Upload
undpbdlgc
View
219
Download
0
Embed Size (px)
Citation preview
8/3/2019 Learning & Innovations Component of the Local Government Support Projectin Ban Glades Hi Union Parishads
1/35
Local Governance Support Project-
Learning and Innovation Component (LGSP-LIC)Local Government Division
Ministry of Local Government, Rural Development and Co-operatives
Government of Peoples Republic of Bangladesh (GoB)
The Learning and InnovationsComponent of the Local Government
Support Project in Bangladeshi Union
Parishads - Lessons Learned
by
Simon De-Lay
Consultant, UNCDF
LGSP-LIC is implemented with support from
Copyright 2010 by Local Government Division
Disclaimer: Views expressed in this report are those of author/s and do not necessarily reflect the views of
Local Government Division (LGD), Ministry of Local Government Rural Development and Cooperatives,
Government of Bangladesh, any other ministry of GoB and UN agencies including UNDP and Local Governance
Cluster of UNDP Bangladesh.
8/3/2019 Learning & Innovations Component of the Local Government Support Projectin Ban Glades Hi Union Parishads
2/35
LIC-LGSP: Lessons Learned page 1
Contents
1 Background and objective ....................... .................. ......................... ......................... .. 2
2 Methodology and Evidence Base ......................... ......................... ......................... ........ 3
3 The Context ................................................................................................................. 4
3.1 Union Parishads and the Bangladesh Government Structure ......................................... 4
3.2 Distribution of functions and financing .......................................................................... 4
3.3 Local Governance and the history of reform initiatives .................................................. 5
4 What the LIC Project Did ......................... .................. .......................... ......................... . 6
4.1 Sirajganj and the wider Project influences...................................................................... 6
4.2 LIC and LGSP .................................................................................................................. 7
4.3 LIC Project Objectives and Coverage .............................................................................. 7
4.4 Key LIC activities ............................................................................................................ 8
5 Project Lessons .......................................................................................................... 11
5.1 The Grant System......................................................................................................... 11
5.2 Using Performance Conditions for Grants .................................................................... 12
5.3 Participation in Planning, Implementation and Review ................................................ 13
5.4 Spending Decisions ...................................................................................................... 15
5.5 LIC and Local Power ..................................................................................................... 19
5.6 LIC and Revenue Mobilisation ...................................................................................... 22
5.7 Project Facilitation and Support ................................................................................... 25
5.8 Information and Dissemination .................................................................................... 28
5.9 Learning in LIC .............................................................................................................. 28
6 Conclusions................................................................................................................ 31
Abbreviations and Terms......................... ........................ ......................... ...................... ... 32
References ....................................................................................................................... 33
8/3/2019 Learning & Innovations Component of the Local Government Support Projectin Ban Glades Hi Union Parishads
3/35
LIC-LGSP: Lessons Learned page 2
1 Background and objectiveThis study reviews the lessons of the Learning and Innovation Component (LIC) of the
Local Government Support Programme (LGSP) in Bangladesh from its inception in 2007 to
2010. It outlines best practices, learning and innovation for replication, up-scaling and
government mainstreaming.
Thus the study is not an evaluation of the project, nor a complete description of every
aspect of the projects design and implementation, but rather a selective study which
emphasises relevant lessons. Lessons considered include both positive lessons where
successful practices have been developed and negative lessons where approaches have
been unsuccessful.
The intended audience is both within Bangladesh (including those involved in developing
future phases of LGSP and LIC as well as other local governance projects) but also those
interested outside Bangladesh in the lessons of a project which has successfully improved
local governance in a difficult context.
The document outlines briefly the methodological approach and describes the approach
adopted by LIC, linking it to the earlier SLGDP project in Sirajganj and wider developments
internationally. It then goes on to analyse the key lessons in detail under a number of
headings:
The Grant System
Participation in Planning, Implementation and Review
Spending Decisions
Spending and the Allocation of Functions between tiers of government
LIC and Local Power
Project Facilitation and Support
Learning in LIC
8/3/2019 Learning & Innovations Component of the Local Government Support Projectin Ban Glades Hi Union Parishads
4/35
LIC-LGSP: Lessons Learned page 3
2 Methodology and Evidence BaseThe study relies on a number of sources. A survey done prior to this consultancy by
another group of some 1200 respondents in LIC and LGSP areas looked at effects of the
project (Dash and Ahmed, 2010). It also draws on survey results from a baseline survey on
revenue mobilisation, a survey of communication and information issues (DCGCI, 2010),
other project reports, other studies of local governance in Bangladesh plus the results ofinterviews with current and former project staff, senior policy makers, and stakeholders
in two districts and ten Union Parishads.
The nature of the project impact is hard to ascertain definitively for a number of reasons
Because the project was not the only change being undertaken in UPs at the time
Information on outcomes is not wholly reliable we rely on evidence from
interviews and subjective responses from survey data. There is comparatively
little hard evidence and most data relates to process changes rather than ultimate
policy objectives like reduced poverty.
Attribution of causality is especially hard given the multiplicity of otherdevelopments affecting local communities at the same time and the
comparatively limited control group data.
This leads to a particular lesson discussed at the end of the document on the value of
adopting a consciously more experimental design for future interventions. Nevertheless
the lessons described here have been distilled from a broad series of data sources and
carefully triangulated. We indicate where lessons are firmly established and where the
evidence is less well-established.
8/3/2019 Learning & Innovations Component of the Local Government Support Projectin Ban Glades Hi Union Parishads
5/35
LIC-LGSP: Lessons Learned page 4
3 The Context3.1 Union Parishads and the Bangladesh Government Structure
Union Parishads form the lowest tier of formal governance structures in rural Bangladesh.
The sub-national government system has strong elements of deconcentration with thefirst level below the central government being formed of 6 Administrative Divisions,
below which are 64 Zila Parsihads. In rural areas there is then a layer of around 500
Upazila Parishads. The approximately 5000 Union Parishads (UPs) lie below these (Fox
and Menon, 2008). UPs in turn are each subdivided into nine wards for electoral and
some administrative purposes.
UPs are quite sizeable in population terms by international standards ranging up to
40,000- 50,000 and covering usually a number of sizeable villages (literally a Union).
This current pattern of local governance reflects the outcome of a long history of change
in the governance structures but one in which the functions of government and the
resources to govern have remained heavily centrally controlled. Elected elements at tiers
above the UP have remained in abeyance for long periods. However the UPs have
survived as an elected element of governance, albeit one with limited functions and
resources.
3.2 Distribution of functions and financingThe provision of major government functions is heavily centralised with key sectors that
are frequently decentralised in developing countries such as primary healthcare andeducation remaining outside the control of local government. The Public Administration
Reforms Commissions of 1996 reporting in June 2000 observed that, although laws
passed in 1993 and 1997 earmarked 38 functions for UPs, in actual practice, their
functions remained very limited. This leaves UPs with poorly specified roles mainly
consisting of supporting the community, primarily through the provision and
maintenance of local infrastructure such as small markets, minor roads etc plus being the
local arm of governance for minor regulatory functions such as registration of citizens.
They have the power to undertake a range of functions such as economic development of
their residents although use of these powers is patchy
This lack of functions and especially of functions with significant recurrent expenditure
needs is reflected in very limited financing for UPs. Total government expenditure at UP
level is estimated at around 2% of GDP (Fox and Menon, 2008) and much of this is
channelled via specific grants over which UPs have very limited discretion.
The UP does have access to a range of local taxes including a property tax as well as a
series of miscellaneous minor tax sources but the revenue from these has historically
8/3/2019 Learning & Innovations Component of the Local Government Support Projectin Ban Glades Hi Union Parishads
6/35
LIC-LGSP: Lessons Learned page 5
been limited by a mixture of central restrictions (e.g. a cap on the maximum property tax
that can be levied); political concerns about raising taxes and the poverty of many
citizens. Charges for services are levied for some regulatory functions but are not at a
level where they can fund wider service provision.
