Upload
valentine-maldonado
View
39
Download
1
Embed Size (px)
DESCRIPTION
LCLS. LCLS Commissioning Status P. Emma for The LCLS Commissioning Team LCLS FAC Meeting November 11, 2008. Machine Performance Estimated FEL Power Ultra-Short Pulse Possibilities Plans for 2009. Results published in FEL’08 and Linac’08 proceedings. - PowerPoint PPT Presentation
Citation preview
Paul EmmaPaul Emma
LCLSLCLS Commissioning Status Commissioning Status [email protected]@SLAC.Stanford.edu
Nov. 11, 2008Nov. 11, 20081
SLAC National Accelerator Laboratory
LCLSLCLS Commissioning Status Commissioning StatusP. Emma for P. Emma for The The LCLSLCLS Commissioning Team Commissioning Team
LCLS FAC MeetingLCLS FAC Meeting
November 11, 2008November 11, 2008
LCLSLCLSMachine PerformanceMachine Performance
Estimated FEL PowerEstimated FEL Power
Ultra-Short Pulse PossibilitiesUltra-Short Pulse Possibilities
Plans for 2009Plans for 2009
Results published in FEL’08 and Linac’08 proceedingsResults published in FEL’08 and Linac’08 proceedings
Paul EmmaPaul Emma
LCLSLCLS Commissioning Status Commissioning Status [email protected]@SLAC.Stanford.edu
Nov. 11, 2008Nov. 11, 20082
SLAC National Accelerator Laboratory
Phase-II Commissioning Highlights (2008)Phase-II Commissioning Highlights (2008)
Injector CommissioningInjector Commissioning: Apr-Aug, 2007 (: Apr-Aug, 2007 (DONEDONE))
Phase-II CommissioningPhase-II Commissioning: Dec-Aug, 2008 (: Dec-Aug, 2008 (DONEDONE) )
Great drive-laser uptime (Great drive-laser uptime (99%99%) and good performance) and good performance
Projected emittances Projected emittances 0.7-1.6 0.7-1.6 mm at 0.25 nC, 10 GeV at 0.25 nC, 10 GeV
Routine 30-Hz Routine 30-Hz ee to 14 GeV (~24/7 with ~90% up-time) to 14 GeV (~24/7 with ~90% up-time)
Bunch compression fully demonstrated down to 1-2 Bunch compression fully demonstrated down to 1-2 µµmm
New cathode installed with greatly improved thermal emittanceNew cathode installed with greatly improved thermal emittance
20-pC bunch with 20-pC bunch with 0.14-0.14-µµmm emittance (and 2-fs length?) emittance (and 2-fs length?)
Electron bunch appears bright enough to drive Electron bunch appears bright enough to drive 1.5-1.5-ÅÅ FEL FEL
Phase-III commissioning started Nov. 3, 2008 – X-rays by July ‘09Phase-III commissioning started Nov. 3, 2008 – X-rays by July ‘09
Paul EmmaPaul Emma
LCLSLCLS Commissioning Status Commissioning Status [email protected]@SLAC.Stanford.edu
Nov. 11, 2008Nov. 11, 20083
SLAC National Accelerator Laboratory
Design and Typical Measured Parameters Design and Typical Measured Parameters (Aug. 2008)(Aug. 2008)
ParameterParameter symbolsymbol designdesign measuredmeasured unitunit
Final linac Final linac ee energy energy mcmc22 13.613.6 13.613.6 MeVMeV
Bunch chargeBunch charge QQ 11 0.250.25 nCnC
Initial bunch length (rms)Initial bunch length (rms) z0z0 0.90.9 0.750.75 mmmm
Final bunch length (rms)Final bunch length (rms) zfzf 2020 8-108-10 mm
ProjectedProjected emittance (injector) emittance (injector) xx,,yy 1.21.2 0.7-1.00.7-1.0 μμmm
SliceSlice emittance (injector) emittance (injector) ssxx,,yy 1.01.0 0.60.6 μμmm
ProjectedProjected emittance (linac end) emittance (linac end) LLxx,,yy 1.51.5 0.7, 1.6*0.7, 1.6* μμmm
Single bunch repetition rateSingle bunch repetition rate ff 120120 3030 HzHz
