FOUNDATION MANUAL - LATTICE TOWER
Gaia-Wind 11 kW Turbine
2 of 16
GW-UK-22 Foundation Manual - Lattice Tower Issue Number: 2
Date of Issue: 29th Jan 2010
Your own
Wind Turbine
Copyright © 2009 Gaia-Wind Ltd. 1 Ainslie Road Hillington Park
Glasgow G52 4RU United Kingdom
Tel: +44 (0) 845 871 4242
Document Ref number: GW-UK-22 Foundation Manual - Lattice Tower
Date of Original Issue: August 2008
Issue Number: 2
Date of Revised Issue: 29th January 2010
All illustrations and photographs Copyright © Gaia-Wind Ltd.. No part of this manual may be transmitted into any form by any means without permission from Gaia-Wind Ltd. The information given in this user manual is believed to be accurate and reliable at time of printing. However, Gaia-Wind Ltd. Accepts no liability for the details contained herein. All specifications are subject to change without prior notice.
3 of 16
GW-UK-22-0110 Foundation Manual - Lattice Tower Issue Number: 2 Date of Issue: 29th Jan 2010
Table of Contents
Health and Safety Information ......................................................................... 4
Foundation Kits................................................................................................. 5
SUPPLIED BY GAIA-WIND ................................................................................... 5
TO BE PROVIDED BY THE INSTALLER .................................................................... 5
TOOLS AND PLANT REQUIREMENTS ..................................................................... 6
1. Introduction ............................................................................................... 7
2. Excavation and Mesh Installation ............................................................ 8
2.1. LOCATION ............................................................................................. 8
2.2. EXCAVATION ......................................................................................... 8
2.3. EARTH CONNECTION AND CABLING .......................................................... 9
2.4. LEVEL AND COMPACT ........................................................................... 10
2.5. STEEL MESH INSTALL ........................................................................... 10
3. Tower Base Installation .......................................................................... 12
3.1. STEEL FOUNDATION FRAME .................................................................. 12
3.2. LEVELLING .......................................................................................... 13
3.3. MOUNT CONTROLLER STAND ................................................................ 13
3.4. CASTING CONCRETE ............................................................................ 14
4 of 16
GW-UK-22 Foundation Manual - Lattice Tower Issue Number: 2
Date of Issue: 29th Jan 2010
Health and Safety Information
• It is compulsory that anybody involved in the construction wear
appropriate personal protective equipment at all times;
including, but not limited to, a high visibility jacket, hard hat, and
safety boots.
• All workers involved in installation must be fully briefed on the
sequence of operations before commencement. This is to
include the identification of danger areas that must not be
occupied.
• Existing site factors, e.g. overhead or underground electric
cables should be identified and an exclusion zone set.
• Temporary signs, notices, and barriers should be erected.
• Structural and mechanical installation must be actively
managed and supervised by a suitably experienced and
competent person.
Gaia-Wind strongly recommends that the foundation
installation be carried out by adequately trained and
experienced personnel. Ensure that these
instructions are read thoroughly and understood. It
is essential that they are retained, along with the
remainder of the manual, as they contain important
safety information that must be adhered to.
5 of 16
GW-UK-22-0110 Foundation Manual - Lattice Tower Issue Number: 2 Date of Issue: 29th Jan 2010
Foundation Kits
Supplied by Gaia-Wind
Quantity Part Description Drawing Position
Size (mm)
1 Controller Cabinet Stand
8800 2700 x 600 x 50
1 Lattice Tower Foundation with Pouring Frame
2057 x 2057 x 1176
To be provided by the Installer
Quantity Part Description Drawing Position
Size (mm)
1 Coil of 16 Gauge Tying Wire
N/A 75 m (length)
8 Reinforcement Mesh (12mm diameter main & cross)
84.0
Shape Code A393 4800 x 2400
104 U-Braces
84.2
Shape code 13 Bar diameter 12 mm A =400 mm B = 140 mm C = 400 mm Overall bar length = 850 mm
104
U-Braces
84.3
Shape code 21 Bar Diameter 12 mm A = 400 mm B = 250 mm C = 350 mm Overall bar length = 1000 mm
1 Coil of 16 Gauge Tying Wire
N/A 75 m (length)
6 of 16
GW-UK-22 Foundation Manual - Lattice Tower Issue Number: 2
Date of Issue: 29th Jan 2010
8 Reinforcement Mesh (10mm diameter main & cross)
84.0
Shape Code A393 4800 x 2400
4 Earth Rods N/A M16 x 1000
1 Earth Wire N/A 25mm2
6 Single Cover Concrete Spacers
N/A Height: 50mm
Concrete
Strength Class: 30 MPa Max. Gravel Content: 32 mm Water/Cement: 0.55 Quantity: 16 m
3 (aprox.)
Tools and Plant Requirements
The provision of all suitable tools and plant are the responsibility of the
individual contractor.