3.3 Local Governance and the history of reform initiativesThe UPs have a relatively slim political formal administrative structure. An elected
chairman and nine elected members (one per ward) plus three elected women members
direct the policy of the UP. An appointed Secretary represents the only administrative
post in most UPs although there are also UP police who can support administrative
functions.
Government in Bangladesh has suffered from concerns over corruption and inefficiency
and UPs are not exempt from these problems. There are concerns over the extent to
which formal rules are followed, over the regularity of spending and over the influence of
elites in the areas (see e.g. Alim, 2007). Aminuzzaman (2009) quotes a section of UP
Chairmen agreeing that some UP projects are determined not by development need of
the area but on the political priority of the influencing political elite.
Decentralisation is frequently seen as a possible counter to such weak accountability and
poor governance (see e.g. Shah, 1997) and decentralisation reforms have been pursued in
Bangladesh with these sort of objectives. They have met with limited success however
(see for example Westergaard and Alam, 1995; Sarker, 2003; Fox and Menon 2008). As
Aminuzzaman notes:
Four different commissions/committees were constituted in 1993, 1997, 1999and 2008 respectively to reform/ reorganize and strengthen the role, structure
and functions of local government in Bangladesh. However, it was observed that
no significant attempt has subsequently been made to operationalize and/or
implement the major recommendations of these reform
commissions/committees.
Explanations for the lack of success with decentralisation initiatives tend to focus on
central politicians viewing local governments as part of a patron-client network rather
than as an autonomous provider of services. Thus reform initiatives are not accompanied
by significant transfers of services or of resources and there is limited attention tocreating genuine accountability at local level with local politicians who might rival in
legitimacy central politicians. This is not therefore a promising area for policy reform and
indeed governance reforms in Bangladesh in general have proved difficult (see for
example World Bank, 2000; Parnini, 2009).
8/3/2019 Learning & Innovations Component of the Local Government Support Projectin Ban Glades Hi Union Parishads
7/35
LIC-LGSP: Lessons Learned page 6
4 What the LIC Project Did4.1 Sirajganj and the wider Project influences
The project would not claim to be especially creative in terms of any one particular new
approach. Instead the project represents the adoption of a range of measures which havebeen tried elsewhere but in combination and with a serious and concerted effort at
facilitation within a level of Bangladeshi local government which had previously proved
somewhat difficult.
Thus the project can be seen as drawing on a number of reform initiatives which can be
seen in operation in other countries:
Participative budgeting
Rapid rural appraisal
Community based development
Social Funds
Community contracting
Open budgets
Community auditing
Womens empowerment
Inter-governmental grants
Performance based grants
Good revenue administration
A large part of the underlying reforms attempted in the LIC had already been attempted
in the smaller Sirajganj project (albeit with rather more intensive facilitation). LICextended these to a much wider area and reduced the intensity of facilitation support
reflecting concerns for the sustainability of such approaches once donor support had
ended. The Sirajganj project had four key objectives:
1. UPs supported to improve their performance & accountability
2. Participatory planning process at local level supported
3. Formation, Selection and Implementation of LDF schemes supported
4. Lessons learned analyzed and disseminated to key actors
The Project Completion Report for Sirajganj (UNDP/UNCDF, 2008) identified the following
lessons:
Direct fund allocation to the UP has proved to be feasible.
Community involvement in planning, implementation, supervision and monitoring
has ensured efficient use of resources and helped create ownership of the people.
Operation and maintenance of the implemented schemes by the community has
been effective and ensured sustainability.
8/3/2019 Learning & Innovations Component of the Local Government Support Projectin Ban Glades Hi Union Parishads
8/35
LIC-LGSP: Lessons Learned page 7
Ward level committees involving UP representatives and community have been
found to be effective in local level development.
Performance based fund allocation for UPs have proved to be effective and have
been welcomed by the stakeholders.
Eligibility criteria for access to Block Grants have ensured accountability of the
UPs.
Union Facilitation Team has revealed a sustainable human resource at local levelto facilitate local development.
Introduction of bidding process at the union level has been found to be
transparent and has made the UPs capable of efficient contract management.
Transparency and accountability in UP activities have been practiced.
Participatory assessment of UP performance has effective to enhance the capacity
of the UPs and established transparency and accountability as well
GoB commitment to expanding block grants across the country and support from other
donors led to the Local Government Support Project with LIC conceived as a component
of that project.
4.2 LIC and LGSPThe Local Government Support Programme is a reform program implemented by the
Local Government Division (LGD) of the Government of Bangladesh with financial support
of the World Bank, UNDP, UNCDF, EC and Danida. The initiative of the project is to
consolidate the first steps towards strengthening Union Parishads (UPs), through
expanding the size of the block grant and institutionalizing mechanisms of transparency
and accountability towards citizens. LIC represents one of six components and is
conceived as a learning component which provides a means of piloting initiatives, testingtheir value and feeding into wider application in LGSP which operates across all UPs
nationally.
4.3 LIC Project Objectives and CoverageThe project has 5 key desired outputs:
Output 1: Increased financial resources made available to UPs in equitable and
appropriate ways;
Output 2: Improved public expenditure systems for UPs are developed and used;
Output 3: Enhanced mechanisms for local accountability are established and
implemented;
Output 4: More effective framework for capacity development support is
established;
Output 5: Policy development is informed by lessons of program implementation.
8/3/2019 Learning & Innovations Component of the Local Government Support Projectin Ban Glades Hi Union Parishads
9/35
LIC-LGSP: Lessons Learned page 8
The Component is being piloted in six different districts, Barguna, Habiganj, Sirajganj,
Narsingdi, Feni and Satkhira, one from each of the six administrative divisions of the
country. 388 unions have been covered progressively over the five year duration of the
project. The total budget of the project is US$ 18.118 million and is being grant-funded by
UNDP, UNCDF, EC and Danida.
4.4 Key LIC activitiesThe key activities of the LIC involved the development of a participative planning and
implementation system with several formal elements:
The functions of the Ward Development Committee (WDC) is to organize ward
level participatory planning meetings, ensuring environmental sustainability of
schemes, prioritizing selected schemes and submitting to UPs, implementing
approved schemes, preparing three monthly report of ward level work, organizing
meetings for other matters
The functions of the Scheme Supervision Committee include supervision andmonitoring of ward level scheme implementation. It monitors the cost and quality
of implementation of approved schemes. The SSC advises the WDC on faulty
scheme implementation and informs the UP if WDC fails to address. In some areas
the SSC has been used to promote the involvement of younger members of the
community in UP and development work.
The Union Facilitation Team are formed to train the Union Parishad Planning
Committee (UPPC) for technical evaluation, prioritizing and recommending
schemes submitted by the WDCs; the WDC and SSC members, to assist the WDC
and the UP in participatory planning through training on the LIC and other UP
functions.
The Women Development Forum for the LIC districts is to facilitate the fullparticipation of the women members in the local government administration and
to assist the UPs in the work of socio-economic uplift of the hard core poor
women of the community.
District Facilitators (DFs) worked to support UPs in the process but with only one
facilitator covering each of the 6 districts involved this meant a significantly reduced
facilitation role. However other sources of facilitation were present drawing in Union
Facilitation Teams (UFTs) which involved local citizens who had been trained in relevant
skills along with further support provided from upazila level staff (UNOs - Upazila Nirbahi
Officers) and others at higher tiers of government such as Deputy Directors Local
Government (DDLGs).
DFs were also involved in coordinating a systematic process ofmonitoring and reporting
from individual UP. This reporting focused on basic elements of recording expenditure
and securing compliance with project rules
8/3/2019 Learning & Innovations Component of the Local Government Support Projectin Ban Glades Hi Union Parishads
10/35
LIC-LGSP: Lessons Learned page 9
These planning and implementation processes were conceived of as being capable of
generally managing UP projects but were inevitably focused on the management of the
grants provided by LIC which for example required their usage as a condition of the fund
disbursement. LIC provided a general block grant with deliberately few restrictions on
what it could be spent on allowing for example spending of capital or recurrent costs and
with no sectoral limitations.