RF gun field at cathodeRF gun field at cathode EEgg 120120 115115 MV/mMV/m
Laser energy on cathodeLaser energy on cathode uull 250250 20-15020-150 μμJJ
Laser diameter on cathodeLaser diameter on cathode 22RR 1.51.5 1.21.2 mmmm
Cathode quantum efficiencyCathode quantum efficiency QEQE 66 0.7-70.7-7 101055
* horizontal slice emittance likely < 1 * horizontal slice emittance likely < 1 µµmm
Paul EmmaPaul Emma
LCLSLCLS Commissioning Status Commissioning Status [email protected]@SLAC.Stanford.edu
Nov. 11, 2008Nov. 11, 20084
SLAC National Accelerator Laboratory
Bunch Compression & CSR Measured after BC2 (0.25 nC)Bunch Compression & CSR Measured after BC2 (0.25 nC)
zz > 25 > 25 mm
BC2BC2(4.3 GeV)(4.3 GeV)
BSYBSY(14 GeV)(14 GeV)
TCAVTCAV(5.0 GeV)(5.0 GeV)
550 m550 m
zz < 5 < 5 mm
old screen usedold screen used
L2L24 wires4 wires
zz 2 2 mmno
min
alno
min
al
Paul EmmaPaul Emma
LCLSLCLS Commissioning Status Commissioning Status [email protected]@SLAC.Stanford.edu
Nov. 11, 2008Nov. 11, 20085
SLAC National Accelerator Laboratory
long long weekend weekend
run at run at 0.25 nC 0.25 nC with no with no tuningtuning
Emittance Near End of Linac Over Long WeekendEmittance Near End of Linac Over Long Weekend
(3.3 days) May 24, 2008 00:01 to May 27 09:00(3.3 days) May 24, 2008 00:01 to May 27 09:00
((xxyy))1/21/2 = 1.04 = 1.04 mm
Paul EmmaPaul Emma
LCLSLCLS Commissioning Status Commissioning Status [email protected]@SLAC.Stanford.edu
Nov. 11, 2008Nov. 11, 20086
SLAC National Accelerator Laboratory
Beam Appears Bright Enough for FEL Saturation at 0.15 nmBeam Appears Bright Enough for FEL Saturation at 0.15 nm
Calculation based on measured end-of-linac Calculation based on measured end-of-linac projectedprojected emittance values, measured peak emittance values, measured peak current, and design undulator parameters (assuming undulator alignment and current, and design undulator parameters (assuming undulator alignment and 0.01% 0.01% rms slice energy spread – not yet measurable) rms slice energy spread – not yet measurable)
M. Xie method, with wakesM. Xie method, with wakes
FEL Power3D Gain Length
FEL Power3D Gain Length
Paul EmmaPaul Emma
LCLSLCLS Commissioning Status Commissioning Status [email protected]@SLAC.Stanford.edu
Nov. 11, 2008Nov. 11, 20087
SLAC National Accelerator Laboratory
New Cathode: Time-sliced New Cathode: Time-sliced xx-Emittance at Very Low Charge-Emittance at Very Low Charge
20 pC, 135 MeV, 0.6-mm spot diameter, 400 20 pC, 135 MeV, 0.6-mm spot diameter, 400 µµm rms bunch length (5 A)m rms bunch length (5 A)
TAILTAIL
(not same data)(not same data)
0.14 0.14 µµmm
Paul EmmaPaul Emma
LCLSLCLS Commissioning Status Commissioning Status [email protected]@SLAC.Stanford.edu
Nov. 11, 2008Nov. 11, 20088
SLAC National Accelerator Laboratory
zz 1 1 m ?m ?
8 kA?8 kA?
LiTrackLiTrack(no CSR)(no CSR)
Measurements and Measurements and SimulationsSimulations for 20-pC Bunch at 14 GeV for 20-pC Bunch at 14 GeV
Photo-diode signal on OTR after BC2 shows Photo-diode signal on OTR after BC2 shows minimum compression at minimum compression at 34.5 deg34.5 deg L2-linac phase.L2-linac phase.
Horizontal projected emittance measured at 10 Horizontal projected emittance measured at 10 GeV, after BC2, using 4 wire-scanners.GeV, after BC2, using 4 wire-scanners.
