for off-grid component by June 30, 2011.

Attachment: sample inventory of impact

Lao Peoples’ Democratic Republic

Peace Independence Democracy Unity Prosperity

Summary report on Social and Environment work of REP I

Village: Sokbo, District: Xabangfai, Province: Khammouane

1. Propose:

To implement the Khammouane province’s Social and Economic development plan

To complete the REP I construction plan

To reduce the impact to the Social and Environment

2. Social and Environment impact:

Khammouane province’s EdL (as project) has allowed the construction company (Electricity

construction State Enterprise, Khammouane province branch) to construct the 20KV and 0,4 KV

on-grid electricity and set up …….as REP I contract.

This would be impacted to people’s property, where is the on-grid electricity passed zone, such

as: trees, land… as detail below:

No. Owner’s

name

Type of lands Type of Trees (amount) Remark

Rice

farm

Garden Building forest reserved Coconut mango Jack

fruit

tamarind kepok

Yes no yes no yes no yes no yes no

01 Mr. Ta 1 1 5

02 Mr.

Bounthan

1

03 Mr. Dom 1

04 Ms. Vieng 1

05 Mr. Somsy 1 1 9

06 Ms. Hou 1

07 Mr. Sone

08 Mr. Air 1 3 1 1

09 Ms. Yeng 1 1 1

10 Ms. Soun 2 2

11 Mr.

Bountieng

1 2 2 1

12 Mr. Deng 1

13 Ms. War 1

14 Ms. Lai 1 1

15 Mme. Bou 1 1 1

16 Mr. Tar 1

17 Mr. Phomma 3 2

18 Ms. Thom 1 4 3 1

Page 40: LAO PDR: Implementation Support for the Rural ... · 5.01 (c) of the IFC-EdL Loan agreement. 11. Norad Co-financing. Norad grant agreement which provides parallel financing to REP

40

Annex 10: Field Notes from Site Visits in Champasak Province, May 26 and 27, 2011

The Team carried out field visits on May 26 and 27, 2011 to villages in Champasak province electrified

under REP I and REP I-AusAID additional financing on-grid, P2P and off-grid components, as well as to a

target village to be electrified on-grid under the REP II. Champasak and Attapu PESCO SHS warehouse

was visited as well in order to evaluate possible improvements.

A WB fiduciary team formed by Mr. Chanvongnaraz Khamphet (Procurement Specialist), Ms. Malarak

Souksavat (Financial Management) and Mr. S. Sisomphone (Consultant) joined the field visits as part of

the integrated fiduciary team for the Lao PDR portfolio. A summary of the main points is provided

below.

General information about Champasak province electrification was provided by EdL branch. Seventy-

nine percent of villages and 77.6% of households in the province have been electrified as of April 2011.

The highest household electrification rates are in Pakse district (100%) and the lowest in Paksong district

(57%) and Moonlapamok district (58.7%). The largest consumer category is residential, comprising 43%

of electricity billed and 47% of bills collected. Average energy losses have decreased from 18.8% in 2006

to 12.7% in 2010. Champasak province is supplied by two hydropower plants and purchases electricity

from the Thai grid in the dry season.

Key findings

(a) SHS being portable is highly appreciated as it allows families to carry the system with them when moving to live in the huts in the rice fields for six months a year in the dry season.

(b) SHS are used as well for recharging small batteries directly, sometimes selling this service. (c) Villagers that charge their batteries through the installed SHS are collateral beneficiaries do not

have to travel to the nearest town for this purpose and they are charged 1,000 Kip instead of 5,000 Kip, getting to save 4,000 each time.

(d) Main uses of electricity are for lighting and for cell phones recharging. And for water pumping when having access to the grid.

(e) Some SHS repayments collectors keep the repayments when not paid their agreed good performance bonus. PESCO is strongly advised to avoid these situations.

(f) Main cause of SHS withdrawal seems to be the HHs connection to the grid, 15%-20% of the units were withdrawn because of not working. When the withdrawn taking place, just the panel is removed. Non-working units are used as a source of spare parts.

(g) A capacity building necessity on testing and fixing SHS was identified in order to VEMs and PESCO staff to be able to deal properly with the withdrawn units.

(h) Most of P2P beneficiaries found repayments affordable. (i) In the P2P village visited two different EdL staff collect monthly the P2P payments and electricity

bills, an opportunity for optimization was identified. (j) EdL representatives were pointing that female-headed households and families with disabled

members are giving priority to access to the P2P program. (k) Main productive developed uses of the electricity are: water pumping, use of small machinery

for furniture’s production and welding machines for construction. (l) Previous source of electricity was mainly diesel generators, environmental benefits are evident.

Page 41: LAO PDR: Implementation Support for the Rural ... · 5.01 (c) of the IFC-EdL Loan agreement. 11. Norad Co-financing. Norad grant agreement which provides parallel financing to REP

41

(m) Access to the grid and SHS is meaning high savings for the beneficiaries, being around half of the amount of money they used to spend on diesel. When selling their old generators beneficiaries get 30% or more of the originally invested money.