The grant scheme did however have elements of a performance-based grant scheme
controlling access to grant funds under LIC with a number of relatively simple
performance criteria adopted consisting of, in summary:
Regular opening of the UP office
Village Court Operational
All the standing committees are established
UPs participation in BGCC meetings
Regular Monthly Meetings of UPs:
Women participation in UP Regular Monthly Meetings Tax assessment done
These criteria were specified with slightly more detail but were deliberately designed to
be relatively simple both to achieve and to measure and to reflect a mix of issues closely
related to LIC concerns (such as the establishment of the committees) and broader UP
issues (such as the village courts).
These were in addition to a broader set of criteria for access to LGSP consisting of initially:
1. No adverse or disclaimer audit opinion (i.e. no major financial irregularities)
2. Existence of an Official UP Bank Account3. Staff Capacity: Post of the UP Secretary filled and attendance in the financial
management/procurement training
4. Annual budget for the forthcoming financial year approved by UP in an open
meeting
5. Ones the list of eligible UPs is announced, the UPs must pass a resolution agreed
upon in a full UP meeting to accept the conditions of the LGSP (letter of
commitment).
In subsequent years LGSP grants (and therefore LIC grants) required the following criteria:
1. Hold quarterly open community meetings (at Ward and UP level) for participatory
planning and budgeting purposes
2. Publicity and regularly disclose UP level and scheme specific information and
display this on UP notice boards
3. Submit quarterly reports to community, UNO and LGD according to approved
formats
8/3/2019 Learning & Innovations Component of the Local Government Support Projectin Ban Glades Hi Union Parishads
11/35
LIC-LGSP: Lessons Learned page 10
4. Comply with the requirements in the Environmental and Social Management
Framework (incl. gender issues). All schemes have to be screened and it should be
ensured that all schemes funded by the grant are not on the LGSP negative list.
5. Comply with the procurement regulations of LGSP and guidelines
The project promoted transparency and disclosure through a combination of measures.In addition to the open budget meetings and the general access to UP processes
promoted there was an emphasis on publication of key data including notice boards
conveying details of project schemes both at the UP offices and at individual project sites.
Preparation of an annual budget book showing all funds received directly by the UP and
their uses was supported.
LIC work on revenue mobilisation in the early stages of the project has been largely
preparatory with activity to identify appropriate reform opportunities, build awareness,
develop draft manuals and do some training. Systematic work on extending revenue
bases, raising tax rates, improving valuation and making administration more effectiveare beginning in the latter stages of the project. Meanwhile individual developments by
particular UPs, encouraged by the benefits of the improved planning process for spending
have progressed supported by the local facilitation units.
8/3/2019 Learning & Innovations Component of the Local Government Support Projectin Ban Glades Hi Union Parishads
12/35
LIC-LGSP: Lessons Learned page 11
5 Project Lessons5.1 The Grant System
L1 Funds can be channelled to UP level successfully without significant leakage
demonstrating absorptive capacity
The project has disbursed funds successfully to a large number of UPs and has
documented evidence of these funds being spent on locally determined projects. The
disbursement systems work via higher tiers of local government. Concerns that there
might be leakage of the funds before they reach the UPs do not seem to be supported by
any evidence see the discussion on transparency below. This is important since
concerns over leakage have often led to suggestions that channelling of funds needs to
bypass intervening institutions and go direct to the target local government (UPs in this
case) perhaps via a direct bank transfer.
In this case that does not seem to be necessary. UP Chairmen, Secretaries and other local
stakeholders do not report delays in funds transfer or leakage of funds as a significant
issue. On the contrary, some stakeholders made a point of saying the opposite, that,
unlike other sources these funds were transferred without leakage.
Using existing disbursement channels seems to have provided a cost-effective solution to
disbursement especially in terms of local costs.
This may suggest that the bottom-up accountability mechanism emphasised within the
project may have equal or greater importance than conventional top-down controls for
ensuring secure funds flow.
L2 Local communities feel ownership over LIC funds thanks to the local discretion over
spending and the use of participatory methods in planning and management
The most striking comment from visits to the field was the frequency with which local
stakeholders beyond elected politicians or appointed officials referred to the improved
ownership of funds. This was normally expressed by means of contrasting the LIC project
activities with other activities spending money locally which were said to be lacking in
transparency or responsiveness to local needs.
Most frequently local respondents contrasted the role of UP Chairmen and Secretaries
under LIC and non-LIC projects. This frequently involved overt criticism of the
transparency and accountability of UP Chairmen and Secretaries for conventional
spending. The processes adopted under LIC had turned these processes around.
8/3/2019 Learning & Innovations Component of the Local Government Support Projectin Ban Glades Hi Union Parishads
13/35
LIC-LGSP: Lessons Learned page 12
L3 Funds have been transferred and managed in a highly transparent way.
Funds under LIC have been managed transparently with a variety of measures to achieve
this. Monies transferred are open and publicly known with each UP recording receipt of
funds in an annual budget book printed for public dissemination, the use of notice boards
both centrally and at project sites detailing agreed spending; control over the release of
funds for individual projects by the SSC and collation of reports by the LIC project office.
The result appears to be a channel which is low on leakage within the UP as well as in
higher tiers involved in disbursement. There have been discussions on what proportion of
funds should be allowed for administrative overheads but, unlike some other channels
where unofficial extraction of funds for overheads have taken place, this appears to be an
open discussion and subject to accountability
5.2 Using Performance Conditions for GrantsL4 Results of using simple performance criteria for grant distribution are positive butlimited.
The LIC grant distribution has been conditional on meeting a limited number of relatively
simple process-based performance indicators. These include factors closely related to the
project activities such as the conduct of a tax assessment in line with the legal
requirement (that it be done every 5 years) and indicators rather less closely related such
as the functioning of a village court. (Village courts represent a form of alternative dispute
resolution focusing on civil disputes.)
Performance criteria have two potential points at which they can take effect. The promise
of grants can motivate up-front activity to secure funding. Alternatively, after grants are
distributed, those who lose out can be motivated to do better next time. Also there is
some potential for difference in how the motivation is channelled. One possibility is that
senior decision-makers are the key channel in this case the UP Chairmen and Secretary
and perhaps elected members acting in their own incentives to improve funding. An
alternative is that the community hold senior decision-makers to account this is
probably more likely to work on an ex post basis where lack of the funds is revealed.
Ideally all these mechanism would operate to get the strongest effect.
In the case of LIC, ex ante awareness of performance conditions amongst stakeholders
appears to have been limited and the positive effects of performance improvement have
probably come more after initial grant distributions. This suggests greater potential for
up-front publicisation of the conditions to secure earlier compliance. Evidence on the
mechanism through which change happens is weak but the impression is that
accountability mechanism has been less important than UP Chairmen wanting to secure
better funding for their area. This again suggests more publicity both of disclosure and of
the receipt (and more importantly non-receipt) of funds could yield further benefits.
8/3/2019 Learning & Innovations Component of the Local Government Support Projectin Ban Glades Hi Union Parishads
14/35
LIC-LGSP: Lessons Learned page 13
The value of the underlying changes achieved through greater compliance could be
questioned. Conditions have been implemented with a light touch meaning that the
quality of changes or their real impact has not been probed. Thus the thoroughness of tax
assessments has not been pursued nor the underlying impact of the village courts. This is
arguably the correct approach in the early years of a performance condition system.
Evidence from elsewhere suggests that building up the intensity and focus of conditionsover time achieves better results than setting over-demanding conditions initially.
That however does suggest a need for a conscious move into more demanding
performance conditions in the next stages of the project. To some extent this is already in
hand with the next phase of LIC planning a more elaborate Performance Based Grant
Scheme. But care needs to be taken that that represents an appropriate step forward
and, for example, not merely a multiplication of the number of performance criteria.