Y. DingY. Ding
LCLS FEL simulation at 1.5 LCLS FEL simulation at 1.5 ÅÅ based on measured based on measured injector beam and injector beam and ElegantElegant tracking tracking with CSR at 20 with CSR at 20 pC.pC.
1.5 Å1.5 Å,,3.63.610101111 photons photonsIIpkpk = 4.8 kA = 4.8 kA 0.4 µm0.4 µm
SIMULATED FEL PULSESIMULATED FEL PULSE
Paul EmmaPaul Emma
LCLSLCLS Commissioning Status Commissioning Status [email protected]@SLAC.Stanford.edu
Nov. 11, 2008Nov. 11, 20089
SLAC National Accelerator Laboratory
120-Hz RF & Controls Testing Done120-Hz RF & Controls Testing Done(Gun, L0a, L0b, L1-S, & L1-X)(Gun, L0a, L0b, L1-S, & L1-X)
Measured 120-Hz “Timeslot” phase jitter for all injector RF stations:Measured 120-Hz “Timeslot” phase jitter for all injector RF stations:
Gun, L0a, L0b ~0.8 deg rms (tol. = 0.1 deg)Gun, L0a, L0b ~0.8 deg rms (tol. = 0.1 deg)
L1S ~0.17 deg rms (tol. = 0.1 deg)L1S ~0.17 deg rms (tol. = 0.1 deg)
L1X ~0.3 deg rms (tol. = 0.5 deg)L1X ~0.3 deg rms (tol. = 0.5 deg)
Observe ~1 deg difference on every 4th pulse (L0a, L0b, L1X)Observe ~1 deg difference on every 4th pulse (L0a, L0b, L1X)
Measurements confirmed with old SLC control system and new Measurements confirmed with old SLC control system and new Beam Synchronous Acquisition systemBeam Synchronous Acquisition system
More feedback development is needed (beam-based and RF-More feedback development is needed (beam-based and RF-based)based)
Radiation measured are below posted limits at each klystronRadiation measured are below posted limits at each klystron
Gun temperature and vacuum response OK at 120 HzGun temperature and vacuum response OK at 120 Hz
M. StanekM. Stanek
Paul EmmaPaul Emma
LCLSLCLS Commissioning Status Commissioning Status [email protected]@SLAC.Stanford.edu
Nov. 11, 2008Nov. 11, 200810
SLAC National Accelerator Laboratory
The The LCLSLCLS Laser Heater is Ready (except undulator) Laser Heater is Ready (except undulator)
IR & e- beams on IR & e- beams on OTR screens nowOTR screens now
Controls Controls readyready
Beam through chicane already…Beam through chicane already…
Paul EmmaPaul Emma
LCLSLCLS Commissioning Status Commissioning Status [email protected]@SLAC.Stanford.edu
Nov. 11, 2008Nov. 11, 200811
SLAC National Accelerator Laboratory
RF Deflector (LOLA) + special RF Deflector (LOLA) + special lattice configuration in lattice configuration in spectrometer allows fine spectrometer allows fine measurement of time-sliced measurement of time-sliced energy spread (to <6 keV)energy spread (to <6 keV)
EE 6 keV rms 6 keV rms (40 (40 m)m)
OTR screens (7)OTR screens (7)YAG screens (7)YAG screens (7)Wire scanners (7)Wire scanners (7)Dipole magnets (8)Dipole magnets (8)Beam stoppers (2)Beam stoppers (2)S-band RF acc. sections (5)S-band RF acc. sections (5)
RF GunRF GunSolenoidSolenoid
GunGunSpectrometerSpectrometer
RFRFDeflectorDeflector
X-band RFX-band RFacc. sectionacc. section
BC1BC1L1SL1S
L0aL0a
L0bL0b
2-km point in 3-km SLAC 2-km point in 3-km SLAC linaclinac 135-MeV135-MeV
SpectrometerSpectrometer
EmittanceEmittanceScreens/WiresScreens/Wires
EmittanceEmittanceScreen/WiresScreen/Wires
135 MeV135 MeV 250 MeV250 MeV
TD11TD11stopperstopper
Laser-HeaterLaser-Heater
Paul EmmaPaul Emma
LCLSLCLS Commissioning Status Commissioning Status [email protected]@SLAC.Stanford.edu
Nov. 11, 2008Nov. 11, 200812
SLAC National Accelerator Laboratory
qq = 0.25 nC = 0.25 nC
xx = 0.61 = 0.61 µµmm
yy = 0.67 = 0.67 µµmm
New emittance New emittance data at 135 MeV data at 135 MeV taken on Nov. 8, taken on Nov. 8, 2008 just 2 days 2008 just 2 days into the turn-oninto the turn-on
Paul EmmaPaul Emma
LCLSLCLS Commissioning Status Commissioning Status [email protected]@SLAC.Stanford.edu
Nov. 11, 2008Nov. 11, 200813
SLAC National Accelerator Laboratory
Important Dates for 2008/2009 Commissioning
Nov. 3, 2008:Nov. 3, 2008: Startup (establish beam to end of linac again)Startup (establish beam to end of linac again)
Dec. 3, 2008:Dec. 3, 2008: Install laser-heater undulator (?)Install laser-heater undulator (?)
