Lawrence Berkeley National Lab Capital Projects Presentation to Community Advisory Group June 13, 2016

Lawrence Berkeley National Lab Capital Projects · 2016. 9. 13. · Lawrence Berkeley National Lab Capital Projects Presentation to Community Advisory Group June 13, 2016 . Building

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Lawrence Berkeley National Lab Capital Projects · 2016. 9. 13. · Lawrence Berkeley National Lab Capital Projects Presentation to Community Advisory Group June 13, 2016 . Building

Lawrence Berkeley National Lab Capital Projects

Presentation to Community Advisory Group

June 13, 2016

Page 2: Lawrence Berkeley National Lab Capital Projects · 2016. 9. 13. · Lawrence Berkeley National Lab Capital Projects Presentation to Community Advisory Group June 13, 2016 . Building

Building Construction and Demolition Map

Page 3: Lawrence Berkeley National Lab Capital Projects · 2016. 9. 13. · Lawrence Berkeley National Lab Capital Projects Presentation to Community Advisory Group June 13, 2016 . Building

Old Town Demolition Phase 1

Page 4: Lawrence Berkeley National Lab Capital Projects · 2016. 9. 13. · Lawrence Berkeley National Lab Capital Projects Presentation to Community Advisory Group June 13, 2016 . Building

Old Town Demolition Phase 1

Page 5: Lawrence Berkeley National Lab Capital Projects · 2016. 9. 13. · Lawrence Berkeley National Lab Capital Projects Presentation to Community Advisory Group June 13, 2016 . Building

Old Town Demo Phase 1: Project update

•  Removal of low-level radioactive waste processing yard slabs, utilities, soils completed

•  Redesign of new B5 yard retaining wall extension completed; installation in progress

•  Packaging and shipping of soils continuing

•  Filtration of collected stormwater in progress

•  Cleanup of PCB contamination in soils near B52/B52A areas expected to begin this month

•  Phase I completion expected in 4-7 months

Page 6: Lawrence Berkeley National Lab Capital Projects · 2016. 9. 13. · Lawrence Berkeley National Lab Capital Projects Presentation to Community Advisory Group June 13, 2016 . Building

Old Town Demo Phase 1

Page 7: Lawrence Berkeley National Lab Capital Projects · 2016. 9. 13. · Lawrence Berkeley National Lab Capital Projects Presentation to Community Advisory Group June 13, 2016 . Building

Old Town Demo Phase 1

Page 8: Lawrence Berkeley National Lab Capital Projects · 2016. 9. 13. · Lawrence Berkeley National Lab Capital Projects Presentation to Community Advisory Group June 13, 2016 . Building

Old Town Demo Phase 1

Page 9: Lawrence Berkeley National Lab Capital Projects · 2016. 9. 13. · Lawrence Berkeley National Lab Capital Projects Presentation to Community Advisory Group June 13, 2016 . Building

IGB: Perspective from northwest

9

Page 10: Lawrence Berkeley National Lab Capital Projects · 2016. 9. 13. · Lawrence Berkeley National Lab Capital Projects Presentation to Community Advisory Group June 13, 2016 . Building

IGB: Status

•  Subcontractor bids have been received and budget documents sent to DOE

•  DOE has scheduled a meeting on October 7, 2016 for final review and approval of construction plan

•  Anticipate construction to take approximately 24 to 30 months completing in November 2018

•  Move in to the building will take approximately 6 months