Greater analysis of the upfront relevance of chosen conditions and ex post analysis within
the project of their value has significant value.
L5 Use of independent auditors to assess performance has worked well (but need to be
institutionalised)
The performance criteria were independently verified by external auditors contracted
from outside of government. This appears to have produced reliable and quick results
which are accepted as legitimate by UPs. Interestingly two UPs visited in the field made a
point of saying that these auditors (unlike other auditors with whom the UPs were used
to dealing) had not requested improper payments as part of their activity. This does raise
questions of the appropriate route to wider institutionalisation conventionalapproaches would say that this measure should be undertaken by government auditors.
However trust in current government audit control mechanisms is limited and it may be
too early to abandon the useful process pioneered within LIC.
5.3 Participation in Planning, Implementation and ReviewL6 Ownership is directly related to participation in planning, delivery and monitoring.
LIC grants are block grants with a large degree of freedom over their spending. This then
creates a meaningful role for local planning in the use of the funds. The mechanismemphasised is a bottom-up mechanism with considerable real influence over spending
from the bottom level rather than deciding on priorities purely at an overall UP level,
The participation in planning, delivery and monitoring expenditure are positively
commented on by local stakeholders. Understanding the complex process of participation
would require a much larger (and difficult) task of observing a significant number of such
participation processes in a number of areas and over time. It would have to be done in a
8/3/2019 Learning & Innovations Component of the Local Government Support Projectin Ban Glades Hi Union Parishads
15/35
LIC-LGSP: Lessons Learned page 14
way that did not itself distort the process. Limited resources meant that this extensive
observation could not be undertaken. Thus the spread of participation, whether there is
equal access for all groups (rich, poor, young/old, educated/uneducated etc) to such
activities could not definitively be confirmed. There is always a concern that such
participation is dominated by an elite (in terms of decision-making even if not in terms of
attendance). However the project did seem to have opened up access to decision-makingto people who were previously excluded.
L7 Ward Level Meetings and Open budget meetings do give an effective voice to local
participants
The particular measures of ward level meetings and open budget meetings have involved
large numbers of peoples and have received considerable positive comment. In some
forms of bottom-up planning eventual top-level decisions on spending neglect the
bottom-up voice but this does not appear to have happened in the LIC project.
The result is that there are a relatively large number of meetings to decide upon a
relatively small amount of resources. Whilst this might be criticised in terms of the
relative value of the process in fact the participants d seem to value the process and it
does have potential to be expanded to cover greater volumes of resources
Evidence from the survey conducted on dissemination and information (DCGCI, 2010)
found that 25.6% of respondents said they had been called to open budget meetings and
around 7% had participated.
Use of the published budget books seemed patchier with high numbers being reported inthe DCGCI survey as being unaware of the budget book. This may suggest the face-to-face
meetings are more important than the printed documents although the latter are
perhaps more relevant for upward accountability.
L8 Improvements in accountability and transparency have spilled over from LIC-funded
projects into other UP-controlled spending but this effect is partial.
The intention of LIC is clearly not restricted to securing better governance only of those
funds provided by the LIC project itself. Evidence on how far improved accountability and
participation have spread from LIC funding to other sources of funding is not
systematically available. But evidence from field trips suggest that some areas have
moved to following LIC approaches for a large variety of miscellaneous funding sources.
Projects identified in the LIC process but for which insufficient funds were available have
been funded by other routes where the UP has some discretion. But in other UPs it
appears that LIC funding has become an enclave of good practice with little change for
8/3/2019 Learning & Innovations Component of the Local Government Support Projectin Ban Glades Hi Union Parishads
16/35
LIC-LGSP: Lessons Learned page 15
other funding sources. The underlying determinant may be the UP Chairman and
Secretary. Where these have bought into the LIC approach there has been fundamental
change but, for some, older patterns have remained. There is however bottom-up
pressure to change to LIC approaches and thus over time, perhaps supported by election
results, there might be a stronger spill-over effect but it appears that the value of LIC
processes may need some top-down pressure to achieve universal adoption quickly.
5.4 Spending DecisionsL9 Small capital schemes are the preferred use of the funds and are highly valued
The chosen expenditure locally has been heavily dominated by small physical capital
infrastructure schemes typically earthworks, short earth roads, culverts, small bridges
etc. The project itself has not specified such a focus its rules permit a very wide range of
spending with no restriction against recurrent spending or in favour of particular sectors.
(There are very limited numbers of exclusions such as religious buildings but these do notseem to have been a significant impediment to local planning. Additionally during one
period of the project limitations caused by donor funding conditions meant that there
was a requirement to spend overwhelmingly on capital. Whilst this was unhelpful in
terms of the long term development of the project, it seems to have confirmed an
existing tendency rather than being the primary cause of the problem.)
A number of reasons can be identified for why small capital schemes have dominated:
Uncertainty over whether funds (and limited existing own source revenues) will
continue in future years make committing to recurrent expenditure rather unwise
Recurrent expenditure needs in areas like education and healthcare are probablyviewed as the responsibility of higher levels of government There may be a sense
that spending on non-infrastructure items more closely related to sectoral areas
like education or healthcare may simply crowd-out spending that would have
happened form higher levels
Bottom-up planning processes are likely to identify very local needs which may be
dominated by local physical infrastructure
UPs tend to share money out equally between wards (see below)
Facilitation and training have focused on concrete processes for planning,
implementation and supervision of infrastructure rather than on recurrent costs
or on soft capital. It is not clear how far this is a cause or an effect however.
Some guidance provided by the project seems oriented to physical capital e.g. arequirement for schemes to be easily maintained
There may be a degree of path dependence an early focus on small capital
schemes has perhaps become locked in through custom and practice
A further conventional explanation of over-expenditure on capital schemes in other
contexts has been the greater salience of capital schemes they are more visible and
8/3/2019 Learning & Innovations Component of the Local Government Support Projectin Ban Glades Hi Union Parishads
17/35
LIC-LGSP: Lessons Learned page 16
more easily claimable by key decision-makers as being due to their efforts within, for
example, a patron client system. This explanation does not completely seem to fit the LIC
context where choice of schemes does seem to be genuinely driven bottom-up rather
than by elected politicians or by an elite. However the salience of capital projects in terms
of their immediate obvious benefits may have added to their attractiveness to the
community whereas other types of scheme (e.g. skills development programmes) mightbe rather hard to value in the absence of clear nearby examples that have worked.
Khan (2009) did note based on her study of women and LIC that issues of lack of proper
service in education, health etc are raised in WDC discussions with the community. There
seems to be a demand to design schemes for ensuring services but this does not seem to
have fed through into significant project proposals that are accepted. Similarly
Aminuzzaman(2009) quotes survey data suggesting that local citizens aspire to have social
services and economic development functions provide by UPs for example 74% of
respondents stating an expectation for the provision of income generating activities and
58% education functions.
Local stakeholders value the accepted small capital schemes highly. They are readily able
to recount benefits in terms of access to social facilities, improved economic
opportunities and so on. Thus there is considerable implied evidence that this spending
represent high value for money.
However the project has not been able to track these benefits in systematic ways and
indeed to do so would regard an enormous effort, probably out-of-scale with the
individual spending given the currently limited state of socio-economic data at UP and
ward level.
L10 Moving away from small capital schemes is hard without considerable effort
As suggested above there are a number of reasons why small physical capital schemes
make sense locally.
However there is perhaps potential for opening up decision-making more:
Spending on soft capital projects such as training and capacity building for
income generation. This was one area which was sometimes mentioned as a
possible area (and one which might specially benefit women - see below) but
only a small number of UPs seemed to be pursuing these
Capital items more directly related to sectoral areas. There were some limited
examples of spending on e.g. replacement furniture for classrooms
Spending on recurrent costs on sectoral areas e.g. on medical supplies or teaching
materials. This seems rare or non-existent.