Dec. 15, 2008:Dec. 15, 2008: First beam through LTU & to dump?First beam through LTU & to dump?
Dec. 19, 2008:Dec. 19, 2008: SLAC shuts down for holidaysSLAC shuts down for holidays
Jan. 5, 2009:Jan. 5, 2009: Startup again (establish beam in LTU & Startup again (establish beam in LTU &
dump)dump)
March 2, 2009:March 2, 2009: Install ~25 undulators & PPS cert. (~2 wks)Install ~25 undulators & PPS cert. (~2 wks)
May 14, 2009:May 14, 2009: First beam in FEEFirst beam in FEE
July 2009:July 2009: Photons in NEHPhotons in NEH
August 2009:August 2009: Start AMO ExperimentStart AMO Experiment
Paul EmmaPaul Emma
LCLSLCLS Commissioning Status Commissioning Status [email protected]@SLAC.Stanford.edu
Nov. 11, 2008Nov. 11, 200814
SLAC National Accelerator Laboratory
Re-establishRe-establishee to SL2 to SL2
LTU/LTU/UndUnd
Comm. Comm.
Firs
t Li
ght
in
Firs
t Li
ght
in
FEE
FEE
Firs
t Li
ght
in F
EH
Firs
t Li
ght
in F
EH
NEH Ops & NEH Ops & CommissioningCommissioning
JJJJ FFFF MMMM AAAA MMMM JJJJ JJJJ AAAA SSSS DDDD JJJJ FFFF MMMM AAAA MMMM JJJJ JJJJ AAAA SSSS OOOO NNNN DDDD JJJJ FFFF MMMM AAAA MMMM JJJJ JJJJOONNAA
2008 2009 20102008 2009 2010 2008 2009 20102008 2009 2010DownDownPPS
PPS
Linac/BC2 Linac/BC2 CommissioninCommissionin
g g FEL/FEEFEL/FEECommissioniCommissioni
ng ng Nov. 3, 2008Nov. 3, 2008
Inst
all
Inst
all U
ndula
tors
Undula
tors
MMDD
LCLSLCLS Installation and Commissioning Time-Line Installation and Commissioning Time-Line
LTU
/Und
In
stall
LTU
/Und
In
stall
PEP-I
I ru
n
PEP-I
I ru
n
ends
ends
FEE/N
EH
In
stall
FEE/N
EH
In
stall
PPS C
ert
. LT
U/D
um
pPPS C
ert
. LT
U/D
um
p
CD-4
CD-4
(7
/31
/201
0)
(7/3
1/2
01
0)
X-R
ays
in N
EH
X-R
ays
in N
EH
no
wn
ow
DDDown?Down?
FEH
Hutc
h B
OFE
H H
utc
h B
O
Paul EmmaPaul Emma
LCLSLCLS Commissioning Status Commissioning Status [email protected]@SLAC.Stanford.edu
Nov. 11, 2008Nov. 11, 200815
SLAC National Accelerator Laboratory
LTU/Undulator/FEE/FEL CommissioningLTU/Undulator/FEE/FEL Commissioning
H. TompkinsH. Tompkins
+ heater+ heater