7 of 16
GW-UK-22-0110 Foundation Manual - Lattice Tower Issue Number: 2 Date of Issue: 29th Jan 2010
1. Introduction
This guide outlines the procedures relating to the installation of the
foundations for a Gaia-Wind 11kW wind turbine with a Lattice tower.
Please ensure that this document is read thoroughly prior to
commencing the foundation installation and pay specific attention to the
health and safety guidelines on the opening page. We would also
strongly advise that this document is retained for future reference.
The Foundation Kits consist of the bespoke parts for the assembly of
the required steel work. Page 5 of this document catalogues the
contents of the Foundation Kits. These are divided into two sections;
bespoke parts supplied by Gaia-Wind, and parts that are to be supplied
by the contracted installer. It should be ensured that all parts are
accounted for prior to commencing with the installation.
Provided are details and step-by-step instructions concerning the
excavation, earth connection, and steelwork assembly, with specific
reference to the Foundation Specification Drawings that are attached to
this document.
It remains the responsibility of the contractor to ensure that the
foundation work is complete and acceptable standard and to exact
requirements of the Gaia-Wind foundation specifications. Should there
be any additional queries or comments please contact Gaia-Wind.
8 of 16
GW-UK-22 Foundation Manual - Lattice Tower Issue Number: 2
Date of Issue: 29th Jan 2010
2. Excavation and Mesh Installation
2.1. Location
The precise location for the installation of the wind turbine foundations
will be dependent on that outlined in the approved planning application.
It must be ensured that prior to the commencement of any work that the
exact location of the foundations exactly matches that of the detailed in
the planning consent.
2.2. Excavation
The excavation for the turbine base
requires a volume of approx. 29
cubic meters; that is 5 m length and
breadth, and 1.15 metres in depth.
The ground should be levelled, and
all large rocks removed from the
excavated dig.
In adittion It is required that a cable
trench is excavated, leading away
from the hole.
The trench will be used for the laying
of electrical power cables.
It is required that the trench is at least 750 mm in depth. The exact
positioning, direction, and length of this trench will be site specific.
9 of 16
GW-UK-22-0110 Foundation Manual - Lattice Tower Issue Number: 2 Date of Issue: 29th Jan 2010
2.3. Earth Connection and Cabling
The dedicated turbine earth connection
requires digging a small channel for the
running of the earth cables.
This channel should form the outline of
a square on the inside of the excavated
hole - 1 metre in from the outside walls
and approximately 100 mm in depth.
Four earth rods should be hammered
into the ground at each
corner.
Interconnect the earth
rods with 25mm2 bare
copper wire using rod to
cable clamps to secure.
Attach separate sheathed
earth wires to two of the
earth rods. These earth
wires will protrude from
the finished foundation
and be attached to the
tower base during the turbine installation. It should be ensured that the
wire is sufficiently long for this to be achieved - approx. 2 metres.
The earth wire channel should be backfilled with earth.
10 of 16
GW-UK-22 Foundation Manual - Lattice Tower Issue Number: 2
Date of Issue: 29th Jan 2010
2.4. Level and Compact
Prior to advancing with the installation of the steelwork it should be
ensured that the base of the foundation excavation is suitably levelled
and that all obstructions are removed.
The earth at the base of the foundation should be suitably compacted
as site conditions dictate.
2.5. Steel Mesh Install
The foundation steelwork must be
raised 50mm above the base of the
excavation.
This can be achieved with spacers
spread evenly across the excavated
area.
Assemble the three layers of mesh.
Use the U and Z-Braces to hold the
three layers a mutual distance apart,
as detailed in the foundations
specification drawings – see ‘UK
Lattice Tower Foundation’.
11 of 16
GW-UK-22-0110 Foundation Manual - Lattice Tower Issue Number: 2 Date of Issue: 29th Jan 2010
Ensure that all U and Z braces are
securely fastened to each layer of
mesh using sufficient tying wire.
12 of 16
GW-UK-22 Foundation Manual - Lattice Tower Issue Number: 2
Date of Issue: 29th Jan 2010
3. Tower Base Installation
3.1. Steel Foundation Frame
If the foundation steelwork
is not assembled on
delivery, assemble
maintaining dimensions in
drawing P0000105.
Taking care not to alter the set critical dimensions lift the steelwork into
position over the reinforcement mesh so that the threaded rods extending
from the feet contact good bearing
surfaces, e.g. concrete blocks.
Ensure the steelwork is centred with
the reinforcement mesh.
Ensure a balanced lift using
appropriately rated and tested lifting
tackle.
Ensure threaded rods are supported with a good bearing surface.
13 of 16
GW-UK-22-0110 Foundation Manual - Lattice Tower Issue Number: 2 Date of Issue: 29th Jan 2010
3.2. Levelling and Height Adjustment
It must be verified that the foundation steelwork is appropriately level
before continuing with the installation.
Place a spirit level across the top of the steelwork to check the level of the
steelwork. Adjust the threaded rods extending from the feet to ensure
that all corner flanges are level. Also ensure that the height of the flanges
is as per drawing P0000105.