8/3/2019 Learning & Innovations Component of the Local Government Support Projectin Ban Glades Hi Union Parishads
18/35
LIC-LGSP: Lessons Learned page 17
Given the effectiveness of the mechanism identified for funds channelling there does
seem to be unexploited potential here. The project could address some of the reason for
the bias towards small infrastructure projects e.g. in reorienting training and guidance.
But a more substantial effort depends on a reassessment of the role for UPs in service
delivery see below.
L12 Concern for local horizontal equity and short time horizons make fund usage less
strategic
L13 Equal distribution of resources between wards may be a poor reflection of inter-
ward needs
The de facto practice in most UPs to determine the final allocation of funds between
projects was to allocate funds equally or roughly equally between wards and then select
the highest ranking project(s) in each ward. This seemed to be driven by an admirable
concern to ensure demonstrable horizontal equity between wards. The unintended
consequence however is that LIC is dominated by small projects with very local impacts.
Many of these projects will be very desirable. However larger projects and ones which cut
across ward boundaries or which are UP-wide tend to be neglected. Also the simple
equivalence between wards may not reflect genuine horizontal equity different wards
might be rather different in terms of size or other measures of need.
In part this is the result of responding to a perceived inequity of other funding sources
with the need to pay heed (rather than lip-service) to bottom-up planning meaning that
small local projects win out. There is likely to be a limited voice for UP-wide projects in
ward meetings. There might for example be a thought that such things will occur any way
and the ward can free-ride on those projects whilst also getting projects of its own.
Thus a prisoners' dilemma effect may crowd out bigger projects. As such it is perhaps
unreasonable to be too critical. But it does limit the value of spending on projects.
This issue relates closely to the extent to which the UP and individual wards have a long-
term time horizon. LIC has promoted the idea of a 5 year socio-economic plan and the
results survey indicated that 67% of respondent were familiar with such a plan in their UP
in LIC areas (and higher at 78% for Sirajganj) compared with only 37% in non-LIC LGSP
areas. However the impact of this strategy on in-year planning appears to have been
limited. This is not surprising a dominance of short-term thinking is a common issue in
budgeting across many of not most countries and at central as well as local level.
However more effort to make a longer term vision real at both UP and ward level could
be a powerful assistance.
8/3/2019 Learning & Innovations Component of the Local Government Support Projectin Ban Glades Hi Union Parishads
19/35
LIC-LGSP: Lessons Learned page 18
Thus resolving the lack of a strategic view requires:
Over time, as confidence in the continuity of funds develops communities may be
more willing to accept that a strategic use of funds means that not all areas will
get equal amounts each year
Commitment by central government to continuity of funds over a medium term
period Adopting an approach which precedes the initial bottom-up planning process with
a stronger visioning exercise setting out a longer term plan for what the UP wants
to become may help encourage the adoption for a more strategic approach.
L14 Limited UP responsibilities within the overall LG system restrict the current value of
the grant mechanism
UPs currently have very limited responsibilities for service delivery functions. They do
have roles in regulatory functions like the confirmation of citizenship and they do have
some permissive powers but generally delivery of services, especially social services, islocated at higher levels. This is despite the fact that UPs represent, by international
standards, a reasonably sizeable unit in population terms with population ranging up to
40,000-50,000 in some cases.
De facto, many social services are delivered within the Union area and there are current
legislative proposals to increase the number of staff from higher tiers of government
posted to the UP office. This may well provide benefits in terms of policy cooperation and
service accessibility. But, until the UP has responsibility for some basic service provision,
there is a neglected opportunity for greater use of the effective LIC mechanism at lower
levels. As noted above, Aminuzzaman (2009) observes some degree of expectation bylocal citizens for the provision of such services but the current LIC and wider governance
structures do not promote this role.
L15 There is potential to secure greater community commitment to responsibility for
maintenance
In some other countries similar types of capital spending initiatives have been
accompanied by efforts to secure formal community commitment to assist in maintain
the assets. Given the well-known tendency in developing countries for under-spending on
maintenance; the exposure of works like earthwork roads to collapse and the basic
nature of the maintenance involved this does seem a possible fruitful area for LIC. It has
however not been followed in this project. An approach followed but with limited success
has been to encourage UPs to devote sums within their budget for use of grants to
recurrent expenditure on maintenance.
8/3/2019 Learning & Innovations Component of the Local Government Support Projectin Ban Glades Hi Union Parishads
20/35
LIC-LGSP: Lessons Learned page 19
One explanation may be that in many cases the community does autonomously engage in
repair work (the writer observed this happening in one spot-visit).
However the impression is that other assets do suffer from under-maintenance and this is
an area that can be explored. A commitment to maintenance could for example improve
a projects chances of being selected in the final budget allocation meeting and would
help cement agreement to further works being included as the UP monitors the
implementation of such works.
5.5 LIC and Local PowerL16 LIC has been an effective mechanism in supporting the empowerment of women
Khans (2009) study specifically of the impact of LIC on women found that there was a
gradual change identifiable in a number of aspects of womens role in the UP:
o Assumption of leadership roles in the UP planning, implementation andsupervision of developmental projects is leading to ownership of the
projects by the women members, thereby fostering greater individual and
collective responsibility. The women members have been reported to be
more punctual, informed and proactive in their activities in the UP.
o Greater interaction of the women UP members with the community
members including women and the male co-colleagues is changing the
perceptions of the women members and the community regarding their
public roles and responsibilities. The community people have been found
to be appreciative of the women members efforts. Importance of the
women in their families is also being enhanced.
o The open discussions regarding the schemes and the budgets promotingattentiveness towards accountability in delivery of services among the
female and male councillors. The perception that women cannot assume
roles of managing and leading activities and finances is gradually changing
LIC has promoted the role of women most notably by a requirement that 30% of spending
must be on projects that favour women and through the promotion of the Womens
Development Forums (WDFs).
Tracking the detailed impact of these measures is rather hard for the reasons stated
above about unpicking what actually happens in participatory planning meetings. Thereappears to a variety of practices in terms of the institutional arrangements. In some
areas, women have separate meetings and produce separate proposed project lists. They
may or may not take part in the general meeting in addition. In other areas they are part
of a broader meeting but some projects are somehow deemed to be women's projects
perhaps as part of a separate decision within the larger meeting.
8/3/2019 Learning & Innovations Component of the Local Government Support Projectin Ban Glades Hi Union Parishads
21/35
LIC-LGSP: Lessons Learned page 20
In the lessons survey 85% of respondents reported that at least 30%of projects were
favoured by women and this was a notably higher figure than in non-LIC LGSP areas
where the result was 50%. However the nature of the projects which are accepted
generally (small capital projects) in many ways appear to be overwhelmingly of general
benefit rather than of benefit specifically to women. That includes both projects which
are labelled as projects favouring women and others with little obvious variation betweenthe two. There does appear to be a genuine case however that many of these projects are
specifically of benefit to women more than men. One type of example frequently quoted
was the building of access roads where otherwise access routes would be flooded.
Because women typically would find it more difficult to wade through water this was
seem as especially important for women both in going about their daily activities and for
accessing services such as healthcare or taking children to schools.
Nevertheless there remains a suspicion that in some areas there is a more general
prioritising of projects and that there is then is a labelling of some of these projects as
womens projects. This not the same as alleging that womens interest are neglected as
noted above, the projects mostly favour the community broadly without discriminating
between men and women. Khan (2009) put this more positively stating:
The provision of 30% women prioritized schemes is being accepted by the UPs
and the community. This may be taken as an indication that the women are listing
schemes that not only benefit women but the entire community. This is an
innovative way of integrating grassroots level women in the planning process but
also of establishing the credibility of women UP members as responsible leaders
in such activity.