Rural Electrification project component related: SHS

Site visited no.1: Bontkair Village, near Pakse city

44SHS installed. Electrified under SPREE I since 2007.

HHs pay 87.5USD in 10 years; 20.000 Kip/month (USD 2.5); including the installation and the wiring.

Chief of the Village each the one collecting the SHS repayments. He records the payments in a logbook along with the signatures of the beneficiary and himself. It takes him 10 days a month to visit the HHs with SHS for finishing the re-collection task, once sometimes the families are absent or not have the money available.

Source of income: agriculture. Monthly average earnings of the visited family: 500,000- 1,000,000 Kip (USD 62.5-125). They consume 5 ton of their own produced rice a year.

Sources of energy used previously: diesel burn, and car batteries that used to recharge in the village (5,000 Kip/recharge, USD 0.6)

Villagers that charge their batteries through the installed SHS do not have to travel to the nearest town for this purpose anymore, they are charged 1,000 Kip (USD 0.1) instead of 5,000 Kip (USD 0.6).

SHS Payments Fees inserted on the monthly payment (increased in 2010)

Type Payment upfront to PESCO (KIP)

Payment monthly by HH (KIP)

Monthly Payment to VEM* (KIP)

Monthly Payment to VEAC** (KIP)

Monthly Payment to PESCO (KIP)

50 Watt 160,000- USD 20

20,000 – USD 2.5

4,500- USD 0.6 1,000- USD 0.1 4,500- USD 0.6 30 Watt 160,000- USD 20

18,000- USD 2.25

20 Watt 160,000- USD 20

13,000- USD 1.6

*VEM, Village Electricity Manager. Person in charge to solve the technical problems.

** VEAC, Village Electricity Advisory Committee. Mediates in disputes and take decisions when needed.

SHS being portable is highly appreciated as it allows families to carry the system with them when moving to live in the huts in the rice fields for six months a year in the dry season.

Uses of electricity are for lighting and for cell phones recharging mainly. In the HH visited they use to charge people for recharging their batteries for 1,000 Kip each.

After the one –year warranty period, when batteries not working they get new ones in Pakse city for 700, 000 Kip (USD 87.5). PESCO provides thenm as well for 680,000 Kip in 5 payments of 136,000 Kip (~17USD).

It was expressed by another PESCO worker in charge of collecting the monthly payments that he is not giving the paybacks to PESCO since June 2010 as he did not get the bonus payment agreed.

A distribution line built by ECI just arrived to the village, the grid will be bought by EdL. Connection fee for this grid including the wiring and two lamps is 3,500,000 Kip (436 USD). A whole agreement has been set for connecting the village. Once connected the villagers expressed their desire to keep using the SHS when working in the rice fields. They plan to get pumps in order to improve their agricultural production, and later on invest on rising chicken with the benefits. They plan as well to get refrigerators and fans when connected.

Page 42: LAO PDR: Implementation Support for the Rural ... · 5.01 (c) of the IFC-EdL Loan agreement. 11. Norad Co-financing. Norad grant agreement which provides parallel financing to REP

42

Image 1: 50 W SHS, battery Image 2: Solar panel Image 3: Just arrived grid

Rural Electrification project component related: SHS

Site visited no.2: Champasak and Attapu PESCO SHS Warehouse

This PESCO providing service to Champsak and Attapu provinces has installed 2,000 SHS under SPRE

and REP I.

Withdrawal:

Main cause of withdrawal is due to HHs connecting to the grid, 15%-20% of the units were

withdrawn because of not working. Only 20 units were withdrawn because of beneficiary not

affording it, after a three months grace period.

Main cause of SHS break down store was overloading in those SHS installed under SPRE in 2003.

REP I SHS were identified as better quality as the ones provided under SPRE. Non-working units

are used as a source of spare parts.

When the withdrawn taking place, just the panel is removed.

A proper logbook recording of withdrawals is being filled with the following information: date of

installation, date of withdrawn, beneficiary name and unit number.

Withdrawn working units are placed in another beneficiary HH, being the re-payment payments

only the remaining ones up to 10 years.

A capacity building necessity on testing and fixing SHS was identified in order to VEMs and PESCO

staff to be able to deal properly with the withdrawn units. It is being studied y the team the possibility to

create a mobile training unit that will go once a year PESCO by PESCO testing and fixing the non-

working SHS and at the same time providing on-hands training, probably funded by Norad.

It was advised to this PESCO to take off all the parts of the SHS when withdrawn as they can be used as

spare parts.

Page 43: LAO PDR: Implementation Support for the Rural ... · 5.01 (c) of the IFC-EdL Loan agreement. 11. Norad Co-financing. Norad grant agreement which provides parallel financing to REP

43

Image 4: SHS in the warehouse Image 5: Non-working SHS being checked

Image 6: Financial Management Specialists checking the financial and inventory recordings

Rural Electrification project component related: P2P

Site visited no.3: Phiangdi Village, Four Thousand Islands

400HH, 86 HH connected trough P2P as part of the pilot project under REP I in 2009. All the connections and wiring were done within a month by ECI, Electric Company Installation, owned by EdL. ECI provided each P2P beneficiary family with two bulbs and a kettle.