3.3. Mount Controller Stand
Locate the control box stand.
The control box stand should be placed onto
the mesh according to the foundation
specification drawings.
The stand should be secured to the mesh with
tying wire.
Additionally the stand can be strapped or
pegged into the ground. This will avoid
movement whilst the concrete is curing.
14 of 16
GW-UK-22 Foundation Manual - Lattice Tower Issue Number: 2
Date of Issue: 29th Jan 2010
3.4. Casting Concrete
Firstly, ensure that the earth wire is
secured against the top of the
assembled steelwork. It is vitally
important that the earth wire is not
embedded into the concrete.
Ensure once more that the steelwork
has been assembled exactly according
to the foundation specification drawings
and suitably plumb and level.
The grade of concrete should match
that according to the attached
foundation specification.
Concrete should be poured into the
foundation base, 5m x 5m x 0.55m.
The concrete should be vibrated using
a vibration poker for the removal of air
is pockets. This is essential for the
concrete to achieve full strength and
therefore durability.
15 of 16
GW-UK-22-0110 Foundation Manual - Lattice Tower Issue Number: 2 Date of Issue: 29th Jan 2010
Gaia-Wind Ltd, 1 Ainslie Road, Hillington Park, Glasgow G52 4RU. Tel: +44 (0) 845 871 4242, E: [email protected]
Gaia-Wind document reference: GW-UK-22 Foundation Manual - Lattice Tower. Website: www.gaia-wind.co.uk
www.gaia-wind.co.uk
1826CTR-CTR
1826CTR-CTR
CTR-CTR2692
1756CTR-CTR
2483CTR-CTR
1756CTR-CTR
87.7°4 PLACES
87.7°4 PLACES
(POURING FRAME HIDDENFOR CLARITY)
(NOTE 4)
310
1
8
2
45
7
6
9
(192)
LOWER HOLE
SCALE 1 : 2
SEE NOTE
DETAIL X
2&3
A
CONCRETE BOTTOM LEVEL
4. HOLE SPACING IS GOVERNED BY THE POURING FRAME.3. DATUM A IS TO BE WITHIN 0.1 DEGREES OF LEVEL.
1 HEX HEAD NUT ISO 4033 M16-8Z-tZn 8
9 0170010 - PLAIN WASHER ISO 7089 M10 - 200 HV-tZn
LOWER HOLE (TOP FACE).
0168163
5. WEIGHT IN BRACKETS INCLUDES POURING FRAME AND FASTENERS.
GROUND LEVEL
2. DATUM A PASSES THROUGH THE CENTERS OF EACH FOUNDATION LEG'S FOOT FLANGE THREADED ROD AND NUTS.OF EACH LEG AND THEREFORE DATUM A'S LEVEL CAN BE ADJUSTED USING THE M16 1. PLACE THIS FOUNDATION STEELWORK ONTO A GOOD BEARING SURFACE(S). THE HEIGHT
READ THIS DRAWING IN CONJUNCTION WITH GAIA-WIND DRAWING LAL-1060-02.
NOTES:
- THREADED ROD ISO 898-1 M16x300-8.8-tZn 4
8
10
CONCRETE TOP LEVEL
ITEM NO. PART NO. REVISION DESCRIPTION
WITH POURING FRAME/
QTY.
1 2081010 - FOUNDATION LEG 4
2 2082010 1 FOUNDATION LEG BRACE 4
3 0141030 - HEX HEAD SCREW ISO 4017 M10x30-8.8-tZn 8
4 0181010 - HEX HEAD NUT ISO 4033 M10-8Z-tZn 8
5 2083010 - POURING FRAME 1
6 0142500 - HEX HEAD SCREW ISO 4017 M24x100-10.9-tZn 12
7 0182024 - HEX HEAD NUT ISO 4033 M24-10Z-tZn 12
8 0181016
ZONE REV. DESCRIPTION DRAWN APPV'D DATE
REVISIONS
- 0 FIRST ISSUE DJL PJR 14/10/2009
A
8
SEE NOTE 1
A X
123
450
550
883
2057 TYP
310
WEIGHT (kg):
FILENAME: P0000105.SLDDRW
0
ISO2768-mK
12
H
G
F
E
D
C
B
A
J
K
L
M
N
P
Q
R
A
B
C
D
E
F
G
H
J
K
L
M
N
P
1110987654321 13 14 15 16 17 18 19 20 21 22 23 24
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
TOLERANCES
DRAWN
CHK'D
APPV'D
FINISH:
NAME DATE
MATERIAL:
TITLE:
DWG NO.
-
DJL
PJR
PJR 14/10/2009
13/10/2009
14/10/2009
THIRD ANGLE PROJECTION
DEBUR AND BREAK SHARP EDGES
DO NOT SCALE DRAWING
FOUNDATION INSTALLATION (18M)
P0000105
136
- A0SHEET 1 OF 1SCALE:1:10
REVISIONCOPYRIGHT © 2009 GAIA-WIND LTD