Thus the degree of change in terms of womens empowerment achieved by the project is
hard to pin down and will vary between areas. Also this theme is one pursued by a
number of other initiatives, both government and NGO-supported, and hence it is hard to
attribute all of the gains to the LIC project.
The LIC project does however seem to have had a signalling or demonstration function
here which appears to be important at least in some areas. It has signalled and
legitimated the rightful roles of women in decision-making and demonstrated how that
can proceed to the benefit of the community as a whole. In this respect the WDFs have
played a role in giving additional opportunities for womans representation and
contribution. There is some evidence that in Sirajganj, where there has been longer timefor evolution of womens role, that they have found greater opportunities with, for
example, greater likelihood that the char of the Ward Development Committee will be a
woman.
Similarly there is quite strong evidence of the substantial role of women in the
participatory meetings. This suggests that in Sirajganj substantial participation by women
is the norm with 71% of respondents reporting that more than 30% of participants are
8/3/2019 Learning & Innovations Component of the Local Government Support Projectin Ban Glades Hi Union Parishads
22/35
LIC-LGSP: Lessons Learned page 21
women whilst the equivalent figure in other LIC areas is a more modest 32% but still
substantially higher than in non-LIC LGSP areas where the figure is only 13%.
Evidence from the DCGCI study (2010) suggested that around 37% of respondents
specifically said that womens contributions to the planning process were valued with
13% only saying it was not valued
On the back of this development some women seem to have been empowered to
develop broader roles going beyond the narrow limits of the LIC functions. For example
there are frequent anecdotes about women members taking action to deal with dowry
issues or female abuse issues. Khan (2009) noted that:
The leadership roles and authority of women in the LIC processes have increased
their confidence in interacting with offices of authority at the UPZ and districts as
well as with the Chairman and male councillors of their own UPs. This is enabling
them to be a part of the delivery that is effective in satisfying the local
community.
o The UP women members are found to be regularly visiting and interacting
with the UPZ officials as WDC and WDF committee members for
clarification of rules and procedures and information.
o Many of the UP women members particularly those in the WDF (Tarash
UPZ in Sirajganj and Belabo UPZ in Norshingdhi) have reported to monitor
schools in the unions, interacting with the school authorities to retrieve
drop outs of girls and improving attendance of students and teachers.
o Many are monitoring and intervening in the union health centres and are
effectively doing similar work in the area of motivating families to install
sanitary latrines.
These observations are real and not uncommon. It is however very hard to be sure that
they can be completely attributed to LIC without careful study of control groups from
non-LIC areas. A number of projects have sought to develop womens roles in UPs for
example. However the signalling role noted above and the experience provided by LIC in
participating in committee work over real resource allocation seems to have provided a
positive contribution.
L17 LIC has developed countervailing power sources within the UP
The LIC project can be argued to have developed countervailing centres of power within
the UP including but extending well beyond women. Government is often seen as a set of
checks and balances on power and setting up a series of committees with power or
influence over spending has made it harder for a narrow elite to control spending
providing a series of checks to improper spending.
8/3/2019 Learning & Innovations Component of the Local Government Support Projectin Ban Glades Hi Union Parishads
23/35
LIC-LGSP: Lessons Learned page 22
The countervailing forces come from a variety of institutional mechanisms promoted by
the project the Scheme Supervision Committees, the Ward Development Committees,
the District Facilitators and the Union Facilitation Teams. Khans (2009) study found that
the project had led to the UPs functioning as a parishad of all the members and not just
that of the chairman reflecting the prior perception of UPs as being identical with the
Chairman.
Hossein (2009) develops the idea of rude accountability: strong social and local
political pressures go some way towards supplying a rough responsiveness to demands
for service. These work through shame and embarrassment, pressures to maintain
reputation and status, and the threat of violence and sees this as one way for poor
people, especially women to secure some representation in governance where otherwise
decision would be wholly dominated by an elite. To some extent the LIC project has
enabled a slightly politer form of accountability, providing low-level formal institutions
which give the weak a place to apply their pressure.
L18 Relatively over-structured systems have probably been helpful in the early stages of
LIC
Viewed from the outside, the LIC structure of committees can appear overly elaborate. In
conventional approaches there might be greater reliance on committees of UP members
and on single community-level structures covering for example both resource allocation
and implementation. LIC instead has proposed a series of committees. These have some
benefits in that they perhaps collectively give a greater strength to oppose dominance by
UP chairmen and secretaries and also avoid simply replacing one centre of power with anew centre of power by diversifying responsibilities and avoiding conflicts of interest
between e.g. committing resources and supervising spending.
5.6 LIC and Revenue MobilisationL19 Linking between spending and improved willingness to pay have been
disappointingly patchy
One hope for involving the community in planning, implementing and monitoring
expenditure is that it can give them increased willingness to pay taxes which can then inturn be spent through the enhanced planning mechanism producing a virtuous circle
confirming a simple but effective form of social contract between local government and
people.
In discussions with local stakeholder this appears as an important effect and is frequently
claimed by stakeholders at both local and central level. There are anecdotal stories of
individual UP chairmen seeking substantial increases in revenue collected e.g. through a
8/3/2019 Learning & Innovations Component of the Local Government Support Projectin Ban Glades Hi Union Parishads
24/35
LIC-LGSP: Lessons Learned page 23
commitment to collect 100% of tax due and the limited statistics from UP in the revenue
mobilisation study do show some significant increases in actual revenue raised over short
term periods as much as 500% in some areas.
However the size of the effect on willingness to pay and how distinct it is from non-LIC
areas remains in some doubt. Available statistics suggest the average effect is small. The
revenue survey found that around 78% of respondents reported a willingness to pay
more tax. However the percentage is identical in the non-LIC LGSP areas suggesting the
more intensive LIC work has not produced a greater willingness to pay. The typical
amounts suggested as extra tax to be paid is rather limited around 90 Taka
(approximately US$13) per household per year.
There are question marks over the validity of hypothetical survey questions on willingness
to pay but these numbers are disappointing. It may be that the relative youth of the
project means that substantial commitment to pay extra revenues is still developing. The
limited roles of the UP and the modest scope of LIC grant funding may restrict the
imagination of householders in responding to this question. However the willingness does
appear to exist to be exploited and, as the project moves further into revenue
mobilisation as an explicit focus, this can be tested further.
L20 Support to Revenue Mobilisation requires considerable effort and cannot rely on
bottom-up pressure alone
As noted above increased evidence for increased willingness to pay is patchy but there
does appear to be potential to improve revenue collection. Given the opportunities
identified for spending on high value projects and the low starting base of revenue
collected it would appear that improved policy and practice on revenue collection
represent important potential within the project.
However progress to date has been limited. There are multiple examples of individual
good practice in particular areas such as better organised tax assessments, use of tax pass
books to record taxes paid better and link access to service provision to tax payment but
these have not been spread widely.
A number of reasons can be identified for this
There is reluctance from elected politicians to raising tax rates, applying new
taxes or significantly changing tax systems in ways that change the burden of
taxes and some reluctance to enforce the existing system
The nationally-specified tax system itself sets very low tax rates (for example an
absolute maximum of 500 taka for property taxes per household which
represents the broadest tax source for UPs currently that equates to a
maximum of around US$7 per year with, of course, the vast majority of
8/3/2019 Learning & Innovations Component of the Local Government Support Projectin Ban Glades Hi Union Parishads
25/35
LIC-LGSP: Lessons Learned page 24
household paying considerably less. Changing the details of tax bases and tax
rates in many cases needs central government support.
The administrative system is rather complex given the sums that can be raised
e.g. a relatively complex method of appraisal for property given the low rates that
are then produced
There is a lack of clarity about UP powers in some respects e.g. whether a
community can voluntarily breach the normal property tax cap in specialcircumstances
UP resources are constrained although a number of tax related functions have
been effectively contracted out in many areas especially assessment and
collection
Thus, although there has been considerable discussion about revenue mobilisation and
some local initiatives, the level of support from the project to systematic reform has been
limited until recently when there has been conscious effort to embark on a formal
revenue mobilisation strategy with appropriate support.