Structure of P2P payments: 700,000 Kip-USD 87.5 (500,000 Kip-USD 62.5 cheaper than the standard one) to be repaid in 35 monthly repayments of 20,000 Kip-USD 2.5. No upfront money asked.

Average electricity bill of the beneficiaries visited was 10,000- 16,000 K.ip (USD 1.25-2). Two visited beneficiaries found the P2P re-payments and electricity bill affordable, but a third visited beneficiary, a lady heading her family with 4 children was staying is hard for her coping with her 15,000 Kip (USD 1.9) average electricity bill as her average monthly income rises up to 200,000 -300,000 kip (USD 25-37.5)a month from agricultural labor.

Two different EdL staff collect monthly the P2P payments and electricity bills, an opportunity for optimization was identified if coordinating the collections and being done by a single EdL staff.

EdL representatives were pointing that female-headed households and families with disabled members are giving priority to access to the P2P program.

Page 44: LAO PDR: Implementation Support for the Rural ... · 5.01 (c) of the IFC-EdL Loan agreement. 11. Norad Co-financing. Norad grant agreement which provides parallel financing to REP

44

Image 7: P2P bill and electricity bill of a beneficiary Image 8: team meeting a female headed HH beneficiary

Image 9: Female headed family beneficiaries

Rural Electrification project component related: On-Grid

Site visited no.4: Somren-Ok Village, Done Some Island, Four Thousand Islands

14,500 citizens, 266HH, 261 of them have been connected to the new grid, 5 HH could not afford the fee. Connections took place in April 2011 and were finished within the same month.

Average income per family is 417,000 Kip a month (USD52), coming from fishing, rice harvesting and livestock mainly.

Price of the connection, including the wiring was:

Meter type 3-9 Amps.: 1,500,000 Kip (USD187)

Meter type 5-20 Amps: 2,500,000 Kip (USD 312)

Main productive developed uses of the electricity are: water pumping, use of small machinery for furniture’s

Page 45: LAO PDR: Implementation Support for the Rural ... · 5.01 (c) of the IFC-EdL Loan agreement. 11. Norad Co-financing. Norad grant agreement which provides parallel financing to REP

45

production and welding machines for construction. They have now fans, refrigerators and televisions at home.

Previous source of electricity: diesel generators. The interviewed beneficiary stated that he sold his used generator for 8,000 Bahts (USD ~267), and he bought it for 13,000 Baths (USD ~433).

It seems to be blackouts take place 2 or 3 times a month.

Electricity bills of the schools and health centers in this just electrified island are paid by the village chiefs.

Electricity payments are collected by EdL once a month.

Beneficiaries wish they could have enough electricity supply for a big water pump to set in place an irrigation system. A generator based pump was running from 1978 to 2002 in the community thanks to an Indian loan, but finally they had to quit because they could not afford anymore the diesel.

Image 10: Beneficiary being interview Image 11: Extended grid

Image 12: Plugged refrigerator in a health center

Rural Electrification project component related: On-Grid

Site visited no.5: Hangkhon Village, Done Some Island, Four Thousand Islands

56HH, 30 of them have been connected to the new grid since early 2010..

Daily expenses on diesel for generators used to be 1l/night for a restaurant owner, 13,000 Kip (USD 1.6),

Page 46: LAO PDR: Implementation Support for the Rural ... · 5.01 (c) of the IFC-EdL Loan agreement. 11. Norad Co-financing. Norad grant agreement which provides parallel financing to REP

46

making 390,000 Kip (USD 48.75) a month to be covered with average monthly earnings of 500,000 Kip (USD 62.5). Connection to the grid has meant for them great shavings, once his average electricity bill is 200,000 Kip (USD 25). Interviewed sir stated that he is using mainly the shavings to provide better schooling for his six children now and in the future.

The interviewed beneficiary stated that he sold his used generator for 5,000 Baht (USD ~166), and he bought it for 16,000 Bath (USD ~533).

Main productive use of the electricity is for pumping water from the Mekong river, previously women used to carry it all the way to their homes. Women have now more time for other activities and are not so exhausted. They use electricity for plugging in appliances as T.V. and radios.

It seems to be blackouts when having heavy rains.

In this village, a volunteer collects the bill payments once a month and brings it to the district EdL manager. Image 13: Extended grid

Rural Electrification project component related: Target for On-Grid under REP II in 2012

Site visited no.6: Village in Done Some Island, Four Thousand Islands

Image 14: Potential beneficiary being interviewed

230 citizens, 36 HH, 16 HH could afford the connection fee if being under 3

million Kip (USD 375).

Current sources of energy: oil lamps and diesel generators.

This community does not provide with a borrowing system that could

facilitate the affordability of the connections.

They wish to be connected to the grid mainly in order to be able to have

water pumps.