One area where the project has focused some systematic attention has been the tax
assessment where conducting the five-yearly assessment was made part of the conditions
for accessing LIC grants. How far this has improved tax collection rates however remains
unclear. Evidence from the revenue mobilisation survey indicated that most UPs
continued to operate an ad hoc scheme of assessing property taxes which seems unlikely
to produce substantial increases.
Hopes for improved revenue mobilisation lie in several areas but can be summarised as
Better assessment systems for the current primary revenue source of the
property tax
Better collection and administration processes
Expanded revenue sources
L21 Improving Revenue Mobilisation requires effective resources at the national level in
support of the project as well as the local facilitation skills.
Many of the improvements in collection and administration are relatively non-technical
and often do not require substantial legislative change. Thus the project is well placed to
increase its support in this field through existing mechanisms of, for example, DFs and
UFTs.
However some aspects of improvement in revenue policy and administration are in need
of central direction. Development of training materials, administration manuals etc are
already underway. But behind this lies a prior series of questions about what tax bases to
allow to UPs and what tax rates to allow them to collect. This is normally regarded as a
question for central government in a unitary state like Bangladesh. The nature of the LIC
8/3/2019 Learning & Innovations Component of the Local Government Support Projectin Ban Glades Hi Union Parishads
26/35
LIC-LGSP: Lessons Learned page 25
project means that its mode of development is essentially as a pilot project. This does
present some particular technical problems for improvement in revenue mobilisation:
There may be central unwillingness to allow UPs in a pilot access to a different
range of revenue sources than the rest of the country perhaps on grounds of
equity
Where tax bases being considered for UPs are already in use at a higher tier ofgovernment then a non-uniform system may be difficult to manage
Where new sources of revenue are envisaged or significant increases in rates
considered, there may be problems of tax avoidance by shifting resources e.g. if
say vehicles were newly taxed in LIC UPs it is likely that vehicle-owners might
attempt to avoid tax by shifting their registration to non-LIC areas.
Thus there are practical difficulties and problems of distortion involved in LIC UPs
pioneering completely new sources of revenue and, perhaps to a lesser extent,
pioneering significantly higher tax rates. These might be overcome with strong levels of
central support for such initiatives and with demonstrated local backing. To date central
support has actually been patchy reflecting the general problems of securing
commitment to policy reform in Bangladesh. Local support has been rather more
forthcoming especially with regard to new tax bases. But this often appears to be a rather
simplistic desire to tax those perceived as able to pay, often outsiders such as large
businesses (e.g. mobile telephone companies) or NGOs. That is not surprising but may
reflect a limited understanding of the technical or broader political issues e.g.
discouraging the spread of mobile telephone masts or of local NGO offices might be
counter-productive in terms of the broader socio-economic development of the area. The
local appetite for significantly higher local tax rates does not seem to be strong.
Developing a sound technical basis for an enlarged revenue base and getting commitmentto it from central government requires a type of resource which has not been the main
focus of the project to date.
Thus the nature of the project as a pilot and the current state of political commitment to
revenue mobilisation suggest that the most fruitful areas for this project to focus on are
improvements in the tax administration system (including valuation, assessment, billing,
collection, recording banking etc). These generally do not require significant legislative
change (valuation may be an exception) and can proceed using the resources already
available to the project.
5.7 Project Facilitation and SupportL22 facilitation from within the project has been an important but underused resource
Sirajganj was widely viewed as depending on the strength of facilitators. In LIC there has
been one District Facilitator supporting a number of UPs. This has inevitably diluted the
time they can spend with each UP. The role of the facilitator is in practice much wider
8/3/2019 Learning & Innovations Component of the Local Government Support Projectin Ban Glades Hi Union Parishads
27/35
LIC-LGSP: Lessons Learned page 26
than the name implies. In part they have a controlling function enforcing project rules and
ensuring the monitoring of spending. This is conducted in a manner which is facilitative
but is nevertheless ultimately a part of control. The DFs appear to be widely respected
and to be successful relationship with UP stakeholders although Khan (2009) noted that
"[i]n some cases the project District Facilitators are less proactive in providing advice,
inspiration and motivation to women members.
The DFs have also been a key training resources disseminating knowledge and skills
downwards to UP level. Other training, facilitating and capacity building resources used in
the project have been the Union Facilitation Teams using educated local young people to
fulfil a range of training and facilitation support and Upazila Cooperation Officers who
have also contributed to the project. Both of these latter resources do appear to have
been useful but their role has varied between areas reflecting different levels of ability
and commitment amongst those involved. Again, it is quite hard to track their effect but it
seems likely that in some areas they have been very useful especially in strengthening the
roles of the local committees but in other areas they appear to have had rather less
impact.
In summary the District Facilitators appear to the strongest feature of the facilitation but
their effort is spread rather thinly and this remains a question mark over future adoption
of LIC-like funding across the country. Dedicated DFs existing outside normal civil service
systems and incentives appear valuable but whether civil servants will be appointed to do
the same role and whether they can cope with other competing demands on their time
remains uncertain.
L23 Project design has emphasised top-down facilitation and under-emphasised
horizontal sharing
The style of facilitation as noted above appears to be often a rather top-down approach
emphasising correct processes and what to do to stay within the project rules and access
funds. This has produced benefits but means that other methods of learning and sharing
have perhaps been relatively neglected. In particular explicit mechanisms to identify
innovative practice being developed locally and share it horizontally have been under-
emphasised. There is some parallel experience here from the ESP-supported Horizontal
Learning project (Horizontal Learning Project, 2009) which has in part worked in relatedfields such as planning and revenue mobilisation suggesting this can be a powerful
mechanism. In their case, there is a reliance on NGOs to lead the process and generally
their emphasis is on learning from the bottom up. In the LIC context a mixture of top-
down guidance based on good international practice allied to horizontal learning would
appear to be a powerful tool.
8/3/2019 Learning & Innovations Component of the Local Government Support Projectin Ban Glades Hi Union Parishads
28/35
LIC-LGSP: Lessons Learned page 27
For example, field studies found a variety of ways of contracting for essentially similar
types of project like earthworks. In some cases the relevant UP committee effectively
managed the process and employed individual workers on a daily basis. In other cases
they employed a foreman type worker on a higher wage to supervise their workers, in
other cases there was something akin to a contracting out of the work to a community
group. Payment of workers was sometimes a daily rate (perhaps subject to some controlover satisfactory performance) and in other cases was based on work done e.g. earth
shifted. Interestingly each area had their idea on which was best and there did not appear
to have been any interchange to explore the different merits of these different
approaches. A greater emphasis on horizontal earning opportunities (perhaps in some
cases facilitated by special staff with expert relevant knowledge) could pay off in term so
effectiveness of expenditure.
L24 The project has relied on local knowledge and perhaps missed opportunities to
examine better technical approaches and deploy outside technical expertise
The limited scale of the facilitation resources and the nature of the facilitators expertise
have meant that the emphasis on their facilitation has been on process issues. Decisions
on what projects to fund and on implementation and monitoring of individual projects
are effectively left to the local stakeholder bodies. This of course rightfully reflects the
overall aim of LIC to develop and demonstrate a capacity for participatory planning.
However the schemes being chosen (and in fact the ones not chosen) are frequently
schemes which involve the potential to deploy a degree of expert knowledge. For
example the widespread use of earthworks roads suffers from the fact that many suchroads are frequently washed away within a few years raising the question of whether a
more expensive and more permanent solution might be more cost effective in the long
run.
Similarly, appropriate quality of building materials is a matter of expert knowledge. Local
communities sometimes claimed this expertise through experience but in other cases
they appeared to be doing what had always been done. UPs were very reliant on getting
limited technical assistance from LGED specialists locally (located in higher tiers of
government) but this appeared to be rather restricted to costing and specifying a project
once it had already been identified rather than on saying whether that was the rightsolution to begin with.
Khan (2009) notes the technical issues surrounding the validity of market rates quoted by
officials from higher tiers in costing projects suggesting that more training is needed here
to allow local stakeholders (particularly women) greater access to key technical planning
issues.
8/3/2019 Learning & Innovations Component of the Local Government Support Projectin Ban Glades Hi Union Parishads
29/35
LIC-LGSP: Lessons Learned page 28
Given the predominance of certain types of spending it does raise the issue of whether
the project could contribute to expenditure effectiveness but deploying selective
specialist expertise (manly engineering probably) to assist in developing best practice
guidance which could then be disseminated. There is a risk here however that
inappropriate deployment of expertise could undermine the bottom-up virtues of LIC so
interventions here need to be designed with care.
5.8 Information and DisseminationL25 A variety of broader information and dissemination channels to promote the
approach have benefited the project but dissemination could be broadened.
The project has invested considerable resources in dissemination within Bangladesh both
within LIC areas and in the wider country. These have used a range of attractive methods
including materials produced in local languages, materials like calendars which are likely
to find wide distribution and display and modes other than printed materials such asvideos which give good popular access. These methods have played a role in awareness
building but in also in capacity building. Videos of bottom-up participative meetings for
example have been useful in making participants understand what is meant by these
concepts and seeing that it is a real process which can be accessible to all.
Knowledge of the earlier Sirajganj project appears to be quite well spread both within
Bangladesh and beyond (e.g. Sirker and Cosic, 2007; Deles et al, 2010). Knowledge of the
LIC project is however less well developed despite the potential offered by new
technology such as video since the Sirajganj project. Dissemination of products like the
video records of community meetings would allow greater insight into how these
methods work and act as a counterweight to the scepticism that sometimes (often quite
properly) surrounds the claims for such approaches. Potential to use new channels such
as video sharing websites like YouTube could be exploited more.
5.9 Learning in LICL26 There is potential for use of a more experimental design for future interventions.
LIC is explicitly a learning-focused project with the intention of its lessons being applied
nationally across all UPs, not least via the national LGSP. In general public policyinterventions are known to be difficult to learn from because typically it is hard to run the
equivalent of a laboratory experiment in the field of governance. Such experiments
require holding other factors constant, repeating experiments and running well-
structured control groups. Such approaches are typically not possible in, for example
projects affecting central governments since there is only one experimental subject and
no ability to hold all relevant factors constant. Without this quasi-experimental approach
8/3/2019 Learning & Innovations Component of the Local Government Support Projectin Ban Glades Hi Union Parishads
30/35
LIC-LGSP: Lessons Learned page 29
it is hard to be sure about what the effects of specific interventions have been and hence
to know for sure what the lessons are that are to be learned.
However local governance offers an opportunity to conduct studies which are closer to
experiments since within a country there are multiple local governments. Thus initiatives
can be attempted in a selected group and effects measured against a control group (see
Humphreys and Weinstein, 2009 and for a specific example, Olken, 2005). This does
however require careful initial design on the interventions and awareness that, unlike in a
laboratory experiment, not every other relevant factor can be held constant. Use of a
strong representative control group can reduce the latter problem however.
LIC has not consciously adopted an experimental approach. A number of reasons can be
identified for this. The Bangladesh public policy reform context is difficult. Securing
agreement to new reforms and gaining commitment to their implementation is hard.
Arguably that is more so in local governance given the highly centralized nature of much
of Bangladeshi government. Thus the project has moved relatively fluidly with some
broad overall emphases like the bottom-up planning within the context of a discretionary
grant.
This effect has been strengthened by the desire to give space to local preferences. A
strongly disciplined structured approach requires top down controls which could easily
undermine the spirit of the bottom-up planning. Arguably many of the projects which
have adopted an experimental approach have been much narrower in scope than LIC
which has sought improvements across a wide range of governance processes and
utilised a discretionary grant in contrast to funding for specific initiatives like roadwork in
some other projects.
L27 Effects are hard to demonstrate definitively because of a fluid project
design/management reflecting national policy styles and local variety
Nevertheless this does make demonstrating LICs results convincingly more challenging
that it might be. There are multiple initiatives in the field of local governance in
Bangladesh the broader including the broader LGSP programme, other work by UNDP
such as the REOPA project; work by multiple international donors (see for example
support by the SDC to local capacity building) and by NGOs like CARE (see for example
their owrk in slected UPs on local governance). In addition there are broader political and
economic developments in the country.
The consequence of this is that isolating the impact of LIC initiatives is already difficult.
Where there has not been a consistent uniform intervention then convincing empirical
demonstration of a causal effect is very hard.
8/3/2019 Learning & Innovations Component of the Local Government Support Projectin Ban Glades Hi Union Parishads
31/35
LIC-LGSP: Lessons Learned page 30
To some extent this is unavoidable given that the project has had to be opportunistic in
its approach to what can be progressed. For examples developments in areas such as tax
administration have been held up because of concerns over the need for central changes
in law to permit pilots to go ahead. In the face of these obstacles the project has sought
to proceed where possible and sometimes this has varied between areas.
L28 Learning effects have been slow because of the slow cycle of policy development
nationally
LIC was conceived as a component of LGSP with a role of feeding into national decisions
on funding local governments. In practice this requires entry points in terms of project
design and national policy. However in practice the national LGSP policy has proved to be
hard to adjust mid-cycle. This reflects the relatively slow pace of change generally within
the country for policy reform where a critical mass of support for developments needs to
be assembled against a complex national political structure. This has meant that,
although lessons of the project in terms of the value of block grants, the need for
facilitation etc have been well understood by those close to the project, translating this
into an evolved LGSP project has had to wait until the second LGSP project rather than
being able to take place within the existing LGSP programme.
The message here is that ambitions about learning from projects need to be set
realistically. The well-known difficulties of securing administrative reform in Bangladesh
require considerable time scales to achieve change where the drivers of reform in a
range of parts of society need to develop (see for example Duncan et al, 2002).
8/3/2019 Learning & Innovations Component of the Local Government Support Projectin Ban Glades Hi Union Parishads
32/35
LIC-LGSP: Lessons Learned page 31
6 ConclusionsThe LIC is clearly the descendent of the earlier SLGDP project in Sirajganj. The core
reforms promoted within LIC bear a close resemblance to those pursued in the earlier
project. Perhaps unsurprisingly, there is a close similarity between the lessons identified
here from LIC and the lessons identified earlier at the completion of SLGDP and quoted at
the beginning of this study.
In a sense this could be interpreted negatively. In fact LIC has expanded the range of
interventions and refined them. More importantly though, it has demonstrated the
relevance of these lessons across a broad range of UPs showing for example that
absorptive capacity is high across the country. It has also demonstrated that the relatively
intensive facilitation inputs adopted in Sirajganj (which were probably unrealistic at a
national level) are not required to get significant achievements.
LIC is not the only project working in these areas and reaching a robust understanding of
the attribution of different effects is probably impossible in the fluid context of
Bangladesh governance. But, subject to this caveat, LIC does appear to have produced
significant gains in accountability and transparency and to have made modest but
important improvements to the welfare of local citizens.
These gains are transferable and there are already clear signs of lessons from LIC being
transmitted to national policy through the planning for the next stage of the LGSP.
However the scale of local grants remains limited with a policy dialogue on governance at
UP level remaining one focused on a narrow set of functions to be delivered by UPs
themselves. LIC has demonstrated a mechanism for determining and implementing local
spending that appears capable of dealing with much larger responsibilities and of doing it
in a way which is much more effective and accountable than at higher levels of
government where ownership of resource allocation and management remains low.
Ultimately the value of lessons from learning projects depends as much on the audience
for those lessons as on those directly involved in the reforms being tested. In this case the
key domestic audience in the GoB national policy community for whom LIC provides
lessons which challenge the conventional centralist domination of Ba